Amend0001-W912C324B0001-NewPaving IDIQ -20240507.pdf
PDF 286 KB Posted
- Solicitation number
- W912C324B0001
About this file
This document is an amendment to a solicitation for an Indefinite Delivery/Indefinite Quantity (IDIQ) construction contract for paving and sustainable infrastructure work at Fort Buchanan, Puerto Rico. The key details are:
The amendment extends the bid opening date to May 17, 2024 and provides answers to questions received from potential offerors. It clarifies various aspects of the solicitation, including the use of milled material, required permits, paving fabric requirements, and the need to submit a bid bond. The solicitation is a 100% small business set-aside with a NAICS code of 237310 and a size standard of $45 million. The magnitude of the overall requirement is between $5-10 million. Offerors must submit pricing for all contract line items and are cautioned to ensure their mathematical calculations are accurate. Bids can be hand-delivered or mailed, but must be received by the specified date and time. A site visit is not contemplated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a.The purpose of this amendment is for the follow ing:
1. To add received Questions and Answ ers to this solicitation.
2. Extend the Bid Opening date and time to: 17 May 2024; 10:00 am Puerto Rico time
b. All other terms and conditions remain unchanged.
See Page Tw o
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912C324B0001
X 9B. DATED (SEE ITEM 11)
10-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-May-2024
CODE
MICC - FT BUCHANAN
FT BUCHANAN
DIRECTORATE OF CONTRACTING
34 SOUTH GATE RD, STE 1104
FORT BUCHANAN PR 00934-4206
W912C3 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912C324B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
QUESTIONS AND ANSWERS
Question 1: Due to the nature of the contract (Fixed‐Firm Price IDIQ Type) and not knowing specifically the location in which anyone delivery order will be executed, should an MOT be required, there is no ELIN provided with costs and description under Attachment 1, LINE ITEMS.
Answer 1: The Government consider Movement of Traffic (MOT) costs as project incidentals per delivery order. Those costs shall be included in your proposal on ELIN required, if required.
Note: Contract will be a firm‐fixed price. Therefore, after award no increases will be made to the contract because the contractor omitting materials or work necessary for the specific ELIN.
Question 2: Drawing PS‐1, Full Depth (New Construction), indicates installation of “Geotextile Separation Fabric”. However, ELIN 0001AE‐0001AG states “installation of 6 mil polyurethan sheets.” Please confirm the “Geotextile Separation Fabric” intended in PS‐1 is the “installation of 6 mil polyurethan sheets.”
Answer 2: Confirmed. the “Geotextile Separation Fabric” intended in PS‐1 is the “installation of 6 mil polyurethan sheets.”
Question 3: Please confirm whether or not for all related work at Fort Buchanan, contractor will be allowed to use removed material resulting from the cold milling work as part of the federal recycling program at the Garrison.
Answer 3: Section 32 01 16.71, paragraph 3.10 ‐ REMOVAL OF MILLED MATERIAL indicates ‐ Material that is removed will become the property of the Contractor and removed from the site.
The milled material which means Asphalt removed material (scarification/milling) shall not be used for backfill (Contractor will need to remove from site).
Question 4: Under ELIN 0001AU, 0001AV, 0001AW it states the area of transition will be backfilled with “similar material (topsoil, concrete or asphalt). Drawing (PS‐5)….” Drawing PS‐5 is a standard detail. It lacks specific information of area for anyone to be able to calculate quantities of any “similar material” intended for backfill. Due to the nature of a Fixed‐Firm Price IDIQ Type contract and only knowing that delivery orders will be issued somewhere within Fort Buchanan, it is difficult to calculate cost with information given. Please provide which ELIN you will use for bidders to better calculate.
Answer 4: Removed material resulting from the required excavation on those ELIN's, can be used to fill those transition areas. No additional material is needed. Only “Mill Material” will be removed from Fort Buchanan
Question 5: ELIN 0001Bl – Please provide:
5a. No sodding area is provided. Please provide ELIN to be used.
