This is a draft solicitation for an Optimized Remediation Contract to support the Joint Base Andrews Environmental Remediation Program. The solicitation requires the contractor to perform all necessary environmental remediation activities to achieve performance objectives at 14 Installation Restoration Program sites and 9 Military Munitions Response Program sites at Joint Base Andrews. The contractor must develop plans, conduct investigations and remediation, implement optimization strategies, and achieve site closure goals over a 10-year period of performance. Feedback on the draft solicitation must be submitted by October 4, 2019. The final solicitation will be issued later to request proposals. The U.S. Army Corps of Engineers Baltimore District is the issuing agency seeking these environmental remediation services at Joint Base Andrews in Maryland.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| JBA ORC Final Solicitation_Amendment #2_19NOV19.pdf | ||
| Price_Schedule_Template_Solicitation_Attachment_07NOV19.xlsx | XLSX spreadsheet | |
| JBA_ORC_Final_Solicitation_Amendment__1_07NOV19.pdf | ||
| Draft_Solicitation_RFI_Questions_Responses_final_17OCT19.pdf | ||
| JBA_ORC_Final_Solicitation_19OCT19.pdf | ||
| Site_Visit_Inquiries_Responses.pdf | ||
| JBA_ORC_Site_Visit_Presentation_30Jul19.pdf | ||
| B.07.01_Sign_in_Roster_Combined.pdf | ||
| JB_Andrews_AR_Public_Site_Training_Guide_8Aug19.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A
X B
X C
D
EX
X
G
F 81 - 89
90 - 120
X H 121 - 127
Leigha.M.Arnold@usace.army .mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA
FAR (48 CFR) 53.214(c)
1 127
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W912DR 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 4 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
Room 00-A-22 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
LEIGHA M ARNOLD 410-962-0641
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 13
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT
PACKAGING AND MARKING
14 - 53 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 56 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 57 - 58 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIO NS AND INSTRUCTIO NS
PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS
59 - 80
PART II - CO NTRACT CLAUSES
U.S. ARMY CORPS OF ENGINEERS, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
24 Sep 2019
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W912DR19R0025
Section B - Supplies or Services and Prices
PRICE SCHEDULE
Installation Site CLIN/Sub-
CLIN
Number
CLIN/Sub-CLIN Description Projected
Award Date
(Pending availability of funding and bona fide need)
JB Andrews N/A 0001 Complete Project Management Plan (PMP) At Award
JB Andrews N/A 0002 Develop Integrated Master Schedule (IMS)/Milestone
Payment Schedule (MPS) and Update Monthly
JB Andrews N/A 0002CA Develop IMS/MPS and Update Monthly At Award
JB Andrews N/A 0002CB Update IMS/MPS Monthly - Year 2 FY21
JB Andrews N/A 0002CC Update IMS/MPS Monthly - Year 3 FY22
JB Andrews N/A 0002CD Update IMS/MPS Monthly - Year 4 FY23
JB Andrews N/A 0002CE Update IMS/MPS Monthly - Year 5 FY24
JB Andrews N/A 0002CF Update IMS/MPS Monthly - Year 6 FY25
JB Andrews N/A 0002CG Update IMS/MPS Monthly - Year 7 FY26
JB Andrews N/A 0002CH Update IMS/MPS Monthly - Year 8 FY27
JB Andrews N/A 0002CJ Update IMS/MPS Monthly - Year 9 FY28
JB Andrews N/A 0002CK Update IMS/MPS Monthly - Year 10 FY29
JB Andrews N/A 0003 Complete Basewide Quality Program Plans (QPPs) At Award
JB Andrews N/A 0004 Complete Quality Assurance Surveillance Plan (QASP) At Award
JB Andrews N/A 0005 Update Basewide Conceptual Site Model
JB Andrews N/A 0005CA Update Basewide Conceptual Site Model - Year 1 At Award
JB Andrews N/A 0005CB Update Basewide Conceptual Site Model - Year 2 FY21
JB Andrews N/A 0005CC Update Basewide Conceptual Site Model - Year 3 FY22
JB Andrews N/A 0005CD Update Basewide Conceptual Site Model - Year 4 FY23
JB Andrews N/A 0005CE Update Basewide Conceptual Site Model - Year 5 FY24
JB Andrews N/A 0005CF Update Basewide Conceptual Site Model - Year 6 FY25
JB Andrews N/A 0005CG Update Basewide Conceptual Site Model - Year 7 FY26
JB Andrews N/A 0005CH Update Basewide Conceptual Site Model - Year 8 FY27
JB Andrews N/A 0005CJ Update Basewide Conceptual Site Model - Year 9 FY28
JB Andrews N/A 0005CK Update Basewide Conceptual Site Model - Year 10 FY29
JB Andrews N/A 0006 Update Basewide Land Use Control (LUC) Boundary figures and GIS files
JB Andrews N/A 0006CA Update Basewide Basewide LUC Boundary figures and GIS files - Year 1
At Award
JB Andrews N/A 0006CB Update Basewide Basewide LUC Boundary figures and GIS files - Year 2
FY21
JB Andrews N/A 0006CC Update Basewide Basewide LUC Boundary figures and GIS files - Year 3
FY22
JB Andrews N/A 0006CD Update Basewide Basewide LUC Boundary figures and GIS files - Year 4
FY23
JB Andrews N/A 0006CE Update Basewide Basewide LUC Boundary figures and GIS files - Year 5
FY24
JB Andrews N/A 0006CF Update Basewide Basewide LUC Boundary figures and GIS files - Year 6
FY25
JB Andrews N/A 0006CG Update Basewide Basewide LUC Boundary figures and GIS files - Year 7
FY26
JB Andrews N/A 0006CH Update Basewide Basewide LUC Boundary figures and GIS files - Year 8
