RFQ # W912CN-20-Q-0006
Fire Suppression Systems – Inspection, Maintenance & Repair Solicitation – Question & Answer 13 Dec 2019
Do you have a list on when those hoods are due for inspection? Are they in different months throughout the year or do you have them serviced all in the same months every year?
Per PWS para. 2.22.3.1.1 (Initial Inspections) and para. 2.22.3.1.2 (Semi-Annual Testing and Maintenance); Contractor shall provide a schedule and required to complete initial inspections of the systems within 90 days after contract start date, and schedule and conduct semi-annual inspections within six months after the initial inspection date.
Incumbent Contractor has performed system inspections at KMC and PTA on the same day. Systems in Oahu were inspected within a period of a month or two. Contractor shall coordinate with the COR and customers to produce an inspection schedule.