About this file
This is a Request for Quotation (RFQ) issued by the Army Contracting Command Detroit Arsenal for a Traversing Mechanism component used in 120mm mortars. The solicitation number is W912CH-25-Q-0101, issued on 26 April 2026, with quotes due by 14 May 2026. This is a 100% small business set-aside under FAR 52.219-6, utilizing NAICS code 332994 (Small Arms, Ordnance, and Ordnance Accessories Manufacturing).
The requirement includes a single one-time buy with 100% option on a Firm Fixed Price basis for Traversing Mechanism (NSN 1015-01-387-0589, Part Number 12901123). The contract includes a First Article Test (FAT) requirement with contractor testing per FAR 52.209-3, with 150 days allowed for FAT submission, 300 days for production without FAT approval. The basic production quantity is 13 units with an unexercised option for an additional 133 units, both due 150 days after award (or 300 days without FAT). Delivery is FOB Destination to SR W0LX Army General Supply DLA Distribution Anniston, Alabama. A Technical Data Package (TDP) with distribution code "D" is available via SAM.gov and requires DD Form 2345 certification for access. The contract requires compliance with MIL-DTL-16232 heavy phosphate coating specifications, MIL-STD-2073-1 military preservation and packing standards, and multiple contract data requirements including engineering change proposals, requests for variance, and acceptance inspection equipment reports. OPSEC training and counterintelligence awareness briefing requirements apply to all contractor personnel. Inspection occurs at origin with acceptance at destination. Proposals must be submitted electronically to ryan.d.nawrocki.civ@army.mil with cc to richard.g.hall64@civ.army.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912CH25Q0101-0001.pdf | ||
| Attachment 0002 - FAT Waiver Worksheet.pdf | ||
| Attachment 0001 - Attachment A CUI 2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of
(This is NOT an Order)
1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating
See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)
See Schedule
7. Delivery
FOB Other Destination
5B. For Information Call: (Name and telephone no.) (No collect calls)
8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)
See Schedule
10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.
Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.
11. Schedule (Include applicable Federal, State, and local taxes)
Item Number (a)
Supplies/Services (b)
Quantity (c)
Unit (d)
Unit Price (e)
Amount (f)
(See Schedule)
12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage
NOTE: Additional provisions and representations are are not attached.
13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation
16. Signer
a. Name (Type or Print) b. Telephone
Area Code
c. Title (Type or Print) Number
AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)
X
W912CH-25-Q-0101 2026APR14 DOA4
W912CHACC-DTA
6501 E. 11 MILE RD.
DETROIT ARSENAL, MI 48397-5000
RYAN D. NAWROCKI (520)687-3764
CCTA-APS-C
EMAIL: RYAN.D.NAWROCKI.CIV@ARMY.MIL
X
2026MAY14
1 44
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SUPPLEMENTAL INFORMATION
Buyer Name: RYAN D. NAWROCKI
Buyer Office Symbol/Telephone Number: CCTA-APS-C/(520)687-3764
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
Weapon System: Mortar, 120mm
*** End of Narrative A0000 ***
A.1 DESCRIPTION OF THE ACTION
A.1.1 This solicitation is intended to result in the award of a single one-time buy with 100% option Firm Fixed Price (FFP) contract for
Traversing Mechanism, National Stock Number (NSN) 1015-01-387-0589, Part Number (PN) 12901123.
A.1.2 This solicitation is a 100% set aside for small businesses in accordance with (IAW) Federal Acquisition Regulation (FAR) 52.219-6.
A.1.3 There is a Technical Data Package (TDP) associated with this procurement. The TDP distribution code is "D" which limits access to
U.S. Government agencies and its contractors. Please refer to Section C.2 for additional information.
A.1.4 Offerors shall follow Section L for Instructions, Conditions, and Notices to Offerors for proposal submission and Section M for
Evaluation Factors.
A.2 SOLICITATION STRUCTURE
A.2.1 The Government will utilize North American Industry Classification System (NAICS) code 332994 Small Arms, Ordnance, and Ordnance
Accessories Manufacturing for this procurement.
A.2.2 Failure to register in the System for Award Management (SAM) for the corresponding NAICS code identified in paragraph A.2.1 prior to submitting a proposal for this solicitation may preclude an award made to your company. Offerors should be award of how U.S. Small
Business (SB) concerns are defined in FAR Part 19, Defense Federal Acquisition Regulation Supplement (DFARS) part 219, and 13 CFR 121
Small Business Size Regulations. Offerors are advised to review 13 CFR 121.103 How does SBA determine affiliation, if applicable to this solicitation.
