W912DS-14-B-0009 AMENDMENT 0001 ATTACHMENT SPECIFICATION SECTION 32 11 16

View the file

Other files

File Type Posted
Thule_Runway_Phase_I _II.pdf PDF
Amendment_W912DS-14-B-0009-0003.pdf PDF
W912DS-14-B-0009-0002.pdf PDF
Plans_-_Phase_2_-_Amendment__2.pdf PDF
Plans_-_Phase_1_-_Amendment__2.pdf PDF
Appendix_R_-_FY14_-_FY17_Sealift_Rates_-_Amendment__1.pdf PDF
Appendix_T_-_Fuel_Pricing_and_DLA_info_-_Amendment__1.pdf PDF
W912DS-14-B-0009_AMENDMENT_0001.pdf PDF
Appendix_Q_-_Pacer_Goose_Shipping_Instructions.pdf PDF
Appendix_I_-_Slug_Mgmt_Plan.pdf PDF
Package_1_-_Replace_Runway_Pavement_-_Specs.pdf PDF
Appendix_A_-_Active_Landfills.pdf PDF
Appendix_M_-_PCB_Replacement_Plan.pdf PDF
Appendix_G_-_Solid_Waste_Mgmt_Plan.pdf PDF
Package_3_-_Replace_Runway_Pavement_Phase_2_-_Plans.pdf PDF
Appendix_B_-_NFS_Material_Borrow_Site.pdf PDF
Appendix_S_-_DBA_Waiver.pdf PDF
Appendix_J_-_Installation_HAZMAT_Management_Plan.pdf PDF
Package_2_-_Replace_Runway_Pavement_Phase_1_-_Plans.pdf PDF
Appendix_F_-_PPM_Plan.pdf PDF
Appendix_L_-_Affirmative_Proc_Plan.pdf PDF
Appendix_P_-_Shipping_Rates_Gov_Furnished_Transport.pdf PDF
Appendix_K_-_FGS-GL_(Environmental_Protection).pdf PDF
Appendix_H_-_Storm_Water_Mgmt_Plan.pdf PDF
Appendix_R_-_FY14_ _FY15_Sealift_Rates.pdf PDF
Appendix_E_-_Spill_Prevention-Response_Plan.pdf PDF
Appendix_N_-_Asbestos_Management_Plan.pdf PDF
W912DS-14-B-0009_SOLICITATION.pdf PDF
Appendix_D_-_HWM_Plan.pdf PDF
Appendix_C_-_Conservation_Mgmt_Plan.pdf PDF
Appendix_O_-_Lead_Paint_Management_Plan.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Runway Pavement, Phase 1, Thule Air Base, Greenland THULERUNWAYPH1

SECTION 32 11 16

SUBBASES FOR FLEXIBLE PAVING

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO T 180 (2010) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop

AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test

ASTM INTERNATIONAL (ASTM)

ASTM C 88 (2005) Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate

ASTM C117 (2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing

ASTM C131 (2006) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine

ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method

ASTM D1557 (2009) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils

SECTION 32 11 16 Page 1

ASTM D4318 (2010) Liquid Limit, Plastic Limit, and Plasticity Index of Soils

ASTM D6938 (2010) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

ASTM D75/D75M (2009) Standard Practice for Sampling Aggregates

ASTM E11 (2009e1) Wire Cloth and Sieves for Testing Purposes

1.2 DEFINITION

Degree of compaction required is expressed as a percentage of the maximum laboratory dry density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum dry density. One exception is as follows: Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve will be expressed as a percentage of the laboratory maximum dry density in accordance with AASHTO T 180 Method D and corrected with AASHTO T 224.

1.3 SYSTEM DESCRIPTION

All plant, equipment, and tools used in the performance of the work will be subject to approval before the work is started and shall be maintained in satisfactory working condition at all times. Submit a list of proposed equipment, including descriptive data. Provide equipment which is adequate and has the capability of producing the required compaction, meeting grade controls, thickness control, and smoothness requirements as set forth herein.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Equipment

SD-06 Test Reports

Sampling and Testing Field Density Tests

1.5 QUALITY ASSURANCE

Sampling and testing are the responsibility of the Contractor, to be performed by an approved testing laboratory in accordance with Section 01 45 00.00 10 QUALITY CONTROL. Perform tests at the specified frequency.

No work requiring testing will be permitted until the testing laboratory

SECTION 32 11 16 Page 2 has been inspected and approved. Test the materials to establish compliance with the specified requirements.

1.5.1 Sampling

Take samples for laboratory testing in conformance with ASTM D75/D75M.

When deemed necessary, the sampling will be observed by the Contracting Officer.

1.5.2 Tests

1.5.2.1 Sieve Analysis

Make sieve analysis in conformance with ASTM C117 and ASTM C136. Complete particle-size analysis of the soils in conformance with ASTM D422. Sieves shall conform to ASTM E11.

1.5.2.2 Liquid Limit and Plasticity Index

Determine liquid limit and plasticity index in accordance with ASTM D4318.

