This is a draft solicitation for an optimized remediation contract to support the Joint Base Andrews Environmental Remediation Program. The solicitation seeks a contractor to perform necessary environmental remediation activities to achieve performance objectives at 14 Installation Restoration Program sites and nine Military Munitions Response Program sites. The US Army Corps of Engineers, Baltimore District is the contracting agency and will consider feedback submitted on the draft solicitation by 11:00 AM ET on October 4, 2019 before issuing a final solicitation requesting proposals. The contractor will be required to develop performance models, conduct long-term monitoring, optimize remedies, reduce life cycle costs, achieve various site-specific objectives including proposed plans, records of decision, and site closeouts. The period of performance and performance standards for each site are defined.

JBA ORC Final Solicitation_19OCT19

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 10:00 AM local time 20 Nov 2019

X

A X B X C

D

EX

X G F 187 - 194

195 - 214 H 215 - 231

Leigha.M.Arnold@usace.army.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 231

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

W912DR 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 4 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

Room 00-A-22 conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

LEIGHA M ARNOLD 410-962-0641

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 18

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT

PACKAGING AND MARKING

19 - 161 J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 164 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

165 - 186

PART II - CONTRACT CLAUSES

U.S. ARMY CORPS OF ENGINEERS, BALTIMORE

2 HOPKINS PLAZA

BALTIMORE MD 21201

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

19 Oct 2019

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

W912DR19R0025

Section B - Supplies or Services and Prices

PRICE SCHEDULE

Installation Site CLIN/Sub-

CLIN

Number

CLIN/Sub-CLIN Description Projected Award Date (Pending availability of funding and bona fide need)

N/A N/A 0001 Complete Project Management Plan (PMP) N/A N/A 0001AA Complete PMP Base Year N/A N/A 0001AB Update PMP Optional Task N/A N/A 0001AC Update PMP Optional Task N/A N/A 0002 Complete Quality Assurance Surveillance Plan (QASP) N/A N/A 0002AA Complete QASP Base Year N/A N/A 0002AB Update QASP Optional Task

N/A N/A 0002AC Update QASP Optional Task N/A N/A 0003 Develop Work Breakdown Structure (WBS)/Integrated

Master Schedule (IMS)/Milestone Payment Schedule (MPS) and Update Monthly

N/A N/A 0003CA Develop WBS/IMS/MPS and Update Monthly Base Year N/A N/A 0003CB Update WBS/IMS/MPS Monthly - Year 2 Option Year - FY21 N/A N/A 0003CC Update WBS/IMS/MPS Monthly - Year 3 Option Year - FY22 N/A N/A 0003CD Update WBS/IMS/MPS Monthly - Year 4 Option Year - FY23 N/A N/A 0003CE Update WBS/IMS/MPS Monthly - Year 5 Option Year - FY24 N/A N/A 0003CF Update WBS/IMS/MPS Monthly - Year 6 Option Year - FY25 N/A N/A 0003CG Update WBS/IMS/MPS Monthly - Year 7 Option Year - FY26 N/A N/A 0003CH Update WBS/IMS/MPS Monthly - Year 8 Option Year - FY27 N/A N/A 0003CJ Update WBS/IMS/MPS Monthly - Year 9 Option Year - FY28 N/A N/A 0003CK Update WBS/IMS/MPS Monthly - Year 10 Option Year - FY29

JB

Andrews

N/A 0004 Complete Basewide Quality Program Plans (QPPs)