A.2.3 All proposals received in response to this solicitation shall remain valid for a minimum of 120 calendar days.
A.3 ELECTRONIC CONTRACTING
A.3.1 All Army Contracting Command Detroit Arsenal solicitations will be publicized on the System for Award Management website
(https://www.sam.gov). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.
A.3.2 Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Governments intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the
Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.
A.3.3 Interested offerors shall submit a proposal via email to the Contract Specialist ryan.d.nawrocki.civ@army.mil and cc the corresponding Secondary Contract Specialist richard.g.hall64@civ.army.mil with the subject header: Proposal Submission W912CH-25-Q-0101
(company name). Once a proposal is received, the Contract Specialist/Contracting Officer will reply with the respective Offeror stating receipt of proposal submission.
arA.3.4 Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, to be received by the Government office designated in the solicitation by the time specified.
A.3.5 Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.
2 44
W912CH-25-Q-0101
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
A.3.6 Solicitations may remain posted on www.SAM.gov after the solicitation closing date.
A.3.7 Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. All questions regarding the requirements of this solicitation and applicable attachments must be submitted by 28 APR 2026
1:00 PM EST to ryan.d.nawrocki.civ@army.mil and richard.g.hall64@civ.army.mil . The Government will review all questions received but is not obligated to answer questions submitted after the date noted above prior to the solicitation close date. For technical assistance in doing business with the Government, and doing business electronically, please visit the Procurement Technical Assistance Center
(PTAC) website at http://www.aptac-us.org/ to locate a regional center.
A.4 ACKNOWLEDGEMENT OF AMENDMENTS
Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:
Amendment Number: Date:
A.5 DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE
A.5.1 This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act
(Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
A.5.2 To be eligible to gain access to this export controlled TDP (via SAM.gov) an offeror must have a current DD 2345, Militarily
Critical Technical Data Agreement certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, contractors must submit a DD Form 2345 to the United States (U.S.)/Canada Joint Certification Office (JCO), along with a copy of supporting documentation. DD Form 2345 and instructions can be found on the Joint Certification Program website at:
http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP.aspx Processing time is estimated at six (6) to ten (10) weeks after receipt. Upon receipt of certification, an offeror may request the TDP in accordance with the solicitation's
Section C Technical Data Package instructions.
A.5.3 Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed.
A.5.4 Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the
TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
A.6 ARMY CONTRACTING COMMAND DETROIT ARSENAL OMBUSPERSON
A.6.1 Information regarding the Ombudsperson for this contract is located at the following website:
https://www.tacom.army.mil/ombudsperson . (Best viewed using Google Chrome or Microsoft Edge)
A.7 ALL OR NONE
A.7.1 Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.
A.7.1.1 ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.
A.7.1.2 OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL BE DEEMED NONRESPONSIVE.
*** END OF NARRATIVE A0001 ***
3 44
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SUPPLIES OR SERVICES AND PRICES/COSTS
0001 TRAVERSING MECHANISM
0001AA FIRST ARTICLE TEST REPORT (FATR) $ ________________________________ __________________
SERVICE REQUESTED: TRAVERSING MECHANISM
FIRST ARTICLE TEST (FAT) - CONTRACTOR, PURSUANT TO
THE REQUIREMENTS LISTED IN:
SECTION E:
- E.2, Supplemental Requirements to First Article
Approval (Contractor Testing);
SECTION I:
- FAR 52.209-3 (ALT I and ALT II), First Article
Approval-Contractor Testing
DELIVERY SCHEDULE:
Please refer to F.1 for delivery schedule requirements.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Destination
Deliveries or Performance _________________________
0002 TRAVERSING MECHANISM
NSN: 1015-01-387-0589
Mfr CAGE: 19206
Mfr Part Number: 12901123
0002AA PRODUCTION QUANTITY 13 EA $ $ _____________________ ______________ __________________
COMMODITY NAME: TRAVERSING MECHANISM
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: EH4C0335EH PRON AMD: 03
AMS CD: SM2B1100000
Please refer to F.1 for delivery schedule
4 44
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
requirements.