1.5.2.3 Moisture-Density Determinations

Determine the laboratory maximum dry density and optimum moisture in accordance with ASTM D1557 or AASHTO T 180, Method D and corrected with

AASHTO T 224.

1.5.2.4 Field Density Tests

Measure field density in accordance with ASTM D1556, or ASTM D6938. For the method presented in ASTM D1556, use the base plate, as shown in the drawing. For the method presented in ASTM D6938, check and adjust the calibration curves, if necessary, using only the sand cone method as described in paragraph Calibration, of the ASTM publication. Tests performed in accordance with ASTM D6938 result in a wet unit weight of soil and ASTM D6938 will be used to determine the moisture content of the soil.

The calibration curves furnished with the moisture gauges shall also be checked along with density calibration checks as described in ASTM D6938.

The calibration checks of both the density and moisture gauges shall be made by the prepared containers of material method, as described in paragraph Calibration, in ASTM D6938, on each different type of material to be tested at the beginning of a job and at intervals as directed.

a. Submit certified copies of test results for approval not less than 30 days before material is required for the work.

b. Submit calibration curves and related test results prior to using the device or equipment being calibrated.

c. Submit copies of field test results within 24 hours after the tests are performed.

1.5.2.5 Wear Test

Perform wear tests in conformance with ASTM C131.

1.5.2.6 Soundness

Perform soundness tests in conformance with ASTM C 88.

SECTION 32 11 16 Page 3

1.5.3 Testing Frequency

1.5.3.1 Initial Tests

Perform one of each of the following tests on the proposed material prior to commencing construction to demonstrate that the proposed material meets all specified requirements prior to installation.

a. Sieve Analysis including 0.02 mm size material

b. Liquid limit and plasticity index

c. Moisture-density relationship

d. Wear

e. Soundness

1.5.3.2 In-Place Tests

Perform one of each of the following tests on samples taken from the placed and compacted subbasecourse. Samples shall be taken and tested at the rates indicated.

a. Perform density tests on every lift of material placed and at a frequency of one set of tests for every 500 square yards, or portion thereof, of completed area.

b. Perform sieve analysis including 0.02 mm size material on every lift of material placed and at a frequency of one sieve analysis for every 1000 square yards, or portion thereof, of material placed.

c. Perform liquid limit and plasticity index tests at the same frequency as the sieve analysis.

d. Measure the thickness of each course at intervals providing at least one measurement for each 500 square yards or part thereof. The thickness measurement shall be made by test holes, at least 3 inches in diameter through the course.

1.5.4 Approval of Material

Select the source of materials 30 days prior to the time the material will be required in the work. Tentative approval will be based on initial test results. Final approval of the materials will be based on tests for gradation, liquid limit, and plasticity index performed on samples taken from the completed and compacted course.

1.6 ENVIRONMENTAL REQUIREMENTS

Perform construction when the atmospheric temperature is above 35 degrees F.

When the temperature falls below 35 degrees F, protect all completed areas by approved methods against detrimental effects of freezing. Correct completed areas damaged by freezing, rainfall, or other weather conditions to meet specified requirements.

SECTION 32 11 16 Page 4

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Subbase Course

Provide aggregates consisting of crushed stone , gravel, sand, or other sound, durable, approved materials processed and blended or naturally combined. Provide aggregates which are durable and sound, free from lumps and balls of clay, organic matter, objectionable coatings, and other foreign material. Material retained on the No. 4 sieve shall have a percentage of wear not to exceed 50 percent after 500 revolutions when tested as specified in ASTM C131. Aggregate shall be reasonably uniform in density and quality. Aggregates shall have a maximum size of 1 inch and shall be within the limits specified as follows:

Maximum Allowable Percentage by Weight Passing Square-Mesh Sieve

Sieve Designation No. 1

No. 10 50 No. 200 8

Particles having diameters less than 0.0008 inches shall not be in excess of 3 percent by weight of the total sample tested as determined in accordance with ASTM D422. The portion of any blended component and of the completed course passing the No. 40 sieve shall be either nonplastic or shall have a liquid limit not greater than 25 and a plasticity index not greater than 5.

PART 3 EXECUTION

3.1 OPERATION OF AGGREGATE SOURCES

Clearing, stripping and excavating are the responsibility of the Contractor. Operate the aggregate sources to produce the quantity and quality of materials meeting the specified requirements in the specified time limit. Upon completion of work, aggregate sources on Government property shall be conditioned to drain readily, and shall be left in a satisfactory condition. Aggregate sources on private lands shall be conditioned in agreement with local laws and authorities.

3.2 STOCKPILING MATERIAL

Prior to stockpiling of material, clear and level storage sites. Stockpile all materials, including approved material available from excavation and grading, in the manner and at the locations designated. Aggregates shall be stockpiled on the cleared and leveled areas designated by the Contracting Officer to prevent segregation. Materials obtained from different sources shall be stockpiled separately.

3.3 PREPARATION OF UNDERLYING MATERIAL

Prior to constructing the subbase course, clean the underlying course or subgrade of all foreign substances. The surface of the underlying course or subgrade shall meet specified compaction and surface tolerances.