FY27
JB Andrews N/A 0006CJ Update Basewide Basewide LUC Boundary figures and GIS files - Year 9
FY28
JB Andrews N/A 0006CK Update Basewide Basewide LUC Boundary figures and GIS files - Year 10
FY29
JB Andrews N/A 0007 Complete Basewide Well Inventory/Inspection
JB Andrews N/A 0007CA Inventory and Inspect Basewide Wells - Year 1 At Award
JB Andrews N/A 0007CB Inventory and Inspect Basewide Wells - Year 2 FY21
JB Andrews N/A 0007CC Inventory and Inspect Basewide Wells - Year 3 FY22
JB Andrews N/A 0007CD Inventory and Inspect Basewide Wells - Year 4 FY23
JB Andrews N/A 0007CE Inventory and Inspect Basewide Wells - Year 5 FY24
JB Andrews N/A 0007CF Inventory and Inspect Basewide Wells - Year 6 FY25
JB Andrews N/A 0007CG Inventory and Inspect Basewide Wells - Year 7 FY26
JB Andrews N/A 0007CH Inventory and Inspect Basewide Wells - Year 8 FY27
JB Andrews N/A 0007CJ Inventory and Inspect Basewide Wells - Year 9 FY28
JB Andrews N/A 0007CK Inventory and Inspect Basewide Wells - Year 10 FY29
JB Andrews N/A 0008 Complete Basewide Well Repair (up to 5 wells/year) and
LUC Sign Repair/Replacement (up to 2 signs/year)
JB Andrews N/A 0008CA Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 1
Optional - TBD
JB Andrews N/A 0008CB Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 2
Optional - TBD
JB Andrews N/A 0008CC Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 3
Optional - TBD
JB Andrews N/A 0008CD Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 4
Optional - TBD
JB Andrews N/A 0008CE Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 5
Optional - TBD
JB Andrews N/A 0008CF Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 6
Optional - TBD
JB Andrews N/A 0008CG Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 7
Optional - TBD
JB Andrews N/A 0008CH Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 8
Optional - TBD
JB Andrews N/A 0008CJ Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 9
Optional - TBD
JB Andrews N/A 0008CK Repair Basewide Wells and LUC Sign Repair/Replacement -
Year 10
Optional - TBD
JB Andrews N/A 0009 Complete Well Abandonment
JB Andrews N/A 0009AA Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AB Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AC Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AD Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AE Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AF Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AG Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AH Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AJ Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0009AK Abandon up to 14 wells Optional - TBD
JB Andrews N/A 0010 Complete Tier 1 Meeting Facilitation and Support
JB Andrews N/A 0010CA Support and facilitate Tier 1 Meeting - Year 1 At Award
JB Andrews N/A 0010CB Support and facilitate Tier 1 Meeting - Year 2 FY21
JB Andrews N/A 0010CC Support and facilitate Tier 1 Meeting - Year 3 FY22
JB Andrews N/A 0010CD Support and facilitate Tier 1 Meeting - Year 4 FY23
JB Andrews N/A 0010CE Support and facilitate Tier 1 Meeting - Year 5 FY24
JB Andrews N/A 0010CF Support and facilitate Tier 1 Meeting - Year 6 FY25
JB Andrews N/A 0010CG Support and facilitate Tier 1 Meeting - Year 7 FY26
JB Andrews N/A 0010CH Support and facilitate Tier 1 Meeting - Year 8 2Y27
JB Andrews N/A 0010CJ Support and facilitate Tier 1 Meeting - Year 9 FY28
JB Andrews N/A 0010CJ Support and facilitate Tier 1 Meeting - Year 10 FY29
JB Andrews N/A 0011 Complete Community Surveys and Community Involvement
Plans (CIP) for JB Andrews
JB Andrews N/A 0011CA Conduct Community Surveys for JB Andrews - Year 1 At Award
JB Andrews N/A 0011CB Conduct CIP for JB Andrews - Year 1 Upon
Completion of
0011CA
JB Andrews N/A 0011CC Conduct Community Surveys for JB Andrews - Year 3 FY22
JB Andrews N/A 0011CD Conduct CIP for JB Andrews - Year 3 Upon
Completion of
0011CC
JB Andrews N/A 0011CE Conduct Community Surveys for JB Andrews - Year 5 FY24
JB Andrews N/A 0011CF Conduct CIP for JB Andrews - Year 5 Upon
Completion of
0011CE
JB Andrews N/A 0011CG Conduct Community Surveys for JB Andrews -Year 7 FY26
JB Andrews N/A 0011CH Conduct CIP for JB Andrews - Year 7 Upon
Completion of
0011CG
JB Andrews N/A 0011CJ Conduct Community Surveys for JB Andrews - Year 9 FY28
JB Andrews N/A 0011CK Conduct CIP for JB Andrews - Year 9 Upon
Completion of
0011CJ
JB Andrews N/A 0012 Complete Community Surveys and CIP for Brandywine
DRMO
JB Andrews N/A 0012CA Conduct Community Surveys for Brandywine DRMO - Year
At Award
JB Andrews N/A 0012CB Conduct CIP for Brandywine DRMO - Year 1 Upon
Completion of
0012CA
JB Andrews N/A 0012CC Conduct Community Surveys for Brandywine DRMO - Year
FY22
JB Andrews N/A 0012CD Conduct CIP for Brandywine DRMO - Year 3 Upon
Completion of
0012CC
JB Andrews N/A 0012CE Conduct Community Surveys for Brandywine DRMO - Year
FY24
JB Andrews N/A 0012CF Conduct CIP for Brandywine DRMO - Year 5 Upon
Completion of
0012CE
JB Andrews N/A 0012CG Conduct Community Surveys for Brandywine DRMO - Year
FY26
JB Andrews N/A 0012CH Conduct CIP for Brandywine DRMO - Year 7 Upon
Completion of
0012CG
JB Andrews N/A 0012CJ Conduct Community Surveys for Brandywine DRMO - Year
FY28