(End of narrative B001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE SECTION D PACKAGING AND MARKING
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W52H094037021V W562RP J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 13 0150
FOB POINT: Destination
SHIP TO:
(W562RP) SR W0LX ARMY GENERAL SUPPLY
DLA DISTRIBUTION ANNISTON
7 FRANKFORD AVE 362
ANNISTON,AL,36201-4199
0003 TRAVERSING MECHANISM
NSN: 1015-01-387-0589
Mfr CAGE: 19206
Mfr Part Number: 12901123
0003AA UNEXERCISED OPTION QUANTITY $ $ ___________________________ ______________ __________________
COMMODITY NAME: TRAVERSING MECHANISM
CLIN CONTRACT TYPE:
Firm Fixed Price
OPTION QUANTITY, PURSUANT TO FAR CLAUSE 52.217-7:
OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED
LINE ITEM.
The quantity stated for option CLIN 0003AA DOES NOT
FORM A PART OF THE BASIC CONTRACTUAL QUANTITY. Part or all of it may, however, be added to the contract at the discretion of the Government, by exercise of the Option clause.
Failure of the offeror to insert a unit price
5 44
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
applicable to the option quantity shall mean the offeror will supply all or any part of the option, if exercised by the Government, AT THE BASIC CONTRACT
UNIT PRICE, and the offer will be evaluated for award accordingly.
Please refer to F.1 for delivery schedule requirements.
(End of narrative B001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE SECTION D PACKAGING AND MARKING
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
FOB POINT: Destination
SHIP TO:
(W562RP) SR W0LX ARMY GENERAL SUPPLY
DLA DISTRIBUTION ANNISTON
7 FRANKFORD AVE 362
ANNISTON,AL,36201-4199
9000 CONTRACTING DATA REQUIREMENTS LIST (CDRL) _________________________________________
A001 ENGINEERING CHANGE PROPOSAL (ECP) 1 LO $ ** NSP ** _________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A001
Engineering Change Proposal (ECP).
(End of narrative B001)
6 44
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A002 REQUEST FOR VARIANCE (RFV) 1 LO $ ** NSP ** __________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A002 Request
For Variance (RFV).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A003 NOTICE OF REVISION (NOR) 1 LO $ ** NSP ** ________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A003 Notice
Of Revision (NOR).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
7 44
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
A004 ACCEPTANCE INSPECTION EQUIPMENT (AIE) REPORT 1 LO $ ** NSP ** ____________________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A004
Acceptance Inspection Equipment (AIE) Report.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A005 TEST PROCEDURE - HEAVY PHOSPHATE COATING 1 LO $ ** NSP ** ________________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A005 Test
Procedure Heavy Phosphate Coating.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A006 START OF WORK MEETING MINUTES 1 LO $ ** NSP ** _____________________________ __________________
8 44
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A006 Start of
Work Meeting Minutes.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A007 CERTIFICATE OF COMPLIANCE 1 LO $ ** NSP ** _________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
The contractor shall prepare and deliver data submissions IAW Exhibit A Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423, A007
Certificate Of Compliance.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
9 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1.1 The contractor shall hold a start of work meeting at its facility, unless some other location is designated in the contract, within 30 days after contract award. The Start of Work Meeting is to assure a clear and mutual understanding of the contract terms, conditions, line items, technical requirements and sequence of events needed for successful execution of the subject contract effort.
The contractor shall participate with the Government to arrange a schedule and agenda for the meeting.
C.1.2 The contractor shall at a minimum invite Government contracting personnel (PCO/Contract Specialist). At the discretion of the PCO, other Government technical personnel may be invited to the meeting: Contracting Officer's Representative (COR) identified in Section G or in an appointment letter; Quality Assurance personnel; DCMA; etc. All Government invitees shall be given at least 14 days advance notice of the time, date, and location of the start of work meeting. The preferred method of notification is by email. The contractor shall provide the Government with minutes of the Start of Work Meeting in accordance with CDRL A006.
C.2 TECHNICAL DATA PACKAGE INFORMATION
The following "X"d item applies to this solicitation:
[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.
[X] 2. The TDP for this solicitation resides within the System for Award Management (SAM) (https://SAM.gov) associated with this solicitation number:
W912CH-25-Q-0101
To access the data through SAM:
a. Log on to the SAM web site: https://SAM.gov.
b. Search for the solicitation number.
c. Click on the attachment you would like to view.
d. If the attachment is restricted, request access to the document.
