Attachment_1_to_W912BU-19-B-0012_Reference_Drawings_1.pdf
PDF 12 MB Posted
- Attached to
- Specialty Steel Barge Federal contract opportunity
- Solicitation number
- W912BU-19-B-0012
About this file
Section J Attachment 1 titled Reference Drawings 1
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REV. DESCRIPTION DATE APRD.
- Initial Issue 12/11/2017 TJK
1 2/9/2018 TJK
General Notes:
DR. BY DES. BY CHK'D BY
CJH TJK
APRD. FOR THE DIR. - CH. DES. BR. SIZE REV.
DATE
SHEET: COVER
788-D115-02 1
Updated tangent-moment plot on page 10
REVISIONS
MARINE DESIGN CENTER
100 PENN SQUARE EAST
PHILADELPHIA, PA 19107
DEPARTMENT OF THE ARMY
MARINE DESIGN CENTER
CORPS OF ENGINEERS
December 11, 2017 SCALE: AS SHOWN
LOUISVILLE DISTRICT - WICKET LIFTER KEEN
110'-6" x 60' x 8'-6"
INCLINE EXPERIMENT RESULTSRECOMMENDED - CH. HULL SEC.
/S/ Timothy Keyser, PE
PROJECT NO. DRAWING NO.
/S/ Gregory Lee, PE A 2525
Revised per ABS Comments:
Updated incline weight on pages 6-9, 13-15
Updated Condition 1 & 2 on pages 13-17 e5mdctjk
PE STAMP
e5mdctjk Stamp
Rev 1
MDC PROJECT # 2525
DATE 12/11/17
Description of Vessel Type: Official Number:
Builder: Gross Tons:
Hull No.:
Date Built: Owner:
Hull: Owner's Address:
Vessel Inclined At:
Machinery: Date:
Time:
Test Requested By:
Plans Furnished By:
Classed By Route Offsets Measured By
Curves of Form Computed By:
Inspected X Ocean
Safety Certificate Coastwise Test Conducted By:
Load Line Great Lakes Stability Calculations By:
Bays Calculations Checked By:
Rivers x
Limited
STABILITY TEST DATA
MDC Project # 2525
American Bureau of Shipping
USACE MDC - Collin Helm
December-17 Welded steel
(2) 200 kW Generators
(1) 99 kW Generators
(2) Cranes: Appleton KB600-77, EB750-71-47
(8) Winches
U.S. Army Corps of Engineers - Olmsted Lock and Dam
567 New Dam Road, Olmsted, IL 62970
Conrad Amelia
CELRL WICKET LIFTER KEEN
Floating Crane Barge Barge Conrad Industries C1166 (MDC Hull No. 788)
USACE MDC
USACE MDC - Collin Helm
Government / ABS
USACE MDC - Tim Keyser, PE
U.S. Army Corps of Engineers Marine Design Center
Philadelphia, PA 19107
November 20, 2017
USACE MDC
DATE 12/11/17
PRINCIPAL DIMENSIONS
Length Over All 110 Ft. 6 In. ( 110.500 Ft.)
Length Between Perpendiculars which are at the extremities of Design waterline 110 Ft. 6 In. ( 110.500 Ft.)
Length between Draft Marks, (Frame #1 to #13) 84 Ft. 6 In. ( 84.500 Ft.)
Breadth, extreme at 8.5 Ft above Baseline 60 Ft. 0 In. ( 60.000 Ft.)
Breadth, molded, amidships at 8.5 Ft above Baseline 60 Ft. 0 In. ( 60.000 Ft.)
Breadth at load water line 60 Ft. 0 In. ( 60.000 Ft.)
Depth amidships, from Baseline to Molded Deck 8 Ft. 6 In. ( 8.500 Ft.)
Molded Baseline 4 Ft. 0 In. ( 4.000 Ft.)
Apparent full-load mean draft for stability
Bottom of Keel 4 Ft. 0.000 In. ( 4.000 Ft.)
Displacement, fresh water, tons (2240 lb), at above full-load draft 618.05 Long Tons Freeboard amidships at above full-load draft 4 Ft. 6 In. ( 4.500 Ft.)
Freeboard at low point of deck 4 Ft. 6 In. ( 4.500 Ft.)
Location of ports, in hull, which may affect stability 0 Ft. 0 In. ( 0.000 Ft.)
General Information
Names and duties of official observers ABS represented by Builders represented by Owners represented by Test conducted by Weather, tide, and mooring conditions Condition of ship as to completeness and as to water in boilers, machinery and bilges
Stability Test: CELRL WICKET LIFTER KEEN
All machinery installed, tanks empty except for fuel tank, minor work to be completed.
