Bid_Abstract_16B0014_Manasquan.pdf

PDF 296 KB Posted

Attached to
Initial Construction, Beachfill, Manasquan Inlet to Barnegat Inlet, Ocean County, New Jersey
Solicitation number
W912BU16B0014
Issued by

About this file

Abstract of Bids_16B0014_Beachfill Manasquan Inlet to Barnegat Inlet NJ

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Issued: 09/26/2016 Date Opened: 11/18/2016

Amendment Nos. 0001 through 0005 All Amends Ack 20% - Bid Bond All Amends Ack 20% - Bid Bond All Amends Ack 20% - Bid Bond

Item Number Description Qty Unit Price Extension Price Extension Price Extension Price Extension

BASE BID:

1 Mobilization & Demobilization 1 JOB LS 9,006,529.00$ JOB 14,250,000.00$ JOB 18,424,000.00$ JOB 13,900,000.00$

BOROUGH OF MANTOLOKING - FROM STATION 207+68 TO STATION 277+58

2 Demolition 1 JOB LS 25,586.00$ JOB 5,000.00$ JOB 2,500.00$ JOB 1,055.45$

3 Structures Monitoring 1 JOB LS 110,546.00$ JOB 25,000.00$ JOB 17,500.00$ JOB 58,000.00$

4 Beachfill 1,607,000 CY $10.90 17,516,300.00$ 7.00$ 11,249,000.00$ 8.60$ 13,820,200.00$ 10.80$ 17,355,600.00$

5 Pedestrian Crossovers 7,496 SF 8.41$ 63,041.36$ 5.00$ 37,480.00$ 5.20$ 38,979.20$ 6.40$ 47,974.40$

6 ADA Accessible Crossovers 5,257 SF 8.28$ 43,527.96$ 5.00$ 26,285.00$ 4.85$ 25,496.45$ 6.00$ 31,542.00$

7 Vehicle Crossovers 4,144 SF 11.91$ 49,355.04$ 5.00$ 20,720.00$ 3.85$ 15,954.40$ 4.75$ 19,684.00$

8 Sand Fence 14,384 LF 9.77$ 140,531.68$ 8.00$ 115,072.00$ 7.35$ 105,722.40$ 9.05$ 130,175.20$

9 Split Rail Fence 1,943 LF 26.07$ 50,654.01$ 9.00$ 17,487.00$ 8.00$ 15,544.00$ 10.00$ 19,430.00$

10 Post and Rail Fence 1,052 LF 185.44$ 195,082.88$ 85.00$ 89,420.00$ 82.00$ 86,264.00$ 101.00$ 106,252.00$

11 Berm Stabilization Mat 450 SF 6.60$ 2,970.00$ 8.00$ 3,600.00$ 7.85$ 3,532.50$ 9.70$ 4,365.00$

12 Dune Grass Planting 18" O.C. 62,293 SY 6.53$ 406,773.29$ 4.00$ 249,172.00$ 3.85$ 239,828.05$ 4.80$ 299,006.40$

13 Dune Grass Planting 24" O.C. 29,137 SY 4.02$ 117,130.74$ 3.00$ 87,411.00$ 2.45$ 71,385.65$ 3.00$ 87,411.00$

Name the State of NJ and the Borough of Mantoloking as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

BRICK TOWNSHIP-FROM STATION 277+58 TO STATION 371+64

15 Demolition 1 JOB 34,002.00$ 34,002.00$ JOB 5,000.00$ JOB 2,500.00$ JOB 1,000.00$

16 Structures Monitoring 1 JOB $128,869.00 128,869.00$ JOB 25,000.00$ JOB 22,000.00$ JOB 70,000.00$

17 Beachfill 1,573,000 CY 13.38$ 21,046,740.00$ 9.25$ 14,550,250.00$ 9.40$ 14,786,200.00$ 11.50$ 18,089,500.00$

18 Pedestrian Crossovers 11,186 SF 8.28$ 92,620.08$ 5.00$ 55,930.00$ 5.00$ 55,930.00$ 6.25$ 69,912.50$

19 ADA Accessible Crossovers 11,242 SF 8.28$ 93,083.76$ 5.00$ 56,210.00$ 5.00$ 56,210.00$ 6.45$ 72,510.90$

20 Vehicle Crossover 9,770 SF 12.15$ 118,705.50$ 4.00$ 39,080.00$ 3.50$ 34,195.00$ 4.35$ 42,499.50$

21 Sand Fence 18,730 LF 9.77$ 182,992.10$ 8.00$ 149,840.00$ 7.35$ 137,665.50$ 9.10$ 170,443.00$

22 Split Rail Fence 3,514 LF 25.17$ 88,447.38$ 9.00$ 31,626.00$ 8.00$ 28,112.00$ 10.00$ 35,140.00$

23 Post and Rail Fence 2,128 LF 182.76$ 388,913.28$ 85.00$ 180,880.00$ 80.00$ 170,240.00$ 98.00$ 208,544.00$

Certified by:

Denise DeTitta

Bid Opening Officer

24 Berm Stabilization Mat 1,800 SF 6.60$ 11,880.00$ 8.00$ 14,400.00$ 7.25$ 13,050.00$ 9.00$ 16,200.00$ 25 Dune Grass Planting 18" O.C. 82,834 SY 6.53$ 540,906.02$ 4.00$ 331,336.00$ 3.85$ 318,910.90$ 4.80$ 397,603.20$ 26 Dune Grass Planting 24" O.C. 33,138 SY 4.03$ 133,546.14$ 3.00$ 99,414.00$ 2.45$ 81,188.10$ 3.00$ 99,414.00$