(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Section 2751 of Title 22, United States
Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 48014852 of Title 50, United States Code).
(2) Further dissemination of the TDP must be in accordance with provisions of DoD Directive 5230.25, DoDI 5230.24, its Distribution
Statement markings, and U.S. export control laws. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
(3) To obtain these TDPs, contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense
Logistics Information Service (DLIS). To obtain certification, go to DD FORM 2345 Instructions and DD 2345.
(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.
Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
e. If technical data is otherwise restricted, select "Request Explicit Access." This will generate an email to the Contract Specialist and Contracting Officer at Army Contract Command - Warren (DTA) with all the information needed to grant contractor access to restricted documents. SAM will automatically generate an email stating when the requesting contractor has permission to view or download TDP items.
f. If multiple individuals in the contractor's organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP.
Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted. Questions related to registration in SAM should be directed to https://www.sam.gov/ The SAM helpdesk phone number is (866) 606-8220. Vendors are responsible for placing correct information in SAM.
g. It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed "Use and Non-
Disclosure Agreement" at the same time if the solicitation requires both to gain access to view the TDP.
C.3 DRAWING LIMITATIONS
C.3.1 The drawings supplied with this contract are not shop or process drawings. The drawings are engineering design drawings, are adequate to permit manufacture, and:
10 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
C.3.1.1 depict the completed (item(s), and
C.3.1.2 serve as the basis for inspection of the completed item(s).
C.3.2 These drawings DO NOT cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if all the dimensions and tolerances specified in the engineering design drawing for each individual part are met, a cumulative unacceptable fit for the contract item could result.
C.3.3 The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the manufacturing process.
C.3.4 The Contractor agrees that he has obtained all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings. The contractor is responsible for having all drawings and specifications. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.
C.3.5 Failure to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, will result in the Contractor being responsible for correcting this condition at no additional cost to the
Government and no delivery schedule extension.
C.4 CONFIGURATION MANAGEMENT DOCUMENTATION
C.4.1 The Contractor may submit Engineering Change Proposals (ECPs), Requests for Variance (RFVs), and Notices of Revision (NORs) for the requirements in the Government-provided Technical Data Package (TDP).
C.4.2 The Configuration Change Management section of SAE EIA-649-1(current revision) Configuration Management Requirement for Defense
Contracts, Paragraph 3.3, shall be used for configuration control of material with the following exclusions: paragraph 3.3(3); the second sentence of paragraph 3.3.1.8.1(1).
C.4.3 Furnished item(s) shall conform to the approved configuration requirements/revision, unless a Request for Variance (RFV) is processed and approved as provided by Paragraph E. below. The term "Request for Variance" includes Requests for Deviations and Waivers.
C.4.4 Value Engineering Change Proposals (VECPs) for cost saving improvements to the TDP should not be processed per SAE EIA-649-1 and should be referred to Section I FAR Clause 52.248-1 - Value Engineering.
C.4.5 All ECPs submitted will be deemed routine. If an ECP is considered as an emergency or urgent; that justification for the rationale shall be included in the ECP submittal with all applicable supporting documentation.
rC.4.6 For ECPs, RFVs, or NORs, the Contractor must submit the documentation listed in sub-paragraphs e (i) through e (iii). Failure to submit a complete legible package may result in return of the ECP/RFV/SCN/NOR without processing.
C.4.6.1 for ECPs, the Contractor shall prepare and deliver the ECP in accordance with (IAW) CDRL A001.
C.4.6.2 for RFVs, the Contractor shall prepare and deliver the RFV IAW CDRL A002.
C.4.6.3 for NORs, the Contractor shall prepare and deliver the NOR IAW CDRL A003.
C.4.7 The Government's acceptance of the data deliverable required by CDRL/DD Form 1423 in e(i)-(iii) above signifies only that the data satisfies the requirements of the DID and is considered acceptable for Government processing. Acceptance of the data deliverable does not signify "technical approval" of the change proposed by the deliverable and should not be interpreted as authorizing the Contractor to proceed with the work proposed by the change. Disposition of the change (approval/disapproval) will follow acceptance of the CDRL at the Government's sole discretion. Incorporation of an approved RFV or ECP will require execution of a contract modification.
