This document is a solicitation for a federal construction contract to conduct stone restoration work on the Mid Chesapeake Bay Barren Island. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Baltimore.
The solicitation requires furnishing all labor, materials, and equipment to construct stone sills and breakwaters using various stone types including 4300-lb, 2600-lb, and 5400-lb armor stone, quarry run stone, core stone, and #10 stone. Payment will be made by unit price for items including performance and payment bonds, mobilization and demobilization, pre-placement surveys, stone materials, geotextiles, and final acceptance of work segments. The contractor must also conduct various surveys during construction and submit data, notes, and calculations on a defined schedule for progress payments. The solicitation includes detailed specifications for stone weighing methods, surveys, material placement and tolerances, and payment calculations.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mid Bay BIR PH1 Stone MDBYBIRPH1
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-1005 (2007) Control and Topographic Surveying
EM 1110-2-1003 (2013)Hydrographic Surveying
EM 1110-2-2302 (1990) Construction with Large Stone
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Stone Weighing Methods; G, AO
Submit for approval the method of weighing stone tonnages in accordance with this specification no later than 60 days after receipt of Notice to Proceed and no less than 30 days prior to beginning any work.
SD-01 Preconstruction Submittals
Survey Methods; G, AO
Submit for approval the methods of performing surveying in accordance with this specification no later than 60 days after receipt of Notice to Proceed and no less than 30 days prior to beginning any work.
Surveyor Qualifications; G
Submit for approval the qualifications for the proposed surveyor no less than 30 days prior to any surveying.
SD-02 Shop Drawings
Pre-Placement Survey And Sections; G, AO
At least 30 days prior to placement of any material, submit pre-placement surveys for all cross section lines. Superimpose the design cross sections on the pre-placement survey.
SECTION 01 20 00 Page 1
SD-03 Product Data
Weight Tickets
Copies of stone weight tickets must be provided within 1 week of delivery.
SD-03 Product Data
Stone Deduction Log; G, AO
Logs of stone deductions, as described in the Paragraph "Stone Deductions", must be submitted monthly, or at the time of progress payment invoices.
SD-06 Test Reports
Surveys; G, AO
Survey data files must be submitted no more than 24 hours after completion of each section.
Survey Field Notes
All survey field notes must be submitted no later than 1 week after completion of the survey.
Quantity Calculations; G, AO
End area and volume calculations must be submitted no more than
1 week after the surveyed section is completed.
SD-07 Certificates
Weight Certificates; G, AO
1.3 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or
SECTION 01 20 00 Page 2 size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.4.2 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.5 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in the PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.6 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the PRICING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
SECTION 01 20 00 Page 3
1.6.1 Survey Requirements
1.6.1.1 General Survey Requirements
Employ an independent registered professional land surveyor licensed in the State of Maryland or a registered professional engineer licensed in the State of Maryland with a minimum of 10 years experience in topographic and hydrographic surveying. The surveyor must have experience in performing topographic and hydrographic surveys of stone structures (breakwaters, sills, groins, jetties, or other similar structures) in either the Chesapeake Bay or Atlantic Ocean. Perform all surveys required by this contract with equipment and personnel completely independent from the Contractor's forces. Surveyor must be approved by the Contracting Officer. Submit the surveyor qualifications for approval. The qualifications must include a resume of each individual surveyor who will be used. The resume must demonstrate experience on at least two survey jobs with stone structures where the cost of the stone (not the total project cost) exceeded $5 million for each project. Conduct surveys in accordance with the most current versions of U.S. Army Corps of Engineers Engineer Manuals EM 1110-2-1003 , Hydrographic Surveying as well as EM 1110-1-1005 , Topographic Surveying. Surveying tasks outlined within this contract specification must be conducted following quality control and quality assurance procedures outlined within EM 1110-2-1003 for all hydrographic surveys and EM 1110-1-1005 for all topographic surveys. The licensed surveyor or engineer must be present for all surveys. Surveys conducted in the absence of the licesened surveyor or engineer will be automatically rejected. Unless otherwise noted, all hydrographic surveys must be single-beam surveys utilizing a high frequency (200 kHz) transducer. Single-beam surveys must be motion corrected for vessel heave, roll, pitch, and yaw as well as corrected for tide/stage. Bar checks must be performed at a minimum of two times a day - one before work and one after completing a day's activity. Single-beam surveys must meet the "Inland Navigation Projects" standard of accuracy, as presented in Table 3-1 of EM 1110-2-1003. All surveys must be referenced to NAVD88. The survey control data are reflected on the drawings. All data as required in this section must be submitted through RMS. See Section 01 33 00 SUBMITTAL PROCEDURES for required formats. Survey data must be provided in digital AutoCAD design (DWG) files and PDF format. All surveys required under the terms and conditions of this contract, except for the Pre-Placement Survey and Sections (Bid Item No. 0003), are considered incidental to the performance of the contract and must be performed at no additional cost to the Government. In addition to the above, adhere to the following requirements:
a. Quantity surveys must be conducted, and the data derived from these surveys must be used in computing the quantities of work performed and the actual construction completed and in place.