Name the State of NJ and Brick Township as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOMS RIVER TOWNSHIP (NORTH)-FROM STATION 371+64 TO STATION 449+81

28 Demolition 1 JOB 27,603.00$ 27,603.00$ JOB 5,000.00$ JOB 2,500.00$ JOB 1,000.00$

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

29 Structures Monitoring 1 JOB 102,301.00$ 102,301.00$ JOB 15,000.00$ JOB 19,000.00$ JOB 58,000.00$ 30 Beachfill 1,139,000 CY 14.10$ 16,059,900.00$ 9.00$ 10,251,000.00$ 11.25$ 12,813,750.00$ 11.50$ 13,098,500.00$

31 Graded Sand Crossovers with Stabilization Mats 33,178 SF 7.19$ 238,549.82$ 7.00$ 232,246.00$ 7.25$ 240,540.50$ 8.90$ 295,284.20$ 32 ADA Accessible Crossovers 3,314 SF 8.28$ 27,439.92$ 5.00$ 16,570.00$ 5.25$ 17,398.50$ 6.55$ 21,706.70$ 33 Vehicle Crossover 4,035 SF 12.12$ 48,904.20$ 5.00$ 20,175.00$ 4.00$ 16,140.00$ 5.00$ 20,175.00$ 34 Sand Fence 15,518 LF 9.77$ 151,610.86$ 8.00$ 124,144.00$ 7.50$ 116,385.00$ 9.35$ 145,093.30$ 35 Split Rail Fence 7,150 LF 25.33$ 181,109.50$ 9.00$ 64,350.00$ 8.00$ 57,200.00$ 10.00$ 71,500.00$ 36 Post and Rail Fence 663 LF 180.58$ 119,724.54$ 85.00$ 56,355.00$ 80.00$ 53,040.00$ 98.00$ 64,974.00$ 37 Berm Stabilization Mat 600 SF 6.60$ 3,960.00$ 8.00$ 4,800.00$ 7.50$ 4,500.00$ 9.35$ 5,610.00$ 38 Dune Grass Planting 18" O.C. 65,568 SY 6.53$ 428,159.04$ 4.00$ 262,272.00$ 3.85$ 252,436.80$ 4.80$ 314,726.40$ 39 Dune Grass Planting 24" O.C. 39,624 SY 3.99$ 158,099.76$ 3.00$ 118,872.00$ 2.45$ 97,078.80$ 3.15$ 124,815.60$

Name the State of NJ and Toms River Township as "Additonal Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,245.00$

BOROUGH OF LAVALLETTE-FROM STATION 449+81 TO STATION 526+37

41 Demolition 1 JOB 38,438.00$ 38,438.00$ JOB 5,000.00$ JOB 3,200.00$ JOB 4,000.00$ 42 Structures Monitoring 1 JOB 121,540.00$ 121,540.00$ JOB 20,000.00$ JOB 23,000.00$ JOB 60,000.00$ 43 Beachfill 1,410,000 CY 13.90$ 19,599,000.00$ 8.50$ 11,985,000.00$ 11.00$ 15,510,000.00$ 11.25$ 15,862,500.00$ 44 Pedestrian Crossovers 47,674 SF 8.28$ 394,740.72$ 5.00$ 238,370.00$ 5.00$ 238,370.00$ 6.25$ 297,962.50$ 45 ADA Accessible Crossovers 11,796 SF 8.28$ 97,670.88$ 5.00$ 58,980.00$ 5.25$ 61,929.00$ 6.55$ 77,263.80$ 46 Vehicle Crossover 8,031 SF 12.10$ 97,175.10$ 5.00$ 40,155.00$ 4.00$ 32,124.00$ 5.00$ 40,155.00$ 47 Sand Fence 14,962 LF 9.77$ 146,178.74$ 8.00$ 119,696.00$ 7.50$ 112,215.00$ 9.30$ 139,146.60$ 48 Split Rail Fence 10,123 LF 25.44$ 257,529.12$ 9.00$ 91,107.00$ 8.00$ 80,984.00$ 10.00$ 101,230.00$ 49 Post and Rail Fence 2,300 LF 182.56$ 419,888.00$ 85.00$ 195,500.00$ 80.00$ 184,000.00$ 98.00$ 225,400.00$ 50 Berm Stabilization Mat 1,800 SF 6.60$ 11,880.00$ 8.00$ 14,400.00$ 7.00$ 12,600.00$ 8.50$ 15,300.00$ 51 Dune Grass Planting 18" O.C. 65,901 SY 6.53$ 430,333.53$ 4.00$ 263,604.00$ 3.85$ 253,718.85$ 4.75$ 313,029.75$ 52 Dune Grass Planting 24" O.C. 34,027 SY 4.00$ 136,108.00$ 3.00$ 102,081.00$ 2.45$ 83,366.15$ 3.20$ 108,886.40$

Name the State of NJ and the Borough of Lavallette as "Additonal Insured" under General Liabiity Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOMS RIVER TOWNSHIP (SOUTH)-FROM STATION 526+37 TO STATION 567+09

