This document provides information on a draft solicitation for optimized environmental remediation services at Joint Base Andrews. The U.S. Army Corps of Engineers Baltimore District seeks these services to support the base's Environmental Remediation Program. The performance-based contract will require the contractor to conduct all necessary remediation activities to achieve the objectives outlined in the draft solicitation. This includes ongoing work at over 30 identified sites involving releases of fuels, solvents, and other contaminants. Feedback on the draft solicitation is due by October 4th via the projNET website. A final solicitation with a request for proposals will be issued at a later date. The optimized remediation contract aims to complete ongoing investigations and remedial actions, achieve regulatory closure at sites where possible, and reduce long-term lifecycle costs under the oversight of the Army Corps and federal and state regulators.
Site Visit 30-31 July 2019 Presentation Slides
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| JBA ORC Final Solicitation_Amendment #2_19NOV19.pdf | ||
| Price_Schedule_Template_Solicitation_Attachment_07NOV19.xlsx | XLSX spreadsheet | |
| JBA_ORC_Final_Solicitation_Amendment__1_07NOV19.pdf | ||
| Draft_Solicitation_RFI_Questions_Responses_final_17OCT19.pdf | ||
| JBA_ORC_Final_Solicitation_19OCT19.pdf | ||
| Site_Visit_Inquiries_Responses.pdf | ||
| JBA_ORC_Draft_Solicitation_24SEP19.pdf | ||
| JB_Andrews_AR_Public_Site_Training_Guide_8Aug19.pdf | ||
| B.07.01_Sign_in_Roster_Combined.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Warfighters Supporting Warfighters!
UNCLASSIFIED
UNCLASSIFIED
Air Force Installation & Mission Support CenterAir Force Installation & Mission Support Center
JB ANDREWS
ENVIRONMENTAL
RESTORATION PROGRAM
OVERVIEW
William K. Burris, PG
AFCEC/CZOE
30 July 2019
UNCLASSIFIED
Welcome
On behalf of the Air Force Civil Engineer Center, Air Force District of Washington, and Joint Base
Andrews, the Home of Air Force One!
UNCLASSIFIED
Your Host
Air Force Material Command Air Force Installation Management Support Center
Air Force Civil Engineer Center Environmental Directorate
Environmental Operations East JBLE/JBA/Dover Installation Support Section Environmental Restoration Program Manger
William K. Burris, PG aka… just Bill
UNCLASSIFIED
The AGENDA
Part A: Introduction
Part B: Regulatory Considerations and Issues at JB Andrews
Part C: Logistical Challenges of Working at JB Andrews
Part D: JB Andrews Administrative Record & GFI
Part E: Overview and Status of JB Andrews Environmental Sites
UNCLASSIFIED
Part A: Introduction
Who is here?
USACE Remarks
ERP mission
Caveats and disclaimers
Installation Overview
Site List
UNCLASSIFIED
Who is here?
USAF / AFCEC
USACE
Regulators
UNCLASSIFIED
USACE Baltimore District
Remarks from the Corps
UNCLASSIFIED
JB ANDREWS ERP
JB Andrews ERP operates under the following:
1) Protect Human Health and Safety
2) Support the Mission
3) Effective Stewardship of Taxpayer Dollars
•8
UNCLASSIFIED
Caveats and Disclaimers
Everything presented here today is based on our most up to date understanding of scope of the project, timelines, current acquisition strategy, etc.
All information must still be considered provisional until a final RFP is released.
UNCLASSIFIED
Andrews Overview Facility Assets Valued at over $660 Millon Over 4,400 Total Acres (not incl. Remote Sites) Over 380 Bldgs (minus housing) over 6M sq ft 111 miles of roadways
21.8M sq ft of airfield pavements
Approx. 2,900 Residents (2010 Census)
Over 14,000 uniformed and civilian employees
UNCLASSIFIED
History of JB Andrews
Camp Springs Air Base was established in Sept. 1942 and the runways became operational in May 1943. Renamed Andrews Field in
UNCLASSIFIED
History of JB Andrews
Used to train Pilots on P-47 Thunderbolt
UNCLASSIFIED
Andrews AFB rebuilt in late 1950s early 1960s
UNCLASSIFIED
ERP Overview
2 National Priority Listed (NPL) Sites:
JB Andrews Brandywine DRMO
32 sites at JBA in Federal Facility Agreement (FFA)
71 Sites total
34 Sites Closed
1 LTM
11 Sites Active Remediation 25 Sites various stages of investigation ranging from RI to no action closeout
UNCLASSIFIED
Andrews Sites
Andrews has been in operation since 1943. As expected with over half a century of functioning as a active air base, there have been several releases of contamination into the environment.
