AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
THIS AMENDMENT DOES NOT EXTEND THE NOVEMBER 15, 2016 BID OPENING DATE.
1. CONTRACT ID CODE PAGE OF PAGES
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU-16-B-0014
X 9B. DATED (SEE ITEM 11)
26-Sep-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) BEACHFILL, INITIAL CONSTRUCTION, MANASQUAN INLET TO BARNEGAT INLET, OCEAN COUNTY, NEW JERSEY
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02 Nov 2016
CODE
CONTR DIV-CONTRACTS BR
USACE, PHILA DISTRICT
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
This page was intentionally left blank for duplex printing.
Amendment No. 0002
IFB W912BU-16-B-0014
14. DESCRIPTION OF AMENDMENT (continued)
a. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0002, are attached to this amendment.
b. BIDDING SCHEDULE: Please delete the Bidding Schedule in its entirety, and substitute the revised Bidding Schedule, annotated Amendment No. 0002, attached hereto.
c. SECTION 00 73 15 - WAGE RATES: Please delete pages 00 73 15-5 through 00 73 15-12 in their entirety and substitute revised pages 00 73 15-5 through 00 73 15-12, annotated Amendment No. 0002, attached hereto.
d. SECTION 00 73 41 – VIBRACORE BORING LOGS: Please add new page 00 73 41-75, annotated Amendment No. 0002, attached hereto.
e. SECTION 00 73 42 - VIBRACORE SAMPLE GRAIN SIZE DISTRIBUTION DATA: Please add new pages 00 73 42-124 through 00 73 42-127, annotated Amendment No.
0002, attached hereto.
f. TECHNICAL SPECIFICATIONS:
(1) Section 01 35 30 - MUNITIONS AND EXPLOSIVES OF CONCERN (MEC) CONSTRUCTION SUPPORT: Please delete this section in its entirety, and substitute the revised section 01 35 30, annotated Amendment No. 0002, attached hereto.
(2) Section 03 30 53 – CAST-IN-PLACE CONCRETE: Please delete page 03 30 53-13 in its entirety, and substitute the revised page 03 30 53-13, annotated Amendment No. 0002, attached hereto.
(3) Section 32 15 00 – DUNE CROSSOVERS: Please delete pages 32 15 00-5 and 9 through 12, in their entirety, and substitute revised pages 32 15 00-5 and 9 through 12, annotated Amendment No. 0002, attached hereto.
(4) Section 33 41 13 – REPLACEMENT OF SEA AVENUE PUMP STATION FORCE MAIN:
Please delete pages 33 41 13-6 and 8, in their entirety, and substitute revised pages 33 41 13-6 and 8, annotated Amendment No.
0002, attached hereto.
g. CONTRACT DRAWINGS: Please delete the following drawings in their entirety and substitute the revised drawings of the same numbers, with the latest revision date of 31 October 2016, attached hereto:
C-100 CM-102 CL-101 CBL-100
C-101 CM-103 CL-102 C-400
CPP-100 CB-100 CTS-100 C-401
CPP-101 CB-101 CTS-101 C-404
CPP-102 CB-102 CSH-100 C-410
CBH-100 CTN-100 CSH-101 C-413
CBH-101 CTN-101 CSP-100 C-418
CM-100 CTN-102 CSP-101 C-421
CM-101 CL-100 CSP-102
h. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0002. Failure to acknowledge all amendments may be cause for rejection of the bid.
RFI#
Dwg Sheet/ Spec Section Request for Information Response
Due to the complexity of the lump sum demo items please provide an extension of the bid opening date See Amendment No. 0001.
Section 35 31 00
Section 35 31 00 3.5.1 excludes mobilization and demobilization costs for other work under this contract. Where are crossover/ force main fixed costs to be captured if excluded from mobe/demobe?
Section 35 31 00 paragraph 3.5.1 also states that "Mobilization and demobilization costs for other work under this contract (ex. crossover, outfalls, etc.) shall be included in the costs of the bid items to which the mobilization and demobilization is incidental. Please Bid per the plans and specifications.
Section 35 31 00
Section 35 31 00 does not mention edge board requirements? Are the edge boards to meet the “dense standard decking” requirement for lumber and timbers or the Southern Yellow Pine Grade No. 1?
Section 32 15 00 has been revised to include timber edge boards. See Amendment No. 0002.
Heiring Ave and Philadelphia Ave show the split rail fence ending before the pavement. Do the edgeboards extend to the pavement or stop at the split rail fence on all crossovers like this?
Split rail fence only ends. Timber edge boards extend to pavement.
Please provide a sheet length or tip elevation for the sheet pile wall at Grant Ave. See Sheet C-414, Detail 6.
Is the reinforcement steel for the concrete cap at Grant Ave to be plain or epoxy coated
Section 03 30 53 has been revised to require epoxy coated reinforcement steel. See Amendment No. 0002.
Sheet C-418
C-418 Detail 2 shows the geotextile extending the full length of the pile. Please confirm Sheet C-418 revised. See Amendment No. 0002.
Sheet C-401
C-401 Detail 1 references timber bulkhead (see note 3). Please confirm that note 3 should not read SEE DETAIL 6/C-418. Sheet C-418 revised. See Amendment No. 0002.
