W912BU25BA009-Specs.pdf
PDF 15 MB Posted
- Solicitation number
- W912BU25BA009
About this file
This is a detailed solicitation for a beach renourishment project by the U.S. Army Corps of Engineers Philadelphia District. The contract (W912BU25BA009) involves placing approximately 300,000-500,000 cubic yards of beach fill material along the north shore of Indian River Inlet in Delaware's Sussex County, with the primary objectives of providing coastal storm damage reduction to Delaware Seashore State Park, Route 1, and the Route 1 bridge. The project will use sand exclusively from the Indian River Ebb Shoal borrow area located approximately 3,500 feet offshore, with a base bid for restoring the beach to a design template and up to three optional placements for advanced nourishment.
The solicitation includes a comprehensive set of technical specifications covering various aspects of the project, such as survey requirements, environmental controls, dredging quality management, safety protocols, and material placement specifications. The beach design template calls for a minimum 60-foot berm at 9.2 ft NAVD elevation with a 1V:10H slope, extending 5,000 feet including end tapers. The project is valued between $5-10 million, has a 120-calendar day completion timeline from Notice to Proceed, and is classified under NAICS code 237990 with a size standard of $45.0 million. Bidders must be registered in the System for Award Management (SAM) and PIEE databases.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB W912BU25BA009
US Army Corps of Engineers Philadelphia District
Beach Nourishment
Indian River Inlet - North Beach Sussex County, Delaware
Construction Specifications
May 2025
This page was intentionally left blank for duplex printing.
SECTION 00 50 05
PRE-AWARD SURVEY SUBMITTAL REQUIREMENTS
PART 1 GENERAL
1.1 AWARD CRITERIA
Award of this Contract will be made as a whole to the lowest responsive and responsible Bidder whose bid conforms to all requirements of the specifications. Subsequent to the bid opening, the apparent low Bidder must submit Pre-Award Survey Information that demonstrates compliance with the requirements set forth in this section as a precondition to receiving award.
1.2 GENERAL PRE-AWARD SURVEY INFORMATION
Complete the pre-award survey information sheets attached to this section, and submit to the Contracting Officer within 5 calendar days after bid opening.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
DOCUMENT 00 50 05 Page 1
US ARMY CORPS OF ENGINEERS
PHILADELPHIA DISTRICT
PRE-AWARD SURVEY
A. GENERAL INFORMATION
1) Name of Firm: ___________________________________________________________________
Address: __________________________________________________________________________
Phone: _____________________________________ Fax:__________________________________
Email: ____________________________________________________________________________
CAGE CODE:
If your company has more than one CAGE Code, please list all that apply.
2) Location where accounts are kept (if different than item 1 above): ____________________________
3) Type of Firm (Please check one):
Sole Proprietorship [ ] Partnership [ ] Corporation [ ] Joint Venture [ ] Other
Date Organized: ____________________________________
Date Incorporated: __________________________________
State of Incorporation: _______________________________
4) Attach list of Name of Officers.
Please check "Yes" or "No" for each of the following:
Have current officers of your firm ever been indicted? Yes [ ] No [ ]
Are any of your officers currently under indictment? Yes [ ] No [ ]
If you have answered "Yes" to either of the above, please attach an explanation.
5) Has your firm been terminated for default on any contracts in the past six years? Yes [ ] No [ ] (If yes, please attach an explanation)
Section 00 50 05 Page 2
B. PROPOSED SCHEDULE
Submit a preliminary schedule depicting your project plan from start to final completion. The schedule you submit will be used to determine your ability to successfully perform the project within the time frame stated in the specifications.
IAW FAR 52.236-15, Schedules for Construction Contracts, you will be required to submit a fully loaded schedule within five days after work commences on the awarded contract.