5b. Drawing PS‐8 “Typical Open Concrete Drain Detail” states “Remove exist conc drain,” but there is no mention of it in the description under ELIN 0001Bl. One could assume that because these are typical details, if the condition arises, item 0001DN Remove/Dispose reinforce concrete will be used. Please confirm if this assumption is correct.
Answer 5a. See Drawing R8, Sheet 9 of 11, Typical Open Drain Detail (new grade with sodding 2 to 1 ratio (For bid purpose, assume 1.5 ft. on each side per lineal feet)) For Elin indicated: 0001Bl, Typical open concrete drain
Answer 5b: Assumption for reinforced concrete demolition and disposal is correct.
Question 6: ELIN 0001EF – 0001EG (retaining walls) ‐ Description provided is only for foundations. Because there is no specific area and description for work, please confirm government intends to use ELIN 0001DS Excavation additional and beyond the incidental for work other than foundations.
Also and since an exact location can’t be given, please confirm government intends to use ELIN 0001DT Backfill additional and beyond the incidental for any and all required backfill material for front and back of retaining wall.
Answer 6: ELIN's 0001EF ‐ 0001EG (retaining walls) includes foundations and wall heights. Any additional work will be included with the specific applicable item on this contract.
0001EF
Retaining Wall 4' - 6' height
Line items includes excavation, crushed stone base preparation, form work, rebars, weep pipe, concrete, clean gravel filter material, Geotech fabric; 1 cubic foot of backfill, including 4” Topsoil. In accordance with drawing (PS-12) and specifications within this contract.
0001EG
Retaining Wall 6' - 7' height
Line items includes excavation, crushed stone base preparation, form work, rebars, weep pipe, concrete, clean gravel filter material, Geotech fabric; 1 cubic foot of backfill, including 4” Topsoil. In accordance with drawing (PS-12) and specifications within this contract.
Question 7: Please confirm date of Bid opening is 10 MAY 2024 as indicated on Page 1, item 13A of Solicitation. Question arises because on Page 6, item 17d. BID OPENING states 9 MAY 2024.
Answer 7: Confirmed. Bid Opening Date is 10 May 2024 as indicated on Page 1, Item 13A of SF1442. Item 17d. Bid Opening has been corrected to 10 May 2024.
Question 8: On page 2 of Solicitation, it states “Annotate DUNS, CAGE code and Tax ID number with bid.” ‐ Please confirm DUNS is not required as it was replaced with the Unique Entity ID about two (2) years ago.
Answer 8: DUNS is not required. We require the UEI and the Cage Code. It also has been corrected on Page 2 of the Solicitation.
Question 9: For some work pertaining to Asphalt and Concrete sections, it will require excavation and removal of material. Please confirm whether or not a staging area will be provided for storage of aggregate material solely intended to be recycled at Fort Buchanan. The question is based because both local government and the EQB have issued strict guidance to encourage contractors to recycle as much as possible due to the critical land field situation in Puerto Rico. In addition, if material intended to be recycled for work at Fort Buchanan would need to be hauled out and then back in, this requires an ELIN for contractors to use to calculate such hauling activity as this is costly.
Answer 9: The contractor shall dispose of waste and recycle construction material in accordance with instructions and specifications listed in Summary of Work, Section 1.11 RECYCLING PROGRAM. No landfill area will be available for use by the contractor at Fort Buchanan. All generated material shall be kept at work site for re‐use on this specific delivery order as applicable. If the work area is limited, the Contracting Officer will provide a notification for a secondary location to be used. Removed material, by delivery order (DO), can be re‐use, as specified on this contract. Is a Contractor responsibility to dispose the excess material after completion of the delivery order.