Sheet C-
C-410 No. 3 Pedestrian Crossover Seaside Park (N St) shows installation of a timber bulkhead however the bid item is missing from the bid sheet. Please provide this bid item
Bidding Schedule has been revised to add timber bulkhead. See Amendment No. 0002.
Due to the magnitude and complexity of this project, we request that the Corps extend the date for submittal of questions by seven (7) days to 05:00 P.M. on 19 October 2016. See Amendment No. 0001.
Force Main
Please provide a pressure class requirement for the DIP to be replaced with the force main. Section 33 41 13 revised. See Amendment No. 0002.
Force Main
Can Fibercore be substituted instead of 1” stainless steel cable for the tie downs? No. Please bid per the plans and specifications.
Force Main
It appears that the stainless steel cable welded to the 2” square stainless steel tube may fail due to fraying from the bottom. Section 33 41 13 revised. See Amendment No. 0002.
Section 32 15 00
The majority of the ADA Stabilization mats quantities to not match “full” rolls of mats. Will quantities be measured to the “full” roll or will excess mat length not be paid for? Should the last mat at a location be cut to meet the bid quantity? Sheets C-400, C-401 and Bidding Schedule revised to full roll quantities. See Amendment No. 0002.
15 Can the Corps provide the XYZ survey data for the borrow areas? No. Please bid per the plans and specifications.
Section 33 41 13
Section 33 41 13 3.3.1.1 refers to a driving resistance being calculated from test-pile driving data however no test pile information is contained in the spec section. Is a test pile required? No test pile required. See Amendment No. 0002.
Force Main
Does the neoprene bearing pad on Force Main sheet 6 of 9 Section A extend the entire length of the RCP pipe or is it only installed along the bearing surfaces of the concrete box?
Along entire length of each pile bent (6 feet, 6 inches). See sheet 6 of 9 pile bent section and section A. Bid as shown.
Force Main
It does not appear that the warning delineators are available in red. Please provide an alternate material that is available.
This material is readily available from numerous vendors.
Please bid per the plans and specifications.
REQUESTS FOR INFORMATION with RESPONSES Solicitation No. W912BU-16-B-0014
Request For Information Page 1
00 10 00-3
BIDDING SCHEDULE
(To be attached to SF 1442)
Item Estimated Unit Estimated No. Description Quantity Unit Price Amount
BASE BID:
1. Mobilization and Demobilization 1 JOB LS $____________
BOROUGH OF MANTOLOKING - FROM STATION 207+68 TO STATION 277+58:
2. Demolition 1 JOB LS $____________
3. Structures Monitoring 1 JOB LS $____________
4. Beachfill 1,607,000 CY $______ $____________
5. Pedestrian Crossover 7,496 SF $______ $____________
6. ADA Accessible Crossover 5,257 SF $______ $____________
7. Vehicle Crossover 4,144 SF $______ $____________
8. Sand Fence 14,384 LF $______ $____________
9. Split Rail Fence 1,943 LF $______ $____________
10. Post and Rail Fence 1,052 LF $______ $____________
11. Berm Stabilization Mat 450 SF $______ $____________
12. Dune Grass Planting - 18” O.C. 62,293 SY $______ $____________
13. Dune Grass Planting - 24” O.C. 29,137 SY $______ $____________
14. Name the State of New Jersey and the Borough of Mantoloking as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
BRICK TOWNSHIP – FROM STATION 277+58 TO STATION 371+64:
15. Demolition 1 JOB LS $____________
16. Structures Monitoring 1 JOB LS $____________
17. Beachfill 1,573,000 CY $______ $____________
18. Pedestrian Crossover 11,186 SF $______ $____________
19. ADA Accessible Crossover 11,242 SF $______ $____________
20. Vehicle Crossover 9,770 SF $______ $____________
21. Sand Fence 18,730 LF $______ $____________
22. Split Rail Fence 3,514 LF $______ $____________
23. Post and Rail Fence 2,128 LF $______ $____________
24. Berm Stabilization Mat 1,800 SF $______ $____________
25. Dune Grass Planting - 18” O.C. 82,834 SY $______ $____________
26. Dune Grass Planting - 24” O.C. 33,138 SY $______ $____________
00 10 00-4
27. Name the State of New Jersey and Brick Township as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOMS RIVER TOWNSHIP (NORTH) - FROM STATION 371+64 TO STATION 449+81:
28. Demolition 1 JOB LS $____________
29. Structures Monitoring 1 JOB LS $____________
30. Beachfill 1,139,000 CY $______ $____________
31. Graded Sand Crossover with Stabilization Mats 33,178 SF $______ $____________
