This amendment modifies an invitation for bid to repair taxiway whiskey at Joint Base Andrews. The modification corrects the quantity listed for CLIN 0004 in the bid schedule from 12,900 cubic yards to an unspecified revised amount. Bidders are required to bid on all line items, which include repairing or replacing the taxiway, shoulders, soils, drainage systems, signage, lighting, and markings. The work also involves excavation, site preparation, restoration, and construction management services to upgrade affected airfield pavements. The project scope includes a third phase of repairs to conform with Air Force and UFC standards. The solicitation is unrestricted and procured using sealed competitive bidding in accordance with FAR Part 14. The contract type is firm-fixed-price.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to correct the quantity of CLIN 0004 on the Bid Schedule All other terms and conditions remain unchanged.

Contracting POC: David Potocek, David.M.Potocek@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Aug-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR20B0015

X 9B. DATED (SEE ITEM 11)

07-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Aug-2020

CODE

U.S ARMY CORPS OF ENGINEERS

2 HOPKINS PLAZA 03-B-07

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR20B0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been modified:

BID SCHEDULE

PART I - THE PRICE SCHEDULE

SECTION 00010 - SUPPLIES OR SERVICES AND PRICES

UNIT PRICE SCHEDULE

Item No. Description

Estimated Quantity Unit Price Amount

0001 Repair/Replacement of

Taxiway Whiskey 1 LS -- $________

0002 Replacement of 4 Inch HMA Shoulder 1,150 SY ________ $________

0003 Removal and

Replacement of Unsatisfactory Soils 6,215 CY ________ $________

0004 Undercut from Proof Rolling and Replace with Aggregate Base Course 12,900 CY ________ $________

0005 Placement of

Geotextile Fabric 38,760 SY ________ $________

0006 Removal and Replacement of TCE Contaminated Soils 50 CY ________ $________

0007 Removal and

Replacement of Fuel Contaminated Soils 270 CY ________ $________

0008 Removal and

Replacement of Lead Contaminated soils

NOT IN CONTRACT

0009 Removal, Transportation, Liner Trench of ACM Conduit 300 LF ________ $________

W912DR20B0015

0010 West Airfield Storm Drainage Project 1 LS -- $________

Total Estimated Bsae Bid Amount $________

NOTES TO BIDDERS

Bidders must bid on all items. Failure to bid on all items may cause for rejection of bid.

VARIATION IN ESTIMATED QUANTITIES. If the quantity of a unit-price item in this contract is an estimated quantity and the actual quantity of the unit-price item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.

(FAR 52.211-18 APR 1984)

(End of Summary of Changes)