All compartments dry with no water in bilges.
Sacha Wichers, ABS Surveyor Thomas Philbrook (Conrad Industries) Collin Helm (CEMDC) Lines slack, no wind, moderate traffic-induced waves - Water Temp = 59.8 deg F, SG = 1.001
Collin Helm, Conducting test & recording data
DATE 12/11/17
Water Temperature 59.8 degs F Water Specific Gravity 1.001 11/13/2017
P/S/CL Freeboard
CL 52.4375
P 54.8125 S 44.9375 P 56.625 S 45.6875 P 59.6875 S 47.625 P 60.1875 S 49.625 P 62.75 S 50.625
CL* 59.4375
f = Measured Freeboard t = Deck Thickness = 1/2 inches D = Molded Depth from Lines D = 102 inches b = Measured Bulwark Height = 0 inches T = Calculated Molded Draft = See below equations
T = D + t - f
T = D + t + b - f f t D b T Location (inches) (Inches) (Inches) (Inches) (Feet) Port
6.500 54.813 0.500 102.000 0.000 3.974
10.854 55.217 0.500 102.000 0.000 3.940
20.813 56.143 0.500 102.000 0.000 3.863
26.000 56.625 0.500 102.000 0.000 3.823
41.667 58.113 0.500 102.000 0.000 3.699
45.500 58.508 0.500 102.000 0.000 3.666
58.250 59.688 0.500 102.000 0.000 3.568
61.792 60.188 0.500 102.000 0.000 3.526
62.042 60.221 0.500 102.000 0.000 3.523
81.125 62.750 0.500 102.000 0.000 3.313
84.500 - - - - -
Stbd
6.500 - - - - -
10.854 44.938 0.500 102.000 0.000 4.797
20.813 45.688 0.500 102.000 0.000 4.734
26.000 46.169 0.500 102.000 0.000 4.694
41.667 47.625 0.500 102.000 0.000 4.573
45.500 48.039 0.500 102.000 0.000 4.538
58.250 49.253 0.500 102.000 0.000 4.437
61.792 49.600 0.500 102.000 0.000 4.408
62.042 49.625 0.500 102.000 0.000 4.406
81.125 50.475 0.500 102.000 0.000 4.335
84.500 50.625 0.500 102.000 0.000 4.323
HEEL
Average (Degs)
10.854 50.077 0.500 102.000 0.000 4.369 0.786
20.813 50.915 0.500 102.000 0.000 4.299 0.758
26.000 51.397 0.500 102.000 0.000 4.259 0.794
41.667 52.869 0.500 102.000 0.000 4.136 0.716
58.250 54.470 0.500 102.000 0.000 4.002 0.705
61.792 54.894 0.500 102.000 0.000 3.967 0.803
62.042 54.923 0.500 102.000 0.000 3.965 0.841
81.125 56.612 0.500 102.000 0.000 3.824 0.776
AVERAGE 0.772
Interpolated
Stability Test: CELRL WICKET LIFTER KEEN
With Bulwark or Side Shell Coaming -
FRAME #13 S 6'-6" Fwd of Transom FRAME #14 at Transom, 10'-6" to Port of CL
FRAME #3-4 S 20'-9.75" Aft of Headlog FRAME #8-9 P 58'-3" Aft of Headlog FRAME #6-7 S 41'-8" Aft of Headlog FRAME #9-10 P 29'-2.5" Fwd of Transom FRAME #9 10 S 28'-11.5" Fwd of Transom FRAME #12-13 P 9'-10.5" Fwd of Transom
FRAME #4 P 26' Aft of Headlog
FREEBOARD & DRAFT READINGS
POSITION
FRAME #0 at Bow, 20' to Port of CL FRAME #1 P 6'-6" Aft of Headlog FRAME #1-2 S: 10'-10.25" Aft of Headlog
DISPLACEMENT CALCULATIONS
Due to deck machinery locations and bumper arrangements, freeboards could not be obtained at consistent locations on both port and starboard sides. In order to determine average drafts, port and starboard drafts were interpolated along the length of the barge;
averages were then determined and plotted.