JB

Andrews

N/A 0004AA Complete Basewide QPP Base Year

JB

Andrews

N/A 0004AB Update Basewide QPP Optional Task

JB

Andrews

N/A 0004AC Update Basewide QPP Optional Task

JB

Andrews

N/A 0005 Update Basewide Conceptual Site Model

JB

Andrews

N/A 0005CA Update Basewide Conceptual Site Model - Year 1 Base Year

JB

Andrews

N/A 0005CB Update Basewide Conceptual Site Model - Year 2 Optional Year - FY21

JB

Andrews

N/A 0005CC Update Basewide Conceptual Site Model - Year 3 Optional Year - FY22

JB

Andrews

N/A 0005CD Update Basewide Conceptual Site Model - Year 4 Optional Year - FY23

JB

N/A 0005CE Update Basewide Conceptual Site Model - Year 5 Optional Year - FY24

JB

Andrews

N/A 0005CF Update Basewide Conceptual Site Model - Year 6 Optional Year - FY25

JB

Andrews

N/A 0005CG Update Basewide Conceptual Site Model - Year 7 Optional Year - FY26

JB

Andrews

N/A 0005CH Update Basewide Conceptual Site Model - Year 8 Optional Year - FY27

JB

Andrews

N/A 0005CJ Update Basewide Conceptual Site Model - Year 9 Optional Year - FY28

JB

Andrews

N/A 0005CK Update Basewide Conceptual Site Model - Year 10 Optional Year - FY29

JB

Andrews

N/A 0006 Update Basewide Land Use Control (LUC) Boundary figures and GIS files

N/A 0006CA Update Basewide LUC Boundary figures and GIS files - Year 1

Base Year

JB

Andrews

N/A 0006CB Update Basewide LUC Boundary figures and GIS files - Year 2

Optional Year - FY21

JB

Andrews

N/A 0006CC Update Basewide LUC Boundary figures and GIS files - Year 3

Optional Year - FY22

JB

Andrews

N/A 0006CD Update Basewide LUC Boundary figures and GIS files - Year 4

Optional Year - FY23

JB

Andrews

N/A 0006CE Update Basewide LUC Boundary figures and GIS files - Year 5

Optional Year - FY24

JB

Andrews

N/A 0006CF Update Basewide LUC Boundary figures and GIS files - Year 6

Optional Year - FY25

JB

Andrews

N/A 0006CG Update Basewide LUC Boundary figures and GIS files - Year 7

Optional Year - FY26

JB

Andrews

N/A 0006CH Update Basewide LUC Boundary figures and GIS files - Year 8

Optional Year - FY27

JB

Andrews

N/A 0006CJ Update Basewide LUC Boundary figures and GIS files - Year 9

Optional Year - FY28

JB

Andrews

N/A 0006CK Update Basewide LUC Boundary figures and GIS files - Year 10

Optional Year - FY29

JB

Andrews

N/A 0007 Complete Basewide Well Inventory/Inspection

JB

Andrews

N/A 0007CA Inventory and Inspect Basewide Wells - Year 1 Base Year

JB

Andrews

N/A 0007CB Inventory and Inspect Basewide Wells - Year 2 Optional Year - FY21

JB

Andrews

N/A 0007CC Inventory and Inspect Basewide Wells - Year 3 Optional Year - FY22

JB

Andrews

N/A 0007CD Inventory and Inspect Basewide Wells - Year 4 Optional Year - FY23

JB

Andrews

N/A 0007CE Inventory and Inspect Basewide Wells - Year 5 Optional Year - FY24

JB

N/A 0007CF Inventory and Inspect Basewide Wells - Year 6 Optional Year - FY25

N/A 0007CG Inventory and Inspect Basewide Wells - Year 7 Optional Year - FY26

JB

Andrews

N/A 0007CH Inventory and Inspect Basewide Wells - Year 8 Optional Year - FY27

JB

Andrews

N/A 0007CJ Inventory and Inspect Basewide Wells - Year 9 Optional Year - FY28

JB

Andrews

N/A 0007CK Inventory and Inspect Basewide Wells - Year 10 Optional Year - FY29

JB

Andrews

N/A 0008 Complete Basewide Well Repair (up to 5 wells/year) and LUC Sign Repair/Replacement (up to 2 signs/year)

N/A 0008CA Repair Basewide Wells and LUC Sign Repair/Replacement - Year 1

Optional Task

JB

Andrews

N/A 0008CB Repair Basewide Wells and LUC Sign Repair/Replacement - Year 2

Optional Task

JB

Andrews

N/A 0008CC Repair Basewide Wells and LUC Sign Repair/Replacement - Year 3

Optional Task

JB

Andrews

N/A 0008CD Repair Basewide Wells and LUC Sign Repair/Replacement - Year 4

Optional Task

JB

Andrews

N/A 0008CE Repair Basewide Wells and LUC Sign Repair/Replacement - Year 5

Optional Task

JB

Andrews

N/A 0008CF Repair Basewide Wells and LUC Sign Repair/Replacement - Year 6

Optional Task

JB

Andrews

N/A 0008CG Repair Basewide Wells and LUC Sign Repair/Replacement - Year 7

Optional Task

JB

Andrews

N/A 0008CH Repair Basewide Wells and LUC Sign Repair/Replacement - Year 8

Optional Task

JB

Andrews

N/A 0008CJ Repair Basewide Wells and LUC Sign Repair/Replacement - Year 9

Optional Task

JB

Andrews

N/A 0008CK Repair Basewide Wells and LUC Sign Repair/Replacement - Year 10

Optional Task

JB

Andrews

N/A 0009 Complete Well Abandonment

JB

Andrews

N/A 0009AA Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AB Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AC Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AD Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AE Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AF Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AG Abandon up to 14 wells Optional Task

JB

N/A 0009AH Abandon up to 14 wells Optional Task

N/A 0009AJ Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0009AK Abandon up to 14 wells Optional Task

JB

Andrews

N/A 0010 Complete Tier 1 Meeting Facilitation and Support

JB

Andrews

N/A 0010CA Support and facilitate Tier 1 Meeting - Year 1 Base Year

JB

Andrews

N/A 0010CB Support and facilitate Tier 1 Meeting - Year 2 Optional Year - FY21

JB

Andrews

N/A 0010CC Support and facilitate Tier 1 Meeting - Year 3 Optional Year - FY22

JB

Andrews

N/A 0010CD Support and facilitate Tier 1 Meeting - Year 4 Optional Year - FY23

JB

Andrews

N/A 0010CE Support and facilitate Tier 1 Meeting - Year 5 Optional Year - FY24

JB

Andrews

N/A 0010CF Support and facilitate Tier 1 Meeting - Year 6 Optional Year - FY25

JB

Andrews

N/A 0010CG Support and facilitate Tier 1 Meeting - Year 7 Optional Year - FY26

JB

Andrews

N/A 0010CH Support and facilitate Tier 1 Meeting - Year 8 Optional Year - FY27

JB

Andrews

N/A 0010CJ Support and facilitate Tier 1 Meeting - Year 9 Optional Year - FY28

JB

Andrews

N/A 0010CJ Support and facilitate Tier 1 Meeting - Year 10 Optional Year - FY29

JB

Andrews

N/A 0011 Complete 1,4 Dioxane sampling in accordance with para.