These sites fall into several broad catagories:
Spill Sites – Landfills – LUST – Fire Training Areas
UNCLASSIFIED
ORC site list
ORC Site List SS-01 Brandywine DRMO
FT-02
LF-05
LF-06/LF-07/BLNA (Monitoring Only)
ST-08
ST-10
SS-11 Davidsonville
ST-14
SS-22
SS-26
SS-28
TU-167
LF-581/SWMU-66
INCLUDED MMRP SITES
FI-346
RR-004
RR-348
SR-347/A
TS345/A
ZZ349/A
Where is Brandywine DRMO? SS-01
UNCLASSIFIED
Where is Davidsonville, SS-11?
•18
UNCLASSIFIED
Part B
Regulatory Considerations and Issues at Joint Base Andrews
UNCLASSIFIED
Part B
JB Andrews Regulatory Status
CERCLA and the JB Andrews Federal Facility Agreement
Document Review Times
Records of Decision
Challenging Regulatory Issues
Maryland Department of Environment Oil Control Program
QAPPs
Questions
… and a finally your second break
… again you are welcome.
UNCLASSIFIED
JB Andrews Regulatory Status
JB Andrews in on the NPL – with Federal Facility Agreement (FFA)
Brandywine DRMO is on the NPL – Separate listing and FFA
Davidsonville is NOT on the NPL – State regulated cleanup
UNCLASSIFIED
CERCLA/ NON-CERCLA
Two kinds of sites
CERCLA – Subject to the FFA No Permits, that includes wells.
RI must be based on high quality defensible data.
Still have to meet Applicable Requirements (ARARs).
Includes Sediment and Erosion control.
Non-CERCLA: Petroleum only. Regulated by the Maryland Department of Environment Oil Control Program. (ST-08/SS-22) Need well permits.
If Remediation system is in place than applicable permits are required.
If removal occurs then Sediment & Erosion Control / Storm water permits may be required.
SS-11 is State regulated cleanup under Federal Facility Program.
UNCLASSIFIED
Wells
Wells in Maryland!
If applicable well permits are filed with County.
Well abandonment requires rig mobilization.
No stick up wells in the Airfield.
Two inch wells are fine now.
WELL DATA MUST BE PROVIDED TO ERPIMS!
UNCLASSIFIED
ERPIMS
AFCEC manages the USAF Environmental Resources Program Information Management System (ERPIMS).
https://www.afcec.af.mil/What-We- Do/Environment/Restoration/ERPIMS/
UNCLASSIFIED
Code of Maryland REgulations
Sediment & Erosion Control / Storm water Management
On USAF property these plans are reviewed by the state. There is no County Grading Permit process for work on USAF property.
Where will you need these? Excavations.
Plan on working with an expeditor.
Budget for Super Silt Fence.
https://mde.maryland.gov/programs/Water/StormwaterManagementP rogram/Pages/erosionsedimentcontrol.aspx
UNCLASSIFIED
Our Regulatory Partners
P.G County Health Department
Maryland Department of Environment Federal Facilities is the key department Oil Control is the exception
Environmental Protection Agency, Region III
UNCLASSIFIED
Review Times
Ignore the FFA review times.
Working Copy to USAF and USACE for review. We are pretty good at turning these around in about 30 days… at least until lately…
Once RTCs have cleared then the document can be submitted to regulators. Expect EPA comments in 45 to 75 days (the current record is over a year).
UNCLASSIFIED
Review Times
EPA comments can be very challenging to reconcile. You may need to work with USAF in doing so. Some will actually require USAF response (like PFAS related comments)
Maybe say… another 45 days to reconcile RTCs. Then the document can go final… if it made it through OPSEC & Policy Review.
UNCLASSIFIED
But wait… there’s more!
ESDs, RACRs, FS, PPs, and RODs require USAF legal review. This typically takes 21 days.
ESDs, RACRs, PPs, and RODs require EPA legal review. This is typically 60 days.