32. ADA Accessible Crossover 3,314 SF $______ $____________
33. Vehicle Crossover 4,035 SF $______ $____________
34. Sand Fence 15,518 LF $______ $____________
35. Split Rail Fence 7,150 LF $______ $____________
36. Post and Rail Fence 663 LF $______ $____________
37. Berm Stabilization Mat 600 SF $______ $____________
38. Dune Grass Planting - 18” O.C. 65,568 SY $______ $____________
39. Dune Grass Planting - 24” O.C. 39,624 SY $______ $____________
40. Name the State of New Jersey and Toms River Township as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
BOROUGH OF LAVALLETTE - FROM STATION 449+81 TO STATION 526+37:
41. Demolition 1 JOB LS $____________
42. Structures Monitoring 1 JOB LS $____________
43. Beachfill 1,410,000 CY $______ $____________
44. Pedestrian Crossover 47,674 SF $______ $____________
45. ADA Accessible Crossover 11,796 SF $______ $____________
46. Vehicle Crossover 8,031 SF $______ $____________
47. Sand Fence 14,962 LF $______ $____________
48. Split Rail Fence 10,123 LF $______ $____________
49. Post and Rail Fence 2,300 LF $______ $____________
50. Berm Stabilization Mat 1,800 SF $______ $____________
51. Dune Grass Planting - 18” O.C. 65,901 SY $______ $____________
52. Dune Grass Planting - 24” O.C. 34,027 SY $______ $____________
53. Name the State of New Jersey and the Borough of Lavallette as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
00 10 00-5
TOMS RIVER TOWNSHIP (SOUTH) - FROM STATION 526+37 TO STATION 567+09:
54. Demolition 1 JOB LS $____________
55. Structures Monitoring 1 JOB LS $____________
56. Beachfill 1,236,000 CY $______ $____________
57. Graded Sand Crossover with Stabilization Mats 14,710 SF $______ $____________
58. ADA Accessible Crossover 7,062 SF $______ $____________
59. Vehicle Crossover 8,944 SF $______ $____________
60. Timber Bulkhead 320 LF $______ $____________
61. Sand Fence 8,076 LF $______ $____________
62. Split Rail Fence 4,098 LF $______ $____________
63. Post and Rail Fence 1,412 LF $______ $____________
64. Berm Stabilization Mat 1,200 SF $______ $____________
65. Dune Grass Planting - 18” O.C. 35,125 SY $______ $____________
66. Dune Grass Planting - 24” O.C. 32,795 SY $______ $____________
BOROUGH OF SEASIDE HEIGHTS - FROM STATION 567+09 TO STATION 608+70:
67. Demolition 1 JOB LS $____________
68. Structures Monitoring 1 JOB LS $____________
69. Beachfill 655,049 CY $______ $____________
70. Pedestrian Crossover 2,530 SF $______ $____________
71. ADA Accessible Crossover 20,706 SF $______ $____________
72. Vehicle Crossover 12,667 SF $______ $____________
73. Timber Bulkhead 484 LF $______ $____________
74. Steel Sheetpile Bulkhead 200 LF $______ $____________
75. Sand Fence 5,753 LF $______ $____________
76. Split Rail Fence 1,922 LF $______ $____________
77. Post and Rail Fence 4,133 LF $______ $____________
78. Berm Stabilization Mat 6,600 SF $______ $____________
79. Dune Grass Planting - 18” O.C. 22,713 SY $______ $____________
80. Dune Grass Planting - 24” O.C. 17,696 SY $______ $____________
81. Name the State of New Jersey and the Borough of Seaside Heights as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
BOROUGH OF SEASIDE PARK - FROM STATION 608+70 TO STATION 698+01:
82. Demolition 1 JOB LS $____________
83. Structures Monitoring 1 JOB LS $____________
84. Beachfill 931,000 CY $______ $____________
00 10 00-6
85. Pedestrian Crossover 24,323 SF $______ $____________
86. ADA Accessible Crossover 14,241 SF $______ $____________
87. Vehicle Crossover 3,928 SF $______ $____________
88. Timber Bulkhead 40 LF $______ $____________
89. Sand Fence 16,864 LF $______ $____________
90. Split Rail Fence 5,346 LF $______ $____________
91. Post and Rail Fence 2,832 LF $______ $____________
92. Berm Stabilization Mat 1,800 SF $______ $____________
93. Dune Grass Planting - 18” O.C. 77,396 SY $______ $____________
94. Dune Grass Planting - 24” O.C. 26,571 SY $______ $____________
95. Name the State of New Jersey and the Borough of Seaside Park as Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOTAL ESTIMATED BASE BID AMOUNT $__________________
OPTION WORK
OPTION 1
BOROUGH OF POINT PLEASANT BEACH - FROM STATION 0+00 TO STATION 38+50:
96. Demolition 1 JOB LS $____________
97. Structures Monitoring 1 JOB LS $____________
98. Beachfill 59,000 CY $______ $____________
99. Graded Sand Crossover with Stabilization Mats 6,670 SF $______ $____________
100. ADA Accessible Crossover 2,560 SF $______ $____________