C. PERFORMANCE AND PAYMENT BOND INFORMATION
1) Performance & Payment Bonds will be furnished by:
Name of Company: _______________________________________________________________
Phone No: _____________________________________________________________________
2) Firm's bonding capacity as authorized by your Insurance Company:
Single Project: ___________________________________________________________________
Aggregate Basis: _________________________________________________________________
D. BANKING INFORMATION
Name of Bank: ___________________________________________________________________
Address: ________________________________________________________________________
Account Representative: ____________________________________________________________
Phone No: ________________________________ E-mail: _______________________________
Authorized Credit Line: ________________________________________________
If additional banks are utilized, please provide this information for each.
E. INSURANCE INFORMATION
Name of Insurance Company: ______________________________________________________
Type of Insurance Provided: _______________________________________________________
Insurance Agency: _______________________________________________________________
Address: _______________________________________________________________________
Agent: _________________________________________________________________________
Phone No: ______________________________ Email: _________________________________
If more than one insurance company is utilized, please provide this formation for each.
Section 00 50 05 Page 3
F. FINANCIAL DATA
Please provide the last two certified public accountant's financial statements.
G. SAFETYDATA
Please check "Yes" or "No" for each of the following:
1. Does your firm have a Standard Operating Procedure for Safety?
Yes [ ] No [ ] If yes, please provide a copy.
Does your firm have a Policy Letter dealing with Safety?
Yes [ ] No [ ] If yes, please provide a copy.
2. What was your accident rate for last year? _____________________
3. What is your accident rate to date for this year? ____________________
H. QUALITY CONTROL DATA
Please check "Yes" or "No" for each of the following:
1. Does your firm have a Standard Operating Procedure for Quality Control?
Yes [ ] No [ ] If yes, please provide a copy.
2. Does your firm have a Policy Letter dealing with Quality Control?
Yes [ ] No [ ] If yes, please provide a copy.
I. EQUIPMENT DATA
Please provide the following data for each piece of construction equipment (including equipment you will rent or lease), intended to be used on the project. Do not include consumables.
Make Year Mfg.
Description Purchase Price (if equipment is owned) Size Book Value (if equipment is owned) Model Number Unpaid Balance (if equipment is owned)
J. EXPERIENCE DATA
1. Please provide the following data for all major projects in progress or completed with the past three years.
Also, provide the same data for Corps of Engineer projects completed within the last five years. Those projects containing work similar in nature to that involved under this solicitation are to marked with an asterisk (*).
Name and Address of Owner Point of Contact and Telephone Number Project Location Type of Work performed by your firm Indicate whether you performed as a prime or subcontractor Name of Architect/Engineer in charge for Owner Address of Architect/Engineer Contract or Subcontract Amount Approximate date completed or, if not completed provide percent complete
Section 00 50 05 Page 4
Were time extensions necessary? Were penalties imposed? Were liens, claims or stop work orders filed?
2. How many years have you been in business as a contractor? ________________________________
3. How many years experience in the type of work involved in the subject solicitation do you have
a) as prime contractor? ___________________________________
b) as a subcontractor? ___________________________________
K. KEY PROJECT PERSONNEL
Please provide resumes for each of the following key personnel to be assigned to this project:
Project Engineer, Superintendent, Quality Control Manager/Technician, Safety Technician, Office Engineer
(Signature of Person Supplying Data)
(Print or Type Name and Title of Person Supplying Data)
(Phone No.)
(Email Address)
Section 00 50 05 Page 5
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01 PROJECT SCHEDULE
01 32 33 CONSTRUCTION PHOTOGRAPHY
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 30 MUNITIONS AND EXPLOSIVES OF CONCERN (MEC) CONSTRUCTION
SUPPORT
01 35 50 DIVING SERVICES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 05 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 71 23 SURVEY REQUIREMENTS
01 76 00 STRUCTURES MONITORING
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23.23 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - HOPPER
DREDGE
35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - PIPELINE
HYDRAULIC DREDGE
35 31 00 BEACHFILL
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SCOPE
This section presents a general description of the work to be accomplished under this contract at Indian River Inlet (IRI), in Delaware.