Without Bulwark or Side Shell Coaming -
DATE 12/11/17
Approx. Freeboard Reading Locations Port: ft. aft of Fr. 0 Stbd: ft. aft of Fr. 0
1 0 1 10.854 2 6.500 2 20.813 3 26.000 3 41.667 4 58.250 4 62.042 5 61.792 5 84.500 6 81.125 7 91
Forward (10.854' aft of Fr. 0) 4.37 ft - Interpolated Average Mean of forward and after draft 4.10 ft Aft (81.125' aft of Fr. 0) 3.82 ft - Interpolated Average Hog or sag (Sag) 0.006 ft
(from draft marks) Amidships Port 3.67 ft - Interpolated Trim forward 0.870 ft X (from freeboards) STBD 4.54 ft - Interpolated Longitudinal center of floatation 41.85 ft aft of Fr. 0
110.5 feet Molded keel draft at LCF 4.130 ft 0 in Molded keel draft at LCF, correct for hog/sag 4.124 ft
Forward Draft Marks 4.36 feet Total displacement at above drafts, FW - LT Specific gravity of water 1.001 equals 35.936 ft3/LT Total displacement corrected for density 641.03 LT
4.1022
Note: GHS was used to calculate actual condition displacement
Stability Test: CELRL WICKET LIFTER KEEN
Draft when inclined (check)
Molded drafts corrected to "curves of form" perpendiculars for use in calculations
Aft Draft Marks feet
Mean of amidships P and S feet
Bottom of keel below baseline Distance between "curves of form" perpendiculars
3.77
0.000
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
‐19.5000.50020.50040.50060.50080.500
INTERPOLATED DRAFT READINGS
Port
Stbd
AVERAGE
AVERAGE HEEL = 0.772 DEGS TO STBD
Note: black dots represent interpolated values
REV 1
MDC PROJECT #2525
DATE 12/11/17
Pendulums Length Width Height LCG, ft. from FP TCG, ft off CL VCG, ft No.
(in) (in) (in) (+ AFT) (+ STBD) (abv. DK) 1 13,800 48.500 48.500 60.500 40.063 -4.188 2.521 1 2 14,100 48.500 48.500 61.000 40.021 4.188 2.542 3 14,000 49.000 49.000 61.000 35.917 4.208 2.542 2 4 13,900 49.000 49.000 61.000 36.000 -4.208 2.542 15 17,200 61.000 61.000 60.500 31.417 -5.052 2.521 3
16 6,260 44.250 44.250 44.500 29.219 0.000 1.854 25 6,360 44.250 44.250 44.750 31.406 4.969 1.865 * Degital Inclinometers should be same locations.
26 6,280 44.250 44.250 44.000 26.760 4.646 1.833 New 45,260 125.250 52.000 37.500 36.990 0.000 1.563 Total 137,160
Certified by: Conrad Ship Yard, Doc. # ENG-995-R1
Digital Inclinometer Initial Reading (deg)
0.88
0.07
1.38
Location
27.5" Aft Frame #0, 77" off CL port side
43'-1.5" Aft Frame #0, 91" off CL starboard side
100" Fwd of Stern, 18'-7.5" off CL port side
217.125
Length to Batten (in.)
212.250
216.625
SHIP AT TIME OF STABILITY TEST
Initial Position
No. LBS
Stability Test: CELRL WICKET LIFTER KEEN
Weight Dimensions
DATE 12/11/17
Port STBD No. PORT STBD PORT STBD +Stbd / -Port Feet Feet inches inches
1.000 6.161 0.000 0.000
2.000 6.295 0.000 0.000 1.000 0.000 0.000
3.000 6.250 0.000 0.000 2.000 0.000 0.000
4.000 6.205 0.000 0.000 3.000 0.000 0.000
15.000 7.679 0.000 0.000
16.000 2.795 0.000 0.000
25.000 2.839 0.000 0.000 1.000 0.000 0.000
26.000 2.804 0.000 0.000 2.000 0.000 0.000 New 20.205 0.000 0.000 3.000 0.000 0.000
TOTAL 0.000
1.000 6.161 0.000 0.000
2.000 6.295 23.792 149.760 1.000 2.563 0.012
3.000 6.250 23.750 148.438 2.000 2.375 0.011
4.000 6.205 0.000 0.000 3.000 2.438 0.011
15.000 7.679 0.000 0.000
16.000 2.795 0.000 0.000
25.000 2.839 21.375 60.690 1.000 0.720 0.013
26.000 2.804 23.219 65.095 2.000 0.620 0.011 New 20.205 0.000 0.000 3.000 0.610 0.011
TOTAL 423.983
1.000 6.161 0.000 0.000
2.000 6.295 23.792 149.760 1.000 5.563 0.026
3.000 6.250 23.750 148.438 2.000 5.375 0.025
4.000 6.205 0.000 0.000 3.000 5.563 0.026