SECTION 32 11 16 Page 5

Correct ruts, or soft yielding spots, in the underlying courses, subgrade areas having inadequate compaction, and deviations of the surface from the specified requirements, by loosening and removing soft or unsatisfactory material and by adding approved material, reshaping to line and grade, and recompacting to specified density requirements. For cohesionless underlying courses or subgrades containing sands or gravels, as defined in ASTM D2487, the surface shall be stabilized prior to placement of the overlying course. Accomplish stabilization by mixing the overlying course material into the underlying course, and compacting by approved methods.

The stabilized material shall be considered as part of the underlying course and shall meet all requirements for the underlying course. The finished underlying course shall not be disturbed by traffic or other operations and shall be maintained in a satisfactory condition until the overlying course is placed.

3.4 GRADE CONTROL

The finished and completed course shall conform to the lines, grades, and cross sections shown. The lines, grades, and cross sections shown shall be maintained by means of line and grade stakes placed by the Contractor at the work site.

3.5 MIXING AND PLACING MATERIALS

Mix and place the materials to obtain uniformity of the material at the water content specified. Make such adjustments in mixing or placing procedures or in equipment as may be directed to obtain the true grades, to minimize segregation and degradation, to reduce or accelerate loss or increase of water, and to insure a satisfactory subbase course.

3.6 LAYER THICKNESS

The compacted thickness of the completed course shall be as indicated. The existing subbase course material to be reused over the new 12-inch subbase course layer shall have no layer thicker than 6 inches nor be thinner than 3 inches when compacted. Layer thickness requirements for new subbase course material directly above and below rigid board insulation are provided in paragraph COMPACTION.

3.7 COMPACTION

Compact each layer of the existing subbase course material to be reused over the new 12-inch subbase course layer above the rigid board insulation as shown on the drawings, with approved compaction equipment. Compaction of the existing subbase course material to be reused over the new 12-inch subbase course layer shall continue until the layer is compacted through the full depth to at least 100 percent of laboratory maximum density.

Maintain water content during the compaction procedure to within plus or minus 2 percent of optimum water content, as determined from laboratory tests, as specified in paragraph SAMPLING AND TESTING. Below the rigid board insulation compaction of the new 6-inch subbase course shall continue until the layer is compacted through the full depth to at least 100 percent of laboratory maximum density. The new 6-inch subbase course layer below the rigid board insulation shall be placed and compacted in a single layer.

Above the rigid board insulation compaction of the new 12-inch subbase course shall continue until the layer is compacted through the full depth to at least 95 percent of laboratory maximum density using a steel wheel roller. Sheepsfoot rollers shall not be used to compact the new 12-inch subbase course layer above the rigid board insulation. The new 12-inch

SECTION 32 11 16 Page 6 subbase course layer above the rigid board insulation shall be placed and compacted in a single layer. No equipment shall be operated directly on top of the rigid board insulation. Equipment placing subbase course material shall not stop abruptly, make sharp turns, spin their wheels, or travel at speeds exceeding 5 mph. Place subbase course material in a manner that prevents movement of the underlying rigid board insulation sheets. Subbase course material shall not be dropped onto the rigid board insulation from a height greater than 2 feet. For new subbase course material directly above and below rigid board insulation maintain water content during the compaction procedure to within plus or minus 2 percent of optimum water content, as determined from laboratory tests, as specified in paragraph SAMPLING AND TESTING. Make such adjustments in compacting or finishing procedures as may be directed to obtain true grades, to minimize segregation and degradation, to reduce or increase water content, and to ensure a satisfactory subbase course. Any materials that are found to be unsatisfactory shall be removed and replaced with satisfactory material or reworked, as directed, to meet the requirements of this specification.

3.8 EDGES

Place approved material along the edges of the subbase course in such quantity as will compact to the thickness of the course being constructed.

When the course is being constructed in two or more layers, at least a 1 foot width of the shoulder shall be rolled and compacted simultaneously with the rolling and compacting of each layer of the subbase course, as directed.

3.9 SMOOTHNESS TEST

The surface of the top layer shall show no deviations in excess of 3/8 inch when tested with a 12 foot straightedge. Take measurements in successive positions parallel to the centerline of the area to be paved. Measurements shall also be taken perpendicular to the centerline at 50 foot intervals.

Correct deviations exceeding this amount by removing material and replacing with new material, or by reworking existing material and compacting it to meet these specifications.

3.10 THICKNESS CONTROL

The completed thickness of the course(s) shall be in accordance with the thickness and grade indicated on the drawings. The completed course shall not be more than 1/2 inch deficient in thickness nor more than 1/2 inch above or below the established grade. Where any of these tolerances are exceeded, correct such areas by scarifying, adding new material of proper gradation or removing material, and compacting, as directed. Where the measured thickness is 1/2 inch or more thicker than shown, the course will be considered as conforming with the specified thickness requirements plus 1/2 inch. The average job thickness shall be the average of the job measurements as specified above but within 1/4 inch of the thickness shown.

3.11 MAINTENANCE

Maintain the completed course in a satisfactory condition until accepted.

-- End of Section --