101. Vehicle Crossover 8,529 SF $______ $____________
102. Sand Fence 8,190 LF $______ $____________
103. Split Rail Fence 2,316 LF $______ $____________
104. Post and Rail Fence 512 LF $______ $____________
105. Berm Stabilization Mat 300 SF $______ $____________
106. Dune Grass Planting - 18” O.C. 16,273 SY $______ $____________
107. Dune Grass Planting - 24” O.C. 15,959 SY $______ $____________
108. Name the State of New Jersey and the Borough Of Point Pleasant Beach as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOTAL ESTIMATED OPTION 1 TOTAL $_________________
OPTION 2
BOROUGH OF POINT PLEASANT BEACH - FROM STATION 38+50 TO STATION 94+42:
109. Demolition 1 JOB LS $____________
00 10 00-7
110. Structures Monitoring 1 JOB LS $____________
111. Beachfill 464,000 CY $______ $____________
112. Graded Sand Crossover with Stabilization Mats 13,596 SF $______ $____________
113. ADA Accessible Crossover 7,013 SF $______ $____________
114. Vehicle Crossover 4,487 SF $______ $____________
115. Timber Bulkhead 40 LF $______ $____________
116. Sand Fence 11,356 LF $______ $____________
117. Split Rail Fence 3,295 LF $______ $____________
118. Post and Rail Fence 1,402 LF $______ $____________
119. Berm Stabilization Mat 900 SF $______ $____________
120. Dune Grass Planting - 18” O.C. 46,558 SY $______ $____________
121. Dune Grass Planting - 24” O.C. 33,067 SY $______ $____________
122. Name the State of New Jersey and the Borough Of Point Pleasant Beach as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOTAL ESTIMATED OPTION 2 TOTAL $_________________
BOROUGH OF POINT PLEASANT BEACH - FROM STATION 0+00 TO STATION 94+42:
123. OPTION 3 - Beachfill 59,000 CY $______ $____________
124. OPTION 4 - Beachfill 33,000 CY $______ $____________
125. OPTION 5 - Sea Avenue Pump Station Force Main 1 JOB LS $____________
OPTION 6
BOROUGH OF BAY HEAD - FROM STATION 94+42 TO STATION 162+36:
126. Demolition 1 JOB LS $____________
127. Structures Monitoring 1 JOB LS $____________
128. Beachfill 1,412,000 CY $______ $____________
129. Pedestrian Crossover 16,932 SF $______ $____________
130. ADA Accessible Crossover 4,473 SF $______ $____________
131. Vehicle Crossover 5,409 SF $______ $____________
132. Timber Sheeting 1 JOB LS $____________
133. Sand Fence 13,268 LF $______ $____________
134. Split Rail Fence 4,087 LF $______ $____________
135. Post and Rail Fence 895 LF $______ $____________
136. Berm Stabilization Mat 600 SF $______ $____________
137. Dune Grass Planting - 18” O.C. 58,372 SY $______ $____________
138. Dune Grass Planting - 24” O.C. 30,940 SY $______ $____________
00 10 00-8
139. Name the State of New Jersey and the Borough of Bay Head as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOTAL ESTIMATED OPTION 6 TOTAL $_________________
BOROUGH OF BAY HEAD - FROM STATION 94+42 TO STATION 162+36:
140. OPTION 7 - Beachfill 159,000 CY $______ $____________
141. OPTION 8 - Beachfill 88,000 CY $______ $____________
OPTION 9
BOROUGH OF MANTOLOKING - FROM STATION 162+36 TO STATION 182+69:
142. Demolition 1 JOB LS $____________
143. Structures Monitoring 1 JOB LS $____________
144. Beachfill 358,000 CY $______ $____________
145. Pedestrian Crossover 6,056 SF $______ $____________
146. Sand Fence 4,096 LF $______ $____________
147. Split Rail Fence 1,212 LF $______ $____________
148. Dune Grass Planting - 18” O.C. 17,528 SY $______ $____________
149. Dune Grass Planting - 24” O.C. 6,294 SY $______ $____________
TOTAL ESTIMATED OPTION 9 TOTAL $_________________
BOROUGH OF MANTOLOKING - FROM STATION 162+36 TO STATION 182+69:
150. OPTION 10 - Beachfill 50,000 CY $______ $____________
OPTION 11
BOROUGH OF MANTOLOKING - FROM STATION 182+69 TO STATION 207+68:
151. Demolition 1 JOB LS $____________
152. Structures Monitoring 1 JOB LS $____________
153. Beachfill 597,000 CY $______ $____________
154. Pedestrian Crossover 2,880 SF $______ $____________
155. Vehicle Crossover 5,507 SF $______ $____________
156. Sand Fence 5,146 LF $______ $____________
157. Split Rail Fence 1,211 LF $______ $____________
158. Dune Grass Planting - 18” O.C. 22,336 SY $______ $____________
159. Dune Grass Planting - 24” O.C. 9,727 SY $______ $____________
TOTAL ESTIMATED OPTION 11 TOTAL $_________________
BOROUGH OF MANTOLOKING - FROM STATION 182+69 TO STATION 207+68:
160. OPTION 12 - Beachfill 72,000 CY $______ $____________
BOROUGH OF MANTOLOKING - FROM STATION 207+68 TO STATION 277+58
161. OPTION 13 - Beachfill 226,000 CY $______ $____________