8.1.1 g. of the PWS

Base Year

JB

Andrews

N/A 0012 Complete Community Surveys and Community Involvement Plans (CIP) for JB Andrews

N/A 0012CA Conduct Community Surveys for JB Andrews - Year 2 Option Year - FY21

JB

Andrews

N/A 0012CB Conduct CIP for JB Andrews - Year 2 Optional Year - Upon Completion of 0012CA

JB

Andrews

N/A 0012CC Conduct Community Surveys for JB Andrews - Year 4 Option Year - FY23

JB

Andrews

N/A 0012CD Conduct CIP for JB Andrews - Year 4 Optional Year - Upon Completion of 0012CC

JB

Andrews

N/A 0012CE Conduct Community Surveys for JB Andrews - Year 6 Option Year - FY25

JB

Andrews

N/A 0012CF Conduct CIP for JB Andrews - Year 6 Optional Year - Upon Completion of 0012CE

JB

Andrews

N/A 0012CG Conduct Community Surveys for JB Andrews -Year 8 Option Year - FY27

JB

Andrews

N/A 0012CH Conduct CIP for JB Andrews - Year 8 Optional Year - Upon Completion of 0012CG

JB

Andrews

N/A 0013 Complete Community Surveys and CIP for Brandywine

DRMO

N/A 0013CA Conduct Community Surveys for Brandywine DRMO - Year 2

Option Year - FY21

JB

Andrews

N/A 0013CB Conduct CIP for Brandywine DRMO - Year 2 Option Year - Upon Completion of 0013CA

JB

Andrews

N/A 0013CC Conduct Community Surveys for Brandywine DRMO - Year 4

Option Year - FY23

JB

Andrews

N/A 0013CD Conduct CIP for Brandywine DRMO - Year 4 Option Year - Upon Completion of 0013CC

JB

Andrews

N/A 0013CE Conduct Community Surveys for Brandywine DRMO - Year 6

Option Year - FY25

JB

Andrews

N/A 0013CF Conduct CIP for Brandywine DRMO - Year 6 Option Year - Upon Completion of 0013CE

JB

Andrews

N/A 0013CG Conduct Community Surveys for Brandywine DRMO - Year 8

Option Year - FY27

JB

Andrews

N/A 0013CH Conduct CIP for Brandywine DRMO - Year 8 Option Year - Upon Completion of 0013CG

JB

Andrews

N/A 0014 Complete Community Surveys and CIP for Davidsonville Transmitter Site

N/A 0014CA Conduct Community Surveys for Davidsonville Transmitter Site - Year 2

Option Year - FY21

JB

Andrews

N/A 0014CB Conduct CIP for Davidsonville Transmitter Site - Year 2 Option Year - Upon Completion of 0014CA

JB

Andrews

N/A 0014CC Conduct Community Surveys for Davidsonville Transmitter Site - Year 4

Option Year - FY23

JB

Andrews

N/A 0014CD Conduct CIP for Davidsonville Transmitter Site - Year 4 Option Year - Upon Completion of 0014CC

JB

Andrews

N/A 0014CE Conduct Community Surveys for Davidsonville Transmitter Site - Year 6

Option Year - FY25

JB

Andrews

N/A 0014CF Conduct CIP for Davidsonville Transmitter Site - Year 6 Option Year - Upon Completion of 0014CE

JB

Andrews

N/A 0014CG Conduct Community Surveys for Davidsonville Transmitter Site - Year 8

Option Year - FY27

JB

Andrews

N/A 0014CH Conduct CIP for Davidsonville Transmitter Site - Year 8 Option Year - Upon Completion of 0014CG

JB

Andrews

FI346 0015 Achieve ROD and Conduct LTM

JB

Andrews

FI346 0015AA Achieve Proposed Plan Option Year - FY22

JB

Andrews

FI346 0015AB Achieve ROD Option Year - Upon Completion of 0015AA

JB

Andrews

FI346 0015CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Option Year - Upon Completion of 0015AB

JB

Andrews

FI346 0015CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - 1 Year after

0015CA

JB

Andrews

FI346 0015CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - 1 Year after

0015CB

FI346 0015CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - 1 Year after

0015CC

JB

Andrews

FI346 0015CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - 1 Year after

0015CD

JB

Andrews

FI346 0015CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - 1 Year after

0015CE

JB

Andrews

FI346 0015CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - 1 Year after

0015CF

JB

Andrews

FT002 0016 Conduct RA-O and Reduce LCCs

JB

Andrews

FT002 0016CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1

Base Year

JB

Andrews

FT002 0016CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2

Option Year - FY21

JB

Andrews

FT002 0016CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3

Option Year - FY22

JB

Andrews

FT002 0016CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4

Option Year - FY23

JB

Andrews

FT002 0016CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5

Option Year - FY24

JB

Andrews

FT002 0016CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6

Option Year - FY25

JB

Andrews

FT002 0016CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7

Option Year - FY26

JB

Andrews

FT002 0016CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8

Option Year - FY27

JB

Andrews

FT002 0016CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9

Option Year - FY28

JB

Andrews

FT002 0016CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC Summary Report - Year 10

Option Year - FY29

JB

Andrews

LF005 0017 Conduct RA-O and Reduce LCCs

JB

Andrews

LF005 0017AA Abandon up to 7 wells on private property Optional Task

JB

Andrews

LF005 0017CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1

Base Year

JB

Andrews

LF005 0017CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2

Option Year - FY21

JB

Andrews

LF005 0017CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3

Option Year - FY22

JB

Andrews

LF005 0017CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4

Option Year - FY23

JB

Andrews

LF005 0017CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5

Option Year - FY24

JB

Andrews

LF005 0017CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6

Option Year - FY25

LF005 0017CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7

Option Year - FY26

JB

Andrews

LF005 0017CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8

Option Year - FY27

JB

Andrews

LF005 0017CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9

Option Year - FY28

JB

Andrews

LF005 0017CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC Summary Report - Year 10