C.4.8 The Contractor should direct questions regarding the status of an ECP or RFV to the Procuring Contracting Officer (PCO) and copy the Administrative Contracting Officer (ACO).
C.4.9 The submission of an ECP/RFV/SCN/NOR does not affect the required delivery date of the contract.
C.5 HEAVY PHOSPHATE COATING REQUIREMENT
C.5.1 The following requirements regarding heavy phosphate coatings are applicable to this solicitation and any resultant contract in addition to those requirements set forth in specification MIL-DTL-16232.
C.5.2 Paragraph 3.1 of MIL-DTL-16232 refers to "Preproduction Inspection." The procedure shall be submitted in accordance with the
11 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Contract Data Requirements List (CDRL) contained in the contract. The contract number must be cited on all phosphate coating procedures submitted for review and approval. Procedures shall include product name and manufacturer of all chemicals/materials to be used. All processes, equipment, controls along with testing and test frequencies used for phosphating including application of supplemental finishes shall be described in detail.
C.5.3 Paragraph 3.2.5-c of MIL-DTL-16232 refers to the "Chromic acid rinse, (Classes 1, 2 and 3)." The final rinse shall be checked by a standard free and total acid titration along with a pH reading "prior to starting production and at least every 8 hours thereafter."
C.5.4 Paragraph 4.7.3 of MIL-DTL-16232 refers to "Weight per unit area of phosphate coatings." The frequency for testing coating weight is "per lot, at least every 8 hours."
C.5.5 Paragraph 4.7.5 of MIL-DTL-16232 refers to "Accelerated corrosion resistance." Accelerated corrosion resistance shall be determined in accordance with 4.7.5.1. The frequency for testing accelerated corrosion resistance per ASTM B117 is "per lot, at least every 8 hours."
C.5.6 The "product name" along with the manufacturer of the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure and shall be traceable to the applicable Qualified Products List (QPL) or Qualified Products Database (QPD) at
Assist Online. QPD products may be obtained at the quick search site, type the specification number (i.e., 3150) in the second block and click the "Submit" button. Then click on the specification (i.e., MIL-PRF-3150). In the next screen, click on the word "Qualification".
To obtain MIL Specs, MIL Standards, QPL and QPD products see <https://assist.dla.mil/online/start />.
To obtain MIL Specs, MIL Standards, QPD products see <https://assist.dla.mil/online/start/>.
C.5.7 A thickness range for the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure along with a frequency for testing. A daily frequency is required.
C.5.8 Heat cured dry film lubricant shall be air dried for 1.0 hour (until dry to touch) after dipping/spraying or flash dried at 155-
175 degrees F for 10-30 minutes and then heat cured at a temperature of 375-425 degrees F for 55-65 minutes per paragraph 4.4.2.2 of MIL-
PRF-46010.
C.5.9 Air cure dry film lubricant shall be air dried at room temperature for 24 hours minimum.
C.5.10 Adhesion testing shall be stated in the procedure for a supplemental coating of dry film lubricant per ASTM D2510 or CARC paint per ASTM D3359, method B along with the frequency for testing. A daily frequency is required.
C.5.11 Salt spray testing of parts with phosphate and supplemental dry film lubricant per ASTM B117 for 100 hours shall be stated in the procedure along with the frequency for testing. The frequency for testing is "per lot or weekly." Parts shall show no more than 3 rust spots per 3" x 6" area with none larger than 1.0mm in diameter. Salt spray testing of parts with phosphate and primer per ASTM B117 for
336 hours shall be included in the procedure for supplemental coatings of CARC paint along with a frequency for testing. The frequency for salt spray testing is "per lot or monthly." Parts shall show no visible rust exceeding rust grade no. 9 per ASTM D610, no more than
5 blisters per 4" x 6" area with none larger than 3/64 inch in diameter. Under film attack at the scribe shall not exceed 1/8 inch.
C.5.12 Topcoat color shall be visual/equipment checked against the specified chip no. of SAE AMS-STD-595 per paint batch. The procedure shall include the specified color chip number.
C.5.12.1 Cure of the paint shall be checked daily by solvent wipe per paragraph 4.2.3.2 of MIL-DTL-53072. The manufacturer of the MEK solvent shall be stated in the procedure.
