This document contains a pre-solicitation notice and attachments for an environmental consulting services contract. The U.S. Army Corps of Engineers Tulsa District will issue solicitation W912BV20R0028 seeking proposals for indefinite delivery contracts for projects within the Southwest Division geographic area and those assigned to the division. Services include environmental quality, engineering, management, analysis, program support, sampling, testing, auditing, assessments, data, waste handling, permitting, community involvement, investigation, resources conservation, and cultural resources support. The agency intends to award up to three hubzone set-aside contracts under a best value evaluation with a maximum shared capacity of $20 million over a base three-year period and one two-year option. The NAICS code is 541620 and responses are due around April 16, 2020.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ATTACHMENT L-1
MILESTONE PAYMENT SCHEDULE WITHOUT COST

$20M ECS MEGA HUBZONE MATOC

EXAMPLE PROJECT

Solicitation #W912BV-20-R-0028
Contract #W912BV-20-D-TBD

27 March 2020

NOTES: 1) Offerors shall complete and return this Attachment L-1 Excel version with their Volume II proposal; 2) Offerors MAY NOT propose alternate Milestones by supplementing, or adding to, the CLINs identified below; 3) DO NOT make any changes to the spreadsheet cells or formulas below; 4) enter information in the green cells only (Projected Start and Completion Dates)

CLINMILESTONE DESCRIPTIONExpiration Date to Exercise OptionProjected Schedule Start Date (MM/DD/YR)Projected Completion Date (MM/DD/YR)
CLIN 0001 Task Order Kick-Off Meeting
0001Kick-Off Meeting within 15 days following submission of draft PMPAt Award
CLIN 0002 Project Management Plan
0002ADraft Project Management Plan (PMP) within 30 days following task order awardAt Award
0002BFinal PMP within 15 days of resolution of Army commentsAt Award
CLIN 0003 Quality Assurance Surveillance Plan
0003Draft Quality Assurance Surveillance Plan
(QASP) within 45 days following task order awardAt Award
CLIN 0004 UFP-QAPP/APP/SSHP/QCP
0004ADraft UFP-QAPP including SSHP and APP within 45 days following task order awardAt Award
0004BFinal UFP-QAPP including SSHP and APP within 15 days of resolution of Government commentsAt Award
CLIN 0005: Cowbird Trapping
0005ACowbird Trapping Monthly Reports by the
10th of each month after trapping has occurred (May 2020 - August 2020)At Award
0005BDraft Seasonal Trapping Report within 30
days after final trapping eventAt Award
0005CFinal Seasonal Trapping Report within 15
days following resolution of review comments on Draft Seasonal Trapping ReportAt Award
CLIN 0006 Project Records
0006Project File Record within 30 days of completion of the Base TasksAt Award
CLIN 0007 Contracting Manpower Reporting
0007Contracting Manpower Report annually by
October (31 October 2020)At Award

Sheet2

Sheet3