Option Year - FY29

JB

Andrews

LF006 0018 Conduct IRA-O and RA-O

JB

Andrews

LF006 0018CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Base Award

JB

Andrews

LF006 0018CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - FY21

JB

Andrews

LF006 0018CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - FY22

JB

Andrews

LF006 0018CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - FY23

JB

Andrews

LF006 0018CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - FY24

JB

Andrews

LF006 0018CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - FY25

JB

Andrews

LF006 0018CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - FY26

JB

Andrews

LF006 0018CH Maintain Compliance with regulatory requirements and binding agreements - Year 8

Option Year - FY27

JB

Andrews

LF006 0018CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9

Option Year - FY28

JB

Andrews

LF006 0018CK Maintain Compliance with regulatory requirements and binding agreements - Year 10

Option Year - FY29

JB

Andrews

LF007 0019 Conduct IRA-O and RA-O

JB

Andrews

LF007 0019CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Base Year

JB

Andrews

LF007 0019CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - FY21

JB

Andrews

LF007 0019CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - FY22

JB

Andrews

LF007 0019CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - FY23

JB

Andrews

LF007 0019CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - FY24

JB

Andrews

LF007 0019CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - FY25

JB

Andrews

LF007 0019CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - FY26

JB

Andrews

LF007 0019CH Maintain Compliance with regulatory requirements and binding agreements - Year 8

Option Year - FY27

LF007 0019CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9

Option Year - FY28

JB

Andrews

LF007 0019CK Maintain Compliance with regulatory requirements and binding agreements - Year 10

Option Year - FY29

JB

Andrews

LF581 0020 Achieve Site Closeout

JB

Andrews

LF581 0020AB Achieve Feasibility Study Optional Task

JB

Andrews

LF581 0020AC Achieve Proposed Plan Optional Task

JB

Andrews

LF581 0020AD Achieve ROD Optional Task

JB

Andrews

LF581 0020AE Achieve Remedial Design and Remedial Action Work Plan

Optional Task

JB

Andrews

LF581 0020AF Achieve Site Closeout Optional Task

JB

Andrews

RR004 0021 Achieve ROD and Conduct LTM

JB

Andrews

RR004 0021AA Achieve Proposed Plan Option Year - FY22

JB

Andrews

RR004 0021AB Achieve ROD Option Year - Upon Completion of 0021AA

JB

Andrews

RR004 0021CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Option Year - Upon Completion of 0021AB

JB

Andrews

RR004 0021CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - 1 Year after

0021CA

JB

Andrews

RR004 0021CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - 1 Year after

0021CB

JB

Andrews

RR004 0021CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - 1 Year after

0021CC

JB

Andrews

RR004 0021CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - 1 Year after

0021CD

JB

Andrews

RR004 0021CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - 1 Year after

0021CE

JB

Andrews

RR004 0021CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - 1 Year after

0021CF

JB

Andrews

RR348 0022 Achieve ROD and Conduct LTM

JB

Andrews

RR348 0022AA Achieve Proposed Plan Option Year - FY22

JB

Andrews

RR348 0022AB Achieve ROD Option Year - Upon Completion of 0022AA

JB

Andrews

RR348 0022CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Option Year - Upon Completion of 0022AB

JB

Andrews

RR348 0022CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

0022CA

RR348 0022CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - 1 Year after

0022CB

JB

Andrews

RR348 0022CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - 1 Year after

0022CC

JB

Andrews

RR348 0022CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - 1 Year after

0022CD

JB

Andrews

RR348 0022CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - 1 Year after

0022CE

JB

Andrews

RR348 0022CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - 1 Year after

0022CF

JB

Andrews

SR347 0023 Achieve Site Closeout

JB

Andrews

SR347 0023AA Achieve Proposed Plan Base Year

JB

Andrews

SR347 0023AB Achieve ROD Option Year - Upon Completion of 0023AA

JB

Andrews

SR347 0023AC Achieve Site Closeout Option Year - Upon Completion of 0023AB

JB

Andrews

SR347A 0024 Achieve Site Closeout

JB

Andrews

SR347A 0024AA Achieve Proposed Plan Base Year

JB

Andrews

SR347A 0024AB Achieve ROD Option Year - Upon Completion of 0024AA

JB

Andrews

SR347A 0024AC Achieve Site Closeout Option Year - Upon Completion of 0024AB

JB

Andrews

SS001 0025 Conduct RA-O and Reduce LCCs

JB

Andrews

SS001 0025AA Abandon up to 11 wells on private property and install two replacement wells

Optional Task

JB

Andrews

SS001 0025AB Remove water treatment systems and associated buildings

Optional Task

JB

Andrews

SS001 0025AC Complete Environmental Baseline Surveys (EBSs) for access agreements

Optional Task

JB

Andrews

SS001 0025AD Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AE Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AF Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AG Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AH Complete EBSs for access agreements Optional Task

JB

SS001 0025AJ Complete EBSs for access agreements Optional Task

SS001 0025AK Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AL Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AM Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AN Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AP Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AQ Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AR Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AS Complete EBSs for access agreements Optional Task