54 Demolition 1 JOB 48,843.00$ 48,843.00$ JOB 25,000.00$ JOB 18,000.00$ JOB 23,000.00$ 55 Structures Monitoring 1 JOB 104,439.00$ 104,439.00$ JOB 15,000.00$ JOB 20,000.00$ JOB 42,000.00$ 56 Beachfill 1,236,000 CY 13.20$ 16,315,200.00$ 8.00$ 9,888,000.00$ 10.40$ 12,854,400.00$ 10.85$ 13,410,600.00$ 57 Graded Sand Crossovers with Stabilization Mat 14,710 SF 7.19$ 105,764.90$ 8.00$ 117,680.00$ 7.50$ 110,325.00$ 9.25$ 136,067.50$ 58 ADA Accessible Crossovers 7,062 SF 8.28$ 58,473.36$ 6.00$ 42,372.00$ 5.25$ 37,075.50$ 6.55$ 46,256.10$ 59 Vehicular Crossover 8,944 SF 12.14$ 108,580.16$ 4.00$ 35,776.00$ 3.75$ 33,540.00$ 4.60$ 41,142.40$ 60 Timber Bulkhead 320 LF 795.98$ 254,713.60$ 500.00$ 160,000.00$ 455.00$ 145,600.00$ 560.00$ 179,200.00$ 61 Sand Fence 8,076 LF 9.77$ 78,902.52$ 8.00$ 64,608.00$ 7.25$ 58,551.00$ 9.05$ 73,087.80$ 62 Split Rail Fence 4,098 LF 25.15$ 103,064.70$ 9.00$ 36,882.00$ 8.00$ 32,784.00$ 10.00$ 40,980.00$ 63 Post and Rail Fence 1,412 LF 181.70$ 256,560.40$ 85.00$ 120,020.00$ 80.00$ 112,960.00$ 98.00$ 138,376.00$ 64 Berm Stabilization Mat 1,200 SF 6.60$ 7,920.00$ 8.00$ 9,600.00$ 7.50$ 9,000.00$ 9.35$ 11,220.00$ 65 Dune Grass Planting 18" O.C. 35,125 SY 6.53$ 229,366.25$ 4.00$ 140,500.00$ 3.85$ 135,231.25$ 4.80$ 168,600.00$ 66 Dune Grass Planting 24" O.C. 32,795 SY 3.96$ 129,868.20$ 3.00$ 98,385.00$ 2.45$ 80,347.75$ 3.10$ 101,664.50$

BOROUGH OF SEASIDE HEIGHTS-FROM STATION 567+09 TO STATION 608+70

67 Demolition 1 JOB 54,640.00$ 54,640.00$ JOB 25,000.00$ JOB 21,000.00$ JOB 25,500.00$ 68 Structures Monitoring 1 JOB 61,381.00$ 61,381.00$ JOB 12,000.00$ JOB 9,500.00$ JOB 25,500.00$ 69 Beachfill 655,049 CY 12.79$ 8,378,076.71$ 8.00$ 5,240,392.00$ 10.00$ 6,550,490.00$ 11.15$ 7,303,796.35$ 70 Pedestrian Crossovers 2,530 SF 8.28$ 20,948.40$ 5.00$ 12,650.00$ 5.25$ 13,282.50$ 6.55$ 16,571.50$ 71 ADA Accessible Crossover 20,706 SF 8.28$ 171,445.68$ 5.00$ 103,530.00$ 5.25$ 108,706.50$ 6.55$ 135,624.30$ 72 Vehicle Crossover 12,667 SF 11.96$ 151,497.32$ 4.00$ 50,668.00$ 3.75$ 47,501.25$ 4.75$ 60,168.25$ 73 Timber Bulkhead 484 LF 817.69$ 395,761.96$ 600.00$ 290,400.00$ 570.00$ 275,880.00$ 700.00$ 338,800.00$ 74 Steel Sheetpile Bulkhead 200 LF 4,932.35$ 986,470.00$ 1,500.00$ 300,000.00$ 1,425.00$ 285,000.00$ 1,750.00$ 350,000.00$

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

75 Sand Fence 5,753 LF 9.77$ 56,206.81$ 8.00$ 46,024.00$ 7.35$ 42,284.55$ 9.00$ 51,777.00$ 76 Split Rail Fence 1,922 LF 25.28$ 48,588.16$ 9.00$ 17,298.00$ 8.00$ 15,376.00$ 10.00$ 19,220.00$ 77 Post and Rail Fence 4,133 LF 182.48$ 754,189.84$ 85.00$ 351,305.00$ 80.00$ 330,640.00$ 98.00$ 405,034.00$ 78 Berm Stabilization Mat 6,600 SF 6.60$ 43,560.00$ 8.00$ 52,800.00$ 7.00$ 46,200.00$ 8.75$ 57,750.00$ 79 Dune Grass Planting 18" O.C. 22,713 SY 6.53$ 148,315.89$ 4.00$ 90,852.00$ 3.85$ 87,445.05$ 4.75$ 107,886.75$ 80 Dune Grass Planting 24" O.C. 17,696 SY 3.98$ 70,430.08$ 3.00$ 53,088.00$ 2.45$ 43,355.20$ 3.15$ 55,742.40$ 81 Ornamental Aluminum Fence Modification 1 JOB 17,501.00$ 17,501.00$ JOB 10,000.00$ JOB 1,700.00$ JOB 2,120.00$