C.6 CONTRACT DATA REQUIREMENTS LIST (CDRL)
C.6.1 The contractor shall prepare the following deliverable reports IAW Exhibit A, Contract Data Requirements List:
A001 ENGINEERING CHANGE PROPOSAL (ECP)
A002 REQUEST FOR VARIANCE (RFV)
A003 NOTICE OF REVISION (NOR)
A004 ACCEPTANCE INSPECTION EQUIPMENT (AIE) REPORT
A005 TEST PROCEDURE HEAVY PHOSPHATE COATING
A006 START OF WORK MEETING MINUTES
A007 CERTIFICATE OF COMPLIANCE
C.7 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN
C.7.1 The contractor is subject to, at a minimum, the provisions of the current TACOM OPSEC Plan, or other approved U.S. Government
OPSEC plan, per AR 530-1, Operations Security. This Plan specifies the government's critical information, why it needs to be protected, 12 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
where it is located, who is responsible for it, and how to protect it.
C.7.2 The contractor will receive a copy of the Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by TACOM G3/G2 or individual organizations supporting AT/OPSEC Officers.
C.7.3 The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is
OPSEC Level I. Reference Attachment 0001 Additional Guidelines for Controlled Unclassified Information (CUI).
C.8 OPSEC TRAINING REQUIREMENT
C.8.1 Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of reporting for duty. All contractor employees must complete annual OPSEC awareness training. OPSEC awareness training is available at:
https://securityawareness.usalearning.gov/opsec/index.htm. Within 10 days of completing the training, the Contractor shall provide certificates/proof of completion to the Contracting Officer's Representative (COR), if assigned to the contract, or the Procuring
Contracting Officer (PCO).
C.9 Counterintelligence Awareness and Reporting (CIAR); formerly known as Threat Awareness Reporting Program (TARP):
C.9.1 Per AR 381-12, all Department of the Army (DA) personnel (Military/Civilian/Contractor) must complete CIAR training within 30 days of assignment or employment to an organization/contract, and then once every 12 months thereafter pursuant to DoDD 5240.06. DA personnel will complete "Counterintelligence Awareness and Reporting for DoD Employees" CI116.16, located at https://www.cdse.edu/, to satisfy most Army annual training requirements.
C.9.1.1 In addition, per AR 381-12 Chapter 5, the following individual(s) must receive an in-person CIAR briefing directly from an ACI
Special Agent or a CI-experienced person in addition to the annual training requirement:
DA personnel scheduled to travel (official, unofficial, permanent change of station) to or through countries with a high foreign intelligence or terrorist threat level as identified by Defense Intelligence Agency or the Department of State, will receive a special
CIAR briefing prior to the travel and will be debriefed upon return. AR 38112 13 June 2025 11
DA personnel who have security clearances travelling to foreign locations in any duty status must fulfill pre-and-post travel security briefing and debriefing requirements in accordance with the DoD Foreign Clearance Guide and DoDD 4500.54E.
DA personnel deploying in support of military exercises or contingency operations will receive a special CIAR briefing prior to departure.
DA personnel taking part in bilateral or multilateral engagements with foreign governments or international organizations will receive a CIAR briefing prior to the event.
Foreign visitors, personnel, and personal connections Commanders will coordinate with unit security managers to identify personnel potentially vulnerable to FIE exploitation and ensure they are referred to ACI to receive specialized CIAR briefing.
Such personnel will receive foreign intelligence threat briefings prior to foreign travel or event.
Personnel with access to Sensitive Compartmented Information and Special Access Programs.
Personnel assigned to or supporting defense critical infrastructure or associated assets, pursuant to DoDD 3020.40 and DoDI 5240.19, will receive an in-person special CIAR briefing on an annual basis. Such personnel will notify their local ACI office of all projected foreign travel or foreign visits.
Foreign government employment. Current and retired DA personnel seeking employment with foreign government entities will have CIAR training and support made available.
Information technology professionals System administrators, privileged users, and those with privileged access that provides an individual capability to alter the properties, behavior, or control of a DoD information system will receive in-person special CIAR briefings on an annual basis.
Professional and educational exchange programs with foreign governments.
These briefings will be tailored to the particular risk or threat involved, including methods the person may use to minimize the risk, and will place special emphasis on reporting responsibilities. Debriefings will be conducted as soon as feasible following completion of travel, duty, or visit to a foreign country, or attendance at a conference with foreign personnel by an ACI Special Agent. Failure to receive training does not relieve individuals from their reporting responsibilities in chapter 4 of this regulation.