JB

Andrews

SS001 0025AT Repave impacted pavement Optional Task

JB

Andrews

SS001 0025CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1

Base Award

JB

Andrews

SS001 0025CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2

Option Year - FY21

JB

Andrews

SS001 0025CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3

Option Year - FY22

JB

Andrews

SS001 0025CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4

Option Year - FY23

JB

Andrews

SS001 0025CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5

Option Year - FY24

JB

Andrews

SS001 0025CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6

Option Year - FY25

JB

Andrews

SS001 0025CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7

Option Year - FY26

JB

Andrews

SS001 0025CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8

Option Year - FY27

JB

Andrews

SS001 0025CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9

Option Year - FY28

JB

Andrews

SS001 0025CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC Summary Report - Year 10

Option Year - FY29

JB

Andrews

SS001 0026 Maintain CSX Right of Way Access

JB

Andrews

SS001 0026CA Maintain CSX Right of Way Access - Year 1 Base Year

JB

Andrews

SS001 0026CB Maintain CSX Right of Way Access - Year 2 Option Year - FY21

JB

Andrews

SS001 0026CC Maintain CSX Right of Way Access - Year 3 Option Year - FY22

JB

SS001 0026CD Maintain CSX Right of Way Access - Year 4 Option Year - FY23

SS001 0026CE Maintain CSX Right of Way Access - Year 5 Option Year - FY24

JB

Andrews

SS001 0026CF Maintain CSX Right of Way Access - Year 6 Option Year - FY25

JB

Andrews

SS001 0026CG Maintain CSX Right of Way Access - Year 7 Option Year - FY26

JB

Andrews

SS001 0026CH Maintain CSX Right of Way Access - Year 8 Option Year - FY27

JB

Andrews

SS001 0026CJ Maintain CSX Right of Way Access - Year 9 Option Year - FY28

JB

Andrews

SS001 0026CK Maintain CSX Right of Way Access - Year 10 Option Year - FY29

JB

Andrews

SS011 0027 Conduct RA-O and Reduce LCCs

JB

Andrews

SS011 0027CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1

Base Year

JB

Andrews

SS011 0027CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2

Option Year - FY21

JB

Andrews

SS011 0027CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3

Option Year - FY22

JB

Andrews

SS011 0027CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4

Option Year - FY23

JB

Andrews

SS011 0027CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5

Option Year - FY24

JB

Andrews

SS011 0027CF Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6

Option Year - FY25

JB

Andrews

SS011 0027CG Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7

Option Year - FY26

JB

Andrews

SS011 0027CH Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8

Option Year - FY27

JB

Andrews

SS011 0027CJ Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9

Option Year - FY28

JB

Andrews

SS011 0027CK Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC Summary Report - Year 10

Option Year - FY29

JB

Andrews

SS022 0028 Conduct RA-O

JB

Andrews

SS022 0028AA Maintain Compliance with AF and regulatory requirements and binding agreements - Year 1

Base Year

JB

Andrews

SS022 0028AB Maintain Compliance withAF and regulatory requirements and binding agreements - Year 2

Option Year - FY21

JB

Andrews

SS022 0028AC Maintain Compliance with AF and regulatory requirements and binding agreements - Year 3

Option Year - FY22

JB

Andrews

SS022 0028CA Maintain Compliance with AF and regulatory requirements and binding agreements - Year 4

Option Year - FY23

JB

Andrews

SS022 0028CB Maintain Compliance with AF and regulatory requirements and binding agreements - Year 5

Option Year - FY24

JB

Andrews

SS022 0028CC Maintain Compliance with AF and regulatory requirements and binding agreements - Year 6

Option Year - FY25

SS022 0028CD Maintain Compliance with AF and regulatory requirements and binding agreements - Year 7

Option Year - FY26

JB

Andrews

SS022 0028CE Maintain Compliance with AF and regulatory requirements and binding agreements - Year 8

Option Year - FY27

JB

Andrews

SS022 0028CF Maintain Compliance with AF and regulatory requirements and binding agreements - Year 9

Option Year - FY28

JB

Andrews

SS022 0028CG Maintain Compliance with AF and regulatory requirements and binding agreements - Year 10

Option Year - FY29

JB

Andrews

SS026 0029 Conduct RA-O and Reduce LCCs

JB

Andrews

SS026 0029AA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 1

Base Year

JB

Andrews

SS026 0029AB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 2

Option Year - FY21

JB

Andrews

SS026 0029AC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 3

Option Year - FY22

JB

Andrews

SS026 0029AD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 4

Option Year - FY23

JB

Andrews

SS026 0029CA Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 5

Option Year - FY24

JB

Andrews

SS026 0029CB Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 6

Option Year - FY25

JB

Andrews

SS026 0029CC Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 7

Option Year - FY26

JB

Andrews

SS026 0029CD Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 8

Option Year - FY27

JB

Andrews

SS026 0029CE Maintain Compliance with regulatory requirements and binding agreements, and Reduce LCCs - Year 9

Option Year - FY28

JB

Andrews

SS026 0029CF Maintain Compliance with regulatory requirements and binding agreements, and complete the Reduce LCC Summary Report - Year 10

Option Year - FY29

JB

Andrews

SS028 0030 Achieve Remedy in Place

JB

Andrews

SS028 0030AA Achieve Remedial Design and Remedial Action Work Plan

Base Year

JB

Andrews

SS028 0030AB Achieve Remedy in Place Option Year - Upon Completion of 0030AA

JB

Andrews

SS028 0030CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Option Year - Upon Completion of 0030AB