Name the State of NJ and the Borough of Seaside Heights as "Additional Insured" under General Liabiity Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

BOROUGH OF SEASIDE PARK-FROM STATION 608+70 TO STATION 698+01

83 Demolition 1 JOB 147,403.00$ 147,403.00$ JOB 30,000.00$ JOB 25,000.00$ JOB 32,000.00$ 84 Structures Monitoring 1 JOB 77,260.00$ 77,260.00$ JOB 15,000.00$ JOB 10,000.00$ JOB 47,000.00$ 85 Beachfill 931,000 CY 12.23$ 11,386,130.00$ 8.00$ 7,448,000.00$ 8.35$ 7,773,850.00$ 10.80$ 10,054,800.00$ 86 Pedestrian Crossovers 24,323 SF 8.28$ 201,394.44$ 5.00$ 121,615.00$ 5.00$ 121,615.00$ 6.25$ 152,018.75$ 87 ADA Accessible Crossover 14,241 SF 8.28$ 117,915.48$ 5.00$ 71,205.00$ 5.25$ 74,765.25$ 6.50$ 92,566.50$ 88 Vehicle Crossover 3,928 SF 12.08$ 47,450.24$ 5.00$ 19,640.00$ 4.00$ 15,712.00$ 5.00$ 19,640.00$ 89 Timber Bulkhead 40 LF 1,135.91$ 45,436.40$ 600.00$ 24,000.00$ 500.00$ 20,000.00$ 625.00$ 25,000.00$ 90 Sand Fence 16,864 LF 9.77$ 164,761.28$ 8.00$ 134,912.00$ 7.25$ 122,264.00$ 9.00$ 151,776.00$ 91 Split Rail Fence 5,346 LF 25.75$ 137,659.50$ 9.00$ 48,114.00$ 8.00$ 42,768.00$ 10.00$ 53,460.00$ 92 Post and Rail Fence 2,832 LF 182.87$ 517,887.84$ 85.00$ 240,720.00$ 80.00$ 226,560.00$ 98.00$ 277,536.00$ 93 Berm Stabilization Mat 1,800 SF 6.60$ 11,880.00$ 8.00$ 14,400.00$ 7.25$ 13,050.00$ 9.00$ 16,200.00$ 94 Dune Grass Planting 18" O.C. 77,396 SY 6.53$ 505,395.88$ 4.00$ 309,584.00$ 3.85$ 297,974.60$ 4.75$ 367,631.00$ 95 Dune Grass Planting 24" O.C. 26,571 SY 4.05$ 107,612.55$ 3.00$ 79,713.00$ 2.45$ 65,098.95$ 3.10$ 82,370.10$

Name the State of New Jersey and the Borough of Seaside Park as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOTAL ESTIMATED BASE BID AMOUNT 132,524,472.50$ 91,992,023.00$ 109,199,418.10$ 117,546,700.00$

OPTIONS

BOROUGH OF POINT PLEASANT BEACH-FROM STATION 0+00 TO STATION 38+50

OPTION 1

97 Demolition 1 JOB $19,549.00 19,549.00$ JOB 60,000.00$ JOB 57,000.00$ JOB 70,000.00$ 98 Structures Monitoring 1 JOB 19,850.00$ 19,850.00$ JOB 5,000.00$ JOB 500.00$ JOB 22,500.00$ 99 Beachfill 59,000 CY 15.98$ 942,820.00$ 7.00$ 413,000.00$ 9.05$ 533,950.00$ 11.70$ 690,300.00$

100 Graded Sand Crossover with Stabilization Mat 6,670 SF 7.64$ 50,958.80$ 5.00$ 33,350.00$ 6.25$ 41,687.50$ 7.60$ 50,692.00$ 101 ADA Accessible Crossovers 2,560 SF 9.83$ 25,164.80$ 5.00$ 12,800.00$ 4.50$ 11,520.00$ 5.60$ 14,336.00$ 102 Vehicle Crossover 8,529 SF 12.46$ 106,271.34$ 5.00$ 42,645.00$ 4.00$ 34,116.00$ 5.00$ 42,645.00$ 103 Sand Fence 8,190 LF 9.77$ 80,016.30$ 7.00$ 57,330.00$ 6.00$ 49,140.00$ 7.25$ 59,377.50$ 104 Split Rail Fence 2,316 LF 26.14$ 60,540.24$ 7.00$ 16,212.00$ 6.75$ 15,633.00$ 8.25$ 19,107.00$ 105 Post and Rail Fence 512 LF 183.96$ 94,187.52$ 70.00$ 35,840.00$ 65.00$ 33,280.00$ 80.50$ 41,216.00$ 106 Berm Stabilization Mat 300 SF 6.60$ 1,980.00$ 8.00$ 2,400.00$ 7.00$ 2,100.00$ 8.60$ 2,580.00$ 107 Dune Grass Planting 18" O.C. 16,273 SY 6.53$ 106,262.69$ 4.00$ 65,092.00$ 3.75$ 61,023.75$ 4.75$ 77,296.75$ 108 Dune Grass Planting 24" O.C. 15,959 SY 4.02$ 64,155.18$ 3.00$ 47,877.00$ 2.45$ 39,099.55$ 3.10$ 49,472.90$