Any changes made by EPA must be rerun by USAF legal!
UNCLASSIFIED
Typical FS if there are no major issues
Working Copy – USAF/ USACE review 4 weeks
Revise per comments 1 week
Back check/resolution by USAF /USACE 2 weeks
USAF Legal review 3 weeks
Revise/receive USAF legal approval 3 weeks
Regulator Review of Draft 8 weeks
Revise per regulator comment/USAF approval 4 weeks
USAF legal check/approval 2 weeks
Regulator review/approve responses 4 weeks
Draft Final OPSEC & Policy Review 1 week
Finalize Total 32 weeks after initial submittal
UNCLASSIFIED
There will be a slight delay.
ESDs, RACRs, and RODs need USAF signatures.
4 to 6 months!
UNCLASSIFIED
Records of Decision
JB Andrews RODs are highly prescriptive.
Almost any change in a remedy will likely require an ESD.
Keep in mind how long an ESD will take to get in place if you are proposing a change in a remedy to save in life cycle costs, or establish an alternative approach.
UNCLASSIFIED
Emerging Contaminants
PFOS/PFOA
1,4 Dioxane
Impact on Investigation Derived Waste?
No central USAF policy… yet… Current JB Andrews Policy… manage as unregulated waste unless the IDW was generated specifically for sampling for PFAS.
This policy may change in the future.
UNCLASSIFIED
MDE Oil Control Program
We have two sites in the ORC managed by MDE Oil Control.
CERCLA process and approach are NOT applicable.
MDE will close a site based on qualitative risk.
MARYLAND ENVIRONMENTAL ASSESSMENT TECHNOLOGY for
LEAKING UNDERGROUND STORAGE TANKS
Yes that is the MEAT Guidance:
https://mde.maryland.gov/programs/LAND/Documents/MEAT%20Guidance% 20Document%20Rev%20Email%207%2017%20%2713.pdf
UNCLASSIFIED
MDE Oil Control Program
MDE Site Closure No Source No Free Product (just sheen or preferably less) No One Drinking It Levels Trending Down
In USAF program MDE site closure is equivalent to RC. The site cannot be SC until you reach UU/UE.
UNCLASSIFIED
QAPPS
We have agreement from the regulators that there can be one basewide UFP Quality Assurance Program Plan (QAPP) for the contract…
… kind of sort of….
Each project/site needs a QAPP specific to each project. Wherever possible it should refer to the basewide QAPP to limit the size and review time.
UNCLASSIFIED
Labs
Laboratories
DOD ELAP labs only for the CERCLA sites https://www.denix.osd.mil/edqw/accreditation/home/dod-elap-fact-sheet/
OCP sites… we Prefer DOD ELAP but OCP does not care.
Standard OCP sampling MTBE, BTEX, TPH-GRO, TPH-DRO, Naphthalene
UNCLASSIFIED
Welcome to Part C
Logistical Challenges of Working at JB Andrews
UNCLASSIFIED
Part C
JB Andrews is hard to understand
Airfield logistics
Some Basewide Stuff for the ORC
… and a finally your third break
… and again you are welcome.
UNCLASSIFIED
Heads Up
Trying to get stuff done at JB Andrews is hard.
AFCEC staff and support contractors will try to assist in establishing and maintaining the needed lines of communication when attempting to get work done.
Sometimes they are even successful.
UNCLASSIFIED
Airfield Access
Flight line Access
Called Pathfinder for years…
Then changed to FLEX…
Then changed to RAB???
UNCLASSIFIED
Flight Line Access
Flight Line Badge Controlled Area – Favorable background check Restricted Area – Secret Clearance (Interim will suffice) Presidential Areas – Just not going to happen
NO I CANNOT SHOW A MAP!
