B.08.03 07 27 26.pdf
PDF 34 KB Posted
- Solicitation number
- W912DR20B0021
About this file
This document provides specifications for a fluid-applied membrane air barrier for the renovation of Building 3613 at Joint Base Andrews in Maryland. The specifications require a fluid-applied, vapor retarding air barrier that exhibits no visible water leakage when tested in accordance with ASTM E331 and performs as a liquid water drainage plane. The physical properties of the barrier must meet standards for air permeance, air leakage, water vapor permeance, tensile strength, elongation, flexibility, and surface burning characteristics. The document also specifies requirements for primers, adhesives, mastics, transition membranes, sheet metal flashing, joint sealants, and reinforcement materials. It outlines procedures for examinations, preparations, installation, protection, cleaning, and testing of the air barrier system.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Air Force, 11th Squadron Sept 02, 2020
Joint Base Andrews - Renovation of Building 3613 Ready to Advertise
Section 07 27 26 Page 1
SECTION 07 27 26
FLUID-APPLIED MEMBRANE AIR BARRIERS
05/17
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR BARRIER ASSOCIATION OF AMERICA (ABAA)
ABAA Accreditation Accreditation
ABAA QAP Quality Assurance Program
ASTM INTERNATIONAL (ASTM)
ASTM C836/C836M (2015) High Solids Content, Cold Liquid-
Applied Elastomeric Waterproofing Membrane for Use With Separate Wearing Course
ASTM D412 (2016) Standard Test Methods for Vulcanized
Rubber and Thermoplastic Elastomers - Tension
ASTM D4263 (1983; R 2018) Standard Test Method for
Indicating Moisture in Concrete by the
Plastic Sheet Method
ASTM D5590 (2000; R 2010; E 2012) Standard Test Method for Determining the Resistance of Paint Films and Related Coatings to Fungal Defacement by
Accelerated Four-Week Agar Plate Assay
ASTM E84 (2018a) Standard Test Method for Surface
Burning Characteristics of Building Materials
ASTM E96/E96M (2016) Standard Test Methods for Water Vapor
Transmission of Materials
ASTM E283 (2004; R 2012) Determining the Rate of Air
Leakage Through Exterior Windows, Curtain
Walls, and Doors Under Specified Pressure
Differences Across the Specimen
ASTM E331 (2000; R 2016) Standard Test Method for Water
Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static
Air Pressure Difference
ASTM E2178 (2013) Standard Test Method for Air Permeance of Building Materials
Section 07 27 26 Page 2
ASTM E2357 (2017) Standard Test Method for Determining
Air Leakage of Air Barrier Assemblies
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 285 (2012) Standard Fire Test Method for
Evaluation of Fire Propagation
Characteristics of Exterior Non-Load-Bearing
Wall Assemblies Containing Combustible
Components
1.2 RELATED REQUIREMENTS
Coordinate the requirements of the building enclosure sections to provide a complete building air barrier system. Submit all materials, components and assemblies of the air barrier system together as one complete submittal package.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33
29 SUSTAINABILITY REPORTING. Submit the following in accordance with
Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Qualifications of Manufacturer; G, RO
Qualifications of Installer; G, RO
SD-02 Shop Drawings
Fluid-Applied Membrane Air Barrier; G, RO
SD-03 Product Data
Transition Membrane; G, RO
Primers, Adhesives, and Mastics; G, RO
Reinforcement; G, RO
Safety Data Sheets; G, RO
SD-07 Certificates
SD-08 Manufacturer's Instructions
Section 07 27 26 Page 3
Transition Membrane; G, RO
Primers, Adhesives, and Mastics; G, RO
1.4 MISCELLANEOUS REQUIREMENTS
For fluid-applied membrane air barriers provide the following:
1.4.1 Shop Drawings
Submit fluid-applied membrane air barrier shop drawings showing locations and extent of barrier assemblies, transition membranes, details of all typical conditions, intersections with other envelope assemblies and materials, and membrane counterflashings. Show details for bridging of gaps in construction, treatment of inside and outside corners, expansion joints, methods of attachment of materials covering the self-adhered barrier without compromising the barrier. Indicate how miscellaneous penetrations such as conduit, pipes, electric boxes, brick ties, and similar items will be sealed.
1.4.2 Product Data
Submit manufacturer's technical data indicating compliance with performance and environmental requirements, manufacturer's printed instructions for evaluating, preparing, and treating substrates, temperature and other limitations of installation conditions, safety requirements for installation, and Safety Data Sheets. Indicate flame and smoke spread ratings for all products.
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Delivery
Deliver and store materials in sufficient quantity to allow for uninterrupted flow of work. Inspect materials delivered to the site for damage and store out of weather. Deliver materials to the jobsite in their original unopened packages, clearly marked with the manufacturer's name, brand designation, description of contents, and shelf life of containerized materials. Store and handle to protect from damage.