Name the State of New Jersey and the Borough of Point Pleasant Beach as "Additional Insured" under General Liability Insurance 1 JOB $1,500 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOTAL ESTIMATED OPTION 1 AMOUNT 1,573,255.87$ 792,546.00$ 880,049.80$ 1,140,773.15$

BOROUGH OF POINT PLEASANT BEACH-FROM STATION 38+50 TO STATION 94+42

OPTION 2

110 Demolition 1 JOB 27,700.00$ 27,700.00$ JOB 110,000.00$ JOB 100,000.00$ JOB 125,000.00$ 111 Structures Monitoring 1 JOB 47,334.00$ 47,334.00$ JOB 10,000.00$ JOB 3,000.00$ JOB 25,250.00$ 112 Beachfill 464,000 CY 13.14$ 6,096,960.00$ 6.00$ 2,784,000.00$ 7.20$ 3,340,800.00$ 10.75$ 4,988,000.00$

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

113 Graded Sand Crossover with Stabilization Mat 13,596 SF 7.42$ 100,882.32$ 5.00$ 67,980.00$ 6.25$ 84,975.00$ 7.70$ 104,689.20$ 114 ADA Accessible Crossovers 7,013 SF 8.84$ 61,994.92$ 5.00$ 35,065.00$ 4.35$ 30,506.55$ 5.35$ 37,519.55$ 115 Vehicle Crossover 4,487 SF 13.02$ 58,420.74$ 4.00$ 17,948.00$ 3.25$ 14,582.75$ 4.05$ 18,172.35$ 116 Timber Bulkhead 40 LF 760.30$ 30,412.00$ 500.00$ 20,000.00$ 410.00$ 16,400.00$ 500.00$ 20,000.00$ 117 Sand Fence 11,356 LF 9.77$ 110,948.12$ 7.00$ 79,492.00$ 6.00$ 68,136.00$ 7.25$ 82,331.00$ 118 Split Rail Fence 3,295 LF 25.58$ 84,286.10$ 7.00$ 23,065.00$ 6.50$ 21,417.50$ 8.10$ 26,689.50$ 119 Post and Rail Fence 1,402 LF 183.16$ 256,790.32$ 70.00$ 98,140.00$ 65.00$ 91,130.00$ 81.00$ 113,562.00$ 120 Berm Stabilization Mat 900 SF 6.60$ 5,940.00$ 7.00$ 6,300.00$ 7.00$ 6,300.00$ 8.25$ 7,425.00$ 121 Dune Grass Planting 18" O.C. 46,558 SY 6.53$ 304,023.74$ 4.00$ 186,232.00$ 3.75$ 174,592.50$ 4.80$ 223,478.40$ 122 Dune Grass Planting 24" O.C. 33,067 SY 3.98$ 131,606.66$ 3.00$ 99,201.00$ 2.45$ 81,014.15$ 3.05$ 100,854.35$

Name the State of New Jersey and the Borough of Point Pleasant Beach as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOTAL ESTIMATED OPTION 2 AMOUNT 7,318,798.92$ 3,538,423.00$ 4,033,854.45$ 5,874,221.35$

BOROUGH OF POINT PLEASANT BEACH-FROM STATION 0+00 TO STATION 94+42

124 OPTION 3 - Beachfill 59,000 CY 12.31$ 726,290.00$ 5.50$ 324,500.00$ 7.00$ 413,000.00$ 10.65$ 628,350.00$

125 OPTION 4 - Beachfill 33,000 CY 12.40$ 409,200.00$ 5.50$ 181,500.00$ 7.00$ 231,000.00$ 10.65$ 351,450.00$

126 OPTION 5 - Sea Avenue Pump Station Force Main 1 JOB 2,101,365.00$ 2,101,365.00$ JOB 3,000,000.00$ JOB 2,900,000.00$ JOB 3,500,000.00$

BOROUGH OF BAY HEAD-FROM STATION 94+42 TO STATION 162+36

OPTION 6

127 Demolition 1 JOB 30,502.00$ 30,502.00$ JOB 150,000.00$ JOB 135,000.00$ JOB 167,000.00$ 128 Structures Monitoring 1 JOB 146,580.00$ 146,580.00$ JOB 15,000.00$ JOB 10,000.00$ JOB 51,000.00$ 129 Beachfill 1,412,000 CY 17.41$ 24,582,920.00$ 5.50$ 7,766,000.00$ 6.50$ 9,178,000.00$ 10.00$ 14,120,000.00$ 130 Pedestrian Crossovers 16,932 SF 8.58$ 145,276.56$ 5.00$ 84,660.00$ 4.25$ 71,961.00$ 5.25$ 88,893.00$ 131 ADA Accessible Crossover 4,473 SF 9.17$ 41,017.41$ 5.00$ 22,365.00$ 4.25$ 19,010.25$ 5.35$ 23,930.55$ 132 Vehicle Crossover 5,409 SF 12.88$ 69,667.92$ 4.00$ 21,636.00$ 3.00$ 16,227.00$ 3.60$ 19,472.40$ 133 Timber Sheeting 1 JOB 8,304.00$ 8,304.00$ JOB 20,000.00$ JOB 12,000.00$ JOB 14,000.00$ 134 Sand Fence 13,268 LF 9.77$ 129,628.36$ 7.00$ 92,876.00$ 6.00$ 79,608.00$ 7.25$ 96,193.00$ 135 Split Rail Fence 4,087 LF 25.24$ 103,155.88$ 7.00$ 28,609.00$ 6.75$ 27,587.25$ 8.25$ 33,717.75$ 136 Post and Rail Fence 895 LF 179.47$ 160,625.65$ 70.00$ 62,650.00$ 65.00$ 58,175.00$ 80.00$ 71,600.00$ 137 Berm Stabilization Mat 600 SF 6.60$ 3,960.00$ 7.00$ 4,200.00$ 6.50$ 3,900.00$ 8.10$ 4,860.00$ 138 Dune Grass Planting 18" O.C. 58,372 SY 6.53$ 381,169.16$ 4.00$ 233,488.00$ 3.75$ 218,895.00$ 4.80$ 280,185.60$ 139 Dune Grass Planting 24" O.C. 30,940 SY 4.00$ 123,760.00$ 3.00$ 92,820.00$ 2.45$ 75,803.00$ 3.10$ 95,914.00$

