This document is an amendment to a solicitation for the construction of an F-16 flight simulator facility at Joint Base Andrews in Maryland. The amendment modifies the specification requirements to stipulate that all secure compartmented information facility and non-SCIF walls must be finished to Level 5 on visible areas and below access flooring, with Level 3 finish required above ceilings and in plenum spaces. All SCIF walls must be uniformly finished on both sides from floor slab to underside of floor or roof deck. The transition from Level 5 to Level 3 finish on SCIF walls shall occur at the ceiling elevation, with Level 1 finish permitted only for non-SCIF substrate conditions. The solicitation was issued as a competitive 8(a) Invitation for Bid by the Department of the Army Corps of Engineers Baltimore District for the construction of the flight simulator facility at Joint Base Andrews.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE: F-16 FLIGHT SIMULATOR FACILITY at JOINT BASE ANDREWS, MARYLAND
The purpose of this amendment is to:
1. Amend Specification Section 09 29 00, para 3.3 (Please see attached).
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR22B0004
X 9B. DATED (SEE ITEM 11)
24-Jan-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Mar-2022
CODE
USACE, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
AMENDMENT NO. 0004 TO W912DR22B0004
F-16 FLIGHT SIMULATOR FACILITY at JOINT BASE ANDREWS, MD
EFFECTIVE 04 MARCH 2022
SPECIFICATIONS:
1) Specification 09 29 00, para 3.3: Add the following sentences to the end of the paragraph:
“All SCIF and Non-SCIF walls shall be Level 5 finish on all visible areas and also below finish floor in recessed access flooring areas. All SCIF and non-SCIF walls above ceilings (within plenum spaces) shall be Level 3 finish. All SCIF walls must be uniformly finished on both sides from floor slab (true floor) to underside of floor or roof deck (true ceiling). Transition on SCIF walls from Level 5 finish (below) to Level 3 finish (above) shall take place at the ceiling elevation. Level 1 finish shall be for non-SCIF substrate conditions only.”
(End of Summary of Changes)