Airfield Driver… CAC Card Network Access
T-1 NAC (6 to 9 months if not more) 3 to 4 weeks to get account set up
On line training Practical training day Practical training night
UNCLASSIFIED
Tangent
ORC sites that are at least in part in the Controlled Movement Area
ST-10
LF-06
MMRP Sites
SS-22
TU-167
(maybe? The contamination is not yet delineated and it may extend into a restricted area)
ORC sites that are at least in part within the Restricted Area
FT-02
ST-14
SS-26
ORC Sites that are at least in part within Presidential Areas
SS-28
UNCLASSIFIED
Construction Escort
Air field Driver
Trained on security protocols, markings
Trained to use radio and talk to the tower
Keeps all workers within required distance
UNCLASSIFIED
Temporary Airfield Construction Waiver
Need to get a…
UNCLASSIFIED
Temporary Air Field Construction Waiver
Need to submit a request to the FAA
UNCLASSIFIED
Temporary Air Field Construction Waiver
Need to generate a Operational Risk Assessment
UNCLASSIFIED
Temporary Air Field Construction Waiver
Then you need to meet with airfield ops and all impacted parties to determine when and how to get the work done?
UNCLASSIFIED
During the ops meeting
You will have to work with these guys
UNCLASSIFIED
During the ops meeting
… and these guys.
UNCLASSIFIED
And some other things
Air Field Construction Barriers
UNCLASSIFIED
What else did 8a2 learn
FOD
Ramp Freezes
UNCLASSIFIED
Concrete?
Airfield concrete is 18 to 24 inches thick with plenty of rebar.
Need a FOD box around the coring system.
UNCLASSIFIED
Patching Holes
Must use Set-45 quick setting concrete… absolutely no cold mix asphalt patch.
UNCLASSIFIED
Ready yet?
No now it’s time for dig permits.
Roughly two weeks
Must be walked around
Comm is long pole in this tent
UNCLASSIFIED
Dig Permit
In the past the best strategy to do RI type work has been to use Triad approach with screening data to delineate plumes and select well installation locations.
Use well data to support the Human Health Risk Assessment.
UNCLASSIFIED
Day of Drilling
Problems with Drill Crew getting access?
Outstanding warrant?
Real ID Act?
Moving airfield construction barriers
UNCLASSIFIED
ERPIMS
All the data has to be submitted to ERPIMS.
This includes GIS location and sample depths.
These packages are NOT easy to assemble and submit.
UNCLASSIFIED
Regulatory Review
EPA has at least three reviewers. RPM, Hydrogeologist, and Toxicologist.
Review typically lasts 45 - 75 days.
MDE Review is shorter
UNCLASSIFIED
Typical issues
Vapor Intrusion?
Find the source?
Collect samples from the top of the Calvert Formation?
Is the Plume completely delineated?
Another mobilization?
Elevated metals like arsenic with no real idea where it came from?
Speciate chromium?
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Support the Tier I team Facility Facilitator Record Keeping Coordinate the Agenda
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Update the Community Involvement Plans Every Two years Complete Restoration Advisory Board Surveys per DERP manual
We don’t have RABs.
Update Community Involvement Plans There are three JBA, Brandywine, Davidsonville
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Update the Installation Conceptual Site Model.
Annual update of installation Groundwater Level Map
Includes annual water level sampling across the installation monitoring network
Update CSM with new boring / well data every two years Annual update GIS / ERP maps
Transmit GIS layers to Installation GeoBase group Print hard copy maps for distribution to ERP and base Civil Engineer Squadron Use
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Manage the Base wide Monitoring Well Network Remove unneeded wells.
Repair wells.
First Priority – Remove/replace stick up wells In the airfield!
More details on this will be provided in the RFP.
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Support JB Andrews In Management of Administrative Record.
Ensure final documents are bookmarked pdf less than 25 mb in size.
Assist in categorizing and assigning metadata for final documents.
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Develop Annual Land Use Control Reports This includes maintenance of existing land use control signs.
UNCLASSIFIED
Basewide Issues for the ORC
The ORC contractor will need to…
Support AFCEC in obtaining Real Estate Easements and Licenses of Entry on private property This means writing Environmental Baseline Surveys (EBS)
UNCLASSIFIED
Welcome to Part D
Navigating the JB Andrews Administrative Record
UNCLASSIFIED
Air Force Civil Engineer Center
Please type the website below into your browser to search and review public documents using the Public Administrative Record http://afcec.publicadmin-record.us.af.mil/
UNCLASSIFIED
Air Force Civil Engineer Center
•Welcome Page
•Click Here to enter site
UNCLASSIFIED
Air Force Civil Engineer Center
•Find Joint Base Andrews •Find Joint BaseAndrews 1.Select Active Duty
2.Scroll Down the Installation List to select ‘Joint Base Andrews, MD’
3. Click Search button
UNCLASSIFIED
Keep in Mind
Brandywine DRMO may be a separate CERCLA site. However it is listed as SS-01 in the Joint Base Andrews AR.