Name the State of New Jersey and the Borough of Bay Head as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOTAL ESTIMATED OPTION 6 AMOUNT 25,928,066.94$ 8,595,304.00$ 9,907,166.50$ 15,068,016.30$

BOROUGH OF BAY HEAD-FROM STATION 94+42 TO STATION 162+36

141 OPTION 7 - Beachfill 159,000 CY 17.09$ 2,717,310.00$ 5.00$ 795,000.00$ 6.05$ 961,950.00$ 10.00$ 1,590,000.00$ 142 OPTION 8 - Beachfill 88,000 CY 17.15$ 1,509,200.00$ 5.00$ 440,000.00$ 6.05$ 532,400.00$ 10.00$ 880,000.00$

BOROUGH OF MANTOLOKING-FROM STATION 162+36 TO STATION 182+69

OPTION 9

143 Demolition 1 JOB 7,286.00$ 7,286.00$ JOB 5,000.00$ JOB 1,000.00$ JOB 1,000.00$ 144 Structures Monitoring 1 JOB 37,562.00$ 37,562.00$ JOB 10,000.00$ JOB 5,000.00$ JOB 15,100.00$ 145 Beachfill 358,000 CY 11.45$ 4,099,100.00$ 7.50$ 2,685,000.00$ 9.15$ 3,275,700.00$ 10.00$ 3,580,000.00$ 146 Pedestrian Crossovers 6,056 SF 8.93$ 54,080.08$ 7.00$ 42,392.00$ 7.85$ 47,539.60$ 9.65$ 58,440.40$ 147 Sand Fence 4,096 LF 9.77$ 40,017.92$ 7.00$ 28,672.00$ 6.00$ 24,576.00$ 7.35$ 30,105.60$ 148 Split Rail Fence 1,212 LF 25.17$ 30,506.04$ 7.00$ 8,484.00$ 7.80$ 9,453.60$ 9.60$ 11,635.20$

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

149 Dune Grass Planting 18" O.C. 17,528 SY 6.53$ 114,457.84$ 4.00$ 70,112.00$ 3.75$ 65,730.00$ 4.75$ 83,258.00$ 150 Dune Grass Planting 24" O.C. 6,294 SY 4.05$ 25,490.70$ 3.00$ 18,882.00$ 2.45$ 15,420.30$ 3.10$ 19,511.40$

TOTAL ESTIMATED OPTION 9 AMOUNT 4,408,500.58$ 2,868,542.00$ 3,444,419.50$ 3,799,050.60$

BOROUGH OR MANTOLOKING-FROM STATION 162+36 TO STATION 182+69

151 OPTION 10 - Beachfill 50,000 CY 11.15$ 557,500.00$ 7.50$ 375,000.00$ 5.65$ 282,500.00$ 10.00$ 500,000.00$

BOROUGH OF MANTOLOKING-FROM STATION 182+69 TO STATION 207+68

OPTION 11

152 Demolition 1 JOB 9,154.00$ 9,154.00$ JOB 5,000.00$ JOB 1,000.00$ JOB 1,052.25$ 153 Structures Monitoring 1 JOB 51,609.00$ 51,609.00$ JOB 10,000.00$ JOB 8,000.00$ JOB 20,500.00$ 154 Beachfill 597,000 CY 11.16$ 6,662,520.00$ 7.50$ 4,477,500.00$ 9.05$ 5,402,850.00$ 10.00$ 5,970,000.00$ 155 Pedestrian Crossovers 2,880 SF 9.66$ 27,820.80$ 20.00$ 57,600.00$ 19.00$ 54,720.00$ 23.50$ 67,680.00$ 156 Vehicle Crossover 5,507 SF 12.72$ 70,049.04$ 4.00$ 22,028.00$ 3.00$ 16,521.00$ 3.75$ 20,651.25$ 157 Sand Fence 5,146 LF 9.77$ 50,276.42$ 6.00$ 30,876.00$ 6.00$ 30,876.00$ 7.50$ 38,595.00$ 158 Split Rail Fence 1,211 LF 24.86$ 30,105.46$ 8.00$ 9,688.00$ 7.00$ 8,477.00$ 9.65$ 11,686.15$ 159 Dune Grass Planting 18" O.C. 22,336 SY 6.53$ 145,854.08$ 4.00$ 89,344.00$ 3.75$ 83,760.00$ 4.75$ 106,096.00$ 160 Dune Grass Planting 24" O.C. 9,727 SY 4.03$ 39,199.81$ 3.00$ 29,181.00$ 2.45$ 23,831.15$ 3.10$ 30,153.70$

