This document provides information on a draft solicitation for optimized environmental remediation services at Joint Base Andrews. The U.S. Army Corps of Engineers Baltimore District seeks these services to support the base's Environmental Remediation Program. The performance-based contract will require the contractor to conduct all necessary remediation activities to achieve the objectives outlined in the draft solicitation. This includes ongoing work at over 30 identified sites involving releases of fuels, solvents, and other contaminants. Feedback on the draft solicitation is due by October 4th via the projNET website. A final solicitation with a request for proposals will be issued at a later date. The optimized remediation contract aims to complete ongoing investigations and remedial actions, achieve regulatory closure at sites where possible, and reduce long-term lifecycle costs under the oversight of the Army Corps and federal and state regulators.

Site Visit 30-31 July 2019 Presentation Slides

View the file

Other files for this federal contract opportunity

Other files attached to Joint Base Andrews Optimized Remediation Contract, newest first.
File Type Posted
JBA ORC Final Solicitation_Amendment #2_19NOV19.pdf PDF
Price_Schedule_Template_Solicitation_Attachment_07NOV19.xlsx XLSX spreadsheet
JBA_ORC_Final_Solicitation_Amendment__1_07NOV19.pdf PDF
Draft_Solicitation_RFI_Questions_Responses_final_17OCT19.pdf PDF
JBA_ORC_Final_Solicitation_19OCT19.pdf PDF
Site_Visit_Inquiries_Responses.pdf PDF
JBA_ORC_Draft_Solicitation_24SEP19.pdf PDF
JB_Andrews_AR_Public_Site_Training_Guide_8Aug19.pdf PDF
B.07.01_Sign_in_Roster_Combined.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Warfighters Supporting Warfighters!

UNCLASSIFIED

UNCLASSIFIED

Air Force Installation & Mission Support CenterAir Force Installation & Mission Support Center

JB ANDREWS

ENVIRONMENTAL

RESTORATION PROGRAM

OVERVIEW

William K. Burris, PG

AFCEC/CZOE

30 July 2019

UNCLASSIFIED

Welcome

On behalf of the Air Force Civil Engineer Center, Air Force District of Washington, and Joint Base

Andrews, the Home of Air Force One!

UNCLASSIFIED

Your Host

Air Force Material Command Air Force Installation Management Support Center

Air Force Civil Engineer Center Environmental Directorate

Environmental Operations East JBLE/JBA/Dover Installation Support Section Environmental Restoration Program Manger

William K. Burris, PG aka… just Bill

UNCLASSIFIED

The AGENDA

Part A: Introduction

Part B: Regulatory Considerations and Issues at JB Andrews

Part C: Logistical Challenges of Working at JB Andrews

Part D: JB Andrews Administrative Record & GFI

Part E: Overview and Status of JB Andrews Environmental Sites

UNCLASSIFIED

Part A: Introduction

Who is here?

USACE Remarks

ERP mission

Caveats and disclaimers

Installation Overview

Site List

UNCLASSIFIED

Who is here?

USAF / AFCEC

USACE

Regulators

UNCLASSIFIED

USACE Baltimore District

Remarks from the Corps

UNCLASSIFIED

JB ANDREWS ERP

JB Andrews ERP operates under the following:

1) Protect Human Health and Safety

2) Support the Mission

3) Effective Stewardship of Taxpayer Dollars

•8

UNCLASSIFIED

Caveats and Disclaimers

Everything presented here today is based on our most up to date understanding of scope of the project, timelines, current acquisition strategy, etc.

All information must still be considered provisional until a final RFP is released.

UNCLASSIFIED

Andrews Overview Facility Assets Valued at over $660 Millon Over 4,400 Total Acres (not incl. Remote Sites) Over 380 Bldgs (minus housing) over 6M sq ft 111 miles of roadways

21.8M sq ft of airfield pavements

Approx. 2,900 Residents (2010 Census)

Over 14,000 uniformed and civilian employees

UNCLASSIFIED

History of JB Andrews

Camp Springs Air Base was established in Sept. 1942 and the runways became operational in May 1943. Renamed Andrews Field in

UNCLASSIFIED

History of JB Andrews

Used to train Pilots on P-47 Thunderbolt

UNCLASSIFIED

Andrews AFB rebuilt in late 1950s early 1960s

UNCLASSIFIED

ERP Overview

2 National Priority Listed (NPL) Sites:

JB Andrews Brandywine DRMO

32 sites at JBA in Federal Facility Agreement (FFA)

71 Sites total

34 Sites Closed

1 LTM

11 Sites Active Remediation 25 Sites various stages of investigation ranging from RI to no action closeout

UNCLASSIFIED

Andrews Sites

Andrews has been in operation since 1943. As expected with over half a century of functioning as a active air base, there have been several releases of contamination into the environment.