b. Conduct the original and final surveys for any periods for which progress payments are requested. The Contracting Officer may adjust the timing requirements if a significant storm event is forecast which could disturb in-place materials. The Contracting Officer may also require the Contractor to resurvey any materials following a storm event. All these surveys must be conducted under the direction of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. Make all computations necessary to compute the quantities of material placed in each 50 foot section of stone structure, as described under Survey Requirements.
SECTION 01 20 00 Page 4
c. Upon completing a survey, provide the survey data within 24 hours, and originals of all survey field notes, quantity calculations, sections, and all other records relating to the survey or to the layout of the work within one week to the Contracting Officer, who must use them as necessary to determine the amount of progress payments. For hydrographic surveys, RAW, BIN, EDT, and check in files must be provided upon the Government's request. Survey data files must be submitted in CSV file with format: "station, distance, easting, northing, elevation, survey method (topo or hydro), aligned easting, aligned northing" format. Distance must be measured along the cross section line and must not be the distance from the cross section origin to the surveyed point. Aligned easting and aligned northing are the coordinates of the surveyed point projected onto the cross section line. Surveys must be accompanied by appropriate descriptor data files, including but not limited to: datum, date, time, tidal data, type (e.g. total station, small boat hydro, etc.), and surveyor. For each pay item, submit each cross section plotted from the appropriate survey data and submit the end section area calculation for that pay item. The cross sections must include the pay template and tolerance of the pertinent material. Retain copies of all such material furnished to the Contracting Officer.
d. Develop, or obtain, a quantity calculation program or software compatible with Windows-10 operating system, unless otherwise approved by the Contracting Officer, which must be utilized to calculate the quantities upon which progress payment requests will be based. The quantity calculation program must calculate quantities, using the contract specified templates, as the basis for developing the cross-sectional area for each station. The quantity calculation program must incorporate the ability to correct quantities for curves or breaks in the alignment by adjusting the distance between adjacent cross sections. Specify the quantity calculation program and curve correction method in the survey methods submittal. Where cross section lines from two alignments intersect, overlapping areas of the same material must only be accounted for once; the overlapping area for one alignment will be used and the corresponding area will be subtracted from the computation for the other alignment. A copy of the software which is purchased or developed for use in complying with this specification paragraph must be provided to and become the property of the Government. The Government must also receive a copy of any/all instruction manuals or literature related to the quantity calculation program. Conduct a survey for all payment quantities for which progress payments are being requested.
1.6.1.2 Cross Section Lines
Cross sections must be collected at the start of each alignment, the end of each alignment, at a 50 ft spacing along the alignment, and at every point of intersection. Cross sections must be oriented perpendicular to the alignment unless they are at a point of intersection. The bearing of the cross section line at a point of intersection must bisect the bearings of the cross section lines immediately before and after the point of intersection. Pre-placement survey data must extend a minimum of 100 ft to the left of the alignment and 100 ft to the right of the alignment. Survey data for all stone materials must extend a minimum of 50 ft beyond the material design template.
