Q&A Shipyard Overhaul of S/V Reconnaissance

W912BU19Q0023

Update September 18, 2019

1. Section H-921 - What material is the equipment survey rack?

The equipment rack is 'off the shelf' Steel rack.

2. Section M-151 - Are the fuel valves to be located inside or outside of the main cabin?

The fuel valves will be located below deck, aft of the main cabin in a dry void space, operated by levers/knobs mounted on the aft bhd of the main cabin (in the weather).

3. Section H-921 - It is specified that a representative from Diamond Sea Glaze perform the repair/replacement to the sliding window hardware. Is it permissible for us to do this work ourselves? We can purchase replacement parts from Diamond Sea Glaze if necessary to affect the repairs but it may be cost prohibitive to have them come from British Columbia, Canada to do this work.

It would be acceptable for the Contractor to perform the work themselves as long as any part that is required would be a Diamond Sea Glaze part and any repairs performed would be in accordance with Diamond Sea Glaze recommended practices.