JB Andrews N/A 0012CK Conduct CIP for Brandywine DRMO - Year 9 Upon
Completion of
0012CJ
JB Andrews N/A 0013 Complete Community Surveys and CIP for Davidsonville
Transmitter Site
JB Andrews N/A 0013CA Conduct Community Surveys for Davidsonville Transmitter
Site - Year 1
At Award
JB Andrews N/A 0013CB Conduct CIP for Davidsonville Transmitter Site - Year 1 Upon
Completion of
0013CA
JB Andrews N/A 0013CC Conduct Community Surveys for Davidsonville Transmitter
Site - Year 3
FY22
JB Andrews N/A 0013CD Conduct CIP for Davidsonville Transmitter Site - Year 3 Upon
Completion of
0013CC
JB Andrews N/A 0013CE Conduct Community Surveys for Davidsonville Transmitter
Site - Year 5
FY24
JB Andrews N/A 0013CF Conduct CIP for Davidsonville Transmitter Site - Year 5 Upon
Completion of
0013CE
JB Andrews N/A 0013CG Conduct Community Surveys for Davidsonville Transmitter
Site - Year 7
FY26
JB Andrews N/A 0013CH Conduct CIP for Davidsonville Transmitter Site - Year 7 Upon
Completion of
0013CG
JB Andrews N/A 0013CJ Conduct Community Surveys for Davidsonville Transmitter
Site - Year 9
FY28
JB Andrews N/A 0013CK Conduct CIP for Davidsonville Transmitter Site - Year 9 Upon
Completion of
0013CJ
JB Andrews FI346 0014 Achieve ROD and Conduct LTM
JB Andrews FI346 0014AA Achieve Proposed Plan FY22
JB Andrews FI346 0014AB Achieve ROD Upon
Completion of
0014AA
JB Andrews FI346 0014CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
Upon
Completion of
0014AB
JB Andrews FI346 0014CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
1 Year after
0014CA
JB Andrews FI346 0014CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
1 Year after
0014CB
JB Andrews FI346 0014CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
1 Year after
0014CC
JB Andrews FI346 0014CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
1 Year after
0014CD
JB Andrews FI346 0014CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
1 Year after
0014CE
JB Andrews FI346 0014CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
1 Year after
0014CF
JB Andrews FT002 0015 Conduct RA-O and Reduce LCCs
JB Andrews FT002 0015CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1
At Award
JB Andrews FT002 0015CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2
FY21
JB Andrews FT002 0015CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3
FY22
JB Andrews FT002 0015CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4
FY23
JB Andrews FT002 0015CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5
FY24
JB Andrews FT002 0015CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6
FY25
JB Andrews FT002 0015CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7
FY26
JB Andrews FT002 0015CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8
FY27
JB Andrews FT002 0015CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9
FY28
JB Andrews FT002 0015CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC
Summary Report - Year 10
FY29
JB Andrews LF005 0016 Conduct RA-O and Reduce LCCs
JB Andrews LF005 0016AA Abandon up to 7 wells on private property Optional - TBD
JB Andrews LF005 0016CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1
At Award
JB Andrews LF005 0016CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2
FY21
JB Andrews LF005 0016CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3
FY22
JB Andrews LF005 0016CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4
FY23
JB Andrews LF005 0016CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5
FY24
JB Andrews LF005 0016CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6
FY25
JB Andrews LF005 0016CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7
FY26
JB Andrews LF005 0016CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8
FY27
JB Andrews LF005 0016CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9
FY28
JB Andrews LF005 0016CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC
Summary Report - Year 10
FY29
JB Andrews LF006 0017 Conduct IRA-O and RA-O
JB Andrews LF006 0017CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
At Award
JB Andrews LF006 0017CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
FY21
JB Andrews LF006 0017CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
FY22
JB Andrews LF006 0017CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
FY23
JB Andrews LF006 0017CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
FY24
JB Andrews LF006 0017CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
FY25
JB Andrews LF006 0017CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
FY26
JB Andrews LF006 0017CH Maintain Compliance with regulatory requirements and binding agreements - Year 8
FY27
JB Andrews LF006 0017CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9
FY28
JB Andrews LF006 0017CK Maintain Compliance with regulatory requirements and binding agreements - Year 10
FY29
JB Andrews LF007 0018 Conduct IRA-O and RA-O
JB Andrews LF007 0018CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
At Award
JB Andrews LF007 0018CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
FY21
JB Andrews LF007 0018CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
FY22
JB Andrews LF007 0018CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
FY23
JB Andrews LF007 0018CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
FY24