All generated material shall be kept at work site for re‐use on the specific delivery order as applicable. Only “MILLED MATERIAL” will be removed from Fort Buchanan
Question 10: On page 40 of Solicitation it states “52.236.‐7 PERMITS AND RESPONSIBILITIES” – Please confirm that no environmental permit through the EQB and/or construction permits processed through our local government agencies will be required for the performance of this contract. This excludes local and municipal taxes. The concern arises because for the application of such permits, a contractor will need a specific place of performance other than Fort Buchanan, PR, and specific nature of the work given which is not provided due to the nature of the contract. In addition, request for permits submittals have a cost which we would need to calculate.
Answer 10: No environmental permit through the EQB and/or construction permits processed through our local government agencies will be required for the performance of this contract. This excludes local and municipal taxes. The permits required on this contract are listed in section 3.2 ‐ DELIVERABLES and are due to the Contracting Officer for processing.
Question 11: In Section 32 01 17.62, PAVING FABRIC INTERLAYER is very detailed. It appears that the intent is to have a paving interlayer installed for this project. It is unclear as to where or how much is needed. Please advise whether or not a Paving Fabric is called for on this project. Also, can I get a set of plans showing where and how much Paving Fabric is needed?
Answer 11. See Drawing R5, Sheet 6 of 11. Refer to specific dimensions and/or layer section details to be considered and measurements as it relates to each ELIN.
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 10-May-2024 10:00 AM to 17-May-2024 10:00 AM.
The following have been modified:
NOTICE TO BIDDER
SOLICITATION No : W912C3-24-B-0001, Contractor shall furnishing labor, materials, tools, equipment, supervision, transportation, insurance and all necessary to perform work in connection with the Paving and Sustainable Infrastructure at Fort Buchanan, PR 00934.
This solicitation is issued as 100% Small Buisness Set-Aside. All eiligible contractors cable of successfully completing the work identified in the requirement can submit a bid.
Note: Small Buisness Firms that are not local need to ensure they are familiar with Puerto Rico laws, tax information and any other required in order to suvcessfully submit a bid and complete the work. All interested firms need to ensure proper consideration of all required for successful completion of all work avoiding delays due to not being able to obtain personnel, equipment or materials.
Please carefully read and complete the entire solicitation. The following are highlighted for your attention:
1. Bidders shall incorporate total price for each period in the Schedule of Supplies/Services (CLINS), Section 0010. In addition, Bidders shall incorporate individual price for each work identified in the BID/CLIN Schedule attached. Total Price for all work in each period (Base, First Option, Second Option, etc.) in the attached spreadsheet shall match pricing incorporated in the CLIN Section (Section 0010) of the solicitation.
2. Bidders shall complete all representations and certifications in SAM (www.sam.gov) to include FAR 52.204-26.
3. Annotate their:
Vendor UEI:_______________________ Vendor CAGE Code: ____________________ Tax ID Number:___________________________ submit with bid.
4. Bidders shall complete the SF1442 first page of solicitation, including appropriate signature.
5. BIDDERS SHALL INCLUDE A 20% BID BOND GUARANTEE
AND/OR OTHER REQUIRED DOCUMENT WITH THEIR BID. FAILURE
TO INCLUDE MAY RENDER YOUR BID NOT ELIGIBLE FOR
CONSIDERATION FOR AWARD.
6. Bidders shall be registered in the System for Award Management (SAM). To obtain information on SAM and/or to register with SAM, visit their web site at www.sam.gov Bidders shall acknowledge and include a copy of any amendments issued to the solicitation with the bid, if applicable.
6. All questions shall be in writing and e-mailed to Maria Otero at maria.otero4.civ@army.mil and Felix Marrero at felix.r.marrero2.civ@army.mil no later than April 22, 2024 10:00 AM Puerto Rico local time.
7. It is the bidder’s responsibility that all bids submitted, regardless of method of submission, are received in this office prior to the time and date specified for receipt of bids.
8. The applicable NAICS code for this project is 237310 with a size standard of $45 Million.
9. The magnitude of this project is between $5 MILLION and $10 MILLION.
10. Period of performance: Base Period and four (4) 1-year Option Year periods. Each Delivery Order will specify the Period of Performance for the specific work.