These sites fall into several broad catagories:

Spill Sites – Landfills – LUST – Fire Training Areas

UNCLASSIFIED

ORC site list

ORC Site List SS-01 Brandywine DRMO

FT-02

LF-05

LF-06/LF-07/BLNA (Monitoring Only)

ST-08

ST-10

SS-11 Davidsonville

ST-14

SS-22

SS-26

SS-28

TU-167

LF-581/SWMU-66

INCLUDED MMRP SITES

FI-346

RR-004

RR-348

SR-347/A

TS345/A

ZZ349/A

Where is Brandywine DRMO? SS-01

UNCLASSIFIED

Where is Davidsonville, SS-11?

•18

UNCLASSIFIED

Part B

Regulatory Considerations and Issues at Joint Base Andrews

UNCLASSIFIED

Part B

JB Andrews Regulatory Status

CERCLA and the JB Andrews Federal Facility Agreement

Document Review Times

Records of Decision

Challenging Regulatory Issues

Maryland Department of Environment Oil Control Program

QAPPs

Questions

… and a finally your second break

… again you are welcome.

UNCLASSIFIED

JB Andrews Regulatory Status

JB Andrews in on the NPL – with Federal Facility Agreement (FFA)

Brandywine DRMO is on the NPL – Separate listing and FFA

Davidsonville is NOT on the NPL – State regulated cleanup

UNCLASSIFIED

CERCLA/ NON-CERCLA

Two kinds of sites

CERCLA – Subject to the FFA No Permits, that includes wells.

RI must be based on high quality defensible data.

Still have to meet Applicable Requirements (ARARs).

Includes Sediment and Erosion control.

Non-CERCLA: Petroleum only. Regulated by the Maryland Department of Environment Oil Control Program. (ST-08/SS-22) Need well permits.

If Remediation system is in place than applicable permits are required.

If removal occurs then Sediment & Erosion Control / Storm water permits may be required.

SS-11 is State regulated cleanup under Federal Facility Program.

UNCLASSIFIED

Wells

Wells in Maryland!

If applicable well permits are filed with County.

Well abandonment requires rig mobilization.

No stick up wells in the Airfield.

Two inch wells are fine now.

WELL DATA MUST BE PROVIDED TO ERPIMS!

UNCLASSIFIED

ERPIMS

AFCEC manages the USAF Environmental Resources Program Information Management System (ERPIMS).

https://www.afcec.af.mil/What-We- Do/Environment/Restoration/ERPIMS/

UNCLASSIFIED

Code of Maryland REgulations

Sediment & Erosion Control / Storm water Management

On USAF property these plans are reviewed by the state. There is no County Grading Permit process for work on USAF property.

Where will you need these? Excavations.

Plan on working with an expeditor.

Budget for Super Silt Fence.

https://mde.maryland.gov/programs/Water/StormwaterManagementP rogram/Pages/erosionsedimentcontrol.aspx

UNCLASSIFIED

Our Regulatory Partners

P.G County Health Department

Maryland Department of Environment Federal Facilities is the key department Oil Control is the exception

Environmental Protection Agency, Region III

UNCLASSIFIED

Review Times

Ignore the FFA review times.

Working Copy to USAF and USACE for review. We are pretty good at turning these around in about 30 days… at least until lately…

Once RTCs have cleared then the document can be submitted to regulators. Expect EPA comments in 45 to 75 days (the current record is over a year).

UNCLASSIFIED

Review Times

EPA comments can be very challenging to reconcile. You may need to work with USAF in doing so. Some will actually require USAF response (like PFAS related comments)

Maybe say… another 45 days to reconcile RTCs. Then the document can go final… if it made it through OPSEC & Policy Review.

UNCLASSIFIED

But wait… there’s more!

ESDs, RACRs, FS, PPs, and RODs require USAF legal review. This typically takes 21 days.