SECTION 01 20 00 Page 5
1.6.1.3 Point Spacing
Survey points must be spaced not more than 5 ft apart and at any break in slope. Additional points must be added as necessary to accurately represent the material being surveyed. Expect that more survey points will be required to accurately represent the uppermost layer of armor stone.
Horizontal survey locations surveyed with topographic methods must not deviate more than 5 feet from the line of section. Horizontal survey locations surveyed with hydrographic methods must not deviate more than 10 ft from the line of section. Topographic survey points do not need to be thinned. Hydrographic survey points must be thinned so that points are spaced no closer than 2 ft apart. To the extent practical, topographic and hydrographic surveys must overlap by 10 horizontal feet.
1.6.1.4 Cross Sections
All cross sections must be provided in .dwg format and .pdf format. Cross sections must be plotted on 22 in x 34 in paper at a horizontal scale of 1 in = 10 ft and a vertical scale of 1 in = 2 ft. Cross sections must be produced by projecting each survey point to the cross section line and connecting the points. If cross sections are produced by means of a triangulated irregular network (TIN), the TIN must be constructed with the aligned northing and easting coordinates, and not the actual northing and easting coordinates. Cross sections must include surveys of all previously placed material, the full design template, and tolerance lines for the current material being surveyed. Employ sufficient colors as necessary to distinguish between all survey lines and templates. A legend must be provided on each sheet of surveys.
1.6.1.5 Survey Requirements For Stonework
For each prepared surface, check surveys must be conducted before and after placing each stone layer. Make checks as the work progresses to verify the lines, grades, and thicknesses of the completed stone layers.
At least one check survey must be made for each different layer.
Elevations above water must be determined by the use of a leveling instrument and rod having a base of 12 inches in diameter. Other means, if approved by the Contracting Officer, may also be used. The surveys must be conducted in the presence of the Contracting Officer unless otherwise waived. Resurveys will be required if the initial survey is not performed within the time period specified below. Specifically, the following surveys are required:
a. Surface of the completed #10 stone. The #10 stone must be surveyed immediately before the geotextile is placed (same day).
b. Surface of the completed quarry run stone no earlier than 7 days prior to placement of the core stone or armor stone.
c. Surface of the completed core stone no earlier than 14 days prior to the placement of the armor stone.
d. Surface of the completed armor stone.
A copy of the record of the check survey, including both field notes and plotted cross sections, must be provided to the Contracting Officer, or his authorized representative, as specified in paragraph "Quantity Surveys" sub-paragraph "c" above. Do not permit placement of the next layer of stone until the surveys have been checked by QC personnel to
SECTION 01 20 00 Page 6 verify that the completed stone layer is in compliance with the lines, grades, and tolerances presented in these drawings and specifications.
1.6.2 Requirements for Computing Weights
Stone must be weighed using one of the two methods described below. Submit the stone weighing methods submittal, including Quality Control provisions, to the Contracting Officer for approval. All measurements methods must be conducted in accordance with U.S. Army Corps of Engineers Engineer Manual EM 1110-2-2302 Construction with Large Stone.
1.6.2.1 Vessel Displacement
When vessel displacement is used for the determination of weights, the following procedure will be used for the determination. Each vessel will be accurately measured and will be fitted with gauges graduated to the half-foot. All gauges must be outfitted to the outer hull of each vessel.