15.000 7.679 0.000 0.000
16.000 2.795 21.865 61.104
25.000 2.839 21.375 60.690 1.000 1.500 0.026
26.000 2.804 23.219 65.095 2.000 1.420 0.025 New 20.205 22.375 452.087 3.000 1.370 0.024
TOTAL 937.173
SHIP AT TIME OF STABILITY TEST
Stability Test: CELRL WICKET LIFTER KEEN
2nd
0.026
Digital Inclinometer
0.025
Pendulum
Zero
1 st
Pendulum
Digital Inclinometer
0.000
0.000
Pendulum
0.011
Digital Inclinometer
0.011
Moment Pendulum / Inclinometer Deflection Tangent Tangent Average
Trial Weight Distance from Initial
Position
No. LT +Stbd / -Port
FT-LT
DATE 12/11/17
Port STBD No. PORT STBD PORT STBD +Stbd / -Port Feet Feet inches inches
SHIP AT TIME OF STABILITY TEST
Stability Test: CELRL WICKET LIFTER KEEN
Moment Pendulum / Inclinometer Deflection Tangent Tangent Average
Trial Weight Distance from Initial
Position
No. LT +Stbd / -Port
FT-LT
1.000 6.161 22.375 137.846
2.000 6.295 23.792 149.760 1.000 8.188 0.038
3.000 6.250 23.750 148.438 2.000 7.938 0.037
4.000 6.205 22.375 138.845 3.000 8.125 0.038
15.000 7.679 22.250 170.848
16.000 2.795 21.865 61.104
25.000 2.839 21.375 60.690 1.000 2.200 0.038
26.000 2.804 23.219 65.095 2.000 2.120 0.037 New 20.205 22.375 452.087 3.000 2.020 0.035
TOTAL 1,384.712
1.000 6.161 23.458 -144.520
2.000 6.295 22.729 -143.072 1.000 7.688 -0.035
3.000 6.250 22.729 -142.057 2.000 8.063 -0.038
4.000 6.205 22.667 -140.655 3.000 8.188 -0.038
15.000 7.679 22.490 -172.688
16.000 2.795 22.281 -62.268
25.000 2.839 22.750 -64.594 1.000 2.110 -0.037
26.000 2.804 22.219 -62.292 2.000 2.140 -0.037 New 20.205 22.729 -459.243 3.000 2.200 -0.038
TOTAL -1,391.389
1.000 6.161 23.458 -144.520
2.000 6.295 0.302 1.901 1.000 5.313 -0.024
3.000 6.250 0.302 1.888 2.000 5.813 -0.027
4.000 6.205 22.667 -140.655 3.000 5.875 -0.027
15.000 7.679 22.490 -172.688
16.000 2.795 22.281 -62.268
25.000 2.839 0.063 0.179 1.000 1.500 -0.026
26.000 2.804 0.260 -0.729 2.000 1.570 -0.027 New 20.205 22.729 -459.243 3.000 1.630 -0.028
TOTAL -976.135
5th
Pendulum
-0.026
Digital Inclinometer
-0.027
3rd
4th
Pendulum
Digital Inclinometer
0.038
Digital Inclinometer
0.037
Pendulum
-0.037
-0.038
DATE 12/11/17
Port STBD No. PORT STBD PORT STBD +Stbd / -Port Feet Feet inches inches
SHIP AT TIME OF STABILITY TEST
Stability Test: CELRL WICKET LIFTER KEEN
Moment Pendulum / Inclinometer Deflection Tangent Tangent Average
Trial Weight Distance from Initial
Position
No. LT +Stbd / -Port
FT-LT
1.000 6.161 23.458 -144.520
2.000 6.295 0.302 1.901 1.000 2.250 -0.010
3.000 6.250 0.302 1.888 2.000 2.688 -0.013
4.000 6.205 22.667 -140.655 3.000 2.688 -0.012
15.000 7.679 22.490 -172.688
16.000 2.795 0.000 0.000
25.000 2.839 0.063 0.179 1.000 0.670 -0.012
26.000 2.804 0.260 -0.729 2.000 0.740 -0.013 New 20.205 0.000 0.000 3.000 0.790 -0.014
TOTAL -454.624
1.000 6.161 0.000 0.000
2.000 6.295 0.302 1.901 1.000 0.188 0.001
3.000 6.250 0.302 1.888 2.000 0.000 0.000
4.000 6.205 0.000 0.000 3.000 0.063 0.000
15.000 7.679 0.042 -0.323
16.000 2.795 0.000 0.000
25.000 2.839 0.063 0.179 1.000 0.060 0.001
26.000 2.804 0.260 -0.729 2.000 0.050 -0.001
6th
7th
-0.012
Digital Inclinometer
-0.013
Pendulum
Pendulum
0.000
Digital Inclinometer
0.000 y = 0.0000270x ‐ 0.0000784 R² = 0.9999340
‐0.04
‐0.03
‐0.02
‐0.01
0.00
0.01
0.02
0.03
0.04
‐1,700.00 ‐1,200.00 ‐700.00 ‐200.00 300.00 800.00 1,300.00
Ta ng en t
Moment (ft‐LT)
Tangent‐Moment Plot
Pend. 1
Pend. 2
Pend. 3
Digital Inc. 1
Digital Inc. 2
Digital Inc. 3
Average Tangent
Linear (Average Tangent)
REV 1
DATE 12/11/17
Corrected Displacement LT. 641.03 LT.