ESDs, RACRs, PPs, and RODs require EPA legal review. This is typically 60 days.

Any changes made by EPA must be rerun by USAF legal!

UNCLASSIFIED

Typical FS if there are no major issues

Working Copy – USAF/ USACE review 4 weeks

Revise per comments 1 week

Back check/resolution by USAF /USACE 2 weeks

USAF Legal review 3 weeks

Revise/receive USAF legal approval 3 weeks

Regulator Review of Draft 8 weeks

Revise per regulator comment/USAF approval 4 weeks

USAF legal check/approval 2 weeks

Regulator review/approve responses 4 weeks

Draft Final OPSEC & Policy Review 1 week

Finalize Total 32 weeks after initial submittal

UNCLASSIFIED

There will be a slight delay.

ESDs, RACRs, and RODs need USAF signatures.

4 to 6 months!

UNCLASSIFIED

Records of Decision

JB Andrews RODs are highly prescriptive.

Almost any change in a remedy will likely require an ESD.

Keep in mind how long an ESD will take to get in place if you are proposing a change in a remedy to save in life cycle costs, or establish an alternative approach.

UNCLASSIFIED

Emerging Contaminants

PFOS/PFOA

1,4 Dioxane

Impact on Investigation Derived Waste?

No central USAF policy… yet… Current JB Andrews Policy… manage as unregulated waste unless the IDW was generated specifically for sampling for PFAS.

This policy may change in the future.

UNCLASSIFIED

MDE Oil Control Program

We have two sites in the ORC managed by MDE Oil Control.

CERCLA process and approach are NOT applicable.

MDE will close a site based on qualitative risk.

MARYLAND ENVIRONMENTAL ASSESSMENT TECHNOLOGY for

LEAKING UNDERGROUND STORAGE TANKS

Yes that is the MEAT Guidance:

https://mde.maryland.gov/programs/LAND/Documents/MEAT%20Guidance% 20Document%20Rev%20Email%207%2017%20%2713.pdf

UNCLASSIFIED

MDE Oil Control Program

MDE Site Closure No Source No Free Product (just sheen or preferably less) No One Drinking It Levels Trending Down

In USAF program MDE site closure is equivalent to RC. The site cannot be SC until you reach UU/UE.

UNCLASSIFIED

QAPPS

We have agreement from the regulators that there can be one basewide UFP Quality Assurance Program Plan (QAPP) for the contract…

… kind of sort of….

Each project/site needs a QAPP specific to each project. Wherever possible it should refer to the basewide QAPP to limit the size and review time.

UNCLASSIFIED

Labs

Laboratories

DOD ELAP labs only for the CERCLA sites https://www.denix.osd.mil/edqw/accreditation/home/dod-elap-fact-sheet/

OCP sites… we Prefer DOD ELAP but OCP does not care.

Standard OCP sampling MTBE, BTEX, TPH-GRO, TPH-DRO, Naphthalene

UNCLASSIFIED

Welcome to Part C

Logistical Challenges of Working at JB Andrews

UNCLASSIFIED

Part C

JB Andrews is hard to understand

Airfield logistics

Some Basewide Stuff for the ORC

… and a finally your third break

… and again you are welcome.

UNCLASSIFIED

Heads Up

Trying to get stuff done at JB Andrews is hard.

AFCEC staff and support contractors will try to assist in establishing and maintaining the needed lines of communication when attempting to get work done.

Sometimes they are even successful.

UNCLASSIFIED

Airfield Access

Flight line Access

Called Pathfinder for years…

Then changed to FLEX…

Then changed to RAB???

UNCLASSIFIED

Flight Line Access

Flight Line Badge Controlled Area – Favorable background check Restricted Area – Secret Clearance (Interim will suffice) Presidential Areas – Just not going to happen

NO I CANNOT SHOW A MAP!