1.5.2 Storage
Inspect materials delivered to the site for damage; unload and store out of weather in manufacturer's original packaging. Store only in dry locations, not subject to open flames or sparks, and easily accessible for inspection and handling. Protect stored materials from direct sunlight.
1.6 QUALITY ASSURANCE
1.6.1 Qualifications of Manufacturer
Submit documentation verifying that manufacturer of fluid-applied membrane air barrier is currently accredited by the Air Barrier Association of
America (ABAA Accreditation https://www.airbarrier.org/).
Section 07 27 26 Page 4
1.6.2 Qualifications of Installer
Submit documentation verifying that installers of the fluid-applied membrane air barrier are currently certified in accordance with the ABAA QAP Quality
Assurance Program (https://www.airbarrier.org/qap/).
1.7 PRECONSTRUCTION MEETING
Conduct a preconstruction meeting a minimum of two weeks prior to commencing work specified in this Section. Agenda must include, at a minimum, construction and testing of construction mock up, sequence of construction, coordination with substrate preparation, materials approved for use, compatibility of materials, coordination with installation of adjacent and covering materials, and details of construction. Attendance is required by representatives of related trades including covering materials, substrate materials, adjacent materials, and materials and components of the fluid-applied membrane air barrier.
1.8 ENVIRONMENTAL CONDITIONS
1.8.1 Temperature
Install fluid-applied membrane air barrier within the range of ambient and substrate temperatures as recommended in writing by the fluid-applied membrane air barrier manufacturer. Do not apply fluid-applied membrane air barrier to a damp or wet substrate. Do not apply during inclement weather or when ice, frost, surface moisture, or visible dampness is present on surfaces to be covered, or when precipitation is imminent.
1.8.2 Exposure to Weather
Protect fluid-applied membrane air barrier products from direct exposure to rain, snow, sunlight, mist, and other extreme weather conditions. Replace, at no additional cost to the government, barrier products that have been exposed to ultraviolet (sun)light longer than allowed by manufacturer's written requirements.
PART 2 PRODUCTS
2.1 FLUID-APPLIED MEMBRANE AIR BARRIER
Provide a fluid-applied, vapor retarding, air barrier. This barrier must exhibit no visible water leakage when tested in accordance with ASTM E331 and must perform as a liquid water drainage plane with thru-wall flashing to discharge incidental condensation and water penetration to the exterior of the building enclosure. Provide products suitable for use within temperature ranges specified by manufacturer for the location of the project.
2.1.1 Physical Properties
a. Air Permeance (ASTM E2178): less than 0.004 CFM per sf at 1.57 psf.
b. Air Leakage (ASTM E2357, ASTM E283):Less than 0.04 CFM per sf at 1.57 psf at one inch.
Section 07 27 26 Page 5
c. Water Vapor Permeance (Vapor Impermeable Membrane) (ASTM E96/E96M, desiccant method A): 0.1 perms or less.
d. Tensile Strength (ASTM D412): Not less than 138 psi.
e. Elongation (ASTM D412): Not less than 300 percent.
f. Low temperature Flexibility and Crack Bridging (ASTM C836/C836M): Pass at minus 15 degrees F.
g. Solids by Volume: minimum 50 percent.
h. Flame propagation of wall assemblies (NFPA 285): Pass
i. Surface Burning Characteristics (ASTM E84):
(1) Flame Spread Index Rating not higher than 75.
(2) Smoke Developed Index Rating not higher than 150.
j. Resistance to Mold, Mildew and Fungal Growth (ASTM D5590): 0, No growth.
2.2 PRIMERS, ADHESIVES, AND MASTICS
Provide primers, adhesives, mastics, sealants and other accessories as recommended by manufacturer of fluid-applied membrane air barrier for a complete installation.
2.3 TRANSITION MEMBRANE
Provide as specified.
2.4 SHEET METAL FLASHING
Provide as specified in Section 07 60 00 FLASHING AND SHEET METAL.
2.5 JOINT SEALANTS
Provide as specified in Section 07 92 00 JOINT SEALANTS.
2.6 REINFORCEMENT
Provide fiberglass mesh tape, or fluid-applied air barrier manufacturer's approved comparable equal product, reinforcement at seams, edges, projections and penetrations. Reinforce all joints exceeding1/4 inch with fiberglass mesh.