The gauges will be located on each corner of the vessel, near the lower end of the rake, with two additional gauges amidships. Fore and aft displacement due to load will not differ more than 10 percent from their mean for the determination of tonnage, except in unavoidable cases. All gauge readings will be made in still water, estimated to the nearest tenth of a foot. At the option of the Contracting Officer, tonnage determinations may be made at the loading point by using change in gauge readings from light marks to load marks, or at the unloading point by using change in gauge readings from load marks to light marks. The Contracting Officer must have the opportunity to be present at all draft readings. All vessels must be pumped dry (within the limits of the pump suction) before each gauging, and limbers must be kept open so that any water in the vessel will flow freely to the pump suction. Gauging tables, prepared by an accredited agent satisfactory to the Contracting Officer, must be included in the Contractor's Stone Weighing Methods submittal for each vessel to be used. The weight of the water displaced at the point of gauging will be based on approved hydrometer readings of the water assuming that water weighing 62.4 and 64 pounds per cubic foot for fresh water and salt water, respectively. Each barge must be calibrated a minimum of one time, and additionally as directed by the Contracting Officer, by measuring the weight of all stone placed on the barge by the procedures specified below in the paragraph "Certified Weight", and comparing the sum of those certified weights with the weight determined by the barge displacement method. The gauges on the barge must be adjusted as necessary to address any discrepancy in the certified weights and the weights computed by displacement measurements.
1.6.2.2 Certified Weight
If shipments are made by railroad from the quarry to tidewater and then transferred to barges, certified railroad weights will be accepted in place of weights determined by barge displacements. If shipments are made by truck from the quarry, each truckload of stone must be weighted on scales, which have been carefully verified by a properly accredited official. One original report and duplicate copy of weights of each carload or truckload, certified by the weigher and prepared in ink or indelible pencil, must be furnished to the Contracting Officer. The report must show gross, tare, and net weight of each carload or truckload. If there is, in the opinion of the Contracting Officer or his representative, any doubt as to the quantity of stone on any car or truck, as indicated by the weight determined at the point of shipment, due to loss in transit or other causes, the Contractor must at his expense have such car or truck
SECTION 01 20 00 Page 7 reweighed in the presence of the Contracting Officer or his representative on scales which have been verified by a properly accredited official.
Should there be a difference in weight of stone at the point of shipment and at the point of destination, the weight at the latter point will be accepted as correct and used for payment. The cost of meeting the foregoing requirements must be included in the contract price.
1.6.2.3 Stone Deduction
Stone deduction applies to all stone where the unit of measure is by ton.
Computation of the deduction from delivered tonnage for rejected stone or stone placed beyond the prescribed tolerances will be on the basis of cross-sections of the finished work, and a deduction of 1.5 tons per cubic yard of armor stone, quarry run, and core stone built outside of the prescribed tolerances will be applied. All stone deduction logs must be submitted to the Contracting Officer monthly, or with progress payment invoices.
1.7 PAYMENT ITEMS
For each unit price pay item outlined below, the Government will not pay more than 90 percent of calculated quantities before acceptance of the section. Any excavation and spoiling of existing materials necessary in the completion of work under this contract, beyond that included in the following items, must be considered incidental to the job. No additional payment will be made for any items not included in the following items, including, but not limited to, excavation for placement of quarry run or armor stone.
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed must constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.7.1 Performance And Payment Bonds Reimbursement (Bid Item No. 0001)
1.7.1.1 Payment
The Government will reimburse the Contractor for the entire amount of premiums paid for Performance, Payment and Bid Bonds (including coinsurance and reinsurance agreements where applicable) at the contract lump sum amount under the Unit Price Schedule Item No. 0001, entitled Reimbursement of Performance and Payment Bonds. Such payment will be made only after the Contractor furnishes to the Government evidence of full payment to the surety. In no case will any payment be made by the Government for reimbursement of Performance Payment and Bid Bonds exceeding that amount bid by the Contractor under the aforementioned Unit Price Schedule Item.
1.7.1.2 Unit of Measure
Unit of measure: Job.
SECTION 01 20 00 Page 8
1.7.2 Mobilization And Demobilization (Bid Item 0002)
1.7.2.1 Payment
Mobilization includes all costs associated with the transfer of all equipment from its home station to the site: barges, cranes, draglines, hydraulic excavators, bulldozers, dump trucks, similar large construction equipment required to construct the stone structures. Demobilization must include all costs associated with transferring the above equipment back to its point of origin. Sixty percent (60%) of the contract lump sum price for Item No. 0002 shall be paid after the mobilization of all major construction equipment to the site. The remaining forty percent (40%) shall be paid after the removal of all equipment and plant from the site and the completion of all clean-up of the work site. Costs for mobilization and demobilization must be paid in accordance with Bid Item No. 0002, Mobilization and Demobilization.