Airfield Driver… CAC Card Network Access

T-1 NAC (6 to 9 months if not more) 3 to 4 weeks to get account set up

On line training Practical training day Practical training night

UNCLASSIFIED

Tangent

ORC sites that are at least in part in the Controlled Movement Area

ST-10

LF-06

MMRP Sites

SS-22

TU-167

(maybe? The contamination is not yet delineated and it may extend into a restricted area)

ORC sites that are at least in part within the Restricted Area

FT-02

ST-14

SS-26

ORC Sites that are at least in part within Presidential Areas

SS-28

UNCLASSIFIED

Construction Escort

Air field Driver

Trained on security protocols, markings

Trained to use radio and talk to the tower

Keeps all workers within required distance

UNCLASSIFIED

Temporary Airfield Construction Waiver

Need to get a…

UNCLASSIFIED

Temporary Air Field Construction Waiver

Need to submit a request to the FAA

UNCLASSIFIED

Temporary Air Field Construction Waiver

Need to generate a Operational Risk Assessment

UNCLASSIFIED

Temporary Air Field Construction Waiver

Then you need to meet with airfield ops and all impacted parties to determine when and how to get the work done?

UNCLASSIFIED

During the ops meeting

You will have to work with these guys

UNCLASSIFIED

During the ops meeting

… and these guys.

UNCLASSIFIED

And some other things

Air Field Construction Barriers

UNCLASSIFIED

What else did 8a2 learn

FOD

Ramp Freezes

UNCLASSIFIED

Concrete?

Airfield concrete is 18 to 24 inches thick with plenty of rebar.

Need a FOD box around the coring system.

UNCLASSIFIED

Patching Holes

Must use Set-45 quick setting concrete… absolutely no cold mix asphalt patch.

UNCLASSIFIED

Ready yet?

No now it’s time for dig permits.

Roughly two weeks

Must be walked around

Comm is long pole in this tent

UNCLASSIFIED

Dig Permit

In the past the best strategy to do RI type work has been to use Triad approach with screening data to delineate plumes and select well installation locations.

Use well data to support the Human Health Risk Assessment.

UNCLASSIFIED

Day of Drilling

Problems with Drill Crew getting access?

Outstanding warrant?

Real ID Act?

Moving airfield construction barriers

UNCLASSIFIED

ERPIMS

All the data has to be submitted to ERPIMS.

This includes GIS location and sample depths.

These packages are NOT easy to assemble and submit.

UNCLASSIFIED

Regulatory Review

EPA has at least three reviewers. RPM, Hydrogeologist, and Toxicologist.

Review typically lasts 45 - 75 days.

MDE Review is shorter

UNCLASSIFIED

Typical issues

Vapor Intrusion?

Find the source?

Collect samples from the top of the Calvert Formation?

Is the Plume completely delineated?

Another mobilization?

Elevated metals like arsenic with no real idea where it came from?

Speciate chromium?

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Support the Tier I team Facility Facilitator Record Keeping Coordinate the Agenda

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Update the Community Involvement Plans Every Two years Complete Restoration Advisory Board Surveys per DERP manual

We don’t have RABs.

Update Community Involvement Plans There are three JBA, Brandywine, Davidsonville

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Update the Installation Conceptual Site Model.

Annual update of installation Groundwater Level Map

Includes annual water level sampling across the installation monitoring network

Update CSM with new boring / well data every two years Annual update GIS / ERP maps

Transmit GIS layers to Installation GeoBase group Print hard copy maps for distribution to ERP and base Civil Engineer Squadron Use

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Manage the Base wide Monitoring Well Network Remove unneeded wells.

Repair wells.

First Priority – Remove/replace stick up wells In the airfield!

More details on this will be provided in the RFP.

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Support JB Andrews In Management of Administrative Record.

Ensure final documents are bookmarked pdf less than 25 mb in size.

Assist in categorizing and assigning metadata for final documents.

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Develop Annual Land Use Control Reports This includes maintenance of existing land use control signs.

UNCLASSIFIED

Basewide Issues for the ORC

The ORC contractor will need to…

Support AFCEC in obtaining Real Estate Easements and Licenses of Entry on private property This means writing Environmental Baseline Surveys (EBS)

UNCLASSIFIED

Welcome to Part D

Navigating the JB Andrews Administrative Record

UNCLASSIFIED

Air Force Civil Engineer Center

Please type the website below into your browser to search and review public documents using the Public Administrative Record http://afcec.publicadmin-record.us.af.mil/

UNCLASSIFIED

Air Force Civil Engineer Center

•Welcome Page

•Click Here to enter site

UNCLASSIFIED

Air Force Civil Engineer Center

•Find Joint Base Andrews •Find Joint BaseAndrews 1.Select Active Duty

2.Scroll Down the Installation List to select ‘Joint Base Andrews, MD’

3. Click Search button

UNCLASSIFIED

Keep in Mind

Brandywine DRMO may be a separate CERCLA site. However it is listed as SS-01 in the Joint Base Andrews AR.