There is no separate Brandywine DRMO site on the installation list.
Davidsonville is also included as SS-11 with the rest of the JB Andrews sites.
UNCLASSIFIED
Air Force Civil Engineer Center
•Search Results
•Search results will be displayed here
•Click the magnifying glass in order to view the pdf of the document
•NOTE: Please see the following pages for directions on how to locate particular documents
UNCLASSIFIED
Air Force Civil Engineer Center
Search Tips
Joint Base Andrews has thousands of records. It is best to narrow your search by filling in a few of the fields to help limit the results. These search parameters are listed in order of usefulness:
AR Number Select a Site or Multiple Sites Subject or Title line Author Date range (Use MM/DD/YYYY) Recipient
The following pages of this guide will show you how to search the AR using the following methods:
Select a Site or Multiple Sites AR number
UNCLASSIFIED
Air Force Civil Engineer Center
•Specific Site Search Page •Find Specific Joint Base Andrews Sites 1.Scroll Down the Installation List to select ‘Joint Base Andrews, MD’
2.Select the associated Joint Base Andrews site from the ‘Sites’List •NOTE: To select multiple site use the ‘Shift’ or ‘Ctrl’ Key
3. Click Search button
UNCLASSIFIED
Air Force Civil Engineer Center
•Specific Site Search Page Results
•Search results will be displayed here
•Click the magnifying glass in order to view the pdf of the document
UNCLASSIFIED
Air Force Civil Engineer Center
•How to use the AR# to Find a Specific Document
1.Make sure Joint Base Andrews, MD is selected in the Installation List
2. Enter the provided •AR# here
3.Click Here to start the document search
UNCLASSIFIED
Air Force Civil Engineer Center
•AR# Search Page Results
•Search results will be displayed here
•Click the magnifying glass in order to view the pdf of the document
UNCLASSIFIED
Air Force Civil Engineer Center
•Viewing a Document You now have the option to SAVE
•the document to your local hard drive •or network drive.
You can also PRINT the document to your local or network printer.
Note: If the AR website is inactive for 10 minutes or more your browsing session will expire
UNCLASSIFIED
Air Force Civil Engineer Center
•Search Tips & Help Document •Click Here to review Help document and SearchTips
UNCLASSIFIED
Air Force Civil Engineer Center
For more information about the Joint Base Andrews Environmental Restoration Program, please visit the website below https://www.jba.af.mil/About-Us/Environmental- Mission/
UNCLASSIFIED
Government Furnished Information
Draft documents and documents not yet entered into the AR
Past Presentations
Regulatory meeting minutes
ERPIMS data (January 19 Data)
UNCLASSIFIED
Key Points Documents
Overview of the ORC objectives for each site.
Background for each site
Specific Details that must be considered in reaching the goal for each site.
Key documents list with specific AR#s
UNCLASSIFIED
Part E
Overview and Status of JB Andrews Environmental Sites
UNCLASSIFIED
Let’s Review
ORC Site List SS-01 Brandywine DRMO
FT-02
LF-05
LF-06/LF-07/BLNA (Monitoring Only)
ST-08
ST-10
SS-11 Davidsonville
ST-14
SS-22
SS-26
SS-28
TU-167
LF-581/SWMU-66
INCLUDED MMRP SITES
FI-346
RR-004
RR-348
SR-347/A
TS345/A
ZZ349/A
UNCLASSIFIED
Active Sites Not In the ORC
FT-03 and FT-04 (would be at SC except for PFAS)
LF-06/LF-07 (Final Remedy) (Monitoring is in the ORC)
SWMU-12 (RI is ongoing )
LF-34 (RI is just getting started)
LF-555 (RI is just getting started)
SA-507 (RI is ongoing)
SWMU-69 (stalled because of PFAS)
Yes these will be included in a future contracting effort.
UNCLASSIFIED
Andrews Geology
Andrews is located on a topographic plateau that feeds into five stream systems.
Andrews is located on the Upland Deposits. A mix of sand, silt, gravel, The Upland Deposits are underlain by the Calvert Formation. This thick clay “holds up” contamination.