PART 3 EXECUTION
3.1 EXAMINATION
Before installing fluid-applied membrane air barrier, examine substrates, areas, and conditions under which fluid-applied membrane air barrier assemblies will be applied, with installer present, for compliance with requirements. Ensure the following conditions are met:
Section 07 27 26 Page 6
a. Surfaces are sound, dry, even, and free of oil, grease, dirt, excess mortar or other contaminants detrimental to the adhesion of the membranes.
b. Concrete and masonry surfaces are cured and dry, smooth without large voids, spalled areas or sharp protrusions. Do not proceed with installation until after minimum concrete curing period recommended by fluid-applied membrane air barrier manufacturer.
c. Fill voids, gaps and spalled areas in substrate to provide an even plane. Strike masonry joints full flush.
d. Verify substrate is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method in accordance with ASTM
D4263 and take suitable measures until substrate passes moisture test.
e. Verify sealants used in substrates, and in joints between substrates, are compatible with fluid-applied membrane air barrier.
3.2 PREPARATION
Clean, prepare, and treat substrate in accordance with manufacturer's written instructions. Ensure clean, dust-free, and dry substrate for fluid-applied membrane air barrier application.
a. Remove dust, dirt and other contaminants from joints and cracks before coating surfaces.
b. Prepare, treat, and seal vertical and horizontal surfaces at terminations and penetrations through fluid-applied membrane air barrier.
c. At changes in substrate plane, provide transition material (bead of sealant, mastic, extruded silicone sealant, membrane counterflashing or other material recommended by manufacturer) under transition membrane to eliminate all sharp 90 degree inside corners and to make a smooth transition from one plane to another.
d. Provide mechanically fastened non-corrosive metal sheet to span gaps in substrate plane and to make a smooth transition from one plane to the other. Continuously support membrane with substrate.
e. For exterior sheathing substrates, ensure that exterior sheathing is stabilized, with corners and edges fastened with appropriate screws.
Treat all joints in accordance with the air barrier manufacturer's instructions prior to application of air barrier material. Allow sufficient time for joint treatments to fully cure before application of transition membranes and fluid-applied membrane air barrier.
f. For concrete and masonry substrates, fill all voids and holes, particularly in mortar joints, with non-shrinking grout.
g. Mask off and cover adjacent surfaces to protect from spillage and overspray.
3.3 INSTALLATION
Section 07 27 26 Page 7
3.3.1 Installation of Transition Membrane
Install transittion membrane materials in accordance with the details on the drawings and the following:
a. Install transition membrane at all required locations prior to installation of the fluid-applied membrane air barrier.
b. Verify transition membrane is fully adhered to substrate and that its surface is clean, dry and wrinkle free prior to installation of the fluid-applied membrane air barrier.
c. Verify transition membrane completely covers all transition areas and will provide continuity of the finished fluid-applied membrane air barrier without gaps or cracks.
3.3.2 Installation of Flashing
Counterflash upper edge of thru-wall flashing and fluid-applied air barrier.
Counter flashing and thru-wall flashing are specified in Section 07 60 00
FLASHING AND SHEET METAL.
3.3.3 Installation of Fluid-Applied Membrane Air Barrier
Install materials in accordance with manufacturer's recommendations and the following:
a. Apply fluid-applied membrane air barrier in single or dual coat application by spray or roller. Apply fluid-applied membrane air barrier within manufacturer's recommended temperature range for application.
b. Apply fluid-applied membrane air barrier at rate recommended by manufacturer to yield a wet film thickness of 90 mils.
c. Apply fluid-applied membrane air barrier around all penetrations ensuring a complete and continuous air barrier. Lap fluid-applied membrane air barrier a minimum of 3 inch over transition membrane to seal leading edge.
d. Seal membrane terminations, heads of mechanical fasteners, masonry tie fasteners, around penetrations, HVAC assemblies, plumbing and electrical assemblies, doors, windows, louvers, and other assemblies penetrating the fluid-applied membrane air barrier with a termination sealant recommended by the fluid-applied membrane air barrier manufacturer.
e. Notify the Contracting Officer and Testing Agency upon completion of fluid-applied membrane air barrier installation. Air barrier materials and assemblies must remain exposed until tested and inspected by the
ABAA.
f. Do not allow materials to come in contact with chemically incompatible materials.
3.3.4 Installation of Reinforcement
Section 07 27 26 Page 8
Install reinforcement at projections, corners, joints, and penetrations where applicable.
3.4 PROTECTION AND CLEANING
3.4.1 Protection
Protect fluid-applied membrane air barrier assemblies from damage during application and remainder of construction in accordance with manufacturer's written instructions.
Coordinate installation, testing, and inspection procedures to ensure exposure period does not exceed that recommended by the product manufacturer. Remove and replace, at no additional cost to the government, membrane products that exceed manufacturer's allowed exposure limits.
3.4.2 Cleaning of Adjacent Surfaces
Clean excess product from adjacent construction using cleaning agents and procedures as recommended in writing by the manufacturer of each type of affected construction and as acceptable to same.
3.5 CLEANUP OF SPILLS
Conduct cleanup of uncured product spillage in accordance with manufacturer's written safe handling instructions.
-- End of Section --
File details come from the government source that posted it. Updated .