Mean virtual metacentric height obtained from plot of inclining moments versus tangents of angles of heel feet. 57.78 feet.
Correction for free surface feet.* 57.846 feet.
Mean metacentric height (GM)= feet. 70.65 feet.
Transverse metacenter above baseline corresponding to draft at L.C.F. (corrected for hog or sag) feet.** Transverse metacenter above baseline corrected (for trim, and hog or sag) 68.57 feet.
C.G. above baseline feet. 12.80 feet.
Longitudinal metacenter above C.G. 202 feet.
Longl.GM x ∆
1178.40 ft-LT.
Trim by stern -0.87 feet.
-1.60 feet.
L.C.B. aft of bow, which is 40.23 feet.
L.C.G. aft of bow 41.83 feet. 40.21 feet.
Stability Test: CELRL WICKET LIFTER KEEN
SHIP AT TIME OF STABILITY TEST - CONDITION 0
From GHS
L
Trim x Moment to Trim
FROM
INDEPENDENT
CALCULATIONS
moment displacement x tangent
FROM
HYDROSTATIC
CURVES
Displacement
Moment to alter trim 1 foot, Trimming lever =
From GHS
Displacement And Weight
C.G. Above LT Lever Longitudinal Lever Transverse Lever Vertical Base Feet Moments Feet Moments Feet Moments
Feet Forward
Spud 1 See Below -62.74 35.51 -2227.59 -0.27 16.87 10.63 -667.11
Spud 2 See Below -12.17 74.75 -909.86 -7.50 91.29 5.45 -66.33
Aft Spud See Below 0.92 33.04 30.38 11.72 10.78 9.13 8.39
Bumper 1 See Below 0.00 - 757.75 - -232.82 - -506.78
Bumper 2 See Below Wicket Crane Boom* See Below Maint. Crane Boom* See Below Length B.P. 110.5 feet.
Molded draft at longitudinal center of flotation corresponding to above displacement for FRESH water 3.665 feet.
Transverse metacenter above base at L.C.F. draft 77.91 feet.
Center of gravity above base 12.30 feet.
Metacentric height, G.M. 65.61 feet.
Longitudinal metacenter above C.G. at L.C.F. draft 213.6 feet. Longitudinal center of floatation, aft of FR. 0 (-fwd) 41.86 feet.
Moment to alter trim 1 foot at L.C.F. draft 91.36 ft-LT Difference between L.C.F. and midships draft 0.007 feet.
C.B. of ship on even keel at L.C.F. draft, aft of FR. 0 (-fwd) 41.29 feet. Molded draft amidships 3.658 feet.
C.G. aft of FR. 0 (- fwd) 41.31 feet. Draft at forward perpendicular 3.730 feet.
Trimming lever -0.02 feet. Draft at aft perpendicular 3.570 feet.
Trim, +aft/-fwd -0.25 feet.
* Condition 1 does not include the spuds, spud collars, and bumpers. These items are always on board, but their CGs can vary based on the position they are deployed in.
Condition 1 does included all components of both the maintenance crane and the wicket lifter crane. Since the booms, jobs, and blocks all have variable centers of gravity, it is necessary to remove them from the overall lightship displacement and model them in their respective positions for lifting stability. See drawings BMD-0727 and BMD-0728 for each crane's centers of gravity and geometry.
Stowed position for the wicket crane is facing aft, 25 Deg to port, with a boom elevation of zero degrees and the job boom folded.
Stowed position for the maintenance crane is facing forward, 20 Deg to starboard, with a boom elevation of zero degrees and the boom fully retracted.
