RFP No. W912BV-16-R-0058

US Army Corps of Engineers

Tulsa District

Convert Circuit 6, Selected Portions FY16 Project: VNVP162401

ATS: SWT-15-1094

Sheppard Air Force Base Wichita County, Texas

Design-Build Request for Proposals Phase 1 of 2

JANUARY 2016

THIS IS A TWO-PHASE REQUEST FOR PROPOSAL

PROJECT TABLE OF CONTENTS

SECTION TITLE

Coversheet 00 11 00 Proposal Schedule Design and Construction Schedule (Added Amendment 0002) 00 12 00 Project Description CLIN Schedule & CLIN Notes 00 21 00 Instructions to Offerors 00 22 10 Phase 1 of 2 Phase Design-Build Selection Procedures 00 45 00 Representations & Certifications 00 72 00 Contract Clauses 00 73 00 Special Contract Requirements 00 73 46 Wage Determination Schedule

DIVISION 01 – PROJECT GENERAL REQUIREMENTS (Phase 1) Sections are preliminary and subject to change

01 30 50 Security Requirements (SAFB) Application for Personnel Pass SAFB Main Gate Access USACE Office Location Map 01 32 01.00 14 Project Schedule (Full) Design and Construction Duration Weather Log 01 33 00.10 10 Digital Submittal Procedures and Correspondence Submittal Distribution List / Example Eng Form 4025 01 33 16 Design After Award 01 35 26.10 10 Governmental Safety Requirements Confined Space Permit 01 45 00.00 10 Quality Control 01 45 00.10 10 Quality Control System (QCS) 01 57 20.10 10 Environmental Protection 01 62 35 Recycled/Recovered Materials 01 74 19 Construction and Demolition Waste Management 01 78 00.10 10 Project Closeout Example Red Zone Meeting Checklist

01 10 00 STATEMENT OF WORK SUMMARY

Reference Drawings

E01 Existing Overall Plan E02 New Underground Plan E03 One-Line Diagram Sheet 1 E04 One-Line Diagram Sheet 2

Statement of Work is Subject to Change During Phase 2

Convert Electrical Circuit 6 from OH to UG, DESIGN-BUILD / CONSTRUCTION, Sheppard Air Force Base, Wichita Falls, TEXAS The principal elements of the project are:

1. Perform required site visit(s) to verify w ork required according to the documents provided

2. Design and Workplan developments

3. Construction Management

4. Overhead Electrical Distribution Demolition

5. Underground Electrical Distribution Replacement

6. New Underground Electrical Distribution Work

7. Street Lighting

8. Electrical Transformer and Sw itch Work

9. Utility Trenching and Backfill

10. Electrical Utility underground and under road boring

11. Materials Hauling

12. Sod/Seed and Establishment

13. Concrete Work

14. General Site Clean-up The Construction Cost Limitation (CCL) is as follow s:

FY16 Project: $14,500,000 The CCL is the total contract sum, w hich includes all categories of cost (i.e. design, non-design, and construction).

LEONARD E BUHROW 918.669.7277

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

25-Jan-2016

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________24 Feb 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIV

USACE, TULSA 1645 S 101 E AVE

TULSA OK 74128-4609

W912BV

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W912BV-16-R-0058 86

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

ID Task Mode

Task Name Duration Start Finish Predec

1 Develop Circuit 6 Project 228 days Tue 11/10/15 Fri 6/24/16

2 RFP ‐ Phase 1 99 days Tue 11/10/15 Tue 2/16/16

3 Phase 1 RFP Draft 21 days Tue 11/10/15 Mon 11/30/15

4 Phase 1 Draft Review 7 days Tue 12/1/15 Mon 12/7/15 3

5 Incorporation of Comments 7 days Tue 12/8/15 Mon 12/14/15 4

6 RFP to Contracting 14 days Tue 12/15/15 Mon 12/28/15 5

7 Issue RFP 30 days Tue 12/29/15 Wed 1/27/16 6

8 Hold Board ‐ Phase 1 14 days Thu 1/28/16 Wed 2/10/16 7

9 Board Report ‐ Phase 1 6 days Thu 2/11/16 Tue 2/16/16 8

10 Board Report Complete 0 days Tue 2/16/16 Tue 2/16/16 9

11 Develop Project Scope 151 days Tue 11/10/15 Fri 4/8/16 2SS

12 Initial Scope Discussion W/Team 20 days Tue 11/10/15 Sun 11/29/15 3SS

13 Initial Site Visit 2 days Mon 11/30/15 Tue 12/1/15 12

14 Dev of Scope 20% Design 45 days Wed 12/2/15 Fri 1/15/16 13

15 20% Complete 0 days Fri 1/15/16 Fri 1/15/16 14

16 Review 20% 11 days Sat 1/16/16 Tue 1/26/16 15

17 Incorporate Comments 20% 7 days Wed 1/27/16 Tue 2/2/16 16

18 Develop 35% Design 30 days Wed 2/3/16 Thu 3/3/16 17

19 35% Complete 0 days Thu 3/3/16 Thu 3/3/16 18

20 Review 35% 11 days Fri 3/4/16 Mon 3/14/16 19

21 Inc Comments 35% Design 3 days Tue 3/15/16 Thu 3/17/16 20

22 Finalization Project Scope 5 days Fri 3/18/16 Tue 3/22/16 21

23 Scope and Design Complete 0 days Tue 3/22/16 Tue 3/22/16 22

24 Develop IGE 14 days Wed 3/23/16 Tue 4/5/16 23

25 Review IGE ‐ Send for Signature 3 days Wed 4/6/16 Fri 4/8/16 24

26 IGE Complete 0 days Fri 4/8/16 Fri 4/8/16 25

27 RFP ‐ Phase 2 94 days Wed 3/23/16 Fri 6/24/16 23SS

28 Phase 2 RFP Draft 14 days Wed 3/23/16 Tue 4/5/16 23

29 Phase 2 RFP Draft Review 6 days Wed 4/6/16 Mon 4/11/16 28

30 Incorporation of Comments 7 days Tue 4/12/16 Mon 4/18/16 29

31 Phase 2 RFP to Contracting 7 days Tue 4/19/16 Mon 4/25/16 30,10

32 Issue RFP 45 days Tue 4/26/16 Thu 6/9/16 31

33 Hold Board ‐ Phase 2 7 days Fri 6/10/16 Thu 6/16/16 32,26

34 Board Report ‐ Phase 2 5 days Fri 6/17/16 Tue 6/21/16 33

35 Board Report Complete 0 days Tue 6/21/16 Tue 6/21/16 34

36 Final Project Documents 3 days Wed 6/22/16 Fri 6/24/16 35

2/16

1/15

3/3

3/22

4/8

6/21

Oct 25, ' Nov 1, '1Nov 8, '1Nov 15, Nov 22, Nov 29, Dec 6, '1Dec 13, Dec 20, Dec 27, Jan 3, '1 Jan 10, ' Jan 17, ' Jan 24, ' Jan 31, ' Feb 7, '1Feb 14, Feb 21, Feb 28, Mar 6, '1Mar 13, Mar 20, Mar 27, Apr 3, '1Apr 10, Apr 17, Apr 24, May 1, ' May 8, ' May 15, May 22, May 29, Jun 5, '1 Jun 12, ' Jun 19, ' Jun 26, ' Jul 3

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Project: Circuit 6 OH to UG Sched Date: Thu 11/19/15

DESIGN AND CONSTRUCTION SCHEDULE

SCHEDULED

DAYS REFERENCE NOTE SCHEDULED REQUIREMENT

Calendar Days

60 DESIGN WORK after completion of Design Review Meeting

Contractor begins preparation of 65% Design. Design Analysis, Specifications for Selected Equipment, Major Systems Incorporated Into Design, 65% Design Comments Incorporated Contractor to immediately provide 65% Design and Specifications for Review to Government when completed.

21 Days for Government Review 65% Design Review by USACE & Government Stakeholders. Government review to utilize DrChecks.

2 Days MEETING held at Sheppard AFB COE Office

65% Design Review Meeting

Contractor to begin 65% Design and Specifications and address and/or incorporate all DrCheck comments provided by the Government

7 Days After 65% Design Meeting: Contractor shall provide the meeting minutes prepared by contractor.

45 DESIGN WORK after completion of Design Review Meeting

Contractor begins preparation of 95% Design Drawings and Specifications; Finalize Details and updates all associated workplans to include Quality Control and Inspection Reports for field use.

21 Days for Government Review 95% Design Review by USACE & Government Stakeholders

2 Days MEETING held at Sheppard AFB COE Office

95% Design Review Meeting

Contractor to begin 95% Design and Specifications and address and/or incorporate all DrCheck comments provided by the Government

7 Days After 95% Design Meeting: Contractor shall provide the meeting minutes prepared by contractor.

14 Days to COMPLETE DESIGN after receipt of Minutes and final DrCheck Answers Submitted

Contractor finalizes 100% Design Drawings and Specifications. All workplans are finalized if not already done so.

7 Days Backcheck Review by Government

100% Design Backcheck by Government of Completed Design and Specifications and closed DrCheck Comments.