JB

Andrews

SS028 0030CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - 1 Year after

0030CA

JB

Andrews

SS028 0030CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - 1 Year after

0030CB

JB

Andrews

SS028 0030CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - 1 Year after

0030CC

JB

Andrews

SS028 0030CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

0030CD

ST008 0031 Conduct LTM

JB

Andrews

ST008 0031CA Maintain Compliance with Air Force Requirements - Year 1

Base Year

JB

Andrews

ST008 0031CB Maintain Compliance with Air Force Requirements - Year 2

Option Year - FY21

JB

Andrews

ST008 0031CC Maintain Compliance with Air Force Requirements - Year 3

Option Year - FY22

JB

Andrews

ST008 0031CD Maintain Compliance with Air Force Requirements - Year 4

Option Year - FY23

JB

Andrews

ST008 0031CE Maintain Compliance with Air Force Requirements - Year 5

Option Year - FY24

JB

Andrews

ST008 0031CF Maintain Compliance with Air Force Requirements - Year 6

Option Year - FY25

JB

Andrews

ST008 0031CG Maintain Compliance with Air Force Requirements - Year 7

Option Year - FY26

JB

Andrews

ST008 0031CH Maintain Compliance with Air Force Requirements - Year 8

Option Year - FY27

JB

Andrews

ST008 0031CJ Maintain Compliance with Air Force Requirements - Year 9

Option Year - FY28

JB

Andrews

ST008 0031CK Maintain Compliance with Air Force Requirements - Year 10

Option Year - FY29

JB

Andrews

ST010 0032 Achieve Site Closeout

JB

Andrews

ST010 0032AA Optimize the site in support of achievement of Site Closeout

Base Year

JB

Andrews

ST010 0032AB Achieve Response Complete Option Year - Upon Completion of 0032AA

JB

Andrews

ST010 0032AC Optimize the site in support of achievement of Site Closeout

Option Year - Upon Completion of 0032AB

JB

Andrews

ST010 0032AD Achieve Site Closeout Option Year - Upon Completion of 0032AC

JB

Andrews

ST010 0032CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Base Year

JB

Andrews

ST010 0032CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - FY21

JB

Andrews

ST010 0032CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - FY22

JB

Andrews

ST010 0032CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - FY23

JB

Andrews

ST010 0032CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - FY24

JB

Andrews

ST010 0032CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - FY25

JB

Andrews

ST010 0032CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - FY26

JB

Andrews

ST010 0032CH Maintain Compliance with regulatory requirements and binding agreements - Year 8

Option Year - FY27

ST010 0032CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9

Option Year - FY28

JB

Andrews

ST010 0032CK Maintain Compliance with regulatory requirements and binding agreements - Year 10

Option Year - FY29

JB

Andrews

ST014 0033 Conduct RA-O and Achieve Alternate Objective

JB

Andrews

ST014 0033AA Achieve Vapor Intrusion (VI) Investigation UFP-QAPP and VI Report

Base Year

JB

Andrews

ST014 0033AB Achieve Supplemental Site Investigation Work Plan Optional Task

JB

Andrews

ST014 0033AC Achieve Advanced Site Characterization including Supplemental Site Investigation, Revised 3-D Conceptual Site Model, and Updated Groundwater Monitoring Program

Optional Task

JB

Andrews

ST014 0033AE Achieve Remedy Evaluation and Recommendation Report

Optional Task

JB

Andrews

ST014 0033AD Achieve ESD or ROD Amendment Optional Task

JB

Andrews

ST014 0033CA Maintain Compliance with regulatory requirements and binding agreements - Year 1

Base Award

JB

Andrews

ST014 0033CB Maintain Compliance with regulatory requirements and binding agreements - Year 2

Option Year - FY21

JB

Andrews

ST014 0033CC Maintain Compliance with regulatory requirements and binding agreements - Year 3

Option Year - FY22

JB

Andrews

ST014 0033CD Maintain Compliance with regulatory requirements and binding agreements - Year 4

Option Year - FY23

JB

Andrews

ST014 0033CE Maintain Compliance with regulatory requirements and binding agreements - Year 5

Option Year - FY24

JB

Andrews

ST014 0033CF Maintain Compliance with regulatory requirements and binding agreements - Year 6

Option Year - FY25

JB

Andrews

ST014 0033CG Maintain Compliance with regulatory requirements and binding agreements - Year 7

Option Year - FY26

JB

Andrews

ST014 0033CH Maintain Compliance with regulatory requirements and binding agreements - Year 8

Option Year - FY27

JB

Andrews

ST014 0033CJ Maintain Compliance with regulatory requirements and binding agreements - Year 9

Option Year - FY28

JB

Andrews

ST014 0033CK Maintain Compliance with regulatory requirements and binding agreements - Year 10

Option Year - FY29

JB

Andrews

TS345 0034 Achieve Site Closeout

JB

Andrews

TS345 0034AA Achieve Proposed Plan Base Year

JB

Andrews

TS345 0034AB Achieve ROD Option Year - Upon Completion of 0034AA

JB

Andrews

TS345 0034AC Achieve Site Closeout Option Year - Upon Completion of 0034AB

JB

TS345A 0035 Achieve Site Closeout

TS345A 0035AA Achieve Proposed Plan Base Year

JB

Andrews

TS345A 0035AB Achieve ROD Option Year - Upon Completion of 0035AA

JB

Andrews

TS345A 0035AC Achieve Site Closeout Option Year - Upon Completion of 0035AB

JB

Andrews

TU167 0036 Achieve Record of Decision

JB

Andrews

TU167 0036AA Achieve Phase 1 Triad RI Report Base Year

JB

Andrews

TU167 0036AB Achieve Phase 2 RI Report Option Year - Upon Completion of 0036AA

JB

Andrews

TU167 0036AC Achieve Feasibility Study Option Year - Upon Completion of 0036AB

JB

Andrews

TU167 0036AD Achieve Proposed Plan Option Year - Upon Completion of 0036AC

JB

Andrews

TU167 0036AE Achieve ROD Option Year - Upon Completion of 0036AD

JB

Andrews

ZZ349 0037 Achieve Site Closeout

JB

Andrews

ZZ349 0037AA Achieve Proposed Plan Base Year

JB

Andrews

ZZ349 0037AB Achieve ROD Option Year - Upon Completion of 0037AA

JB

Andrews

ZZ349 0037AC Achieve Site Closeout Option Year - Upon Completion of 0037AB

JB

Andrews

ZZ349A 0038 Achieve Site Closeout

JB

Andrews

ZZ349A 0038AA Achieve Proposed Plan Base Year

JB

Andrews

ZZ349A 0038AB Achieve ROD Option Year - Upon Completion of 0038AA

JB

Andrews

ZZ349A 0038AC Achieve Site Closeout Option Year - Upon Completion of 0038AB

Section C - Descriptions and Specifications

PERFORMANCE WORK STATMENT

PERFORMANCE WORK STATEMENT (PWS)

OPTIMIZED REMEDIATION CONTRACT (ORC)

JOINT BASE ANDREWS (JBA), MD

17 SEPTEMBER 2019

1.0 SCOPE

This requirement is for environmental remediation activities at Joint Base (JB) Andrews. This Performance Work Statement (PWS) defines the scope of environmental services necessary to conduct site restoration. The range of activities include maintenance of established remedies, implementation of optimization to enhance remedial progress at applicable sites, and achievement of site-specific objectives.

The Contractor shall undertake Environmental Remediation activities to achieve performance objectives (POs) at 14 Installation Restoration Program (IRP) sites and nine (9) Military Munitions Response Program (MMRP) sites.

NOTE: For purposes of this ORC, the term “Government” includes the Air Force (AF) and United States Army Corps of Engineers (USACE). While regulators are a governmental entity, they are also a third party over whom the AF has no control and, as such, will be referred to as “regulators”.

1.1 Introduction

JB Andrews is in Camp Springs, MD, approximately 15 miles southeast of Washington, D.C. The 4,300-acre main Installation includes the runways, aircraft support facilities and the administrative, housing and recreational facilities. Remote facilities include the Brandywine Receiver site, consisting of 1,640 acres, the eight-acre Brandywine Defense Reutilization and Marketing Office (DRMO) with two additional parcels totaling 3.6 acres that were acquired in 2009 by the government to execute the interim groundwater remedy (SS001) and the Davidsonville Receiver site (SS011), consisting of 863 acres. Land use immediately surrounding the Installation is primarily residential and commercial. The mission at JB Andrews is to provide a secure and robust infrastructure that supports the President, national leadership, mission partner organizations and the well-being of our Joint Team and their families. The facility serves as the home of the Presidential air fleet, including Air Force (AF) One.

Remediation activities at JB Andrews are being conducted pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund Amendments and Reauthorization Act (SARA), and National Oil and Hazardous Substances Contingency Plan (NCP) requirements. Regulatory partners include the United States Environmental Protection Agency (USEPA) Region 3 and Maryland Department of the Environment (MDE). The Prince George County Health Department is also involved.

JB Andrews, to include Brandywine DRMO, was placed on the National Priorities List on 10 May 1999.

JB Andrews is being administered under a Federal Facility Agreement (FFA) signed by USEPA on 7 September 2011, and Brandywine DRMO is being administered under an FFA signed by USEPA on 25 November 2009.

1.2 Overview of ORC Scope and Requirements

The Contractor shall perform all the necessary environmental remediation activities required to achieve the POs of this PWS. This PWS and enclosures listed below include requirements of the project to meet the AF objectives:

Enclosure 1 – Acronyms and Definitions Enclosure 2 – Government Furnished Information (GFI) o Enclosure 2A – Administrative Record Spreadsheet o Enclosure 2B – GFI o Enclosure 2C – Alternate Objective Site Consideration Summary(ies)

Enclosure 3 – Government Furnished Property (GFP)

The AF is required to implement remedies as necessary to enable the mission, protect human health and the environment, and comply with laws and regulations. The goal of the ORC initiative is to ensure the AF continues to fulfill all facets of its Environmental Restoration Program (ERP) mission, while effectively and efficiently managing the program in a performance-based, results-oriented, and cost-conscious framework. The AF desires all sites be cleaned up to standards that allow for the current or reasonably anticipated future land use of the property. The intent of the ORC initiative is to advance site cleanup during the Period of Performance (POP) in the most efficient and cost-effective manner as supported by a business case analysis that achieves the greatest reduction in life-cycle cost (LCC). The AF is interested in substantial reduction of long-term environmental liabilities and total LCC. Hand in hand, accurate documentation and reporting of contaminant removal and cost savings are critical adjuncts to optimization success. In keeping with Defense Environmental Restoration Program (DERP) and Air Force Instruction (AFI) 32-7020, the AF defines optimization, under the ORC, as the reduction of contaminant mass and concentrations, reduction in LCC, or any combination of activities leading to acceleration of Response Complete/Site Closeout (RC/SC), as a result of remedial implementation the Contractor undertakes, above and beyond what is required to maintain compliance in accordance with an approved Decision Document (DD).

The Contractor shall function as an integral team member in support of the Air Force Civil Engineer Center (AFCEC) mission to include the sharing of information with USACE, other AFCEC Contractors and AF personnel; and cooperation with community stakeholders, regulators, and other Government entities.

Requirements for efficient management of this contract include, but are not limited to, the achievement of POs in the Performance Period (PP) per Table 1 of this PWS, and the timely identification and solution of impediments to successful project execution. The Contractor shall provide all personnel, equipment, supplies, tools, materials and other items necessary to perform the tasks defined in this PWS. The Contractor is solely responsible for reviewing all available information and forming their independent, professional conclusions/interpretations of site conditions and requirements to achieve the POs of this contract within PP specified for each site. AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues during execution of this contract. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. The Contractor shall also comply with installation regulations. Remedies shall conform to environmental permits, DD requirements, or other legal requirements. The Contractor shall continue work throughout the entire duration of the POP.

Site specific POs are identified in Table 1: Performance Table below. POs that are in keeping with standard DERP milestones are defined in Enclosure 1. In addition, for certain categories of sites, the AF has set data-driven POs based on current site conditions in keeping with the POP of the contract and

ORC goal. These POs are Optimized Exit Strategy (OES), Alternate Objectives, and Reduce LCC; these terms are described below.

The PP specified in Table 1 starts from the Obligation Date of the first Sub-Contract Line Item Number (Sub-CLIN) for the site unless otherwise specified. All approvals (both Government and regulator) per the Performance Standard are required in writing.

1.2.1 Performance Models

The Contractor shall develop performance models for all sites listed in Table 1 of this PWS that do not have a PO of Long Term Management (LTM) and have a remedy planned and/or in place. For all sites proposed to reach RC/SC during the POP, work planning documents shall contain the performance model. Performance models shall describe how site conditions are expected to change over time, using appropriate performance indicators, from current state through PO achievement. The Contractor shall provide monitoring reports, in accordance with the DD, that demonstrate whether the remedial response is progressing and performing consistent with the performance model.

Performance model and site management approach shall include the following:

Develop and document the approach to determine remedial progress relative to the defined performance indicators, associated decision criteria, and objectives consistent with the performance model. The documented approach is expected to facilitate decisions about optimization as well as provide a quantifiable understanding of how the response is progressing, list contingency options, and demonstrate when the objective has been reached. An individual site may have more than one performance model (e.g., different parts of the site that are addressed by separate remedies and represented by different sets of monitoring wells).

Demonstrate an understanding of the site-specific Conceptual Site Model (CSM) as it relates to the operation of existing systems, distribution of contaminates, and remedy effectiveness and degradation rates (see details on the definition of CSM in Section 8.1.3). Update the CSM using Data Quality Objectives (DQOs) as needed based on performance and monitoring data throughout the performance period and implement remedy contingencies as warranted by the evolving CSM. Submit updated CSMs subsequent to receipt of new information.

Develop an Exit Strategy that identifies and implements opportunities to improve remedy protectiveness, effectiveness, and cost efficiency, and to facilitate progress toward the end goal of the Exit Strategy, including innovative technologies (see details on the Exit Strategy preparation in Section 8.1.4). The goal is to accelerate contaminant reduction thereby minimizing future AF liability and cost to the greatest degree feasible. Update the Exit Strategy as dictated by site progress throughout the PP. Submit updated Exit Strategies subsequent to receipt of new information.

Develop baselines and performance models representative of the extent of contamination being addressed that describe the historic and expected course of the remedial progress (i.e., how conditions are expected to change over time as demonstrated by appropriate performance indicators) from the current baseline state through PO achievement.

Define the baseline state for each contaminant of concern (COC). The baseline state is determined by using select monitoring wells that are representative of the site and with sufficient data to develop statistic-based historic concentration trends for site COCs. A scientific approach that uses a line of best-fit (e.g., first order decay rate) is appropriate for estimating the baseline attenuation rate. The baseline attenuation rate, in turn, can be used to extrapolate a baseline concentration and measures of future performance. Supporting information for the baseline concentrations shall include the rationale for the well selection and the time period used to develop the trends, justification for the selected line of best-fit, actual values used to define the trend, and extension of the line of best-fit to predict values for future years independent of future remedy implementation plans. For additional detail on development of baselines, refer to “Site-Specific Baseline Development Guidance” version 1, dated July 2019.

Using the baseline as a starting point (above), develop a scientifically-based remedial performance model for each COC. The performance model shall be representative of the contaminant extent being addressed and include performance indicators, decision criteria, and annual and final goals achievable within the performance period. Goals should be consistent with the performance model used to optimize remedial efficiency, quantify how the response is progressing, and demonstrate when the annual and final goals have been achieved. The performance model shall include demonstration of contaminant reduction, process improvement and corrective action level indicators, and process failure and contingency action level indicators that reconcile underperforming remedies when combined with the decision criteria.

1.2.2 Optimized Exit Strategy

NOT APPLICABLE

1.2.3 Alternate Objectives

Table 1 of the PWS identifies Alternate Objectives as the PO for selected sites. These sites have complex attributes that have, to date, inhibited progress towards the achievement of RC. For Alternate Objective sites, as for all sites in Table 1 of the PWS where applicable, the Contractor shall maintain compliance throughout the POP of the contract with all existing regulatory requirements including but not limited to regulations, Federal Facility Agreements, RCRA Permits, final or interim RODs, or other equivalent remedial DDs.