C.10 ENGINEERING EXCEPTIONS
13 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Please note that there are Engineering Exemptions applicable to this procurement. The exemptions can be found with the TDP in SAM.gov and will require the same access procedures as access to the TDP.
*** END OF NARRATIVE C0001 ***
PACKAGING AND MARKING
D.1 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS)
D.1.1 Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, and the Special Packaging Instruction, see below.
(1) LEVEL OF PRESERVATION: Military
(2) LEVEL OF PACKING: B
(3) QUANTITY PER UNIT PACKAGE: 001
(4) SPECIAL PACKAGING INSTRUCTION NUMBER. 1290112368
(a) REVISION B
(b) DATE OF REVISION 16 JULY 2024
(c) THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL: N/A
D.1.2 Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.
D.1.3 Marking:
D.1.3.1 In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and as applicable, unitized loads shall be marked in accordance with MIL-STD-129). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel.
D.1.3.2 When an item is assigned a Unique Item Identifier (UII) as indicated by the inclusion of contract clause DFARS 252.211-7003, refer to the DoD Guide to Uniquely Identifying Items (available at: https://www.acq.osd.mil/dpap/pdi/uid/guides.html) for development of the UII and MIL-STD-129 for UII package marking requirements. Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.
D.1.4 Heat Treatment and Marking of Wood Packaging Materials (WPM):
D.1.4.1 In accordance with DOD 4140.65-M and the requirements of the International Standards for Phytosanitary Measures 15 (ISPM), "Regulation of Wood Packaging Material in International Trade," current edition, (hereinafter "ISPM 15"), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging
Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organization's compliance program.
D.1.4.2 Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging
Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:
http://www.alsc.org). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the
14 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
necessary certifications.
D.1.4.3 Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard. The
ALS approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp. Foreign manufacturers shall comply with ISPM -15 and shall have the marking of WPM verified in accordance with their National Plant Protection Organization's compliance program.
D.1.5 Hazardous Materials (As applicable):
D.1.5.1 Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.
(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)
D.1.5.2 Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:
- International Air Transport Association (IATA) Dangerous Goods Regulations
- International Maritime Dangerous Goods Code (IMDG)
- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49
- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO P4030.19(I)/DLAM 4145.3(I) (for military air shipments).
D.1.5.3 If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the
United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers. A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.
D.1.6 This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the
SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to
PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.
D.1.8 SUPPLEMENTAL INSTRUCTIONS: SEE SECTION C.10 FOR CHANGES/UPDATES TO SPI
*** END OF NARRATIVE D0001 ***
INSPECTION AND ACCEPTANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
For FAR clauses: https://www.acquisition.gov/
For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996
2 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984
15 44
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
3 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
Tailored by excluding paragraph(s) 8.3 STO RQ001
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
E.1 USE OF MIL-STD 1916
E.1.2 The Government will not accept lots whose samples submitted for acceptance contain non-conformances unless appropriately documented and approved by the contracting officer. The contractor shall use MIL-STD 1916, DOD Preferred Methods of Acceptance of
Product. The Verification Level (VL) shall be VL -1- for major characteristics and VL -2- for minor characteristics.
E.1.3 MIL-STD HDBK-1916 provides guidance on the use of MIL-STD 1916. This handbook is not contractually binding.
E.2 SUPPLEMENTAL REQUIREMENTS TO FIRST ARTICLE APPROVAL (CONTRACTOR TESTING)
E.2.1 In accordance with the requirements under FAR clause 52.209-3, found in Section I of this document, the first article approval item(s) shall be examined and tested as required by the item specification(s), Quality Assurance Provisions (QAPs) and all drawings listed in the Technical Data Package.
E.2.2 The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.
E.2.3 The first article shall be inspected and tested by the contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:
E.2.3.1 Inspections and tests contained in material specifications provided that the required inspection and tests have been performed within the last year and the results are submitted with the Certificates of Conformance are submitted with the First Article Test
Report.
E.2.3.2 Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.
E.2.3.3 Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the
First Article Test Report.
E.2.3.4 Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the
First Article Test Report.
E.2.3.5 Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the contractor's facility and certifications are submitted with the First Article Test Report.
E.2.4 Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.
E.2.5 A First Article Test Report shall be compiled by the contractor documenting the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The First Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and QAP requirement and identified by each…