00 10 00-9
162. OPTION 14 - Beachfill 100,000 CY $______ $____________
BRICK TOWNSHIP – FROM STATION 277+58 TO STATION 371+64
163. OPTION 15 - Beachfill 177,000 CY $______ $____________
164. OPTION 16 - Beachfill 98,000 CY $______ $____________
TOMS RIVER TOWNSHIP (NORTH) - FROM STATION 371+64 TO STATION 449+81
165. OPTION 17 - Beachfill 128,000 CY $______ $____________
166. OPTION 18 - Beachfill 71,000 CY $______ $____________
167. OPTION 19 – Dune Crossover Stabilization Mat for ADA Crossovers 3,314 SF $______ $____________
OPTION 20
TOMS RIVER TOWNSHIP (NORTH) - FROM STATION 371+64 TO STATION 449+81
168. Private Dune Crossover with Stabilization Mats 32,431 SF $______ $____________
169. Split Rail Fence 6,485 LF $______ $____________
TOTAL ESTIMATED OPTION 20 TOTAL $_________________
BOROUGH OF LAVALLETTE - FROM STATION 449+81 TO STATION 526+37
170. OPTION 21 - Beachfill 159,000 CY $______ $____________
171. OPTION 22 - Beachfill 88,000 CY $______ $____________
OPTION 23
BOROUGH OF LAVALLETTE - FROM STATION 449+81 TO STATION 526+37
172. ADA Accessible Crossover 3,914 SF $______ $____________
173. Berm Stabilization Mat 600 SF $______ $____________
174. Post and Rail Fence 763 LF $______ $____________
TOTAL ESTIMATED OPTION 23 TOTAL $_________________
TOMS RIVER TOWNSHIP (SOUTH) - FROM STATION 526+37 TO STATION 567+09
175. OPTION 24 - Beachfill 139,000 CY $______ $____________
176. OPTION 25 - Beachfill 77,000 CY $______ $____________
177. OPTION 26 - Dune Crossover Stabilization Mat for ADA Crossovers 7,062 SF $______ $____________
OPTION 27
TOMS RIVER TOWNSHIP (SOUTH) - FROM STATION 526+37 TO STATION 567+09
178. Private Dune Crossover with Stabilization Mats 17,514 SF $______ $____________
179. Split Rail Fence 3,504 LF $______ $____________
TOTAL ESTIMATED OPTION 27 TOTAL $_________________
00 10 00-10
BOROUGH OF SEASIDE HEIGHTS - FROM STATION 567+09 TO STATION 608+70
180. OPTION 28 - Beachfill 75,000 CY $______ $____________
181. OPTION 29 - Beachfill 42,000 CY $______ $____________
BOROUGH OF SEASIDE PARK - FROM STATION 608+70 TO STATION 698+01
182. OPTION 30 - Beachfill 105,000 CY $______ $____________
183. OPTION 31 - Beachfill 58,000 CY $______ $____________
OPTION 32
BERKELEY TOWNSHIP - FROM STATION 698+01 TO STATION 735+40
184. Demolition 1 JOB LS $____________
185. Structures Monitoring 1 JOB LS $____________
186. Beachfill 161,000 CY $______ $____________
187. Pedestrian Crossovers 6,754 SF $______ $____________
188. ADA Accessible Crossovers 3,256 SF $______ $____________
189. Vehicle Crossover 8,168 SF $______ $____________
190. Sand Fence 7,454 LF $______ $____________
191. Split Rail Fence 2,552 LF $______ $____________
192. Post and Rail Fence 649 LF $______ $____________
193. Berm Stabilization Mat 300 SF $______ $____________
194. Dune Grass Planting - 18” O.C. 9,379 SY $______ $____________
195. Dune Grass Planting - 24” O.C. 9,831 SY $______ $____________
196. Name the State of New Jersey and Berkeley Township as “Additional Insured” under General Liability Insurance 1 JOB LS $____________
TOTAL ESTIMATED OPTION 32 TOTAL $_________________
BERKELEY TOWNSHIP - FROM STATION 698+01 TO STATION 735+40
197. OPTION 33 - Beachfill 18,000 CY $______ $____________
198. OPTION 34 - Beachfill 10,000 CY $______ $____________
TOTAL ESTIMATED BASE BID AND OPTIONS 1 THROUGH 34 AMOUNT $_________________
NOTES:
1. Bidders must bid on all items.
2. Bidders shall list the cost of additional premium, if any, to name the State of New Jersey and the municipalities of Point Pleasant Beach, Bay Head, Mantoloking, Brick Township, Toms River Township, Lavallette, Seaside Heights, Seaside Park, and Berkeley Township as “Additional Insured” under General Liability Insurance as noted in Section 00 73 00, Special Clause entitled “INSURANCE REQUIREMENTS”.
General Decision Number: NJ160060 10/14/2016 NJ60
Superseded General Decision Number: NJ20150060
State: New Jersey
Construction Type: Heavy
County: Ocean County in New Jersey.
HEAVY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/08/2016 1 02/19/2016 2 02/26/2016 3 03/04/2016 4 04/01/2016 5 05/06/2016 6 05/13/2016 7 07/01/2016 8 08/05/2016 9 08/19/2016 10 09/09/2016 11 10/14/2016
* ASBE0089-004 07/01/2016
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR ((includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement))......................$ 42.02 31.83
PAID HOLIDAYS:
The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay.