JB Andrews LF007 0018CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
FY25
JB Andrews LF007 0018CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
FY26
JB Andrews LF007 0018CH Maintain Compliance with regulatory requirements and binding agreements - Year 8
FY27
JB Andrews LF007 0018CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9
FY28
JB Andrews LF007 0018CK Maintain Compliance with regulatory requirements and binding agreements - Year 10
FY29
JB Andrews LF581 0019 Achieve Site Closeout
JB Andrews LF581 0019AA Supplemental Remedial Investigation Report Optional - TBD
JB Andrews LF581 0019AB Achieve Feasibility Study Optional - TBD
JB Andrews LF581 0019AC Achieve Proposed Plan Optional - TBD
JB Andrews LF581 0019AD Achieve ROD Optional - TBD
JB Andrews LF581 0019AE Achieve Remedial Design and Remedial Action Work Plan Optional - TBD
JB Andrews LF581 0019AF Achieve Site Closeout Optional - TBD
JB Andrews RR004 0020 Achieve ROD and Conduct LTM
JB Andrews RR004 0020AA Achieve Proposed Plan FY22
JB Andrews RR004 0020AB Achieve ROD Upon
Completion of
0020AA
JB Andrews RR004 0020CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
Upon
Completion of
0020AB
JB Andrews RR004 0020CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
1 Year after
0020CA
JB Andrews RR004 0020CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
1 Year after
0020CB
JB Andrews RR004 0020CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
1 Year after
0020CC
JB Andrews RR004 0020CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
1 Year after
0020CD
JB Andrews RR004 0020CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
1 Year after
0020CE
JB Andrews RR004 0020CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
1 Year after
0020CF
JB Andrews RR348 0021 Achieve ROD and Conduct LTM
JB Andrews RR348 0021AA Achieve Proposed Plan FY22
JB Andrews RR348 0021AB Achieve ROD Upon
Completion of
0021AA
JB Andrews RR348 0021CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
Upon
Completion of
0021AB
JB Andrews RR348 0021CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
1 Year after
0021CA
JB Andrews RR348 0021CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
1 Year after
0021CB
JB Andrews RR348 0021CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
1 Year after
0021CC
JB Andrews RR348 0021CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
1 Year after
0021CD
JB Andrews RR348 0021CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
1 Year after
0021CE
JB Andrews RR348 0021CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
1 Year after
0021CF
JB Andrews SR347 0022 Achieve Site Closeout
JB Andrews SR347 0022AA Achieve Proposed Plan At Award
JB Andrews SR347 0022AB Achieve ROD Upon
Completion of
0022AA
JB Andrews SR347 0022AC Achieve Site Closeout Upon
Completion of
0022AB
JB Andrews SR347A 0023 Achieve Site Closeout
JB Andrews SR347A 0023AA Achieve Proposed Plan At Award
JB Andrews SR347A 0023AB Achieve ROD Upon
Completion of
0023AA
JB Andrews SR347A 0023AC Achieve Site Closeout Upon
Completion of
0023AB
JB Andrews SS001 0024 Conduct RA-O and Reduce LCCs
JB Andrews SS001 0024AA Abandon up to 11 wells on private property and install two replacement wells
Optional - TBD
JB Andrews SS001 0024AB Remove water treatment systems and associated buildings Optional - TBD
JB Andrews SS001 0024AC Complete Environmental Baseline Surveys (EBSs) for access agreements
Optional - TBD
JB Andrews SS001 0024AD Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AE Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AF Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AG Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AH Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AJ Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AK Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AL Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AM Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AN Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AP Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AQ Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AR Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AS Complete EBSs for access agreements Optional - TBD
JB Andrews SS001 0024AT Restore impacted areas Optional - TBD
JB Andrews SS001 0024CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1
At Award
JB Andrews SS001 0024CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2
FY21
JB Andrews SS001 0024CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3
FY22
JB Andrews SS001 0024CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4
FY23
JB Andrews SS001 0024CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5
FY24
JB Andrews SS001 0024CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6
FY25
JB Andrews SS001 0024CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7
FY26
JB Andrews SS001 0024CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8
FY27
JB Andrews SS001 0024CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9
FY28
JB Andrews SS001 0024CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC
Summary Report - Year 10
FY29
JB Andrews SS001 0025 Maintain CSX Right of Way Access
JB Andrews SS001 0025CA Maintain CSX Right of Way Access - Year 1 At Award