1.7.2.2 Unit of Measure
Unit of measure: job.
1.7.3 Pre-Placement Survey and Sections (Bid Item 0003
1.7.3.1 Payment
Conduct a pre-placement survey of all sections prior to the placement of any material. The survey must include all reaches to cover the base contract and all options. The pre-placement survey and sections does not include any check surveys or final surveys of stonework, as required in the paragraph, "Survey Requirements for Stonework". Prepare the design cross sections in accordance with the contract plans and submit the pre-placement survey and sections. Produce the design cross sections solely with the information contained within the plans and specifications.
USACE will not provide three-dimensional AutoCAD models of the proposed work. It is the Contractor's responsibility to interpret the plans and specifications and prepare his own models of the proposed work as necessary to generate the cross sections. USACE will review the surveyed sections and design sections to verify the Contractor full understands the contract plans and has correctly prepared the design sections. Upon approval of the submittal, the design cross sections will be used as the basis to compute progress quantities and enforce tolerance requirements.
Payment for the pre-placement survey and sections must be made in accordance with Bid Item No. 0003.
1.7.3.2 Unit of Measure
Unit of measure: Job.
1.7.4 Stone Sills (Bid Item 0004 )
1.7.4.1 Payment
This section applies to Bid Item Nos. 0004a, 0004b, 0004c, and 0004d ( 4300-lb armor stone, 2600-lb armor stone, quarry run, and #10 stone).
Payment will be made for costs associated with furnishing, transporting, placing, surveying, and reshaping the stone as necessary to meet contract requirements.
SECTION 01 20 00 Page 9
1.7.4.2 Measurement
1.7.4.2.1 Measurement for Bid Item Nos. 0004a, 0004b, and 0004c
The section applies to measurement of stone for Bid Item Nos. 0004a, 0004b, and 0004c (4300-lb armor stone, 2600-lb armor stone, and quarry run). The unit of measurement for stone in place in the finished work will be the ton of 2,000 pounds. Measurement for all stone will be based on the weight of stone, surface dry, in its natural state, as determined by the vessel displacement or certified weight method. Deductions must be applied in accordance with the paragraph "Stone Deduction". Payment for stonework shall be made in accordance with Bid Items No. 0004a, 0004b, and 0004c.
1.7.4.2.2 Measurement for Bid Item No. 004d
The section applies to measurement of stone for Bid Item No. 0004d (#10 stone). Measurement for #10 stone will be based on the volume in-place and within tolerance in the structure. Compute the volume of stone in accordance with the paragraph "Survey Requirements". Apply the tolerance as specified in 35 31 19 STONEWORK. Any #10 stone placed beyond the prescribed tolerance shall not be included in the pay quantity.
1.7.4.3 Unit of Measure
1.7.4.3.1 Unit of Measure for Bid Item Nos. 0004a, 0004b, and 0004c
Unit of measure: ton (2000 lbs).
1.7.4.3.2 Unit of Measure for Bid Item No. 004d
Unit of measure: cubic yard.
1.7.5 Geotextile
1.7.5.1 Payment
Payment will be made for the cost of materials, equipment, installation, testing, and other costs associated with placement of the geotextile.
Payment for geotextile shall be made in accordance with Bid Item No. 0004e.
1.7.5.2 Measurement
Measurement of geotextile must be made on the total surface area covered in square yards, as determined by computing the length of geotextile at each cross section and multiplying by the distance between the sections.
Employ the same curve correction method used for the stonework, as described in the paragraph, "General Survey Requirements". No allowance must be made for material in seams and overlaps. No allowance must be made for material placed beyond the minimum extensions prescribed in the plans.
For example, if the plans state that geotextile must extend a minimum of five feet beyond the #10 stone, and the Contractor provides a ten foot extension, the Contractor shall only be paid for five feet. The number of rolls of geotextile used shall have no bearing on the measurement calculation.