With both cranes in the stowed positions, and with spuds and bumpers in their worst case positions, the weights and centers of gravity are as follows (Condition 2):
Weight LCG TCG VCG The cranes have the following vertical pin offsets and centerlines of rotation:
(LT)
(ft, from FP
+ AFT)
(ft, off CL + STBD) (ft, abv. BL)
Ship in Condition 2 494.85 43.066 1.588 10.379 Maint. Crane Boom 31.52 47.391 6.411 37.360 Maint. Crane Blocks 1.16 20.734 16.080 39.820 Maint. Crane Wicket Crane Boom 24.44 12.047 -10.047 18.125 Wicket Crane Wicket Crane Jib 15.07 20.115 -13.807 11.474 Spud 1 11.91 9.000 22.500 34.000 Spud 2 12.17 9.000 -22.500 34.000 Aft Spud 12.04 88.500 -2.479 34.000 Spud Collar 1 0.54 9.000 22.500 34.000 Spud Collar 2 0.54 9.000 -22.500 34.000 Aft Spud Collar 0.54 88.500 -2.479 34.000 Bumper 1 (FWD) 6.11 14.583 -28.333 1.112 Bumper 2 (AFT) 6.27 67.750 -28.333 1.112
Weight To Add Weight To Relocate
Tanks To Remove
12.3041.31 0.97
LT
Stability Test: CELRL WICKET LIFTER KEEN
Feet
C.G. From M.P.
Feet Aft Ship as Inclined
C.G. From Bow
+ AFT
C.G. From CL
+ STBD
666.671.0440.21 25775.82
Items
List of Major Equipment, etc. included in condition 1
Items Weight
Rev 1
MDC PROJECT # 2525
Ship In Condition 1*
Weight To Remove
567.04
641.03 12.80 8207.50
C.G. Above Base
LIGHTSHIP - CONDITION 1
CRANE WEIGHT AND CG DETAILS
-9.50
Description
Description Vertical Pivot Point (+ ft Above Baseline)
CL of Rotation Measured from Fr. 0 (+ ft Aft)
34.12 20.15
65.00
DATE 12/11/17
LCG TCG VCG L. Mom. T. Mom. V. Mom.
(lbs) (LT) (ft, from FP
+ AFT)
(ft, off CL + STBD) (ft, abv. BL) (ft-LT) (ft-LT) (ft-LT)
8' Timber for Weight (14 at Stbd) 231.0 0.103 34.790 22.597 8.750 3.588 2.330 0.902 8' Timber for Weight (11 at CL) 181.5 0.081 34.790 0.507 8.750 2.819 0.041 0.709 8' Timber for Weight (10 at Port) 165.0 0.074 34.790 -22.672 8.750 2.563 -1.670 0.645 Pendulum #1 143.0 0.064 2.292 -6.417 17.670 0.146 -0.410 1.128 Soap water & Steel Container 193.4 0.086 2.292 -6.417 9.170 0.198 -0.554 0.792 Pendulum #2 143.0 0.064 43.125 7.583 17.670 2.753 0.484 1.128 Soap water & Steel Container 193.4 0.086 43.125 7.583 9.170 3.724 0.655 0.792
Protection Channel 200.0 0.089 43.125 7.583 9.000 3.850 0.677 0.804 Pendulum #3 143.0 0.064 82.667 -18.625 17.670 5.277 -1.189 1.128 Soap water & Steel Container 193.4 0.086 82.667 -18.625 9.170 7.138 -1.608 0.792 Aluminum Grating 20.0 0.009 -2.333 8.583 8.750 -0.021 0.077 0.078 Weight #1 13,800.0 6.161 40.063 -4.188 11.021 246.814 -25.798 67.896 Weight #2 14,100.0 6.295 40.021 4.188 11.042 251.917 26.359 69.503 Weight #3 14,000.0 6.250 35.917 4.208 11.042 224.479 26.302 69.010 Weight #4 13,900.0 6.205 36.000 -4.208 11.042 223.393 -26.114 68.517 Weight #15 17,200.0 7.679 31.417 -5.052 11.021 241.235 -38.793 84.624 Weight #16 6,260.0 2.795 29.219 0.000 10.354 81.656 0.000 28.936 Weight #25 6,360.0 2.839 31.406 4.969 10.365 89.171 14.108 29.428 Weight #26 6,280.0 2.804 26.760 4.646 10.333 75.025 13.025 28.970 Weight New 45,260.0 20.205 36.990 0.000 10.063 747.388 0.000 203.316 Rigging Crew and Witnesses 960.0 0.429 11.292 -7.750 11.500 4.839 -3.321 4.929 Pendulum #1 Recorder - Rainis 260.0 0.116 2.292 -6.417 11.500 0.266 -0.745 1.335 Pendulum #2 Recorder - Helm 180.0 0.080 43.125 7.583 11.500 3.465 0.609 0.924 Pendulum #3 Recorder - To 160.0 0.071 82.667 -18.625 11.500 5.905 -1.330 0.821
TOTALS: 140526.8 62.7 35.51 -0.27 10.63 2227.6 -16.9 667.1
Note: During the incline test, the maintenance crane and wicket crane booms and blocks were listed as weight to remove. It was later determined that these weights would best be represented as part of the official lightship displacement; therefore, these items were moved to the "Weights to be Relocated" section to be accounted for in their stowed position.