JB Andrews SS001 0025CB Maintain CSX Right of Way Access - Year 2 FY21
JB Andrews SS001 0025CC Maintain CSX Right of Way Access - Year 3 FY22
JB Andrews SS001 0025CD Maintain CSX Right of Way Access - Year 4 FY23
JB Andrews SS001 0025CE Maintain CSX Right of Way Access - Year 5 FY24
JB Andrews SS001 0025CF Maintain CSX Right of Way Access - Year 6 FY25
JB Andrews SS001 0025CG Maintain CSX Right of Way Access - Year 7 FY26
JB Andrews SS001 0025CH Maintain CSX Right of Way Access - Year 8 FY27
JB Andrews SS001 0025CJ Maintain CSX Right of Way Access - Year 9 FY28
JB Andrews SS001 0025CK Maintain CSX Right of Way Access - Year 10 FY29
JB Andrews SS011 0026 Conduct RA-O and Reduce LCCs
JB Andrews SS011 0026CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1
At Award
JB Andrews SS011 0026CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2
FY21
JB Andrews SS011 0026CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3
FY22
JB Andrews SS011 0026CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4
FY23
JB Andrews SS011 0026CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5
FY24
JB Andrews SS011 0026CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6
FY25
JB Andrews SS011 0026CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7
FY26
JB Andrews SS011 0026CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8
FY27
JB Andrews SS011 0026CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9
FY28
JB Andrews SS011 0026CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC
Summary Report - Year 10
FY29
JB Andrews SS022 0027 Conduct RA-O
JB Andrews SS022 0027AA Maintain Compliance with regulatory requirements and binding agreements - Year 1
At Award
JB Andrews SS022 0027AB Maintain Compliance with regulatory requirements and binding agreements - Year 2
FY21
JB Andrews SS022 0027AC Maintain Compliance with regulatory requirements and binding agreements - Year 3
FY22
JB Andrews SS022 0027CA Maintain Compliance with regulatory requirements and binding agreements - Year 4
FY23
JB Andrews SS022 0027CB Maintain Compliance with regulatory requirements and binding agreements - Year 5
FY24
JB Andrews SS022 0027CC Maintain Compliance with regulatory requirements and binding agreements - Year 6
FY25
JB Andrews SS022 0027CD Maintain Compliance with regulatory requirements and binding agreements - Year 7
FY26
JB Andrews SS022 0027CE Maintain Compliance with regulatory requirements and binding agreements - Year 8
FY27
JB Andrews SS022 0027CF Maintain Compliance with regulatory requirements and binding agreements - Year 9
FY28
JB Andrews SS022 0027CG Maintain Compliance with regulatory requirements and binding agreements - Year 10
FY29
JB Andrews SS026 0028 Conduct RA-O and Reduce LCCs
JB Andrews SS026 0028AA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1
At Award
JB Andrews SS026 0028AB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2
FY21
JB Andrews SS026 0028AC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3
FY22
JB Andrews SS026 0028AD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4
FY23
JB Andrews SS026 0028CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5
FY24
JB Andrews SS026 0028CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6
FY25
JB Andrews SS026 0028CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7
FY26
JB Andrews SS026 0028CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8
FY27
JB Andrews SS026 0028CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9
FY28
JB Andrews SS026 0028CF Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC
Summary Report - Year 10
FY29
JB Andrews SS028 0029 Achieve Remedy in Place
JB Andrews SS028 0029AA Achieve Remedial Design and Remedial Action Work Plan At Award
JB Andrews SS028 0029AB Achieve Remedy in Place Upon
Completion of
0029AA
JB Andrews SS028 0029CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
Upon
Completion of
0029AB
JB Andrews SS028 0029CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
1 Year after
0029CA
JB Andrews SS028 0029CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
1 Year after
0029CB
JB Andrews SS028 0029CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
1 Year after
0029CC
JB Andrews SS028 0029CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
1 Year after
0029CD
JB Andrews ST008 0030 Conduct LTM
JB Andrews ST008 0030CA Maintain Compliance with Air Force Requirements - Year 1 At Award
JB Andrews ST008 0030CB Maintain Compliance with Air Force Requirements - Year 2 FY21
JB Andrews ST008 0030CC Maintain Compliance with Air Force Requirements - Year 3 FY22
JB Andrews ST008 0030CD Maintain Compliance with Air Force Requirements - Year 4 FY23
JB Andrews ST008 0030CE Maintain Compliance with Air Force Requirements - Year 5 FY24
JB Andrews ST008 0030CF Maintain Compliance with Air Force Requirements - Year 6 FY25
JB Andrews ST008 0030CG Maintain Compliance with Air Force Requirements - Year 7 FY26
JB Andrews ST008 0030CH Maintain Compliance with Air Force Requirements - Year 8 FY27
JB Andrews ST008 0030CJ Maintain Compliance with Air Force Requirements - Year 9 FY28
JB Andrews ST008 0030CK Maintain Compliance with Air Force Requirements - Year 10 FY29
JB Andrews ST010 0031 Achieve Site Closeout
JB Andrews ST010 0031AA Optimize the site in support of achievement of Site Closeout At Award