SECTION 01 20 00 Page 10
1.7.5.3 Unit of Measure
Unit of measure: square yard.
1.7.6 Stone Breakwater (Bid Item 0005)
1.7.6.1 Payment
This section applies to Bid Item Nos. 0005a, 0005b, 0005c, and 0005d (5400-lb armor stone, quarry run, core stone, and #10 stone). Payment will be made for costs associated with furnishing, transporting, placing, surveying, and reshaping the stone as necessary to meet contract requirements.
1.7.6.2 Measurement
1.7.6.2.1 Measurement for Bid Item Nos. 0005a, 0005b, and 0005c
The section applies to measurement of stone for Bid Item Nos. 0005a, 0005b, and 0005c (5400-lb armor stone, core stone, and quarry run). The unit of measurement for stone in place in the finished work will be the ton of 2,000 pounds. Measurement for all stone will be based on the weight of stone, surface dry, in its natural state, as determined by the vessel displacement or certified weight method. Deductions must be applied in accordance with the paragraph "Stone Deduction". Payment for stonework shall be made in accordance with Bid Items No. 0005a, 0005b, and 0005c.
1.7.6.2.2 Measurement for Bid Item No. 005d
The section applies to measurement of stone for Bid Item No. 0005d (#10 stone). Measurement for #10 stone will be based on the volume in-place and within tolerance in the structure. Compute the volume of stone in accordance with the paragraph "Survey Requirements". Apply the tolerance as specified in 35 31 19 STONEWORK. Any #10 stone placed beyond the prescribed tolerance shall not be included in the pay quantity.
1.7.6.3 Unit of Measure
1.7.6.3.1 Unit of Measure for Bid Item Nos. 0005a, 0005b, and 0005c
Unit of measure: ton (2000 lbs).
1.7.6.3.2 Unit of Measure for Bid Item No. 005d
Unit of measure: cubic yard.
1.7.7 Geotextile
1.7.7.1 Payment
Payment will be made for the cost of materials, equipment, installation, testing, and other costs associated with placement of the geotextile.
Payment for geotextile shall be made in accordance with Bid Item No. 0005e.
1.7.7.2 Measurement
Measurement of geotextile must be made on the total surface area covered in square yards, as determined by computing the length of geotextile at each cross section and multiplying by the distance between the sections.
SECTION 01 20 00 Page 11
Employ the same curve correction method used for the stonework, as described in the paragraph, "General Survey Requirements". No allowance must be made for material in seams and overlaps. No allowance must be made for material placed beyond the minimum extensions prescribed in the plans.
For example, if the plans state that geotextile must extend a minimum of five feet beyond the #10 stone, and the Contractor provides a ten foot extension, the Contractor shall only be paid for five feet. The number of rolls of geotextile used shall have no bearing on the measurement calculation.
1.7.7.3 Unit of Measure
Unit of measure: square yard.
1.8 ACCEPTANCE CRITERIA
1.8.1 Acceptance of the Stone Sills or Breakwaters
Breakwater and sill sections will be accepted in continuous 1000 ft segments along the alignments; shorter acceptance reaches will be allowed for the final acceptance reach of each alignment. All materials must be placed according to the plans and specifications before a reach is accepted. Acceptance will not be made until all survey requirements have been met and all corresponding submittals have been approved by the Contracting Officer. Upon acceptance of structures, the Contractor is not responsible for repairing them unless the Contractor is responsible for damaging them. At his own expense and at no cost to the Governement, the Contractor must repair damage to the structures due to wave or storm activity if the structures have not been accepted by the Government.
1.8.2 Final Examination and Acceptance of the Project.
The project will be examined for acceptance at the completion of the contract. Should the Contractor damage any of the previously accepted stone structures, the Contractor will be responsible for repairing the structure. Any portion of repaired structure must be resurveyed for acceptance. The surface of the completed armor stone must be completed within 30 days prior to the final inspection of the project as scheduled by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --