Text version

Construction activities are necessary for the removal of tw o underground storage tanks at Rathbun Lake, Centerville in Wapello County, IA.

Work w ill consist of the removal of the underground tanks, concrete pad, pumps, piping, and monitoring system. This w ill also include disposal of w aste materials to include tank sludge, fuel, and impacted soil, if any. This acquisition w ill include backfilling to the existing grade of surrounding area.

CLIN 0001 Removal of Undergound Storage Tanks

Magnitude of projects CLIN 0001- Betw een $25,000.00 and $100,000.00

Points of Contact for this project are:

CONTRACT SPECIALIST: Laura L. Hedrick PHONE: 816-389-3023 E-MAIL: laura.l.hedrick@usace.army.mil PROJECT MANAGER: John P. Pasa PHONE: 816-389-3114 E-MAIL: john.p.pasa@usace.army.mil CONTRACTING OFFICER: John H. Akin PHONE: 816-389-3577 E-MAIL: john.h.akin@usace.army.mil

X

LAURA L HEDRICK (816)389-3023

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

25-Mar-2019

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________26 Apr 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

816-389-2029/2030FAX:TEL: 816-389-3812 TEL: FAX:

W912DQ19B1007 42

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912DQ19B1007

Section 00 01 10 - Table of Contents

CAUTION PAGE

BEFORE SIGNING AND MAILING YOUR BID, please take note of the following, as failure to perform any one of these actions may cause your bid to be rejected.

1. AMENDMENTS: Have you acknowledged receipt of ALL Amendments? If in doubt as to number of amendments issued, please contact our office.

2. SEALED BIDS: Sealed envelopes containing bids shall be marked to show the bidder’s name and address, the solicitation number, amendments received, and the date and time bids are due.

3. AMENDED BID PAGES: If any of the Amendments furnished amended bid pages, the amended bid pages must be used in submitting your bid.

4. LATE BIDS: In order for a late mailed bid to be considered, generally it must have been sent by either registered or certified mail not later than 5 calendar days before the receipt of bids date.

5. BID GUARANTEE: Sufficient bid guarantee in proper form must be furnished with your bid, if your bid exceeds $150,000.

6. MISTAKE IN BID: Have you reviewed your bid prices for possible errors in calculations or work left out?

7. FACSIMILE BIDS AND MODIFICATIONS: Will not be considered. Facsimile withdrawals will be considered.

8. BUY AMERICAN ACT: All bidders are cautioned that, prior Government conduct notwithstanding, the Contractor's selection of a domestic construction material which would require the subsequent selection of a foreign construction material for compatibility is not a justification for waiver of the Buy American Act. It is the Contractor's responsibility to verify, prior to submitting the materials for approval, which each system can be built to meet the contract specifications without the use of foreign construction materials.

9. BOLLING FEDERAL BUILDING ENHANCED SECURITY.

Due to enhanced security in the Bolling Federal Building, the Bid Opening will be in the Dogwood Room, Ground Floor, and will open 30 minutes prior to bid opening and will remain open until all bids are opened and read. If bids are hand-delivered, you must be aware of enhanced security requirements in effect in the Federal Building and allow for extra time to clear security. You must have a valid picture ID in order to enter the building. No additional time will be allowed due to security requirements. Security Personnel may require you to be escorted to the room holding the bid opening. Person(s) attending the bid opening, will no longer be allowed to remain on Corps of Engineers floors (4, 5 & 6) other than in the Bid Opening Room. The Bid Opening Room is available to all persons delivering bids or attending the bid opening. Please ensure that the solicitation number and title of project appear or can be identified on the outside of bid package. Bidders may wait in the Federal Building cafeteria on the Ground level or outside the building. Under The Federal Acquisition Regulations bids cannot be accepted after the time set for bid opening. Therefore, to ensure your bid is not late, all bidders are encouraged to complete their bids prior to arrival at the Bid Opening Room.

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Drawings

Section 00 10 00 - Solicitation

SCOPE OF WORK

DESCRIPTION OF WORK AND GENERAL REQUIREMENTS

1. DESCRIPTION OF WORK:

1.1. General Description:

1.1.1 The Contractor shall complete removal of two underground storage tanks, 1000 gallon Diesel and 1000 Gallon Unleaded Fuel tanks, at Rathbun Lake (Centerville, IA) to include all concrete, pumps, piping, and monitoring system. Tank material is STI-P3, 10 gauge, type 1 double wall tanks. Disposal or recycling of all materials will be the contractor’s responsibility.

Contractor shall provide all site preparation, materials (unless otherwise noted as supplied by Government), equipment, and labor necessary to meet the requirements of the scope of work.

1.2. Location: Rathbun Project Office

U.S. Army Corps of Engineers 20112 Hwy J5T, Centerville, IA 52544-9461

1.2.1 Points of Contact: John Pasa

john.p.pasa@usace.army.mil 816-389-3114

Phillip Brown Phillip.h.brown@usace.army.mil 816-389-3108

1.3. Work Hours: The standard work day is 7:30am to 4:30pm Monday thru Friday, excluding Federal holidays. Work hours may be adjusted with approval of Contracting Officer Representative (COR) or Operations Project Manager.

2. PRINCIPAL FEATURES: The work to be performed will include, but not be limited to, the following principal features:

2.1. Underground Storage Tank (UST) Removal

2.1.1 Existing conditions: The UST removal site is located within a fenced compound at the USACE project/maintenance compound. The site is located near an asphalt parking lot, but does not connect to the concrete to be removed, there is an approximate 4 feet space between.

2.2 Site Remediation:

2.2.1 Complete remediation of the site to include removal of pumps, piping, and associated concrete (16’x 29’ pad), disposal of all waste materials to include tank sludge, fuel, impacted soil around the tanks and pumps. Max depth of excavation is estimated to be no greater than 12 feet.

During excavation the contractor shall monitor any changes to soil or sand that surrounds the UST’s that displays signs of contamination. If contamination is present the COR is required to be notified to verify the quantity removed. Contractor shall include a line item for disposal of contaminated soil at a per 55 gallon barrel quantity. All waste materials must be disposed of in accordance with Iowa Department of Natural Resources (IDNR) approved procedures and at an approved facility.

2.2.2 Backfill of tank excavation will be completed with lake provided material, (POC will provide the material location), backfill material must be compacted into excavation with excavator bucket, and ground surface is to be level and approximately 4 inches below existing grade. Backfill must be placed in lifts not exceeding 12 inches and at a minimum be bucket compacted, to limit settling of fill materials. Compaction will be tight enough so that no more than 1 inch imprint from a rubber tired machine will be present after driven across.

2.2.3 An approximate layer of 4 inch class A gradation material (lake provided, POC will provide material location) will be used to tie in the excavated area to existing grade. Contractor will be required to transport and place all material. Finish grade of the excavation will match existing grade of surrounding area. Work area is to be returned to equal or better shape than prior to the project beginning. Area may be crowned vertically with additional material no more than 2 inches, starting at the center of the backfill sloping out to the 4 sides of the perimeter. The additional material will allow for additional settling.

2.2.4 The current electrical system is not to be damaged or removed. The current electrical system will be repurposed for the above ground storage tanks.

2.3 Plans and Documentation

2.3.1 Contractor Daily Written and Photographic Documentation Contractor shall submit daily logs of work conducted. Contractor may use own form for documentation. Photos of all phases of the project are required and shall be submitted to John Pasa in .jpeg formatting upon job completion. Each photo shall have a time date stamp. It is recommended that daily logs are submitted on a daily basis.

2.3.2 Contractor may use own form for documentation. The following information must be included:

Date Equipment Used Total hours worked that day Contractor Name Precipitation Controversial Matters Weather description Methods Used Miscellaneous Remarks Air temperature Work completed that day Size of crew Problems encountered

2.4 Coordination with Iowa Department of Natural Resources (IDNR)

2.4.1 Per IDNR procedures for tank closure, the Contractor will submit Form 542-1308 to IDNR, 30 calendar days prior to commencing actual tank removal. The exact date and time of the removal must be provided to the appropriate district office at least three working days prior to the on-site activity proceeding. An environmental assessment (EA) is required for all buried tank removal sites. An EA consultant must provide required information/documentation to IDNR. http://www.iowadnr.gov/Environmental-Protection/.

2.4.2 Underground Storage Tank Closure:

2.4.2.1 Contractor shall follow the IDNR UST removal regulations in accordance to 567 IAC, chapters 120 and 135, applicable OSHA regulations and specifications of Iowa DOT 2537. A closure notice form and a closure report form must be submitted at the appropriate times per IDNR by the contractor. All IDNR closure procedures must be adhered to, IDNR closure procedures http://www.iowadnr.gov/Environmental-Protection/Land-Quality/Underground- Storage-Tanks/UST-Owners-Operators/Tank-Closure-Information. Contractor shall provide copies of all forms submitted to and received from IDNR to John Pasa, Centerville, IA.

2.5 Site Plans/Photos and Site Visits:

Contractors are encouraged to schedule a site visit prior to bidding on this contract. John Pasa (816-389-3114) can be contacted to schedule a site visit. Existing site pictures, installation pictures, and installation diagrams are included in attached Rathbun UST Removal Drawing Section file.

Attachment file titled “Rathbun UST Removal Drawing Section” include the following:

Pic. 1 - Jobsite looking east Dra. 2 - Shop Drawings Pic. 2 - Jobsite looking south Pic. 5 - General Location Pic. 3 - Jobsite looking west Pic. 6 - Rathbun Project House Pic. 4 - Original installation Pic. 7 - UST Location Dra. 1 - Shop Drawings

2.6 Occupancy of Premise

Before work is started, it is the contractor’s responsibility to arrange with Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors and stairways.

2.7 Construction Process Plan

Construction Plan shall include all of the following:

2.7.1 A plan clearly indicating areas of work and description of the work to be completed. Description of work must include processes for demolition, excavation, backfill and final grading.

2.7.2 A time line/schedule of the construction from start to completion.

2.7.3 Material Removal and disposal plan. This plan shall contain all plans and list of state approved landfills.

2.7.4 Submit a testing and remediation plan for the disposal of hazardous material.

2.7.5 The construction process plan shall be submitted for approval prior to work being started.

2.7.6 A plan to minimize the amount of waste that will be placed into a landfill, by either recycling or reutilizing.

2.8 Submittals

Once submittals are received the government has 10 working days for review and acceptance.

2.8.1 Preconstruction Submittals

2.8.1.1 Hazardous Material Testing Plan

2.8.1.2 Construction Process Plan

2.8.1.3 Environmental Hazard Mitigation Plan

2.8.1.4 Material, Delivery, Storage and Placement Plan

2.8.1.5 Disposal of Demolition Materials Plan

2.8.1.6 Testing and Remediation Plan for Hazardous Material

2.8.1.7 Quality Control Plan

2.8.1.8 Daily Log Format

2.8.1.9 Project Schedule

2.8.1.10 All forms for Iowa Department of Natural Resources for Underground Storage Tank for Closeout

2.8.1.11 Waste Diversion/Recycling Plan

2.8.2 Closeout Submittals

2.8.2.1 Daily Reports

2.8.2.2 Photographic Documentation

2.8.2.3 Disposal of Hazard Waste Documentation

2.8.2.4 All forms associated with the Iowa Department of Natural Resources for Underground Storage Tank for Closeout.

2.8.3 All submittals (one copy of each) shall be sent electronically or hard copy to the following:

Primary Contact: Alternate Contact:

U.S. Army Corps of Engineers U.S. Army Corps of Engineers Rathbun Lake Rathbun Lake Attn: John Pasa Attn: Phillip Brown 20112 Hwy J5T, 20112 Hwy J5T, Centerville, IA 52544-9461 Centerville, IA 52544-9461

Fax: 641-647-2888 Fax: 641-647-2888 Email: john.p.pasa@usace.army.mil Email: phillip.h.brown@usace.army.mil

3. SEQUENCE OF WORK:

3.1 Contractor shall coordinate scheduling (minimum of five working days’ notice prior to mobilizing) and the construction sequence with project personnel to minimize interference and allow for planning/coordination by project staff.

4. FIELD MEASUREMENTS: The Contractor shall verify all measurements at the project site and shall be responsible for all dimensions, fittings, and the proper installation of all materials and equipment specified.

5. PERMITS: The Contractor shall be responsible for obtaining any required permit.

5.1. Hot Work Permit: The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of this contract.

6. SAFETY REQUIRMENTS:

6.1. Protection from Hazards: During progress of work, the Contractor shall protect all personnel, whether Government or civilian, from any and all safety hazards caused by the construction operations.

6.2. Traffic Control: Contractor shall provide all temporary signs and markers as necessary to maintain safety in the worksite. All signs shall conform to the latest edition of the Manual of Uniform Control Devices (MUTCD).

6.3. U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS

MANUAL, EM 385-1-1 (2014)

6.3.1 EM 385-1-1 and its changes are available at http://www.hq.usace.army.mil (at the HQ homepage, select Safety and Occupational Health). Select the appropriate manual. The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

2014 Version:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf

6.3.2 Contractor shall prepare a site-specific Accident Prevention Plan (APP). Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for

Accident Prevention Plan". The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written.

6.3.3 An Activity Hazard Analysis must be provided prior to breaking ground. The Activity Hazard Analysis must address all foreseeable safety concerns such as electrical safety, safety zone protection, fall protection, fire safety, personal protective equipment, signage/protective fencing and hazardous material handling.

6.3.4 At least 72 hours prior to any excavation Iowa one-call shall be contacted for utilities clearances.

7. SPECIAL REQUIREMENTS:

7.1. Contractor shall ensure that means of access is not impeded during construction.

8. SECURITY:

8.1. In unoccupied facilities, the Contractor shall be responsible for the security of the facility;

i.e., all exterior doors shall be locked, windows closed and locked, etc.

8.2. The Contractor shall not be on site without prior notification to the Corps of Engineers COR or otherwise designated person(s).

8.3. Contractor personnel shall have valid civilian ID's and Contractor vehicles shall have a valid registration.

8.4. ANTITERRORISM/OPERATION SECURITY REQUIREMENTS

8.4.1 All contractor and all associated sub‐contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

8.4.2 All contractor and all associated sub‐contractors employees will receive a CORPS Watch information paper (provided by the authorized government representative) and provide a written acknowledgement to the COR, no later than 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract.

8.4.3 The Contractor must pre‐screen candidates using the E‐verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E‐verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 business days after the initial contract award.

8.4.4 Per the E-Verify Website the following exemptions apply:

Employers whose contracts are exempt from the E-Verify federal contractor rule are not required to enroll in E-Verify. A contract is considered exempt if any one of the following applies: (1) It is for fewer than 120 days. (2) It is valued at less than $150,000, the simplified acquisition threshold (Source: http://www.uscis.gov/e-verify/federal-contractors/exemptions-and-exceptions).

8.4.5 All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

9. APPLICABLE PUBLICATIONS: The publications referenced herein shall be the most recent at the time of solicitation.

10. WORKSITE HOUSEKEEPING:

10.1. The Contractor shall remove all trash and disposal material from the worksite before the end of each day. The Contractor shall take all possible precautions to maintain the work site, at all times, in a condition that will prevent damage or injury to person or property, Government or otherwise. The above precautions shall include protection from weather conditions. The Contractor shall be responsible for all damages caused by the negligent acts or omissions of his employees, sub-contractors, or agents during Contract performance.

10.2. Materials to be used within 1 week of delivery and scrap material to be used as work progresses shall not be required to be in screened area. However, all such items shall be placed in an orderly manner (i.e. dirt, rock, etc., in piles and stackable items such as pipe, brick, lumber, etc., stacked off the ground on pallets in an orderly manner).

11. RESPONSIBLITY FOR DAMAGE

11.1. Damage to Personal Property: The Contractor shall be solely responsible for all damage to Government and occupant personal property caused by the Contractors' personnel, subcontractors, his agents, or by the performance of his work.

11.2. Damage by Negligence: Damage resulting in gas leaks, electrical outages, loss of heat during cold weather, water leaks, unsecured facilities, weather damage, or oil/hazardous waste spills shall be responded to by the Contractor within 2 hours and repaired within one workday. If the Contractor fails to comply with these requirements, the Government reserves the right to repair the damage and charge the cost to the Contractor. Contractor shall protect all areas through which he will be transporting demolition debris or construction materials. Any damaged turf, sidewalks, roads, vegetation, site amenities, etc, shall be replaced or repaired by the Contractor prior to final Contract closeout.

12. DISPOSAL OF MATERIALS: All materials removed and not reused or designated as salvage material in this project shall become the property of the Contractor, unless otherwise specified, and shall be the Contractor's responsibility for lawful disposal.

12.1. All other wastes generated during Contractor operations shall be disposed of by the Contractor at his/her expense.

12.1.1. Solid wastes (excluding clearing debris) shall be placed in containers which are emptied on a regular schedule. Handling, storage, and disposal shall be conducted to prevent contamination. Segregation measures shall be employed so that no hazardous or toxic waste will become co-mingled with solid waste. The Contractor shall transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal. A Subtitle D RCRA permitted landfill shall be the minimum acceptable off-site solid waste disposal option. The Contractor shall verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate. The Contractor shall comply with Federal, State, and local laws and regulations pertaining to the use of landfill areas.

12.1.2. Wastes classified as hazardous wastes under the Resource Conservation and Recovery Act shall be disposed of, unless otherwise specified in this contract. No hazardous waste shall be disposed of without prior review of the disposal documents, and the approval of the Contracting Officer and the Directorate of Public Works Environmental Coordinator, or his designated representative. The Contractor shall provide an original copy of the disposal document from the approved EPA or State permitted disposal facility for each shipment of hazardous waste generated in this project to the Contracting Officers Representative.

12.1.3 If contaminated soil is found, the contractor will submit a written proposal for the removal and disposal of the contaminated materials. A cubic yard disposal line item will be included in the bid package. This must include all required hazardous material disposal permits and utilization of an Iowa DNR approved disposal site. Special Waste authorization numbers may be obtained from Iowa DNR (515-725-8337). The cost per cubic yard of contaminated soil removal shall include additional line items for any additional materials not designated in this scope of work.

12.1.4 Unified Facilities Guide Specifications (UFGS) 01572, “Construction and Demolition Waste Management,” indicates the Government policy is to “use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling and reuse.” The Contractor shall make all attempts to divert waste material from landfills in coordination of this guidance.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Removal of Underground Storage Tanks

FFP

The contractor shall furnish all labor and materials required to perform the removal of 2 underground storage tanks at Rathbun Lake Project as defined in the Scope of Work of the contract.

FOB: Destination

NET AMT

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 120 dys. ANP 1 USACE, KANSAS CITY +

PHILIP H. BROWN

RATHBUN PROJECT OFFICE 20112 HWY

J5T

CENTERVILLE IA 52544-8308

641-647-2464 FOB: Destination

966103

Section 00 21 13 - Instructions to Bidders

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-12 Preparation Of Bids APR 1984 52.214-34 Submission Of Offers In The English Language APR 1991 52.215-16 Facilities Capital Cost of Money JUN 2003 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

CLAUSES INCORPORATED BY FULL TEXT

52.214-15 PERIOD FOR ACCEPTANCE OF BIDS (APR 1984)

In compliance with the solicitation, the bidder agrees, if this bid is accepted within 60 calendar days from the date specified in the solicitation for receipt of bids, to furnish any or all items upon which prices are bid at the price set opposite each item, delivered at the designated point(s), within the time specified in the Schedule.

(End of clause)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- April 17th, 2019 @ 10:00 am

(c) Participants will meet at-- Rathbun Lake Project Office 20112 Highway J5t Centerville, IA 52554-8308

SCR_CT_001 FIELD OFFICE OVERHEAD (JUL 2002)

NOTICE TO BIDDERS: For your bid to be responsive, you must declare below the single accounting practice that you apply to contracts to calculate field office overhead for all change orders, modifications and requests for equitable adjustment. Pursuant to Federal Acquisition Regulations (FAR) Parts 31.105(d)(3) and 31.203(d)(1), an accounting practice that varies from modification to modification is not allowable. Select one of the following:

1. TIME DISTRIBUTION BASE FOR A PER DIEM RATE

If you use this practice, see Special Clause “Field Office Overhead Per Diem Rate” _____

2. DIRECT COST DISTRIBUTION BASE FOR A PERCENTAGE MARKUP

If you use this practice, see Special Clause “Field Office Overhead Percentage Markup” _____

3. OTHER ACCOUNTING PRACTICE THAT IS ALLOWABLE _____

UNDER THE FAR AND THAT USES A SINGLE DISTRIBUTION BASE.

If you choose 3, you must describe the accounting practice in sufficient detail below to allow the contracting officer to determine what accounting practice is being utilized by your company and that it complies with the FAR.

FAILURE TO FULLY COMPLY WITH THE ABOVE REQUIREMENT OR, IF ALTERNATIVE 3 IS

DECLARED AND YOUR DESCRIPTION DOES NOT CLEARLY STATE OR DESCRIBE A CONSISTENT

ACCOUNTING PRACTICE USING A SINGLE DISTRIBUTION BASE, WILL BE CAUSE FOR YOUR BID

TO BE REJECTED AS NON-RESPONSIVE.

(End)

SCR_CT_003 FIELD OFFICE OVERHEAD PERCENTAGE MARKUP (JUN 2001)

If any change to the contract issued pursuant to the changes Clause, or otherwise, for which the Government is responsible, causes an increase or decrease in the Contractor’s cost, or in the time required for performance under the contract, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

Under such equitable adjustment, no per diem rate for field office overhead shall be allowed if the Contractor has elected a percentage markup in keeping with its standard accounting practices. In such a case, payment of field office overhead shall be allowed for any change on a percentage markup basis regardless of whether the completion of the contract is or is not extended by reason of the change, except for modifications issued pursuant to the Default Clause. The Contractor shall provide a detailed breakdown of its proposed increase or decrease of costs as required by Contract Clause DFARS 252.236-7000 MODIFICATION OF PROPOSALS – PRICE BREAKDOWN.

SCR_CT_004 FIELD OFFICE OVERHEAD PER DIEM RATE

If any change to the contract, issued pursuant to the Changes Clause or otherwise, for which the Government is responsible, causes an increase or decrease in the Contractor’s cost of, or the time required for, performance under the contract, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.

Under such equitable adjustment, no payment of field office overhead shall be allowed for any changes when the completion of the contract is not extended by reason of the change, except the Contractor may be reimbursed any variable expense it incurs due to the change, provided it can substantiate the variables. The Contractor shall be reimbursed for field office overhead on a per diem basis when the completion of the contract is extended by reason of the change issued under any clause except the Default clause. Equitable adjustment shall be made for the costs that are incurred or are to be incurred due to the change. The Contractor shall provide a detailed breakdown of its proposed increase or decrease of costs as required by Contract Clause DFARS 252.236-7000 MODIFICATION OF

PROPOSALS – PRICE BREAKDOWN.

Section 00 45 00 - Representations and Certifications

52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237120.

(2) The small business size standard is $36,500,000.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

( ) Paragraph (d) applies.

( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2; Prohibition on Contracting with Inverted Domestic Corporations--Representation.

(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225- 5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.]

(i) 52.204-17, Ownership or Control of Offeror.

(ii) 52.204-20, Predecessor of Offeror.

(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.

(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.

(vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA- Designated Products (Alternate I only).

(vii) 52.227-6, Royalty Information.

(A) Basic.

(B) Alternate I.

(viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [ offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

Section 00 70 00 - Conditions of the Contract

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

Section 00 72 00 - General Conditions

52.204-13 System for Award Management Maintenance OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.212-1 Instructions to Offerors--Commercial Items OCT 2018 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.215-17 Waiver of Facilities Capital Cost of Money OCT 1997 52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts

SEP 2013

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

AUG 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.243-4 Changes JUN 2007 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

OCT 2016

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea FEB 2019

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after the notice to proceed. The time stated for completion shall include final cleanup of the premises.

52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR

EXECUTIVE ORDERS--COMMERCIAL ITEMS (JAN 2019)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115- 91).

(3) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(4) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(5) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)

___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).

____ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509).

____ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (June 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

___ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2018) (Pub. L. 109-282) (31 U.S.C. 6101 note).

___ (5) [Reserved]

___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

___ (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Oct 2015) (31 U.S.C. 6101 note).

____ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) (41 U.S.C. 2313).

____ (10) [Reserved]

____ (11)(i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (NOV 2011) (15 U.S.C.

657a).

____ (ii) Alternate I (NOV 2011) of 52.219-3.

____ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2014) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

____ (ii) Alternate I (JAN 2011) of 52.219-4.

____ (13) [Reserved]

X (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2011) (15 U.S.C. 644).

____ (ii) Alternate I (NOV 2011).

____ (iii) Alternate II (NOV 2011).

____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).

____ (ii) Alternate I (Oct 1995) of 52.219-7.

____ (iii) Alternate II (Mar 2004) of 52.219-7.

____ (16) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)).

____ (17)(i) 52.219-9, Small Business Subcontracting Plan…