JB Andrews ST010 0031AB Achieve Response Complete Upon
Completion of
0031AA
JB Andrews ST010 0031AC Optimize the site in support of achievement of Site Closeout Upon
Completion of
0031AB
JB Andrews ST010 0031AD Achieve Site Closeout Upon
Completion of
0031AC
JB Andrews ST010 0031CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
At Award
JB Andrews ST010 0031CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
FY21
JB Andrews ST010 0031CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
FY22
JB Andrews ST010 0031CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
FY23
JB Andrews ST010 0031CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
FY24
JB Andrews ST010 0031CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
FY25
JB Andrews ST010 0031CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
FY26
JB Andrews ST010 0031CH Maintain Compliance with regulatory requirements and binding agreements - Year 8
FY27
JB Andrews ST010 0031CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9
FY28
JB Andrews ST010 0031CK Maintain Compliance with regulatory requirements and binding agreements - Year 10
FY29
JB Andrews ST014 0032 Conduct RA-O and Achieve Alternate Objective
JB Andrews ST014 0032AA Achieve Vapor Intrusion (VI) Investigation UFP-QAPP and
VI Report
At Award
JB Andrews ST014 0032AB Achieve Supplemental Site Investigation Work Plan Optional - TBD
JB Andrews ST014 0032AC Achieve Advanced Site Characterization including
Supplemental Site Investigation, Revised 3-D Conceptual
Site Model, and Updated Groundwater Monitoring Program
Optional - TBD
JB Andrews ST014 0032AE Achieve Remedy Evaluation and Recommendation Report Optional - TBD
JB Andrews ST014 0032AD Achieve ESD or ROD Amendment Optional - TBD
JB Andrews ST014 0032CA Maintain Compliance with regulatory requirements and binding agreements - Year 1
At Award
JB Andrews ST014 0032CB Maintain Compliance with regulatory requirements and binding agreements - Year 2
FY21
JB Andrews ST014 0032CC Maintain Compliance with regulatory requirements and binding agreements - Year 3
FY22
JB Andrews ST014 0032CD Maintain Compliance with regulatory requirements and binding agreements - Year 4
FY23
JB Andrews ST014 0032CE Maintain Compliance with regulatory requirements and binding agreements - Year 5
FY24
JB Andrews ST014 0032CF Maintain Compliance with regulatory requirements and binding agreements - Year 6
FY25
JB Andrews ST014 0032CG Maintain Compliance with regulatory requirements and binding agreements - Year 7
FY26
JB Andrews ST014 0032CH Maintain Compliance with regulatory requirements and binding agreements - Year 8
FY27
JB Andrews ST014 0032CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9
FY28
JB Andrews ST014 0032CK Maintain Compliance with regulatory requirements and binding agreements - Year 10
FY29
JB Andrews TS345 0033 Achieve Site Closeout
JB Andrews TS345 0033AA Achieve Proposed Plan At Award
JB Andrews TS345 0033AB Achieve ROD Upon
Completion of
0033AA
JB Andrews TS345 0033AC Achieve Site Closeout Upon
Completion of
0033AB
JB Andrews TS345A 0034 Achieve Site Closeout
JB Andrews TS345A 0034AA Achieve Proposed Plan At Award
JB Andrews TS345A 0034AB Achieve ROD Upon
Completion of
0034AA
JB Andrews TS345A 0034AC Achieve Site Closeout Upon
Completion of
0034AB
JB Andrews TU167 0035 Achieve Record of Decision
JB Andrews TU167 0035AA Achieve Phase 1 Triad RI Report At Award
JB Andrews TU167 0035AB Achieve Phase 2 RI Report Upon
0035AA
JB Andrews TU167 0035AC Achieve Feasibility Study Upon
0035AB
JB Andrews TU167 0035AD Achieve Proposed Plan Upon
Completion of
0035AC
JB Andrews TU167 0035AE Achieve ROD Upon
Completion of
0035AD
JB Andrews ZZ349 0036 Achieve Site Closeout
JB Andrews ZZ349 0036AA Achieve Proposed Plan At Award
JB Andrews ZZ349 0036AB Achieve ROD Upon
Completion of
0036AA
JB Andrews ZZ349 0036AC Achieve Site Closeout Upon
Completion of
0036AB
JB Andrews ZZ349A 0037 Achieve Site Closeout
JB Andrews ZZ349A 0037AA Achieve Proposed Plan At Award
JB Andrews ZZ349A 0037AB Achieve ROD Upon
Completion of
0037AA
JB Andrews ZZ349A 0037AC Achieve Site Closeout Upon
0037AB
Section C - Descriptions and Specifications
PERFORMANCE WORK STATMENT
PERFORMANCE WORK STATEMENT (PWS)
OPTIMIZED REMEDIATION CONTRACT (ORC)
JOINT BASE ANDREWS, MD
3 SEPTEMBER 2019
1.0 Scope
This requirement is for environmental remediation activities at Joint Base (JB) Andrews. This
Performance Work Statement (PWS) defines the scope of environmental services necessary to conduct site restoration. The range of activities include maintenance of established remedies, implementation of optimization to enhance remedial progress at applicable sites, and achievement of site-specific objectives.
The Contractor shall undertake Environmental Remediation activities to achieve performance objectives
(POs) at 14 Installation Restoration Program (IRP) sites and nine (9) Military Munitions Response
Program (MMRP) sites.
NOTE: For purposes of this ORC, the term “Government” includes the Air Force (AF) and United States
Army Corps of Engineers (USACE). While regulators are a governmental entity, they are also a third party over whom the AF has no control and, as such, will be referred to as “regulators”.