1.2 DESCRIPTION OF WORK
The contract work consists of placement of satisfactory beachfill material on Indian River Inlet North Shore to construct a beach berm and dune system along the Delaware coast, on the north side of Indian River Inlet, for coastal protection of Route 1.
a. Contract includes a Base Bid and 4 Options
b. The Base bid work includes the placement of approximately 300,000 cubic yards of satisfactory beachfill material along IRI north shore.
c. Option 1 includes the placement of 100,000 cubic yards of satisfactory beachfill material along IRI north shore.
d. Options 2, 3 and 4 each include the placement of 50,000 cubic yards of sand along IRI north shore shore.
e. The approved borrow area available for use under this contract is the Indian River Inlet Ebb Shoal. Obtain all beachfill material for the work under this contract solely from this approved inlet borrow area. Beachfill material from any other source including trucking from upland sources will not be considered under this contract.
f. The use of mechanical/bucket dredges will not be allowed under this contract.
Pre-placement condition surveys, as specified in Section 01 71 23 SURVEY REQUIREMENTS, will determine the exact location and quantity of beachfill material required within the limits indicated, and will be a determining factor in award of options for additional quantities of beachfill. Where options for additional beachfill are awarded, the additional beachfill will be placed immediately after the initial quantity.
1.3 CONTRACTOR ACCESS
Access to the work site is available by land and water. Access to the shorefront shall be at the locations indicated on the drawings. Access to the inlet borrow area is by water only. Conduct all investigations necessary to establish the specific routes to be used for the contract work. Compliance with all applicable Federal, State, County, and local regulations regarding weight limitations and other vehicle restrictions regarding the use of these routes is solely the responsibility of the Contractor.
Document the original conditions of the access area and route by taking detailed photographs of those areas prior to starting work. See Section 01 32 33 CONSTRUCTION PHOTOGRAPHY for requirements.
SECTION 01 11 00 Page 1
Any damage to the roads due to truck traffic or other Contractor operations shall be repaired, subject to the Contracting Officer's approval, at no additional cost to the Government.
1.4 CONTRACTOR'S WORK LIMIT
The Contractor's Work Limit is as shown on the contract drawings. Do not enter upon, affect, or damage, in any way, areas and structures outside that limit of work. Execute work with extreme care and diligence to prevent damage to any existing utilities or structures. Any existing utilities or structures damaged by contractor operations, regardless of whether intentional or accidental, shall be repaired and restored to original conditions, at no additional cost to the Government.
1.5 WORK HOURS
The Contractor may perform beachfill work 24 hours per day, 7 days per week, to complete the beachfill contract work. Equip land-based equipment with noise suppression equipment, if so directed by the Contracting Officer, at no additonal cost to the Government.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 11 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
EM 1110-2-1003 (2013) Hydrographic Surveying Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
33 CFR 88 Pilot Rules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Evidence Of Insurance
SD-11 Closeout Submittals
Certified Payrolls
1.3 SUPERVISION
1.3.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.3.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of
SECTION 01 30 00 Page 1 interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.3.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.3.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.4 PRECONSTRUCTION CONFERENCE
Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.
Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.4.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.5 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (FAR 52.236-4)
SECTION 01 30 00 Page 2
a. The indications of physical conditions on the drawings are the result of site investigations by surveys. Samples of materials to be dredged for beachfill were obtained by using vibracore samplers.
b. Weather Conditions. The site of the work is in the open ocean and is exposed to storms. However, safe refuge from the ocean is available in Indian River Inlet which is immediately south of the site. It is believed that work can be performed during all seasons of the year except during winter months when ice and storm conditions may interfere with dredging operations. Complete weather records and reports may be obtained from the local U.S. Weather Bureau Office nearest to the work site. The Contractor shall satisfy himself as to the hazards likely to arise from weather conditions during the construction period.
c. Channel Traffic. Traffic in the work area consists of ocean going and commercial fishing, sport fishing vessels, U.S. Coast Guard vessels, and recreational craft. The traffic and vessels using Indian River Inlet may interfere with dredging operations.
d. Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such as extent as may be necessary to afford a practicable passage. The Contractor shall request the U.S. Coast Guard to issue a Notice to Mariners for each work assignment advising navigation interests that the Contractor's dredging plant will be operating in the area. The Contractor shall submit each such request to the U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA 19147-4395. The Contractor shall furnish a copy of each request to the Contracting Officer not less than five days prior to the start of dredging.
Each request shall contain the approximate time required for completion of dredging. Upon completion of dredging, the Contractor shall promptly remove his plant, including ranges, buoys, piles and other marks placed by him under the contract in navigable waters and on shore.
e. Navigation Aids. Do not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under this contract, notify the Fifth Coast Guard District (dpw) at least 45 days prior to the desired date for movement of the aid. To request a relocation, Contractors shall contact Waterways Management Section Chief:
Mr. Chris Scraba at (757)398-6230 or Waterways Management Assistant Section Chief/NJ, DE, PA Project Officer: LCDR Tiffany Johnson at (757)398-6516;
e-mail cgd5waterways@uscg.mil or FAX (757)398-6303 at least 45 days before the desired date for movement of the aid. When making a request by telephone, speak to the designated points of contact. The leaving of voicemail messages will not be acceptable. The Fifth CG District (dpw) will coordinate all temporary relocations or discontinuances. A copy of each request (including records of telephone conversations) shall be furnished to the Contracting Officer.
f. Transportation Facilities. The work site is accessible from U.S. Route 113 and Delaware Route 1. The Contractor shall be responsible for all investigations of load carrying capacities of bridges and roadways.
SECTION 01 30 00 Page 3
g. Location. The north shore of Indian River Inlet is located at the Delaware Seashore State Park on the Atlantic Ocean coast of Delaware in Sussex County.
h. Laying of Submerged Pipelines and Obstruction of Channel. If it becomes necessary in the performance of this contract to use a submerged pipeline, the Contractor shall notify the Contracting Officer in advance of the scheduled for placement of the pipeline. If the submerged line is to be placed across a navigable channel, the Contractor shall submit a request for approval at least ten working days (Sundays and holidays excluded) prior to the desired closure date, to the U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA 19147-4395. A copy of each request shall be furnished to the Contracting Officer. This request shall contain the following information:
(1) Location (Channel Centerline Stationing) and depth (over the top of the pipeline) at which the submerged line will be placed;
(2) The desired length of time the channel is to be closed;
(3) The date and hour placement or removal will commence;
(4) The date and hour of anticipated completion; and
(5) The name and telephone number of the person to be contacted for information and response to any emergency condition.
The Coast Guard has indicated that the requirements of navigation may make it necessary to establish times other then those requested. The Contractor shall coordinate his plans with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements. It shall be the Contractor's responsibility to coordinate his plans with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements.
i. Bridge to Bridge Radio Telephone Equipment. In order that radio telephone communication may be made with passing vessels, all dredges engaged in work under the contract shall be equipped with and operate bridge-to-bridge radio telephone equipment. The radio telephone equipment shall operate on VHF Channel 13 (156.65 MHz) with low power output having a communication range of approximately ten miles. The frequency has been approved by the Federal Communication Commission.
j. Survey control description sheets for the project are included as Appendix A30.
k. Magnitude of the Contract Work. The estimated value of the contract work is more than $10,000,000.
l. Vibracore logs believed to be representative of the material to be dredged under this contract are provided in these specifications. Logs for the Ebb Shoal Borrow Area are included in Appendix B41. Associated sieve curves are included in Appendix B42.
m. Inspection of the Site. Prospective bidders are expected to visit the work sites to acquaint themselves with the site conditions and any problems incident to the prosecution of the work.
SECTION 01 30 00 Page 4
n. The location of submarine cables and pipelines are in proximity to the project limits of work. Use extreme caution when operating vessels and equipment in the locations where cables and pipelines exist. Comply with all rules and regulations governing activities within the vicinity of submarine cables and pipelines. Coordinate the location of submarine cables and pipelines with the Department of Homeland Security and the U.S. Coast Guard. Preliminary locations of these structures are identified on NOAA nautical charts for the area. Nautical charts can be downloaded from NOAA's website: http://www.nauticalcharts.noaa.gov/pdfcharts.
Be aware that additional uncharted submarine cable and submarine pipelines may exist within the area of work.
1.6 LAYOUT OF WORK (DEC 1996)
The Contractor shall lay out its work from Government-provided channel coordinates and survey control points, furnished as part of each work assignment. The Contractor shall furnish, at its own expense, such stakes, templates, platforms, equipment, range markers and labor as may be required in laying out any part of the work, from the channel coordinates and surveying benchmarks furnished by the Government and shall be responsible for all measurements in connection therewith. If any Government control is found disturbed or destroyed, this must be communicated to the Philadelphia District Surveys Branch through the COR before any control is re-established. The Contractor shall be responsible for executing the work to such lines and grades as may be established or indicated by the Contracting Officer. The Contractor shall have real time differential GPS positioning in accordance with the Corps surveying manual, EM 1110-2-1003, for class 1 survey requirements for dredge positioning. The Contractor shall provide real time positioning on a computer screen during dredging, and have the capability of playback in 15 minute intervals. The position must be recorded on disk every 15 minutes and submitted to the Contracting Officer on a daily basis. (CENAP)
1.7 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
DAVIS-BACON ACT CERTIFIED PAYROLLS
a. The contractor will use a commercially available electronic system to process and submit certified payrolls electronically to the Government. The Davis-Bacon Act establishes the requirements for preparing, processing, and providing certified labor payrolls.
b. The contractor shall be responsible for obtaining and providing access for all licenses and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon Act and related statutes. When the contractor uses an electronic Davis-Bacon Act payroll service, it shall be used to prepare, process, and maintain the relevant payrolls and basic records for all work under the construction contract. The electronic payroll service shall be capable of preserving the payroll and related basic records for the required three years after contract completion. The contractor shall obtain and provide electronic system access including electronic review to the Government, as required to comply with the Davis- Bacon Act and related statutes through the duration of the construction contract.
c. The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
SECTION 01 30 00 Page 5
(1) commercially available;
(2) compliant with appropriate Davis-Bacon Act payroll provisions in the FAR;
(3) able to accommodate the required number of employees and subcontractors that will be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;
(5) demonstrated security of data and data entry rights;
(6) able to produce contractor-certified electronic versions of weekly payroll data;
(7) able to identify erroneous entries and track the date/time of all versions of the certified Davis-Bacon Act payrolls submitted to the government over the life of the contract; and
(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
d. All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.(UAI 3 Jun 2019; Update 2 - 30 Nov 2021)
1.8 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in the clause of the contract entitled "Permits and Responsibilities". However, if, in the judgement of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or hurricane, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work, and equitable adjustment pursuant to Contract Clause entitled "Changes," will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damages to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense regardless of the cause of such damage. (CENAP)
SECTION 01 30 00 Page 6
1.9 CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specifications requirements shall be executed in triplicate copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies.
Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
(CENAP)
1.10 PERFORMANCE EVALUATION OF CONTRACTOR (MAR 2014)
a. As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work for contracts less than one year in duration.
Contracts in excess of one year will receive at a minimum, an annual interim evaluation in addition to the final evaluation. However, interim evaluation may be prepared at any time during contract performance when determined to be in the best interest of the Government. The evaluation will be entered into the Contractor Performance Assessment Reporting System
(CPARS).
b. CPARS is a web-enabled application that supports the completion, distribution, and retrieval of construction contract performance evaluations. CPARS is for UNCLASSIFIED use only. An evaluation assesses Contractor performance and provides a record, both positive and negative, on a given contract. Each evaluation is based on objective facts and supported by contract management data, such as contract performance elements that evaluate quality, timely performance, effectiveness of management, and compliance with contract terms, labor standards, and safety requirements. The Contractor will be rated either outstanding, above average, satisfactory, marginal, or unsatisfactory in the areas of Contractor Quality Control, Timely Performance, Effectiveness of Management, Compliance with Labor Standards, and Compliance with Safety Standards. The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be made a part of the official record. Performance Evaluation Reports will be available to all DOD Contracting offices for their future use in determining Contractor responsibility, in compliance with ER 415-1-17.
c. Upon successful award of the contract, the Contractor will be notified by CPARS via email that access has been granted to a contract within the system. The email will contain instructions of how to log into the system.
(CENAP)
1.11 SIGNAL LIGHTS (FEB 1983)
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection
SECTION 01 30 00 Page 7 operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working navigable channels, as approved by the Commandant, U.S. Coast Guard with respect to vessels in inland waters (33 CFR 88), as applicable. (CENAP)
1.12 ACCOMMODATIONS AND MEALS FOR GOVERNMENT INSPECTORS (1965 APR OCE)
a. The Contractor shall furnish regularly to Government inspectors on board the dredge a suitable separate area for an office. A separate trailer on the dredge may be supplied in lieu of a room. The trailer must be securely lashed to the dredge and enclosed by railings. The room or trailer shall be fully equipped and maintained to the satisfaction of the Contracting Officer; it shall be properly heated, ventilated, lighted and insulated from noise, and shall have a desk which can be locked, a chair for each inspector, and washing conveniences. The entire cost to the Contractor for furnishing, equipping and maintaining the foregoing accommodations shall be included in the cost of all bid items. If the Contractor fails to meet these requirements, the facilities referred to above will be secured by the Contracting Officer, and the cost thereof will be deducted from payments to the Contractor.
b. If the Contractor maintains on this work an establishment for the subsistence of his own employees, he shall, when requested, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer. The meals furnished will be paid for by the Government at a rate of $5.00 per person for each meal. (CENAP)
1.13 REQUIREMENT TO NOTIFY COAST GUARD OF RELEASE OF OBJECTS INTO THE
NAVIGABLE WATERS OF THE UNITED STATES
a. Requirement: As soon as a person has knowledge of any release from a vessel or facility into the navigable waters of the United States of any object that creates an obstruction prohibited under section 403 of this title, such person shall notify the Secretary and the Secretary of the Army, and the COR of such release.
b. Restriction on use of notification: Any notification provided by an individual in accordance with subsection (a) of this section may not be used against such individual in any criminal case, except a prosecution for perjury or for giving a false statement.
(Pub. L. 92–340, §15, as added Pub. L. 109–241, title VI, §602, July 11, 2006, 120 Stat. 553.)
1.14 INSURANCE REQUIREMENTS
Evidence of Insurance: Evidence of the following insurance shall be submitted to the Contracting Officer prior to commencement of work.
Insurance shall be maintained throughout the period of performance:
a. General Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $500,000 per occurrence.
b. Automobile Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $200,000 per person and $500,000 per accident. Property Damage Liability - $20,000 per accident.
c. Workmen's Compensation and Employer's Liability Insurance: Compliance
SECTION 01 30 00 Page 8 with applicable workmen's compensation and occupational disease statutes is required. Employer's liability coverage in the minimum amount of $100,000 is also required."
d. Applicable Marine Casualty and Marine Workmen's Compensation Insurance:
As appropriate for this contract.
1.15 PARTNERING
Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.15.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
1.16 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of
SECTION 01 30 00 Page 9 any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 10
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G,COR Preliminary Project Schedule; G,COR Initial Project Schedule; G,COR Periodic Schedule Update; G,COR
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
SECTION 01 32 01 Page 1
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of work is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
SECTION 01 32 01 Page 2
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Mobilization.
c. Long procurement activities.
d. Pre-Placement condition surveys.
e. Before-dredging survey of borrow area.
f. Provision of Government field office.
g. Beachfill operations and sequence.
h. After-dredging survey of borrow area.
SECTION 01 32 01 Page 3
i. Post-placement condition surveys.
j. Submission and approval of as-built drawings.
k. Demobilization
l. Contractor's pre-final inspection.
m. Correction of punch list from Contractor's pre-final inspection.
n. Government's pre-final inspection.
o. Correction of punch list from Government's pre-final inspection.
p. Final inspection.
Tasks that are site specific shall be clearly indicated as such.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:
http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
SECTION 01 32 01 Page 4
Field Activity Code Length Description
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
SECTION 01 32 01 Page 5
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the…