Not in-person meeting held

7 Days to prepare final drawing packages

Issue for Construction (IFC) Design Package submitted to the Government. DESIGN IS

COMPLETED - BEGIN CONSTRUCTION

179 DAYS FOR DESIGN (Timeline Above)

560 DAYS FOR CONSTRUCTION

10 DAYS FOR PROJECT CLOSEOUT AND FINAL ACCEPTANCE

749 CALENDAR DAYS - TOTAL CONTRACT DURATION FOR THE BASE BID

749 Backcheck Reference SECTION 01 32 01.00 10 Project Schedule

Repair Circuit 6, Selected Portions

AMENDMENT 0002

SECTION 01 12 00

Convert Circuit 6, Selected Portions (VNVP162401)

SECTION 00 12 00

PROJECT DESCRIPTION – SCOPE OF WORK

Convert Circuit 6, Selected Portions Sheppard Air Force Base, Wichita Falls, TEXAS Sheppard AFB Project Number: VNVP162401

WORK TYPE: DESIGN-BUILD / CONSTRUCTION

1.0 General

Provide all site investigations, workplans, site surveys, studies and design analysis, design drawings and specifications, construction documents, shop and manufacturing drawings, materials, labor, equipment, supervision, testing, submittals, and construction to perform the requirements of this project to make the necessary repairs and rehabilitation services in accordance with the provided scope of work and contract documents. The prime contractor shall be required to coordinate with Government Representatives of the U.S. Army Corps of Engineers, Tulsa District, under the direction of the Contracting Officer (KO) and assigned representatives of the contract. Construction shall commence under the direction of the KO after the work plan(s) and associated shop drawings are completed, reviewed, and approved in writing that the workplan(s) and shop drawings have demonstrated they meet the contract requirements.

The intent of the project is to replace a section of the Sheppard Air Force Base (AFB) 15kV class electrical distribution system (specifically all of Circuit 6). This work includes conversion of overhead (OH) to underground (UG) and replacement of UG electrical primary and secondary service. The finished system shall be 500 kcmil service. Provide the new UG feeder and taps before removing the existing OH and UG feeder and taps to minimize (to the maximum extent possible) the outage(s) associated with replacing Circuit

6. Construct the new UG feeder primary and secondary to include street and parking lot lighting. Demolish the existing OH and UG. Existing ground transformers will be replaced as well as main circuit breakers and switches. Work will also require provision of spare underground ducts and provision for metering. Underground road boring with steel casings is required, but pavement cutting will be considered for government approval in specific situations. The design phase shall determine the best method of accomplishing the replacement of this feeder which consists of approximately 3 miles of OH distribution and approximately 3.6 miles of UG distribution. Reference attached site drawings.

Both the design and the construction shall be handled under the auspices of one prime contractor that shall be responsible for completing the work. It is the prime contractor’s option to subcontract the design and/or construction phase as long as the design is stamped by a licensed Professional Engineer (PE) experienced in ‘15kV Class Distribution System’ design and the construction is accomplished by a contractor experienced in ‘15kV Class Line Construction’ work. The PE that stamps the design shall be the Designer of Record (DOR). The DOR shall submit his or her design experience for evaluation and shall have a minimum of 5 documented ‘15kV Class Distribution System Modification’ projects of similar scope (of which 3 must be designed within the last 5 years). The construction contractor shall submit its construction experience for evaluation and shall have a minimum

SECTION 01 12 00

Convert Circuit 6, Selected Portions (VNVP162401) of 5 years documented ‘15kV Class Line Construction’ experience of similar scope (of which 3 must be successfully completed within the last 5 years).

The replacement of Circuit 6 shall be accomplished with a minimum of power outage(s).

To assist in achieving that requirement, the new UG distribution must be constructed and tested to the maximum extent possible prior to demolishing the existing OH and UG distribution. All outages shall be coordinated with the Contracting Officer (KO) in advance and shall be scheduled through the Sheppard AFB Base Civil Engineer (BCE).

The principal elements of the project are:

The contractor shall perform all the required work for this project in accordance with this task order and base contract.

1. Perform required site visit(s) to verify work required according to the documents provided

2. Design and Workplan developments

3. Construction Management

4. Overhead Electrical Distribution Demolition

5. Underground Electrical Distribution Replacement

6. New Underground Electrical Distribution Work

7. Street Lighting

8. Electrical Transformer and Switch Work

9. Utility Trenching and Backfill

10. Electrical Utility underground and under road boring

11. Materials Hauling

12. Sod/Seed and Establishment

13. Concrete Work

14. General Site Clean-up

2.0 PRODUCTS (NOT APPLICABLE)

3.0 EXECUTION (NOT APPLICABLE)

-- End of Section –

Convert Circuit 6, Selected Portions (VNVP 162401) Sheppard AFB, TX

Item No. Description Quantity Unit Unit Price Line Item Amount

Base Bid: Convert Circuit 6 from OH to UG & Replace UG Main Feeder Cables (VNVP 162401)