Stability Test: CELRL WICKET LIFTER KEEN
WEIGHTS TO BE REMOVED
Description Weight
DATE 12/11/17
Stability Test: CELRL WICKET LIFTER KEEN
SpG. Snding Volume LCG TCG VCG L. Mom. T Mom. V. Mom. FSM
Description Density (ft-in) (Gal.) (lbs) (LT) (ft, from FP
+ AFT)
(ft, off CL + STBD) (ft, abv. BL) (ft-LT) (ft-LT) (ft-LT) (ft-LT)
Fuel Oil Tank 0.870 62.75" (92.3%) 3757 27265.49 12.17 74.750 -7.500 5.449 909.864 -91.291 66.326 44.229
TOTALS: 27265.49 12.172 74.750 -7.500 5.449 909.864 -91.291 66.326 44.229-
TANKS TO BE REMOVED
DATE 12/11/17
Stability Test: CELRL WICKET LIFTER KEEN
LCG TCG VCG L. Mom. T Mom. V. Mom.
(lbs) (LT) (ft, from FP
+ AFT)
(ft, off CL + STBD) (ft, abv. BL) (ft-LT) (ft-LT) (ft-LT)
Cabinet 60.0 0.03 52.000 -13.750 10.750 1.393 -0.368 0.288 Stbd Hand Rail 200.0 0.09 31.000 30.000 10.167 2.768 2.679 0.908 Life Saving & Safety 100.0 0.04 63.250 0.000 4.000 2.824 0.000 0.179 Spud #1 0.0 0.00 9.000 22.500 34.000 0.000 0.000 0.000 Spud #2 0.0 0.00 9.000 -22.500 34.000 0.000 0.000 0.000 Spud - Aft 0.0 0.00 88.500 -2.479 34.000 0.000 0.000 0.000 Spud Collar #1 0.0 0.00 9.000 22.500 34.000 0.000 0.000 0.000 Spud Collar #2 0.0 0.00 9.000 -22.500 34.000 0.000 0.000 0.000 Spud Collar #3 0.0 0.00 88.500 -2.479 34.000 0.000 0.000 0.000 Bumper #1 (FWD) 0.0 0.00 14.583 -28.333 1.112 0.000 0.000 0.000 Bumper #2 (AFT) 0.0 0.00 67.750 -28.333 1.112 0.000 0.000 0.000 Wire Rope Guard1 52.0 0.02 0.500 -17.600 9.250 0.012 -0.409 0.215 Wire Rope Guard2 105.0 0.05 0.500 -7.250 9.250 0.023 -0.340 0.434 Wire Rope Guard3 92.0 0.04 0.500 -3.000 9.250 0.021 -0.123 0.380 Wire Rope Guard4 69.0 0.03 0.500 1.000 9.250 0.015 0.031 0.285 Wire Rope Guard5 21.0 0.01 0.500 14.500 9.250 0.005 0.136 0.087 Wire Rope Guard6 33.0 0.01 0.500 18.250 9.250 0.007 0.269 0.136 Wire Rope Guard7 37.0 0.02 3.500 4.000 9.250 0.058 0.066 0.153 Wire Rope Guard8 38.0 0.02 3.500 13.750 9.250 0.059 0.233 0.157 Wire Rope Guard9 231.0 0.10 10.250 8.500 9.250 1.057 0.877 0.954 Wire Rope Guard10 59.0 0.03 11.250 -1.000 9.250 0.296 -0.026 0.244 Wire Rope Guard11 144.0 0.06 17.000 20.000 9.250 1.093 1.286 0.595 Wire Rope Guard12 132.0 0.06 21.500 23.750 9.250 1.267 1.400 0.545 Wire Rope Guard13 136.0 0.06 30.000 23.750 9.250 1.821 1.442 0.562 Wire Rope Guard14 91.0 0.04 39.000 23.750 9.250 1.584 0.965 0.376 Wire Rope Guard15 98.0 0.04 69.250 23.750 9.250 3.030 1.039 0.405 Wire Rope Guard16 136.0 0.06 78.000 23.750 9.250 4.736 1.442 0.562 Wire Rope Guard17 81.0 0.04 80.000 20.000 9.250 2.893 0.723 0.334 Wire Rope Guard18 64.0 0.03 88.500 6.500 9.250 2.529 0.186 0.264 Wire Rope Guard19 81.0 0.04 80.000 -20.000 9.250 2.893 -0.723 0.334
TOTALS: 2060.0 0.920 33.038 11.725 9.128 30.383 10.783 8.394
Note: Items in red removed per ABS comments
WEIGHTS TO BE ADDED
DATE 12/11/17
Stability Test: CELRL WICKET LIFTER KEEN
LCG TCG VCG L. Mom. T Mom. V. Mom.