UNCLASSIFIED
Andrews Geology
Release
In general releases into the subsurface ultimately migrate to the creeks.
Calvert Formation
Andrews Geology
UNCLASSIFIED
Brandywine DRMO SS-01
The following history is ridiculously condensed that it is essentially fiction.
Feel free to mine the AR for the long and painful history.
Where is Brandywine DRMO?
UNCLASSIFIED
In the town of Brandywine Maryland
8 Acre site
North Brandywine Rd
Next to CSX railroad
TRS ERH PROCESS
•Electricity is directed into the subsurface area.•TRS ERH PROCESS•TRS ERH PROCESS
•TRS Power Control Unit
•Electrical Resistance Heating•Electrical Resistance Heating
UNCLASSIFIED
Proposed Plan & Record of Decision
Proposed Plan Issued to Public in December 2016
Public Meeting on December 2016
Record of Decision – signed March 2018
System finally operational in April 2019
UNCLASSIFIED
ERH at Brandywine
• Treatment from 2‐37 ft bgs
• Original design included 65 sheet pile electrodes and 36 bored electrode pairs
• Modified during construction to address site constraints such as utilities/CSX requirements
• Two equipment compounds
• Vapor recovery
• 9 groundwater monitoring wells
• 17 temperature monitoring points
Site Plan
UNCLASSIFIED
SS-01 Expectations for the ORC
Achieve RA-O Essentially continues monitoring Easy yes?
Not really. You need to work with CSX to access most of the monitoring wells.
Reduce Lifecycle Costs What does that mean?
Remove wells from private property.
Support Real Estate activity – Generate Environmental Baseline Reports Demo the old pump and treat systems
Anything Else?
Maybe repave parts of Cherry Tree Crossing Road
UNCLASSIFIED
FT-02
The remedy is injections to support reductive bioremediation
Achieve RAO and Reduce LCCs.
Try to find ways to minimize mobilizations onto the airfield.
Check colony count specified in the ROD.
UNCLASSIFIED
LF-05
•Leroy’s Lane Landfill
-Operation from late 1950s until the late 1980s
- Received construction debris, sludge, solvent waste, municipal type waste, medical waste, underground storage tanks, and who knows what else
-Covers approximately 14 acres -The only site on Andrews where GW contamination has migrated off site.
LF-05
LF-05 1994 Aerial Photograph
GW Contamination
UNCLASSIFIED
Selected Remedy
Cap over the waste to eliminate infiltration of water.
Funnel and gate system to prevent contamination from migrating off-site.
Injections of substrate to treat off-site contamination
Cap
Funnel and Gate
Land Use Controls
Construction Dec 2010
LF-05: Completed Cap
UNCLASSIFIED
LF-05 Expectations for the ORC
Achieve RA-O and Reduce LCCs
What does that mean?
Maintain the Cap Maintain the Gates
Anything Else?
Work to limit the footprint of offsite LUCs as much as possible!
Remove as many offsite wells as possible.
There may be Real Estate Actions that require EBS.
UNCLASSIFIED
Southern Side of the Airfield
LF-6
LF-7
BLNA
Achieve IRA-O and RA-O
Essentially conduct monitoring per MDE Acceptance Variance from ARARs.
UNCLASSIFIED
Southern Side of the Airfield
MMRP Sites Removal of lead shot from
Skeet Ranges (less than an acre)
Lots of PP/RODs
ISSUES:
Milcon Construction!
Any disturbance of the earth 5000 Sf or greater, OR 100 CYs of cut or fill, requires MDE blessing of S&E plan.
UNCLASSIFIED
ST-08
Motor Pool Oil Control Site
Closed by MDE.
Considered RC by USAF but not
SC.
Recent Sampling found roughly 2 inches of product in one of the well.
Anticipate annual sampling with passive recovery.
UNCLASSIFIED
ST-10
•117
UNCLASSIFIED
ST-10: Changing Standards
When ROD was signed (2005) the Risk Based Standard for Naphthalene was 18 ppb in groundwater.
We have reached that level in our clean up efforts.
However the current standard is 0.165 ppb in water.
We have not reached that level.
Now What?
Get the site to SC! UU/UE. It should be doable.
•118
UNCLASSIFIED
SS-11
Located North of JB Andrews.
TCE Contaminated Groundwater
Not on the NPL
State regulated cleanup.