0001 DESIGN 1 Job LS $_____________________________

0002 Electrical Demolition 1 Job LS $_____________________________

0003 Electrical Construction 1 Job LS $_____________________________

0004 General Conditions 1 Job LS $_____________________________

FIRM FIXED PRICE TOTAL COST FOR BASE BID:

Subtotal Items 0001 thru 0004

OPTION 1: Replace Padmounted Switch VS-601

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0005 DESIGN 1 Job LS $ ____________________________

0006 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 1:

Subtotal Items 0005 thru 0006

OPTION 2: Replace Padmounted Switch VS-602

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0007 DESIGN & WORKPLANS 1 Job LS $ ____________________________

0008 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 2:

Subtotal Items 0007 thru 0008

OPTION 3: Replace Padmounted Switch VS-603

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0009 DESIGN 1 Job LS $ ____________________________

0010 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 3:

Subtotal Items 0009 thru 0010

Contractor shall submit a 65% and 95% Designs for Review and Approval.

Contractor shall submit a 65% and 95% Designs for Review and Approval.

CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

BASE BID

Contractor shall submit 65% and 95% Designs for Review and Approval.

Ten (10 Ea.) Options

Contractor shall submit 65% and 95% Designs for Review and Approval.

OPTION 4: Replace #4/0 UG lateral cables in Identified Areas

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0011 DESIGN 1 Job LS $ ____________________________

0012 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 4:

Subtotal Items 0011 thru 0012

OPTION 5: Replace Padmounted Switch VS-605

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0013 DESIGN & WORKPLANS 1 Job LS $ ____________________________

0014 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 5:

Subtotal Items 0013 thru 0014

OPTION 6: Replace Padmounted Switch VS-610

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0015 DESIGN 1 Job LS $ ____________________________

0016 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 6:

Subtotal Items 0015 thru 0016

OPTION 7: Replace Padmounted Switch VS-611

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0017 DESIGN 1 Job LS $ ____________________________

0018 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 7:

Subtotal Items 0017 and 0018

OPTION 8: Replace UG Ductbank/Manhole System 2500 Area

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0019 DESIGN 1 Job LS $ ____________________________

0020 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 8:

Subtotal Items 0019 thru 0020

Contractor shall submit a 65% and 95% Designs for Review and Approval.

Contractor shall submit a 65% and 95% Designs for Review and Approval.

Contractor shall submit a 65% and 95% Designs for Review and Approval.

Contractor shall submit a 65% and 95% Designs for Review and Approval.

Contractor shall submit a 65% and 95% Designs for Review and Approval.

OPTION 9: Replace UG Secondary at Buildings 2406 & 2410

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0021 Design 1 Job LS $ ____________________________ Contractor shall submit a 65% and 95% Designs for Review and Approval.

0022 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 9:

Subtotal Items 0021 and 0022

OPTION 10: Rework Genset at Building 2559

TYPE C WORK PLAN (DESIGN & CONSTRUCTION)

0023 Design 1 Job LS $ ____________________________ Contractor shall submit a 65% and 95% Designs for Review and Approval.

0024 CONSTRUCTION 1 Job LS $ ____________________________

FIRM FIXED PRICE TOTAL COST FOR OPTION 10:

Subtotal Items 0023 and 0024

Evaluated Cost; Refer Section 00 22 11 Proposal Preparation and Evaluation Criteria

TOTAL ALL OPTIONS:

TOTAL BASE BID + ALL OPTIONS

1)

3)

4)

5)

Total CLIN Items 0005 THRU 0024

Total CLIN Items 0001 THRU 0024

CLIN NOTES

The Offeror shall submit pricing data on the latest Contract Line Item (CLIN) schedule as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

Offerors must insert a price on all numbered items of the CLIN Schedule. Failure to do so will disqualify the Offer.

If a modification to a proposal is submitted and provides for a lump-sum adjustment to the total estimated cost, the application of the lump-sum adjustment to each unit price and/or lump-sum price, in the Contract Line Item schedule must be stated or, if it is not stated, the Offeror agrees that the lump-sum adjustment shall be applied on a prorated basis to every item in the CLIN schedule.

PROPOSAL SCHEDULE NOTES

The Offeror shall submit pricing data on the latest Proposal Schedule as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

Offerors must insert a price on all numbered items of the Pricing Schedule. Failure to do so will disqualify the Offer.

If a modification to a proposal is submitted and provides for a lumpsum adjustment to the total estimated cost, the application of the lump-sum adjustment to each unit price and/or lump-sum price, in the Contract Line Item schedule must be stated or, if it is not stated, the Offeror agrees that the lump-sum adjustment shall be applied on a prorated basis to every item in the Pricing Schedule.