(lbs) (LT) (ft, from FP
+ AFT)
(ft, off CL + STBD) (ft, abv. BL) (ft-LT) (ft-LT) (ft-LT)
Port Handrail - Test Position -200.0 -0.089 51.000 -30.000 10.167 -4.554 2.679 -0.908 Port Handrail - Final Pos 200.0 0.089 33.500 -30.000 10.167 2.991 -2.679 0.908
Fwd Crane Test Position (CL Rotation is 9'-6" Fwd Frame 0, Boom Facing Fwd on CL at 27 Deg Elevation Angle with Arm Tucked in) Turret Assembly - CG at CL of Rotation; Do not need to remove for Lightship Weight because the CG is not variable Boom -54,750.0 -24.442 -31.602 0.000 29.130 772.415 0.000 -712.000 Jib Boom -33,750.0 -15.067 -42.557 0.000 27.256 641.205 0.000 -410.665
Aft Crane Test Position (CL Rotation is 65' Aft Frame 0, Boom Facing Aft on CL at 0 Deg Elevation Angle) Turret Assembly - CG at CL of Rotation; Do not need to remove for Lightship Weight because the CG is not variable Boom -70,600.0 -31.518 83.742 0.000 37.360 -2639.368 0.000 -1177.507 Main & Aux Blocks -2,601.0 -1.161 112.110 0.000 39.820 -130.178 0.000 -46.237
Fwd Crane Stowed Position (CL Rotation is 9'-6" Fwd Frame 0, Boom Facing Aft 25 Deg to Port at 0 Deg Elevation Angle with Arm Tucked in) Turret Assembly - CG at CL of Rotation; Do not need to remove for Lightship Weight because the CG is not variable Boom 54,750.0 24.442 12.047 -10.047 18.125 294.449 -245.565 443.011 Jib Boom 33,750.0 15.067 20.115 -13.807 11.474 303.066 -208.034 172.878
Aft Crane Stowed Position (CL Rotation is 65' Aft Frame 0, Boom Facing Fwd 20 Deg to STBD at 0 Deg Elevation Angle with Boom Retracted) Turret Assembly - CG at CL of Rotation; Do not need to remove for Lightship Weight because the CG is not variable Boom 70,600.0 31.518 47.391 6.411 37.360 1493.651 202.075 1177.507 Main & Aux Blocks 2,601.0 1.161 20.734 16.109 39.820 24.076 18.706 46.237
TOTALS: 0.0 0.000 757.753 -232.818 -506.776
WEIGHTS TO BE RELOCATED
Pendulum
Pendulum
Pendulum e5mdccjh Line e5mdccjh Line e5mdccjh Line
DC VOLTSDC AMPERES
| 703-B427-01 VERTICAL & INCLINED LADDERS |
| 703-B427-01 REV- VERTICAL AND INCLINED LADDERS 1 |
| 703-B427-01 REV- VERTICAL AND INCLINED LADDERS 2 |
| 703-B427-01 REV- VERTICAL AND INCLINED LADDERS 3 |
| 703-B427-01 REV- VERTICAL AND INCLINED LADDERS 4 |
| 703-B427-01 REV- VERTICAL AND INCLINED LADDERS 5 |
| 703-B460-01 REV- HULL MARKINGS |
| 703-B760-01 REV- SHORE POWER & OFF-VESSEL POWER DETAILS 1 |
| 731-E170-01 DRY DOCKING PLAN |
| 731-E170-011 |
| 731-E170-012 |
| 731-E170-013 |
| 731-E170-014 |
| 788-D115-02 REV 1 Incline Experiment Results_PE Stamped |
| 793 - SAMPLE PLACARD |
| 793 SAMPLE PLACARD 1 |
| 793 SAMPLE PLACARD 2 |
| 793-D326-01 TRANSDUCER WELL |
| 793-D710-01 ELECTRICAL LOAD ANALYSIS_AC |
| 793-D710-02 ELECTRICAL LOAD ANALYSIS_DC |
| 793-D720-01 ELECTRICAL SYSTEM ONE-LINE DIAGRAM_AC |
| 793-D720-02 ELECTRICAL SYSTEM ONE-LINE DIAGRAM_DC |