11. BIDS ARE DUE NO LATER THAN THE DATE SPECIFIED IN
BLOCK 13A OF THE SOLICITATION OR AS INDICATED VIA
AMENDMENTS ISSUED, IF ANY.
12. EMAIL OR FAX – ARE NOT ACCEPTABLE
13. CONTRACTOR NEED TO SUBMIT THE FOLLOWING DOCUMENTS WITH
THEIR BID:
a. STANDARD FORM 1442 COMPLETED AND SIGNED
b. SOLICITATION PRICING CLIN SECTION (0010) FOR BASE AND EACH
OPTION
c. PRICING SPREADSHEET ELINS FOR BASE AND EACH OPTION
d. SIGNED COPY(IES) OF ANY AMENDMENTS ISSUED OR
ACKNOWLEDGEMENT IN STANDARD FORM 1442, BLOCK 19.
e. CAGE CODE, DUNS, AND TAX ID NUMBER
f. BID GUARANTEE
ALL ITEMS REQUIRING A BID PRICE SHALL BE FILLED. ANY BID
NOT SUBMITTING PRICING FOR ALL ITEMS MAY BE REMOVED
FROM FURTHER CONSIDERATION FOR AWARD. IT IS VERY
IMPORTANT THAT YOU VERIFY YOUR MATH CALCULATIONS.
BIDDERS ARE CAUTIONED TO CLEARLY PRINT INTENDED PRICES.
IN THE EVENT THERE IS A DIFFERENCE BETWEEN A UNIT PRICE
AND THE EXTENDED TOTAL, THE UNIT PRICE SHALL GOVERN AS
THE INTENDED PRICE. IF THE BIDDER SHOWS ONLY THE TOTAL
PRICE BUT FAILS TO ENTER A UNIT PRICE, THE TOTAL DIVIDED BY
THE ESTIMATED QUANTITY SHALL GOVERN TO BE THE INTENDED
PRICE. IF DURING THE EVALUATION OF THE PROPOSAL IT IS
NOTICE THAT THE TOTAL COST DOES NOT MACTH THE
MATHEMATICAL FORMULA, THE UNIT PRICE PREVAILS.
14. THE BIDDER IS REMINDED IT MUST BID ONLY ON THE
ITEMS/INFORMATION PROVIDED
IN THE SOLICITATION ISSUED WHICH INCLUDES PLANS, DRAWINGS,
AND SPECIFICATIONS AS AMENDED.
15. ANY INCORPORATION OF INFORMATION, DEVIATIONS,
CONDITIONS OR ATTACHMENTS SUBMITTED AS ADDITIONAL
INFORMATION FROM THE ORIGINAL INTENTION OF THE
SOLICITATION MAY RENDER THE BID NON-RESPONSIVE AND MAY
BE CAUSE FOR ITS REJECTION.
16. In accordance with Federal Acquisition Regulation 14.304, Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bid (IFB) by the time specified in the IFB. Any bid, modification, or withdrawal of a bid received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late.”
17. RECEIPT OF BIDS (HAND CARRIED OR MAIL)
17 a. HAND CARRIED BIDS: A bid box is provided for hand carried bids and is located at the Visitor Control Center (VCC) Fort Buchanan, The Borinqueneers’ Gate, PR28 (Goya). Once you arrive at the Borinqueneers Gate, Fort Buchanan (before the gate guard) stay on the far right lane that will lead you to the entrance of the VCC.
Hand carried bids must be deposited in the bid box prior to the time established for opening of bids. The bid box will be inside the Visitor Control Center. Only the MICC Contracting Office will have access to the bid box key. (Note: If bid package too big, it may not fit into bid box slot)
Bidders are cautioned that they should allow time to accomplish the submission of the bid. There may be lines or other restrictions at the gate due to current situation.
This will not be a reason for accepting the bid package late.