BRNJ0004-001 11/01/2015
Section 00 73 15 Page 5
Rates Fringes
CEMENT MASON.....................$ 38.25 30.58
CARP0006-013 05/01/2016
Rates Fringes
CARPENTER (Including Form Work)............................$ 45.94 57%
The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.
CARP0454-009 05/01/2016
Rates Fringes
PILEDRIVERMAN....................$ 43.95 31.32
PAID HOLIDAYS:
New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day; provided that the worker works any of the three days in the five-day work week preceding the holiday and the first work day after the holiday.
CARP0715-007 05/01/2016
Rates Fringes
Millwright.....................$ 46.05 56%
Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.
ELEC0400-007 05/30/2016
Rates Fringes
Electrician & Cable Splicer......$ 46.68 33.50
ENGI0825-021 01/01/2016
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 47.70 29.80
GROUP 2.....................$ 46.05 29.80
GROUP 3.....................$ 43.91 29.80
GROUP 4.....................$ 42.41 29.80
GROUP 5.....................$ 40.69 29.80
Hazardous waste removal work:
Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: 20% per
Section 00 73 15 Page 6 hour additional.
PAID HOLIDAYS:
New Year's Day, Washington's Birthday observed, Memorial Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided
1) that the worker works three of the preceding five work days before the holiday; or, the work day before the holiday and the work day after the holiday; and, 2) that the worker works the work day before and the work day after the holiday.
DEFINITION OF GROUPS:
GROUP 1:
Backhoe, Including Backhoe Track; Boom; Concrete Paving Machine; Crane (all types, including overhead and straddle traveling type); Drill (down-the-hole drill, rotary drill, self-propelled hydraulic drill, self-powered drill);
Elevating Grader; Excavator; Front End Loader (5 cu. yd.
and over); Piledriver (length of boom, including length of leads, shall determine premium rate applicable)
GROUP 2:
Backhoe Loader Combo; Concrete Pumper; Grader/Blade (Finish);
Hoist; Hydraulic Crane, 10 Tons and under; Front End Loader (2 cu. yd. but less than 5 cu. yd.); Scraper; Side Boom
GROUP 3:
Asphalt Spreader; Bulldozer; Compressor(2 or 3) (in Battery) (within 100 ft.); Crusher; Forklift; Front End Loader (1
cu. yd. and over but less than 2 cu. yd.); Lull; Mechanic;
Paver, Asphalt; Roller, Blacktop; Tractor;
GROUP 4:
Broom; Compressor (Single); Farm Tractor; Front End Loader (under 1 cu. yd.); Roller, Grade; Pump
GROUP 5:
Oiler
IRON0011-014 07/01/2016
Northern Third of County
Rates Fringes
IRONWORKER
Reinforcing.................$ 39.24 42.92 Structural, Ornamental and Rigger......................$ 41.54 42.92
IRON0068-018 07/01/2015
Middle Third of County
Rates Fringes
IRONWORKER
Reinforcing.................$ 43.90 20.78 Structural, Ornamental and
Section 00 73 15 Page 7
Rigger......................$ 45.89 20.78
IRON0350-010 07/01/2015
Southern Third of County
Rates Fringes
Ironworkers:
Reinforcing.................$ 45.77 28.75 Structural, Ornamental and Rigger......................$ 46.77 28.75
LABO0172-009 09/01/2012
Rates Fringes
Laborers:
Common or General Laborer;
Landscape Laborer, Power Tool Operator...............$ 33.20 22.40 Pipelayer...................$ 33.90 22.40
Hazardous waste removal work:
Work on a state or federally designated hazardous waste site, where the worker is required to wear Level A, B or C personal protection: $3.00 per hour additional.
Work on a state or federally designated hazardous waste site, where the worker is not required to wear Level A, B, or C personal protection: $1.00 per hour additional.
PAID HOLIDAYS:
New Year's Day, President's Day, Memorial Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided that the worker works three days for the same employer within a period of ten working days consisting of five working days before and five working days after the day upon which the holiday falls or is observed.
LABO0222-013 07/01/2012
Rates Fringes
LABORER
MASON TENDER:
Cement/Concrete.............$ 29.35 23.07
PAIN0711-023 05/01/2016
Rates Fringes
Painters:
Work on bridges (Major Bridges Designed for Commercial Navigation)......$ 52.38 26.05
PAIN0711-024 05/01/2016
Rates Fringes
Painters:
Section 00 73 15 Page 8
New Construction Brush and roller...........$ 38.42 22.09 Repaint work, on projects on which no major alterations occur.