1.1 Introduction
JB Andrews is in Camp Springs, MD, approximately 15 miles southeast of Washington, D.C. The 4,300-acre main Installation includes the runways, aircraft support facilities and the administrative, housing and recreational facilities. Remote facilities include the Brandywine Receiver site, consisting of 1,640 acres, the eight-acre Brandywine Defense Reutilization and Marketing Office (DRMO) with two additional parcels totaling 3.6 acres that were acquired in 2009 by the government to execute the interim groundwater remedy (SS001) and the Davidsonville Receiver site (SS011), consisting of 863 acres. Land use immediately surrounding the Installation is primarily residential and commercial. The mission at JB
Andrews is to provide a secure and robust infrastructure that supports the President, national leadership, mission partner organizations and the well-being of our Joint Team and their families. The facility serves as the home of the Presidential air fleet, including Air Force (AF) One.
Remediation activities at JB Andrews are being conducted pursuant to the Comprehensive Environmental
Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund Amendments and
Reauthorization Act (SARA), and National Oil and Hazardous Substances Contingency Plan (NCP) requirements. Regulatory partners include the United States Environmental Protection Agency (USEPA)
Region 3 and Maryland Department of the Environment (MDE). The Prince George County Health
Department is also involved.
JB Andrews, to include Brandywine DRMO, was placed on the National Priorities List on 10 May 1999.
JB Andrews is being administered under a Federal Facility Agreement (FFA) signed by USEPA on 7
September 2011, and Brandywine DRMO is being administered under an FFA signed by USEPA on 25
November 2009.
1.2 Overview of ORC Scope and Requirements
The Contractor shall perform all the necessary environmental remediation activities required to achieve the POs of this PWS. This PWS and enclosures listed below include requirements of the project to meet the AF objectives:
Enclosure 1 – Acronyms and Definitions
Enclosure 2 – Government Furnished Information (GFI) o Enclosure 2A – Administrative Record Spreadsheet o Enclosure 2B - GFI o Enclosure 2C – Alternate Objective Site Consideration Summary(ies)
Enclosure 3 – Government Furnished Property (GFP)
The AF is required to implement remedies as necessary to enable the mission, protect human health and the environment, and comply with laws and regulations. The goal of the ORC initiative is to ensure the
AF continues to fulfill all facets of its Environmental Restoration Program (ERP) mission, while effectively and efficiently managing the program in a performance-based, results-oriented, and cost-conscious framework. The AF desires all sites be cleaned up to standards that allow for the current or reasonably anticipated future land use of the property. The intent of the ORC initiative is to advance site cleanup during the Period of Performance (POP) in the most efficient and cost-effective manner as supported by a business case analysis that achieves the greatest reduction in life-cycle cost (LCC). The
AF is interested in substantial reduction of long-term environmental liabilities and total LCC. Hand in hand, accurate documentation and reporting of contaminant removal and cost savings are critical adjuncts to optimization success. In keeping with Defense Environmental Restoration Program (DERP) and Air
Force Instruction (AFI) 32-7020, the AF defines optimization, under the ORC, as the reduction of contaminant mass and concentrations, reduction in LCC, or any combination of activities leading to acceleration of Response Complete/Site Closeout (RC/SC), as a result of remedial implementation the
Contractor undertakes, above and beyond what is required to maintain compliance in accordance with an approved Decision Document (DD).
The Contractor shall function as an integral team member in support of the Air Force Civil Engineer
Center (AFCEC) mission to include the sharing of information with USACE, other AFCEC Contractors and AF personnel; and cooperation with community stakeholders, regulators, and other Government entities.
Requirements for efficient management of this contract include, but are not limited to, the achievement of
POs in the Performance Period (PP) per Table 1 of this PWS, and the timely identification and solution of impediments to successful project execution. The Contractor shall provide all personnel, equipment, supplies, tools, materials and other items necessary to perform the tasks defined in this PWS. The
Contractor is solely responsible for reviewing all available information and forming their independent, professional conclusions/interpretations of site conditions and requirements to achieve the POs of this contract within PP specified for each site. AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues during execution of this contract. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. The Contractor shall also comply with installation regulations. Remedies shall conform to environmental permits, DD requirements, or other legal requirements. The Contractor shall continue work throughout the entire duration of the POP.
Site specific POs are identified in Table 1: Performance Table below. POs that are in keeping with standard DERP milestones are defined in Enclosure 1. In addition, for certain categories of sites, the AF has set data-driven POs based on current site conditions in keeping with the POP of the contract and
ORC goal. These POs are Optimized Exit Strategy (OES), Alternate Objectives, and Reduce LCC; these terms are described below.
The PP specified in Table 1 starts from the Obligation Date of the first Sub-Contract Line Item Number
(Sub-CLIN) for the site unless otherwise specified. All approvals (both Government and regulator) per the Performance Standard are required in writing.
1.2.1 Performance Models
The Contractor shall develop performance models for all sites listed in Table 1 of this PWS that do not have a PO of Long Term Management (LTM) and have a remedy planned and/or in place. For all sites proposed to reach RC/SC during the POP, work planning documents shall contain the performance model. Performance models shall describe how site conditions are expected to change over time, using appropriate performance indicators, from current state through PO achievement. The Contractor shall provide monitoring reports, in accordance with the DD, that demonstrate whether the remedial response is progressing and performing consistent with the performance model.