Only one task order for the entire schedule will be awarded under this solicitation in accordance with the Contract.

1. Offeror must bid on all items

2. Costs attributable to Division 01 - General Requirements are assumed to be prorated among proposal items listed unless specifically noted.

3. Responder is advised that this requirement may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process

6)

7)

8) CONDITIONS GOVERNING EVALUATION OF OFFERS AND AWARD OF CONTRACTS:

The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule. Subject to the availability of funds, the Contracting Officer may exercise the option by written notice to the Contractor within the time indicated from the Notice to Proceed (NTP):

AVAILABILITY OF FUNDS (APR 1984) (FAR 52.232-18)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

All the extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

Section 00 21 00 – Instructions, Conditions & Notices to Offerors

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS TO OFFERORS

A. Proposal Submittal and Inquiries

1. Proposals shall be submitted by Email, CD/DVD, or AMRDEC SAFE Access File Exchange (https://safe.amrdec.army.mil/SAFE/Welcome.aspx) (AMEND 0002) prior to the closing date and time specified in this Request for Proposal, to the following address:

U.S. Army Corps of Engineers, USACE, Tulsa District

Email: Leonard.E.Buhrow@usace.army.mil

ATTN: Leonard Buhrow, CESWT-CT 1645 S. 101 E. Avenue, Tulsa, OK 74128

MARK PDF PACKAGES:

Title: Repair Circuit 6, Selected Portions Solicitation No. W912BV-16-R-0058 Offer Closing Date: February 24, 2016 Offer Closing Time: 2:00 pm Central Time RFI due date/time will be February 17, 2016

2. Hardcopy or fax submissions will not be accepted. Offers shall be provided via emailed or

CD/DVD with a single Adobe .pdf file. The proposals shall ONLY be emailed/sent to the Contracting Specialist below. Prepare digital proposals in accordance with Section 01 33 00.10 10

DIGITAL SUBMITTAL PROCEDURES AND CORRESPONDENCE.

a. Tulsa District Corps of Engineers mail room hours are 8:30 am – 11:30 am and 1:00 pm - 4:15 pm.

3. The Contract Specialist is the sole point of contact for this acquisition. The Contracting Specialist may or may not be the Contracting Officer on this project at time of award. Submit inquires related to this solicitation and address all questions or concerns you may have to the Contract Specialist. All contractual matters, questions and or comments relative to these documents should be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet no later than February 2, 2016 in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry Key is BBGTV9-22PBIR to submit questions.

Contract Specialist:

Leonard Buhrow Email: Leonard.E.Buhrow@usace.army.mil Fax: 918-669-7657

a. Include the solicitation number, and project title with your questions. Written inquiries must be received by this office not later than 4 calendar days prior to the date set for receipt of offers.

b. Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

https://safe.amrdec.army.mil/SAFE/Welcome.aspx mailto:Leonard.E.Buhrow@usace.army.mil

c. As this is a competitive negotiation acquisition, there is no public bid opening and no information will be given out as to the number of Offerors or the results of the competition until all awards are made.

d. This solicitation will be distributed using Federal Business Opportunities

(FEDBIZOPPS). For Offerors registered through FEDBIZOPPS, the solicitation and all amendments may be viewed and/or downloaded through the following internet address:

https://www.fbo.gov

e. For further information:

http://www.swt.usace.army.mil/BusinessWithUs/Contracting/FederalBusinessOpportuniti es.aspx

4. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

5. Oral explanations or instructions are not binding. Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

6. As this is a competitive negotiation acquisition, there is no public opening and no information will be given out as to the number of offerors or the results of the competition until award is made.

B. CONSTRUCTION COST LIMITATION (CCL)

The Construction Cost Limitation (CCL) is as follows:

Convert Electrical Circuit 6 from OH to UG FY16 Project: VNVP16201 $14,500,000

The CCL is the total contract sum, which includes all categories of cost (i.e. design, non-design, and construction).

C. GENERAL INSTRUCTIONS

1. Offers will be evaluated using the criteria under Section 00 22 10 Phase 1 of 2 Phase Design- Build Selection Procedures. The intent of this 2-Phase Request for Proposal (RFP) is to solicit proposals for the Design and Construction to convert electrical circuit 6 from overhead (OH) to underground (UG) and to make repairs and replacement to the existing circuit 6 electrical distribution systems in areas already underground at Sheppard Air Force Base (SAFB), Wichita County, Texas. The solicitation criteria shall rely upon industry standards, as much as possible, to allow the Offeror a degree of design flexibility while meeting certain specific project requirements. During Phase 1 of the selection process, interested firms or joint venture entities (referred to as “Offerors”) shall submit certain specified performance capability proposals, demonstrating their capability to successful execute the design-build construction contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described in this section and will select no more than five (5) of the Phase 1 Offerors to compete for the design-build construction contract in Phase 2. Offerors selected to compete during Phase 2 will be notified by letter.

2. During Phase 2 of the selection process, the Offerors selected to compete for the design-build construction contract shall submit a Phase 2 Proposal consisting of the following information:

Design Technical, Remaining Performance Capability, and Price. Proposers shall perform sufficient design work prior to submitting proposals in order to verify quantities and costs.

See Section 00 22 20 PHASE 2 DESIGN-BUILD SELECTION PROCEDURES AND BASIS OF AWARD. The Contracting Officer will award a firm fixed-price contract to that https://www.fbo.gov/ http://www.swt.usace.army.mil/BusinessWithUs/Contracting/FederalBusinessOpportunities.aspx http://www.swt.usace.army.mil/BusinessWithUs/Contracting/FederalBusinessOpportunities.aspx responsible Phase 2 Offeror whose proposal the Source Selection Authority determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government. The intent is to obtain the best proposal within the cost limitation stated in this RFP. There is no obligation for the Offeror to approach or match the cost limitation in the offer. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. The Government will not award a contract to an Offeror whose proposal contains a deficiency as defined in FAR 15.001.

3. Noncompliance with the RFP requirements during phase 1 or 2 will raise serious questions regarding an offeror’s technical ability to perform the services and may be grounds to eliminate the proposal from further consideration for contract award.

4. Upon award, the successful Offeror must design and construct the project Convert Electrical

Circuit 6 from OH to UG at Sheppard AFB, Texas.

D. PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

5. Reference 00 22 10 Phase 1 of 2 Phase Design-Build Selection Procedures.

6. In order to effectively and equitably evaluate all Offerors, the Source Selection Evaluation Board (SSEB) must receive information sufficiently detailed to clearly describe the Offeror’s past performance, qualifications of key individuals and technical approach to successfully complete the design and to construct this project. Offerors shall organize their proposal as described and outlined in 00 22 10 Phase 1 of 2 Phase Design-Build Selection Procedures.

Failure to follow this format may result in the proposal being misinterpreted and could result in a lower overall ranking for such proposal.

7. Deviations and exceptions to the terms and conditions of the solicitation in either the technical proposals or price proposal (Phase 2) are neither encouraged nor desired. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined “unacceptable” and thus ineligible for award. Should the Offeror have any questions related to specific terms and conditions, these must be resolved prior to submission of the offer. Notwithstanding the above, if deviations and exceptions are included with the offer, the Offeror shall list and describe in detail the deviations and/or exceptions on the first page of each Tab. All deviations and exceptions shall be fully supported with the Offeror’s rationale and shall fully explain the impact, if any, on the performance and/or specific requirement of the RFP. In Phase 2, the Offeror shall clearly describe on the Proposal Cover Sheet submitted with the Price Proposal any exception to the contractual and/or technical terms and include the monetary impact on the solicitation.

8. Discussions. The Government does not intend to enter into discussions with offerors prior to determining those contractors within the competitive range, in accordance with FAR 52.215- 1, Instructions to Offerors—Competitive Acquisitions, Alternate I. However, in accordance with FAR Part 15.306, should discussions become necessary, the Government reserves the right to hold them. If this occurs, a competitive range will be determined and offerors notified. The competitive range may be limited for purposes of efficiency in accordance with (IAW) FAR Part 15.306(c)(2).

9. Cost or Pricing Data. Offerors are not required to submit Cost or Pricing Data with their Phase

1 Proposal. Offerors shall provide Financial Capacity only with their Phase 1 proposal.

10. Firms formally organized as design-build entities, design firms and construction contractors that have associated specifically for this project, consortia of firms or any other interested parties may submit proposals. Associations may be as joint ventures or a key team subcontractor. Any legally organized Offeror may submit a proposal. To quality for Phase 2, the Offeror or Offeror’s subcontractor has to have or will have to have professional architects and engineers, registered in the appropriate technical disciplines and the requirements specified in contract clause “Requirements for Registration of Designers” must be met. All designs must be under the direct supervision of appropriately licensed professionals for each discipline involved.

11. “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”.

12. In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.) that will perform work under the prospective contract.

13. In accordance with FAR Subpart 4.8 (Government Contract Files), the Government will retain one copy of all unsuccessful proposals.

14. If an offeror believes that the requirements in these instructions contain an error, an ambiguity, omission, or are otherwise unsound, the offeror shall immediately notify the Contracting Specialist in writing with supporting rationale.

15. All referenced documents are available from the Contract Specialist, Leonard Buhrow, Leonard.E.Buhrow@usace.army.mil

16. Debriefings. The Contracting Officer will promptly notify offerors of any decision to exclude them from the competitive range, whereupon they may request and receive a debriefing in accordance with FAR 15.505. The Contracting Officer will notify unsuccessful offerors in the competitive range of the source selection decision in accordance with FAR 15.506. Upon such notification, unsuccessful offerors may request and receive a debriefing. Offerors desiring debriefing must make their request in accordance with the requirements of FAR

15.505 or 15.506, as applicable. All debriefings will be provided officially in writing.

FOR OFFICIAL USE ONLY, SOURCE SELECTION INFORMATION, SEE FAR 3.104.

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

CLAUSES INCORPORATED BY REFERENCE

52.211-7 Alternatives to Government-Unique Standards NOV 1999 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2004 52.217-4 Evaluation Of Options Exercised At The Time Of Contract Award JUN 1988 52.217-5 Evaluation Of Options JUL 1990 52.225-9 Buy American--Construction Materials MAY 2014 52.225-10 Notice of Buy American Requirement—Construction Materials MAY 2014 52.225-11 Buy American--Construction Materials Under Trade Agreements MAY 2014 52.225-12 Notice of Buy American Requirement – Construction Materials Under

Trade Agreements MAY 2014 52.232-38 Submission of Electronic Funds Transfer Information with Offer JUL 2013 52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7008 Only One Offer OCT 2013

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of provision)

CLAUSES INCORPORATED BY FULL TEXT

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for minority participation for each trade

Goals for female participation for each trade

14.8%

6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.

Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for

Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.

The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-

4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Sheppard Air Force Base, Wichita County, TX

(End of provision)

CLAUSES INCORPORATED BY FULL TEXT

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Leonard Buhrow (Amend 002), US Army Corps of Engineers, Tulsa District, CECT SWT (Contracting Division) 1645 S. 101st E. Ave, Suite 350, Tulsa, OK 74128-4609

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

CLAUSES INCORPORATED BY FULL TEXT

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

SEE AMENDMENT 0001

(c) Participants will meet at--

SEE AMENDMENT 0001

(End of provision)

CLAUSES INCORPORATED BY FULL TEXT

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/

(End of provision)

FOR OFFICIAL USE ONLY. SOURCE SELECTION INFORMATION. SEE FAR 3.104.

SECTION 00 22 00

AMENDMENT 0002

PHASE 1 OF 2 PHASE DESIGN-BUILD SELECTION PROCEDURES

1.0 OVERVIEW

2.0 GENERAL INSTRUCTIONS

3.0 PHASE 1 PROPOSAL AND RELATED EVALUATION FACTORS

4.0 TAB A – STANDARD FORM 1442 AND PROPOSAL DATA SHEET

5.0 TAB B – FACTOR 1 – SPECIALIZED EXPERIENCE

5.1 SUBMISSION REQUIREMENTS

5.2 EVALUATION CRITERIA

6.0 TAB C – FACTOR 2 – PAST PERFORMANCE

6.1 SUBMISSION REQUIREMENTS

6.2 EVALUATION CRITERIA

7.0 TAB D – FACTOR 3 – ORGANIZATION AND TECHNICAL APPROACH

7.1 SUBMISSION REQUIREMENTS

7.2 EVALUATION CRITERIA

8.0 PHASE 1 OVERALL RATING

9.0 PHASE 1 EVALUATION PROCEDURES

9.1 SOURCE SELECTION EVALUATION BOARD (SSEB)

9.2 EVALUATION

9.3 DEFINITIONS

9.4 EVALUATION AND RATING SYSTEM

9.5 PAST PERFORMANCE EVALUATION SYSTEM

PHASE ONE – SECTION 00 22 00 ATTACHMENTS

1 – PROPOSAL DATA SHEETS

2 – COMPANY SPECIALIZED EXPERIENCE CONSTRUCTION OR PRIME

CONTRACTOR

3 – COMPANY SPECIALIZED EXPERIENCE DESIGN FIRM OR IN-HOUSE DESIGN

CAPABILITY

4 – PAST PERFORMANCE SURVEY FORM

5 – KEY PERSONNEL RESUME

6 – LETTER OF COMMITMENT FOR KEY PERSONNEL

7 – LETTER OF COMMITMENT FOR DESIGN FIRM

1.0 OVERVIEW

1.1. The Government is looking for ways to streamline design and construction, manage labor and other resource constraints in an effort to reduce costs and achieve an aggressive schedule in executing contracts to meet the Air Force program and mission goals of faster project execution at lower cost, while taking advantage of industry standards, means and methods. In Phase 1 of the 2 phase design-build selection procedure, interested firms or joint venture entities (referred to as “offerors”) submit certain specified performance capability proposals, demonstrating their capability to successfully execute the design-build construction contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described herein and will select no less than (3) and no more than five (5) of the Phase 1 offerors to compete for the design-build contract in Phase 2.

1.2. In Phase 2, the short-listed offerors will submit proposals in accordance with Section 00 22 20 to be provided with the Phase 2 solicitation.

2.0 GENERAL INSTRUCTIONS

2.1. Firms formally organized as design-build entities, design firms and construction contractors that have associated specifically for this project, consortia of firms or any other interested parties may submit proposals. Associations may be as joint ventures or as key team subcontractors. Any legally organized Offeror may submit a proposal. To qualify for Phase 2, the Offeror or Offerors subcontractor has to have or will have to have a professional engineer(s), registered in the appropriate technical disciplines and the requirements specified in Contract Clause, ”Requirements for Registration of Designers”, must be met.

All designs must be under the direct supervision of appropriately licensed professionals for each discipline involved with the construction work, submittal approvals, and key inspections involving the same licensed engineer until project closeout is completed.

2.2. Submit the ORIGINAL of the written Technical Proposal via Email, CD/DVD, or AMRDEC SAFE Access File Exchange (https://safe.amrdec.army.mil/SAFE/Welcome.aspx) (AMEND 0002) or on CD/DVD. The CD/DVD shall contain the entire proposal in original Adobe PDF format; do NOT scan the document(s) into a .pdf file. The .pdf file content, bookmarks, and structure of the .pdf file shall comply with section 01 33 00.10 10 Digital Submittal Procedures and Correspondence. Submitted CD/DVD shall be labeled in accordance with this same section and 00 21 00 Instructions to Offerors.

2.3. The text portion of the complete proposal shall be contained as a single .pdf file. Sections of the proposal shall be bookmarked (linked to the index) in logical order. Note that the Government will not evaluate any material that exceeds the page limits. Phase 1 does not involve pricing submission.

3.0 PHASE 1 PROPOSAL AND RELATED EVALUATION FACTORS

Location Factor Number Description Relative Importance

Tab A SF 1442 and Proposal Data Sheet

N/A

Tab B Factor 1 Specialized Experience 1st Most Important Factor

Tab C Factor 2 Past Performance 2nd (Slightly less important than Factor 1) https://safe.amrdec.army.mil/SAFE/Welcome.aspx

Tab D Factor 3 Organization and Technical Approach

3rd (Slightly less than Factor 2)

4.0 TAB A - STANDARD FORM 1442 AND PROPOSAL DATA SHEET

4.1. Submit the SF 1442, completed and signed by a person authorized by the Offeror. Include the completed proposal data sheet (See attachment 1, provided at the end of this Section).

5.0 TAB B – FACTOR 1 - SPECIALIZED EXPERIENCE

5.1. SUBMISSION REQUIREMENTS

5.1.1. The prime contractor and the design firm(s) (or prime contractor if design is to be self-performed) shall each demonstrate recent, relevant experience on similar projects, using Construction – Specialized Experience form (Attachment 2), and Designer – Specialized Experience Form (Attachment 3) at the end of the section. Offerors may identify state and local government and private contracts that are similar to the Government’s requirements. If the offeror is a joint venture, each firm shall provide information, demonstrating experience relevant to their role on this project. Submit projects selected from those discussed in the experience narrative that are currently well underway (designed and at least 50% construction progress completed) or completed and turned over no longer that five (5) years preceding the date of this Solicitation. Prime Contractors shall submit at least 3 projects that are relevant/similar to the subject project with a dollar value that equals or exceeds $3 million dollars (Amendment 0002). If any firm has multiple functions or divisions, limit the project examples to those preformed by the division or unit submitting the offer or by the team member. Design firms may list prime contractors they have worked for or government, private or commercial customers. The offeror shall select the design firm(s). If projects were design-build, so identify them. Both the prime contractor and the design firm(s) shall each submit no more than five (5) projects for each of the facility types or their equivalent or similar commercial or institutional type:

Convert Circuit 6, Selected Portions (Amendment 0002)

5.1.2. The offeror may provide a supplemental narrative (not project lists), not to exceed five (Amendment 0002) pages, explaining how any corporate experience that is not directly related to the specific projects above is applicable to this project and how the Government will benefit. The following information may be considered.

5.1.2.1. The offeror should describe any previous teaming experience between current team members, if not described in the project list. Describe team members’ experience on overhead/underground electrical projects, if not included on the project list. Offeror may describe design-build experience on other type projects.