TOTAL ESTIMATED OPTION 11 AMOUNT 7,086,588.61$ 4,731,217.00$ 5,630,035.15$ 6,266,414.35$

BOROUGH OF MANTOLOKING-FROM STATION 182+69 TO STATION 207+68

161 OPTION 12 - Beachfill 72,000 CY 10.91$ 785,520.00$ 7.50$ 540,000.00$ 5.60$ 403,200.00$ 10.00$ 720,000.00$

BOROUGH OF MANTOLOKING-FROM STATION 207+68 TO STATION 277+58

162 OPTION 13 - Beachfill 226,000 CY 10.85$ 2,452,100.00$ 5.00$ 1,130,000.00$ 5.60$ 1,265,600.00$ 11.80$ 2,666,800.00$ 163 OPTION 14 - Beachfill 100,000 CY 10.95$ 1,095,000.00$ 5.00$ 500,000.00$ 5.60$ 560,000.00$ 11.80$ 1,180,000.00$

BRICK TOWNSHIP-FROM STATION 277+58 TO STATION 371+64

164 OPTION 15 - Beachfill 177,000 CY 13.37$ 2,366,490.00$ 6.00$ 1,062,000.00$ 7.25$ 1,283,250.00$ 11.50$ 2,035,500.00$ 165 OPTION 16 - Beachfill 98,000 CY 13.36$ 1,309,280.00$ 6.00$ 588,000.00$ 7.25$ 710,500.00$ 11.50$ 1,127,000.00$

TOMS RIVER TOWNSHIP (NORTH)-FROM STATION 371+04 TO STATION 449+81

166 OPTION 17 - Beachfill 128,000 CY 14.06$ 1,799,680.00$ 6.00$ 768,000.00$ 7.80$ 998,400.00$ 11.50$ 1,472,000.00$ 167 OPTION 18 - Beachfill 71,000 CY 13.99$ 993,290.00$ 6.00$ 426,000.00$ 7.80$ 553,800.00$ 11.50$ 816,500.00$

OPTION 19 - Dune Crossover Stabilization Mat for

ADA 3,314 SF 6.60$ 21,872.40$ 6.00$ 19,884.00$ 6.00$ 19,884.00$ 7.20$ 23,860.80$

TOMS RIVER TOWNSHIP (NORTH)-FROM STATION 371+64 TO STATION 449+81

OPTION 20

169 Private Dune Crossover with Stabilization Mat 32,431 SF 8.26$ 267,880.06$ 8.00$ 259,448.00$ 7.50$ 243,232.50$ 9.35$ 303,229.85$ 170 Split Rail Fence 6,485 SF 25.55$ 165,691.75$ 7.00$ 45,395.00$ 6.50$ 42,152.50$ 8.10$ 52,528.50$

TOTAL ESTIMATED OPTION 20 AMOUNT 433,571.81$ 304,843.00$ 285,385.00$ 355,758.35$

BOROUGH OF LAVALLETTE-FROM STATION 449+81 TO STATION 526+37

171 OPTION 21 - Beachfill 159,000 CY 13.83$ 2,198,970.00$ 6.00$ 954,000.00$ 7.50$ 1,192,500.00$ 11.25$ 1,788,750.00$ 172 OPTION 22 - Beachfill 88,000 CY 13.79$ 1,213,520.00$ 6.00$ 528,000.00$ 7.50$ 660,000.00$ 11.25$ 990,000.00$

BOROUGH OF LAVALLETTE-FROM STATION 449_81 TO STATION 526+37

OPTION 23

173 ADA Accessible Crossover 3,914 SF 8.28$ 32,407.92$ 5.00$ 19,570.00$ 4.25$ 16,634.50$ 5.35$ 20,939.90$ 174 Berm Stabilization Mat 600 SF 6.60$ 3,960.00$ 10.00$ 6,000.00$ 9.00$ 5,400.00$ 11.20$ 6,720.00$ 175 Post and Rail Fence 763 LF 182.28$ 139,079.64$ 60.00$ 45,780.00$ 65.00$ 49,595.00$ 80.00$ 61,040.00$

TOTAL ESTIMATED OPTION 23 AMOUNT 175,447.56$ 71,350.00$ 71,629.50$ 88,699.90$

W912BU-16-B-0014 Beachfill, Initial Construction, Manasquan Inlet to Barnegat Inlet, Ocean County, NJ

Gov't Estimate Manson Construction Company Weeks Marine, Incorporated Great Lakes Dredge & Dock Company, LLC

TOMS RIVER TOWNSHIP (SOUTH)-FROM STATION 526+37 TO STATION 567+09

176 OPTION 24 - Beachfill 139,000 CY 13.09$ 1,819,510.00$ 5.50$ 764,500.00$ 7.10$ 986,900.00$ 10.75$ 1,494,250.00$ 177 OPTION 25 - Beachfill 77,000 CY 13.13$ 1,011,010.00$ 5.50$ 423,500.00$ 7.10$ 546,700.00$ 10.75$ 827,750.00$

Option 26 - Dune Crossover Stabilization Mat for ADA Crossovers 7,062 SF 6.60$ 46,609.20$ 6.00$ 42,372.00$ 6.00$ 42,372.00$ 7.25$ 51,199.50$