Performance model and site management approach shall include the following:
Develop and document the approach to determine remedial progress relative to the defined performance indicators, associated decision criteria, and objectives consistent with the performance model. The documented approach is expected to facilitate decisions about optimization as well as provide a quantifiable understanding of how the response is progressing, list contingency options, and demonstrate when the objective has been reached. An individual site may have more than one performance model (e.g., different parts of the site that are addressed by separate remedies and represented by different sets of monitoring wells).
Demonstrate an understanding of the site-specific Conceptual Site Model (CSM) as it relates to the operation of existing systems, distribution of contaminates, and remedy effectiveness and degradation rates (see details on the definition of CSM in Section 8.1.3). Update the CSM using
Data Quality Objectives (DQOs) as needed based on performance and monitoring data throughout the performance period and implement remedy contingencies as warranted by the evolving CSM. Submit updated CSMs subsequent to receipt of new information.
Develop an Exit Strategy that identifies and implements opportunities to improve remedy protectiveness, effectiveness, and cost efficiency, and to facilitate progress toward the end goal of the Exit Strategy, including innovative technologies (see details on the Exit Strategy preparation in Section 8.1.4). The goal is to accelerate contaminant reduction thereby minimizing future AF liability and cost to the greatest degree feasible. Update the Exit Strategy as dictated by site progress throughout the PP. Submit updated Exit Strategies subsequent to receipt of new information.
Develop baselines and performance models representative of the extent of contamination being addressed that describe the historic and expected course of the remedial progress (i.e., how conditions are expected to change over time as demonstrated by appropriate performance indicators) from the current baseline state through PO achievement.
Define the baseline state for each contaminant of concern (COC). The baseline state is determined by using select monitoring wells that are representative of the site and with sufficient data to develop statistic-based historic concentration trends for site COCs. A scientific approach that uses a line of best-fit (e.g., first order decay rate) is appropriate for estimating the baseline attenuation rate. The baseline attenuation rate, in turn, can be used to extrapolate a baseline concentration and measures of future performance. Supporting information for the baseline concentrations shall include the rationale for the well selection and the time period used to develop the trends, justification for the selected line of best-fit, actual values used to define the trend, and extension of the line of best-fit to predict values for future years independent of future remedy implementation plans. For additional detail on development of baselines, refer to “Site-
Specific Baseline Development Guidance” version 1, dated July 2019.
Using the baseline as a starting point (above), develop a scientifically-based remedial performance model for each COC. The performance model shall be representative of the contaminant extent being addressed and include performance indicators, decision criteria, and annual and final goals achievable within the performance period. Goals should be consistent with the performance model used to optimize remedial efficiency, quantify how the response is progressing, and demonstrate when the annual and final goals have been achieved. The performance model shall include demonstration of contaminant reduction, process improvement and corrective action level indicators, and process failure and contingency action level indicators that reconcile underperforming remedies when combined with the decision criteria.
1.2.2 Optimized Exit Strategy
NOT APPLICABLE
1.2.3 Alternate Objectives
Table 1 of the PWS identifies Alternate Objectives as the PO for selected sites. These sites have complex attributes that have, to date, inhibited progress towards the achievement of RC. For Alternate Objective sites, as for all sites in Table 1 of the PWS where applicable, the Contractor shall maintain compliance throughout the POP of the contract with all existing regulatory requirements including but not limited to regulations, Federal Facility Agreements, RCRA Permits, final or interim RODs, or other equivalent remedial DDs. The Contractor is responsible for implementing changes to the monitoring program based on activities conducted in the Advanced Site Characterization (PWS Section 1.2.3.1) including the addition and decommissioning of wells in the monitoring well network as agreed by the all parties and the addition of new delineation monitoring where new information indicates our understanding of the plumes is changed.
Based on technical review of existing site conditions/activities, the AF placed sites in the category of
Alternate Objective if one or more of the following conditions exist:
1. Achieving RC is expected to require substantially longer than 30 years;
2. Achieving RC is unattainable with standard characterization and/or existing remediation technology due to technical or other limitations related to site conditions
3. Achieving RC is anticipated to require advanced site characterization technologies to improve the
CSM, determine appropriate remedial technology, and/or characterize recently regulated contaminants.
The AF will use data and information obtained during execution of this PWS to determine restoration potential and future investment strategies at Alternative Objective sites. Each Sub-CLIN for the Alternate
Objective sites will only be awarded if the activities are needed to determine the future investment strategy for the site. The decision to award each Sub-CLIN resides solely at the discretion of the AF.
For each Alternate Objective site, a summary of site-specific considerations is provided as GFI. As with all GFI provided, this GFI is provided for informational purposes only; the Contractor remains responsible for developing their own independent, professional conclusions/interpretation of site conditions and requirements to achieve the PO. The Contractor shall conduct project scoping sessions before work plan development and throughout the planning and execution of the project to meet the PO including the Point(s) of Contact (POC[s]), the AFCEC Program Manager, the AF technical support team, and USACE Contracting Officer’s Representative (COR). Upon approval by the AF and USACE, the Contractor shall participate in scoping sessions with the Regulators, as appropriate.
1.2.3.1 Advanced Site Characterization
Based on existing data, the AF has determined that the existing remedial approaches at the Alternate
Objective sites are not achieving satisfactory remedial progress towards their intended goals.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .