Q&A Shipyard Overhaul of S/V Reconnaissance

W912BU19Q0023

1. Section H-921 - What material is the equipment survey rack?

The equipment rack is 'off the shelf' Steel rack.

2. Section M-151 - Are the fuel valves to be located inside or outside of the main cabin?

The fuel valves will be located below deck, aft of the main cabin in a dry void space, operated by levers/knobs mounted on the aft bhd of the main cabin (in the weather).