•119
UNCLASSIFIED
SS-11
Contamination extends approx. 400 feet laterally from the source area.
•120
UNCLASSIFIED
SS-11
Contamination extends to depth of 70 feet beneath the ground surface.
•121
UNCLASSIFIED
SS-11
Bio-remediation by reductive dehalogenation
•122
UNCLASSIFIED
Expectations for the ORC
Currently Achieve RA-O and Reduce LCCs
The current remedy is under evaluation.
Coordination is required to access portions of this site.
UNCLASSIFIED
ST-14
Started as a gas station investigation when… whoops what is this solvent doing here?
UNCLASSIFIED
•125
2017 Plume Locations and bioremediation barriers
UNCLASSIFIED
•126
The Big Issue:
EPA wants Vapor Intrusion Investigation of all buildings location within 100 feet of the plume.
UNCLASSIFIED
ST-14 ORC expectations
Achieve RA-O and achieve Revised CSM, Updated Groundwater Monitoring Program, Remedy Evaluation and Alternatives Analysis, and ESD or ROD Amendment
Vapor Intrusion must be addressed.
UNCLASSIFIED
SS-22
Jet fuel release.
Current contract goal is to reach regulatory site closure.
Site is messed up geology due to infinite utility cuts and fills and buried pavement and who knows.
UNCLASSIFIED
SS-22
2014 BTEX
Plume map
UNCLASSIFIED 130
UNCLASSIFIED
SS-22 Issues
Dual Phase recovery system lowered water table and attempted to capture majority of LNAPL.
Dissolved plume is dramatically reduced in size.
Still no guarantee that the state will close the site.
Status for the ORC? Currently Achieve RA-O/LTM Currently envision monitoring.
The MDE OCP may require that the system be reactivated or request that further remedial action be conducted.
Yes this may change based on OCP regulatory status.
UNCLASSIFIED
SS-26
Chlorinated Solvents
Challenging work area
Natural interception trench?
•132
UNCLASSIFIED
SS-26
•133
UNCLASSIFIED
SS-26 Issues
Active portion of the airfield in midst of 113th ANG operations.
Bioremediation Remedy is installed.
We are still determining if we have reached RIP.
ORC goal will likely be achieve RAO with reduced LCCs.
ISSUES: A new pavement project is due to occur maybe right about the start time of the ORC.
UNCLASSIFIED
SS-28: Ever expanding plume
2009:
PA/SI Results
•135
UNCLASSIFIED
SS-28: Final Results
•136
UNCLASSIFIED
SS-28
Oh that’s where that came from.
•137
UNCLASSIFIED
From the Proposed Plan SS-28
UNCLASSIFIED
SS-28 Issues
ORC Goal: Obtain RIP That means Remedial Design, Implementation, Operation.
PP final… ROD complete by October 2019?
EPA wants Vapor Intrusion Investigation
Portions of the site are in Presidential Areas and will require difficult coordination to access.
Airfield construction related to the new Presidential Hangar MilCon is starting now and may interfere with remedy implementation
UNCLASSIFIED
TU-167
Located between ST-14 and SS-22
UNCLASSIFIED
Location of TU-167
UNCLASSIFIED
Included as part with SS-22 (an OCP site)
PBR contractor took samples and found chlorinated solvents.
Site was disassociated from SS-22 and USAF funded a new site characterization study.
Site characterization study indicates presence of chlorinated solvents in 100 ppb range in groundwater near the Calvert.
LNAPL – waste oil in mass below the former waste oil UST.
Some Benzene hits scattered.
History of TU-167
UNCLASSIFIED 143
TU-167 VOCs
UNCLASSIFIED
Complete an RI, FS, PP, and ROD
The nature and extent of the chlorinated solvent contamination is not delineated.
We recommend you develop a phased approach to the RI.
Triad?
Expectations for TU-167
UNCLASSIFIED
LF-581
Also known as SWMU-66 and hardfill Area D-5
Discussed Earlier in Part B
UNCLASSIFIED
EM-61 Results
UNCLASSIFIED
ORC Status
Achieve SC
Currently the plan is to issue a No CERCLA Action FS/PP/ROD
Conduct removal under MDE regulatory oversite.
UNCLASSIFIED
FIRST BREAK
Whew… that was hard… Lunch Time?