Brush and roller...........$ 28.74 18.47
PLUM0009-025 07/01/2016
OCEAN COUNTY (north of a line drawn from the Atlantic Ocean following a line westerly through the middle of the Barnegat Inlet, continuing west through Barnegat Bay into the town of Waretown; then, continuing along County Road Route 532 until County Road Route 532 becomes State Highway Route 72; then, continuing along State Highway Route 72 until it reaches the Burlington County line):
Rates Fringes
PIPEFITTER.......................$ 47.47 35.51
Service and Repair..........$ 37.18 19.88
PLUM0322-012 05/01/2016
OCEAN COUNTY (south of a line drawn from the Atlantic Ocean following a line westerly through the middle of the Barnegat Inlet, continuing west through Barnegat Bay into the town of Waretown; then, continuing along County Road Route 532 until County Road Route 532 becomes State Highway Route 72; then, continuing along State Highway Route 72 until it reaches the Burlington County line)
Rates Fringes
PIPEFITTER.......................$ 44.42 36.34
TEAM0469-008 05/01/2015
Rates Fringes
Truck drivers:
Dump Truck; Flatbed Truck;Pick up truck.........$ 37.60 29.085 Dump Truck; Flatbed Truck...$ 36.75 27.935 Off the Road Truck; Pickup Truck.......................$ 36.60 27.935 Off the Road Truck..........$ 37.75 29.085
Hazardous waste removal work:
Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional.
Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional.
Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour additional.
Section 00 73 15 Page 9
PAID HOLIDAYS:
New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day.
VACATION PAY CREDIT:
Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours).
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and
Section 00 73 15 Page 10 the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Section 00 73 15 Page 11
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Section 00 73 15 Page 12
Section 00 73 41 Page 75
Section 00 73 42 Page 124
Section 00 73 42 Page 125
Section 00 73 42 Page 126
Section 00 73 42 Page 127
SECTION 01 35 30
MUNITIONS AND EXPLOSIVES OF CONCERN (MEC) CONSTRUCTION SUPPORT
PART 1 GENERAL
1.1 SCOPE OF SECTION
The work required under this Section involves safety support and avoidance of potential unexploded ordnance and exploded ordnance, inert ordnance, and ordnance fragments and similar explosives debris material (defined and identified in these specifications as "Munitions and Explosives of Concern" (MEC)), within the dredging prism of the borrow area during performance of dredging activities.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
MEC Safety and Work Plan; G, DO
Prior to commencement of any work, including delivery of any plant, equipment or construction materials to the site, submit a MEC Safety and Work Plan for MEC safety support and avoidance.
The MEC Safety and Work Plan shall consist of the items as specified herein. Include MEC personnel qualifications.
SD-04 Samples
Discharge End Screening Device; G,COR
Prior to commencement of any beachfill work, provide a working demonstration that intake and discharge end screening devices operate as designed, subject to approval by Contracting Officer.
1.3 MEC IN BORROW AREAS
The borrow area for this project is located in the vicinity of a known World War I dumping site for Discarded Military Munitions (DMM).
1.4 UXO TECHNICIANS
a. Land-based UXO Technicians: Provide one Unexploded Ordnance (UXO) Technician, (as specified in Department of Defense Explosives Safety Board (DDESB), Technical Paper 18, MINIMUM QUALIFICATIONS FOR UNEXPLODED ORDNANCE (UXO) TECHNICIANS AND PERSONNEL). The UXO Technician shall provide 24-hour, 7-days per week, MEC support, on the beach. The UXO Technician shall provide MEC Training and shall inspect the screening devices for damage and presence of MEC.
b. Hopper Dredging Only: If MEC is identified as being dredged from the
Section 01 35 30 Page 1 borrow area, the Government will determine if the following requirements are necessary.
(1) Provide two Unexploded Ordnance (UXO) Technicians per dredge, (as specified in Department of Defense Explosives Safety Board (DDESB), Technical Paper 18, MINIMUM QUALIFICATIONS FOR UNEXPLODED ORDNANCE (UXO) TECHNICIANS AND PERSONNEL), which is included at the end of this section, as Attachment A. The UXO Technicians shall provide 24-hour, 7-days per week, MEC support, aboard the dredge on a rotating watch basis. The UXO Technicians shall provide MEC Training and shall inspect the dragheads for damage and presence of MEC after each load has been taken aboard.
(2) The UXO Technicians shall determine the classification of MEC-like objects discovered, shall dislodge MEC from the draghead(s) if required, and shall properly safeguard the MEC. The Contractor shall provide a dedicated crewboat with crew for transportation of the Technician and MEC to a location as directed by the site OESS. The expected location is the crew boat berth at Barnegat Light. No other persons other than the boat crew and UXO Technicians shall be permitted on the crewboat during transportation of MEC.
(3) The UXO Technicians shall comply with the "STANDARD OPERATING
PROCEDURES FOR UXO TECHNICIANS PROVIDING MEC SUPPORT ABOARD HOPPER
DREDGES AT LONG BEACH ISLAND, N.J.", which is included at the end of this section, as Attachment B. Provide support to the Technicians as required and specified in this attachment.
(4) Provide on-board accommodations and meals for the UXO technicians.
Include as part of the accommodations, internet access, and two bed spaces. Provide an on-board portable magazine/MEC containment vessel, as approved by the OESS, to securely store and transfer collected MEC items. Alternatively, if directed by the Contracting Officer, take on-board, secure and electrically ground, a portable magazine/MEC containment vessel provided by the Government, to be utilized for storage of MEC.
(5) If UXO Technicians are required, do not continue/commence dredging until the UXO Technicians are on-board the dredge.