17 b. BID SHALL BE SUBMITTED IN A SEALED ENVELOPE WITH THE
FOLLOWING INFORMATION ON THE OUTSIDE:
Bidders Name Bidders Address Solicitation Number: W912C324B0001, Paving & Sustainable Infrastructure at Fort Buchanan, PR 00934 Bid Receipt Date: 17 May 2024 (or as amended) Bid Receipt Time: 10:00
17c. MAIL OF BIDS:
Bids may be mailed but shall be received before the date and time at the location designated for receipt of bids. Failure to submit the bid package so as to reach the Government at the location designated for receipt of bids, by the date and time set for receipt of bids, may be cause for rejection of the bid. Sealed bid envelope shall be identified with the same information on the outside of the envelope as indicated in item 1.2. above. See Federal Acquisition Regulation 14.304.
Mailing Address:
Mission and Installation Contracting Command Attn: Felix Marrero/Maria Otero (IFB No: W912C324B0001) 419th Contracting Support Brigade MICC-Fort Buchanan 34 South Gate Road, Suite 1104 Fort Buchanan
PR 00934
17d. BID OPENING:
THE DATE AND TIME FOR OPENING OF THE BIDS IS: 17 May 2024; 10:00 AM
LOCAL PUERTO RICO TIME OR AS AMENDED.
Vendors wanting to participate in the bid opening will need to ensure they arrive, at least, an hour early in order to be sponsored onto Fort Buchanan.
Valid ID, Drivers license for personnel is required. Max Two (2) persons per company.
DUE TO RESTRICTED ACCESS TO FORT BUCHANAN, CONTRACTORS
THAT WILL BE HANDCARRYING THEIR BID ARE REQUIRED TO
CONTACT:
maria.d.otero4.civ@army.mil and to felix.r.marrero2.civ@army.mil in advance to ensure timely submission of the bid package and pick up of package. Contractor can also place your bid in the Visitor Center Bid Box for this Solicitation (Note: If bid package too big, it may not fit into bid box slot)
THE NAMES OF THOSE ATTENDING SHALL BE PROVIDED NOT
LATER THAN FIVE (5) FULL WORK DAYS PRIOR TO THE DATE/TIME
OF BID OPENING DATE.
CONTRACTORS ARE CAUTIONED THAT THERE MAY BE DELAYS AT
THE GATES AND SHOULD ALLOW ADEQUATE TIME FOR ENTERING
THE INSTALLATION TO ENSURE PACKAGES ARE RECEIVED PRIOR TO
THE TIME AND DATE FOR RECEIPT OF THE BID PACKAGE. ALL
INDIVIDUALS MUST HAVE A PICTURE ID AND NO SUBSTITUTIONS
ARE AUTHORIZED. VEHICLES ARE ALSO SUBJECT TO SEARCH. NOTE:
THIS OFFICE MAY ASSIST IN PROVIDING ACCESS TO THE VENDOR;
HOWEVER, THE VENDOR REMAINS RESPONSIBLE FOR ENSURING THE
BID IS RECEIVED AT THE LOCATION SPECIFIED ON THE STANDARD
FORM 1442 BEFORE THE DATE AND TIME SPECIFIED FOR RECEIPT OF
BIDS.
18. SITE VISIT INFORMATION: A site visit is not contemplated at this time.
19. The “Equal Employment Opportunity Is the Law” notice (poster) referenced in FAR clause 52.222-26(b) (3), Equal Opportunity, is located http://www.dol.gov/ofccp/regs/compliance/posters/ofccpost.htm
20. The contractor shall comply with all Federal, State, and Local laws, codes and regulations applicable to his performance under this contract, and shall be solely responsible for all costs associated with the said compliance.
21. ELECTRONIC ANNUAL REPS/CERTS
Prospective contractors shall complete electronic annual representations and certifications at www.sam.gov in conjunction with the required registration in the System for Award Management database as required by FAR
(End of Summary of Changes)