TOMS RIVER TOWNSHIP (SOUTH)-FROM STATION 526+37 TO STATION 567+09

OPTION 27

179 Private Dune Crossover with Stabilizaiton Mats 17,514 SF 8.20$ 143,614.80$ 7.00$ 122,598.00$ 6.00$ 105,084.00$ 7.50$ 131,355.00$ 180 Split Rail Fence 3,504 SF 25.43$ 89,106.72$ 7.00$ 24,528.00$ 6.50$ 22,776.00$ 8.10$ 28,382.40$

TOTAL ESTIMATED OPTION 27 AMOUNT 232,721.52$ 147,126.00$ 127,860.00$ 159,737.40$

BOROUGH OF SEASIDE HEIGHTS-FROM STATION 567+-0 TO STATION 608+70

181 OPTION 28 - Beachfill 75,000 CY 12.63$ 947,250.00$ 5.50$ 412,500.00$ 6.40$ 480,000.00$ 11.10$ 832,500.00$ 182 OPTION 29 - Beachfill 42,000 CY 12.58$ 528,360.00$ 5.50$ 231,000.00$ 6.40$ 268,800.00$ 11.10$ 466,200.00$

BOROUGH OF SEASIDE PARK-FROM STATION 608+70 TO STATION 698+-01

183 OPTION 30 - Beachfill 105,000 CY 12.12$ 1,272,600.00$ 5.50$ 577,500.00$ 5.40$ 567,000.00$ 10.75$ 1,128,750.00$ 184 OPTION 31 - Beachfill 58,000 CY 12.08$ 700,640.00$ 5.50$ 319,000.00$ 5.40$ 313,200.00$ 10.75$ 623,500.00$

BERKLEY TOWNSHIP-FROM STATION 609+01 TO STATION 735+40

OPTION 32

185 Demolition 1 JOB 35,846.00$ 35,846.00$ JOB 50,000.00$ JOB 54,000.00$ JOB 67,000.00$ 186 Structures Monitoring 1 JOB 26,263.00$ 26,263.00$ JOB 5,000.00$ JOB 2,500.00$ JOB 18,500.00$ 187 Beachfill 161,000 CY 13.01$ 2,094,610.00$ 5.50$ 885,500.00$ 10.30$ 1,658,300.00$ 10.80$ 1,738,800.00$ 188 Pedestrian Crossovers 6,754 SF 8.87$ 59,907.98$ 5.00$ 33,770.00$ 4.30$ 29,042.20$ 5.30$ 35,796.20$ 189 ADA Accessible Crossovers 3,256 SF 9.50$ 30,932.00$ 5.00$ 16,280.00$ 4.50$ 14,652.00$ 5.50$ 17,908.00$ 190 Vehicle Crossover 8,168 SF 12.81$ 104,632.08$ 4.00$ 32,672.00$ 3.25$ 26,546.00$ 4.05$ 33,080.40$ 191 Sand Fence 7,454 LF 9.77$ 72,825.58$ 7.00$ 52,178.00$ 6.00$ 44,724.00$ 7.30$ 54,414.20$ 192 Split Rail Fence 2,552 LF 25.32$ 64,616.64$ 7.00$ 17,864.00$ 6.75$ 17,226.00$ 8.25$ 21,054.00$ 193 Post and Rail Fence 649 LF 176.29$ 114,412.21$ 70.00$ 45,430.00$ 65.00$ 42,185.00$ 79.80$ 51,790.20$ 194 Berm Stabilization Mat 300 SF 6.60$ 1,980.00$ 7.00$ 2,100.00$ 7.00$ 2,100.00$ 8.60$ 2,580.00$ 195 Dune Grass Planting 18" O.C. 9,379 SY 6.53$ 61,244.87$ 4.00$ 37,516.00$ 3.75$ 35,171.25$ 4.80$ 45,019.20$ 196 Dune Grass Planting 24" O.C. 9,831 SY 4.08$ 40,110.48$ 3.00$ 29,493.00$ 2.45$ 24,085.95$ 3.10$ 30,476.10$

Name the State of New Jersey and Berkley Township as "Additional Insured" under General Liability Insurance 1 JOB 1,500.00$ 1,500.00$ JOB 1,000.00$ JOB 1,000.00$ JOB 1,250.00$

TOTAL ESTIMATED OPTION 32 AMOUNT 2,708,880.84$ 1,208,803.00$ 1,951,532.40$ 2,117,668.30$

BERKELEY TOWNSHIP-FROM STATION 698+-1 TO STATION 735+40

198 OPTION 33 - Beachfill 18,000 CY $11.75 $211,500.00 6.00$ 108,000.00$ 5.60$ 100,800.00$ 10.90$ 196,200.00$ 199 OPTION 34 - Beachfill 10,000 CY $11.66 $116,600.00 6.00$ 60,000.00$ 5.60$ 56,000.00$ 10.90$ 109,000.00$

TOTAL ESTIMATED BASE BID AND OPTIONS 1 THROUGH 34 AMOUNT $211,300,971.75 128,820,433.00$ 151,861,106.40$ 178,416,600.00$

Sheet1

2016-11-30T15:19:38-0500
DETITTA.DENISE.M.1229151254

File details come from the government source that posted it. Updated .