1.5 GOVERNMENT-PROVIDED MEC SPECIALIST (OESS)
1.5.1 General
The Corps of Engineers Military Munitions Design Center will provide an Ordnance and Explosives Safety Specialist(s) (OESS) to oversee overall MEC safety and training. The OESS will be on-site or in the vicinity (within a 15 minute response time after notification) during the duration of the placement of beachfill for this project. Contact the OESS in the event that an MEC or MEC-like item is located, however the UXO Technicians aboard a hopper dredge will perform this action. The OESS will provide guidance and coordinate emergency response. Stop dredging work immediately upon notification by the OESS of the need for inspection of intake and discharge screening devices during material placement operations to prevent MEC from being dredged and placed on the beach.
1.5.2 Pre-Construction Meeting
The OESS will attend the preconstruction meeting to answer any of the
Section 01 35 30 Page 2
Contractor's questions concerning MEC.
1.5.3 MEC Safety and Work Plan Review
The OESS will review the Contractor's MEC Safety and Work Plan to ensure MEC aspects are adequately addressed. The Contractor's MEC Safety and Work Plan shall communicate the Contractor's understanding of his role and responsiblity in the management of dredging and dredged material placement operations to prevent MEC from being dredged and placed on the beach.
1.5.4 Worker Education
The OESS will conduct or task the UXO Technicians to conduct MEC safety/awareness/ recognition training for the Contractor's dredging vessel and shore based workers, as well as Corps personnel. This training will be provided prior to the start of work on site, and to all newly reporting personnel assigned to the project who have not attended MEC training in the previous twelve months. MEC Training is required once per 12 month period.
1.5.5 Quality Assurance (QA)
The OESS will monitor the beachfill operations on a periodic basis and will be on-site, or on-call in the vicinity to address problems as they arise.
Upon notification by the OESS or the UXO Technicians that the intake screening system on the dredge, or the discharge screening system on the beach, has degraded and is not functioning as intended, stop work and correct the deficiency to prevent MEC from being dredged and placed on the beach during material placement operations.
1.6 MEC SAFETY AND WORK PLAN REQUIREMENTS
a. Include the following in the MEC Safety and Work Plan:
(1) Shop drawings and detailed descriptions of the required screening devices on the dredge intake and at the discharge end of the pipeline.
Also include the materials, equipment, procedures and personnel to be used in the construction, operations and oversight of such devices.
(2) Personnel, equipment, and procedures to be used to perform visual inspections at the discharge end of the pipeline on the beach.
(3) The measures to be followed if oversized material is discovered in the screening devices.
(4) The measures to be followed if oversized material is identified as deposited on the beach.
(5) The measures to be followed if MEC is discovered in the screening devices.
(6) The measures to follow if MEC is identified as deposited on the beach.
b. Coordinate the plan with the Job Hazard Analysis and the project Accident Prevention Plan to ensure worker safety and safety of the public is addressed at all times during the contract.
Section 01 35 30 Page 3
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 SCREENING DEVICES
3.1.1 General
a. Prevent MEC from being placed on the beach by: 1) a screening device placed on the dredge intake or in pipeline section prior to reaching the dredge pump, and; 2) at the discharge end of the pipeline on the beach.
The required screening devices shall meet the following requirements:
(1) The screening device on the dredge intake shall prevent the passage of any material greater than 1.25 inches in diameter. The openings on the screening device may have one dimension greater than the other.
The maximum allowable opening is 1.25 inches x 6 inches.
(2) Design the Discharge End Screening Device to retain all items 0.75 inches in diameter and larger. The openings on the screening device shall be of uniform dimension (i.e. a grid or a series of round holes;
slotted openings will not be permitted).
(3) Construct the screening devices using rugged steel or composite material, one-piece or welded members. The devices shall cover the entire cross sectional area, except where basket type devices are used on the discharge end. Relief windows in basket type devices will be permitted only to the side opposite the inflow and at least 12 inches from the bottom of the basket, or as directed by the OESS. Size and locate windows to prevent large items, and MEC items from escaping the basket during pumping operations. Keep basket type devices in a level and horizontal position when using relief windows, during pumping operations.
(4) The screening devices shall be removable for easy replacement if damaged. Ensure screening devices provide a production rate that allows completion of all dredging and beachfill placement within the contract duration.
(5) Demonstrate on-site, subject to approval of the Contracting Officer, the screening devices meet all requirements specified herein.
(6) Maintain adequate replacement parts and additional screening devices on site to insure production for the work does not stop due to damaged devices, or delays in the inspection process.
b. Provide minor adjustments to the beach screening baskets as directed by the OESS to accommodate varying types and amounts of material being screened at the beach, at no additional cost to the Government. As an example, relief windows, other than the required screen apertures, sometimes need to be enlarged, reduced, or relocated to minimize residual biological debris in the basket during the inflow process and for postflow MEC inspection of residual material.
3.1.2 Dredge Cutterhead Screening Device
If a cutterhead dredge is used, provide an intake screening device for the cutterhead that meets the screen requirements specified above.
Section 01 35 30 Page 4
3.1.3 Draghead Modifications
If a hopper dredge is used, design the dragheads to prevent projectile shaped objects greater than 3 inches in diameter from being trapped between draghead…