There is no separate Brandywine DRMO site on the installation list.

Davidsonville is also included as SS-11 with the rest of the JB Andrews sites.

UNCLASSIFIED

Air Force Civil Engineer Center

•Search Results

•Search results will be displayed here

•Click the magnifying glass in order to view the pdf of the document

•NOTE: Please see the following pages for directions on how to locate particular documents

UNCLASSIFIED

Air Force Civil Engineer Center

Search Tips

Joint Base Andrews has thousands of records. It is best to narrow your search by filling in a few of the fields to help limit the results. These search parameters are listed in order of usefulness:

AR Number Select a Site or Multiple Sites Subject or Title line Author Date range (Use MM/DD/YYYY) Recipient

The following pages of this guide will show you how to search the AR using the following methods:

Select a Site or Multiple Sites AR number

UNCLASSIFIED

Air Force Civil Engineer Center

•Specific Site Search Page •Find Specific Joint Base Andrews Sites 1.Scroll Down the Installation List to select ‘Joint Base Andrews, MD’

2.Select the associated Joint Base Andrews site from the ‘Sites’List •NOTE: To select multiple site use the ‘Shift’ or ‘Ctrl’ Key

3. Click Search button

UNCLASSIFIED

Air Force Civil Engineer Center

•Specific Site Search Page Results

•Search results will be displayed here

•Click the magnifying glass in order to view the pdf of the document

UNCLASSIFIED

Air Force Civil Engineer Center

•How to use the AR# to Find a Specific Document

1.Make sure Joint Base Andrews, MD is selected in the Installation List

2. Enter the provided •AR# here

3.Click Here to start the document search

UNCLASSIFIED

Air Force Civil Engineer Center

•AR# Search Page Results

•Search results will be displayed here

•Click the magnifying glass in order to view the pdf of the document

UNCLASSIFIED

Air Force Civil Engineer Center

•Viewing a Document You now have the option to SAVE

•the document to your local hard drive •or network drive.

You can also PRINT the document to your local or network printer.

Note: If the AR website is inactive for 10 minutes or more your browsing session will expire

UNCLASSIFIED

Air Force Civil Engineer Center

•Search Tips & Help Document •Click Here to review Help document and SearchTips

UNCLASSIFIED

Air Force Civil Engineer Center

For more information about the Joint Base Andrews Environmental Restoration Program, please visit the website below https://www.jba.af.mil/About-Us/Environmental- Mission/

UNCLASSIFIED

Government Furnished Information

Draft documents and documents not yet entered into the AR

Past Presentations

Regulatory meeting minutes

ERPIMS data (January 19 Data)

UNCLASSIFIED

Key Points Documents

Overview of the ORC objectives for each site.

Background for each site

Specific Details that must be considered in reaching the goal for each site.

Key documents list with specific AR#s

UNCLASSIFIED

Part E

Overview and Status of JB Andrews Environmental Sites

UNCLASSIFIED

Let’s Review

ORC Site List SS-01 Brandywine DRMO

FT-02

LF-05

LF-06/LF-07/BLNA (Monitoring Only)

ST-08

ST-10

SS-11 Davidsonville

ST-14

SS-22

SS-26

SS-28

TU-167

LF-581/SWMU-66

INCLUDED MMRP SITES

FI-346

RR-004

RR-348

SR-347/A

TS345/A

ZZ349/A

UNCLASSIFIED

Active Sites Not In the ORC

FT-03 and FT-04 (would be at SC except for PFAS)

LF-06/LF-07 (Final Remedy) (Monitoring is in the ORC)

SWMU-12 (RI is ongoing )

LF-34 (RI is just getting started)

LF-555 (RI is just getting started)

SA-507 (RI is ongoing)

SWMU-69 (stalled because of PFAS)

Yes these will be included in a future contracting effort.

UNCLASSIFIED

Andrews Geology

Andrews is located on a topographic plateau that feeds into five stream systems.

Andrews is located on the Upland Deposits. A mix of sand, silt, gravel, The Upland Deposits are underlain by the Calvert Formation. This thick clay “holds up” contamination.

UNCLASSIFIED

Andrews Geology

Release

In general releases into the subsurface ultimately migrate to the creeks.

Calvert Formation

Andrews Geology

UNCLASSIFIED

Brandywine DRMO SS-01

The following history is ridiculously condensed that it is essentially fiction.

Feel free to mine the AR for the long and painful history.

Where is Brandywine DRMO?

UNCLASSIFIED

In the town of Brandywine Maryland

8 Acre site

North Brandywine Rd

Next to CSX railroad

TRS ERH PROCESS

•Electricity is directed into the subsurface area.•TRS ERH PROCESS•TRS ERH PROCESS

•TRS Power Control Unit

•Electrical Resistance Heating•Electrical Resistance Heating

UNCLASSIFIED

Proposed Plan & Record of Decision

Proposed Plan Issued to Public in December 2016

Public Meeting on December 2016

Record of Decision – signed March 2018

System finally operational in April 2019

UNCLASSIFIED

ERH at Brandywine

• Treatment from 2‐37 ft bgs

• Original design included 65 sheet pile electrodes and 36 bored electrode pairs

• Modified during construction to address site constraints such as utilities/CSX requirements

• Two equipment compounds

• Vapor recovery

• 9 groundwater monitoring wells

• 17 temperature monitoring points

Site Plan

UNCLASSIFIED

SS-01 Expectations for the ORC

Achieve RA-O Essentially continues monitoring Easy yes?

Not really. You need to work with CSX to access most of the monitoring wells.

Reduce Lifecycle Costs What does that mean?

Remove wells from private property.

Support Real Estate activity – Generate Environmental Baseline Reports Demo the old pump and treat systems

Anything Else?

Maybe repave parts of Cherry Tree Crossing Road

UNCLASSIFIED

FT-02

The remedy is injections to support reductive bioremediation

Achieve RAO and Reduce LCCs.

Try to find ways to minimize mobilizations onto the airfield.

Check colony count specified in the ROD.

UNCLASSIFIED

LF-05

•Leroy’s Lane Landfill

-Operation from late 1950s until the late 1980s

- Received construction debris, sludge, solvent waste, municipal type waste, medical waste, underground storage tanks, and who knows what else

-Covers approximately 14 acres -The only site on Andrews where GW contamination has migrated off site.

LF-05

LF-05 1994 Aerial Photograph

GW Contamination

UNCLASSIFIED

Selected Remedy

Cap over the waste to eliminate infiltration of water.

Funnel and gate system to prevent contamination from migrating off-site.

Injections of substrate to treat off-site contamination

Cap

Funnel and Gate

Land Use Controls

Construction Dec 2010

LF-05: Completed Cap

UNCLASSIFIED

LF-05 Expectations for the ORC

Achieve RA-O and Reduce LCCs

What does that mean?

Maintain the Cap Maintain the Gates

Anything Else?

Work to limit the footprint of offsite LUCs as much as possible!

Remove as many offsite wells as possible.

There may be Real Estate Actions that require EBS.

UNCLASSIFIED

Southern Side of the Airfield

LF-6

LF-7

BLNA

Achieve IRA-O and RA-O

Essentially conduct monitoring per MDE Acceptance Variance from ARARs.

UNCLASSIFIED

Southern Side of the Airfield

MMRP Sites Removal of lead shot from

Skeet Ranges (less than an acre)

Lots of PP/RODs

ISSUES:

Milcon Construction!

Any disturbance of the earth 5000 Sf or greater, OR 100 CYs of cut or fill, requires MDE blessing of S&E plan.

UNCLASSIFIED

ST-08

Motor Pool Oil Control Site

Closed by MDE.

Considered RC by USAF but not

SC.

Recent Sampling found roughly 2 inches of product in one of the well.

Anticipate annual sampling with passive recovery.

UNCLASSIFIED

ST-10

•117

UNCLASSIFIED

ST-10: Changing Standards

When ROD was signed (2005) the Risk Based Standard for Naphthalene was 18 ppb in groundwater.

We have reached that level in our clean up efforts.

However the current standard is 0.165 ppb in water.

We have not reached that level.

Now What?

Get the site to SC! UU/UE. It should be doable.

•118

UNCLASSIFIED

SS-11

Located North of JB Andrews.

TCE Contaminated Groundwater

Not on the NPL

State regulated cleanup.

•119

UNCLASSIFIED

SS-11

Contamination extends approx. 400 feet laterally from the source area.

•120

UNCLASSIFIED

SS-11

Contamination extends to depth of 70 feet beneath the ground surface.

•121

UNCLASSIFIED

SS-11

Bio-remediation by reductive dehalogenation

•122

UNCLASSIFIED

Expectations for the ORC

Currently Achieve RA-O and Reduce LCCs

The current remedy is under evaluation.

Coordination is required to access portions of this site.

UNCLASSIFIED

ST-14

Started as a gas station investigation when… whoops what is this solvent doing here?

UNCLASSIFIED

•125

2017 Plume Locations and bioremediation barriers

UNCLASSIFIED

•126

The Big Issue:

EPA wants Vapor Intrusion Investigation of all buildings location within 100 feet of the plume.

UNCLASSIFIED

ST-14 ORC expectations

Achieve RA-O and achieve Revised CSM, Updated Groundwater Monitoring Program, Remedy Evaluation and Alternatives Analysis, and ESD or ROD Amendment

Vapor Intrusion must be addressed.

UNCLASSIFIED

SS-22

Jet fuel release.

Current contract goal is to reach regulatory site closure.

Site is messed up geology due to infinite utility cuts and fills and buried pavement and who knows.

UNCLASSIFIED

SS-22

2014 BTEX

Plume map

UNCLASSIFIED 130

UNCLASSIFIED

SS-22 Issues

Dual Phase recovery system lowered water table and attempted to capture majority of LNAPL.

Dissolved plume is dramatically reduced in size.

Still no guarantee that the state will close the site.

Status for the ORC? Currently Achieve RA-O/LTM Currently envision monitoring.

The MDE OCP may require that the system be reactivated or request that further remedial action be conducted.

Yes this may change based on OCP regulatory status.

UNCLASSIFIED

SS-26

Chlorinated Solvents

Challenging work area

Natural interception trench?

•132

UNCLASSIFIED

SS-26

•133

UNCLASSIFIED

SS-26 Issues

Active portion of the airfield in midst of 113th ANG operations.

Bioremediation Remedy is installed.

We are still determining if we have reached RIP.

ORC goal will likely be achieve RAO with reduced LCCs.

ISSUES: A new pavement project is due to occur maybe right about the start time of the ORC.

UNCLASSIFIED

SS-28: Ever expanding plume

2009:

PA/SI Results

•135

UNCLASSIFIED

SS-28: Final Results

•136

UNCLASSIFIED

SS-28

Oh that’s where that came from.

•137

UNCLASSIFIED

From the Proposed Plan SS-28

UNCLASSIFIED

SS-28 Issues

ORC Goal: Obtain RIP That means Remedial Design, Implementation, Operation.

PP final… ROD complete by October 2019?

EPA wants Vapor Intrusion Investigation

Portions of the site are in Presidential Areas and will require difficult coordination to access.

Airfield construction related to the new Presidential Hangar MilCon is starting now and may interfere with remedy implementation

UNCLASSIFIED

TU-167

Located between ST-14 and SS-22

UNCLASSIFIED

Location of TU-167

UNCLASSIFIED

Included as part with SS-22 (an OCP site)

PBR contractor took samples and found chlorinated solvents.

Site was disassociated from SS-22 and USAF funded a new site characterization study.

Site characterization study indicates presence of chlorinated solvents in 100 ppb range in groundwater near the Calvert.

LNAPL – waste oil in mass below the former waste oil UST.

Some Benzene hits scattered.

History of TU-167

UNCLASSIFIED 143

TU-167 VOCs

UNCLASSIFIED

Complete an RI, FS, PP, and ROD

The nature and extent of the chlorinated solvent contamination is not delineated.

We recommend you develop a phased approach to the RI.

Triad?

Expectations for TU-167

UNCLASSIFIED

LF-581

Also known as SWMU-66 and hardfill Area D-5

Discussed Earlier in Part B

UNCLASSIFIED

EM-61 Results

UNCLASSIFIED

ORC Status

Achieve SC

Currently the plan is to issue a No CERCLA Action FS/PP/ROD

Conduct removal under MDE regulatory oversite.

UNCLASSIFIED

FIRST BREAK

Whew… that was hard… Lunch Time?