W9128F21R0023 Amendment 0006.pdf

PDF 511 KB Posted

Attached to
Offutt AFB Lake Campus Softball Complex Federal contract opportunity
Solicitation number
W9128F21R0023
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This document contains an amendment to a solicitation for a design-build project and the related federal contract opportunity. The amendment updates the wage determination and extends the response date for the solicitation to September 2, 2021. The solicitation is for the construction of a softball support facility at Offutt Air Force Base in Nebraska, including site work and two softball fields. The project is open only to service-disabled veteran-owned small businesses. The specifications, drawings and instructions to offerors are included in the attached documents. Responses must be submitted electronically by the new due date. The selected contractor must commence work within 10 days of notice to proceed and complete the project within 540 calendar days. Performance and payment bonds will be required. The Department of the Army Corps of Engineers Engineering District Omaha is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Offutt AFB Lake Campus Softball Complex, newest first.
File Type Posted
W9128F21R0023 Amendment 0005.pdf PDF
W9128F21R0023 Amendment 0004.pdf PDF
Am-0003_W9128F21R0023.pdf PDF
Am-0002_W9128F21R0023.pdf PDF
W9128F21R0023 Amendment 0001.pdf PDF
Site Visit_Offutt_Softball_Support_Facility_4.22.21.pdf PDF
SPECS_W9128F21R0023_Lake-Campus-SFSF(of68).pdf PDF
OF68 - ADVERTISEMENT.PDF PDF
NDORF17G.pdf PDF
W9128F21R0023 Solicitation Released 20210401.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

LAKE CAMPUS, SOFTBALL FIELD SUPPORT FACILITY, SGBP212908 (FY20), OFFUTT AFB, NEBRASKA

See attached documentation for content of the amendment revisions to solicitation

Date for receipt of submission is 2 SEP 2021 at 1400 hours CDT

Government Point of Contact: Melissa Harlon, Contract Specialist, Melissa.R.Harlon@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F21R0023

X 9B. DATED (SEE ITEM 11)

01-Apr-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Aug-2021

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128F21R0023

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AM0006 - SUMMARY OF CHANGES

27 AUG 2021

Solicitation No. W9128F 21 R 0023

Date of Issue: 01 Apr 2021 Date of Receiving/Confirming Price Proposals: 2 September 2021

SUBJECT: Amendment No. 0006 to Request for Proposal Solicitation Package for Construction of LAKE CAMPUS, SOFTBALL FIELD SUPPORT FACILITY, SGBP212908.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 00 73 00 Wage Rates: Building General Decision Number

NE20210059 has been updated to 27 Aug 2021.

b. Specifications (New and/or Revised and Reissued). NONE.

c. Drawings (Reissued). NONE.

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Responses. This Amendment is to update the Wage Decision.

Solicitation is only extended for response to the items stated herein. Responses will be submitted via email to melissa.r.harlon@usace.army.mil and courtesy copy ann.t.young@usace.army.mil. Responses will either include 1) submittal of signed SF1442 or SF30 with email response advising no change in price; or 2) a signed SF1442 or SF30 with revised Volume II Price Proposal only showing all revisions to price in red text. No other submission is requested. To clarify, acknowledgement of Amendments can be done either on the SF1442 or the SF30, preference is the SF1442.

4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 2 SEP 2021.

Attachments:

Wage Decision listed in 1.a., above

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102 4901

27 AUG 2021

mrh/2490

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

The required response date/time has changed from 31-Aug-2021 02:00 PM to 02-Sep-2021 02:00 PM.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

WAGE DECISION

"General Decision Number: NE20210059 08/27/2021

Superseded General Decision Number: NE20200059

State: Nebraska

Construction Type: Building

BUILDING CONSTRUCTION INCLUDING WORK ON INDUSTRIAL SITES

County: Sarpy County in Nebraska.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/01/2021 1 01/22/2021 2 04/23/2021 3 06/25/2021 4 07/09/2021 5 07/30/2021 6 08/27/2021

BRNE0001-001 06/29/2020

Rates Fringes

BRICKLAYER.......................$ 30.21 17.25

* CARP0427-001 06/01/2021

Rates Fringes

CARPENTER (Including Acoustical Ceiling Installation)....................$ 28.64 15.33

* CARP0427-004 06/01/2021

Rates Fringes

CARPENTER (Drywall Hanging, Finishing/Taping Only)...........$ 28.64 15.33

ELEC0022-001 06/01/2021

Rates Fringes

ELECTRICIAN......................$ 40.00 17.27

ELEV0028-001 01/01/2021

Rates Fringes

ELEVATOR MECHANIC................$ 47.48 35.825+a+b

FOOTNOTE:

a. Vacation Pay: 8% for persons with 5 or more years of service, 6% for persons with less than 5 years of service.

b. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.

ENGI0571-004 10/01/2020

Rates Fringes

OPERATOR: Crane.................$ 32.64 13.29 OPERATOR: Forklift..............$ 27.26 13.29

IRON0021-002 06/01/2020

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 31.75 18.03

LABO1140-003 06/01/2017

Rates Fringes

LABORER (Mason Tender, Brick & Hod)...........................$ 21.69 9.40

PLUM0016-003 05/16/2021

Rates Fringes

PLUMBER (Excluding HVAC Pipe Installation)....................$ 39.95 13.81

PLUM0464-006 05/30/2021

Rates Fringes

PIPEFITTER (Includes HVAC Pipe Installation and Excludes HVAC System Installation)....................$ 39.89 18.71

SFNE0669-001 04/01/2021

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 38.06 23.45

SHEE0003-001 07/01/2015

Rates Fringes

SHEET METAL WORKER (Including HVAC Duct & System Installation)....................$ 32.89 14.93

SUNE2011-033 10/27/2011

Rates Fringes

CARPENTER (Form Work Only).......$ 19.35 4.29

CAULKER..........................$ 17.44 0.00

CEMENT MASON/CONCRETE FINISHER...$ 19.05 4.34

ELECTRICIAN (Low Voltage Wiring)..........................$ 20.66 5.74

GLAZIER..........................$ 17.86 1.70

LABORER: Common or General......$ 15.41 5.20

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 21.20 5.47

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 23.02 0.91

OPERATOR: Loader................$ 19.01 5.68

PAINTER: Brush, Roller and Spray............................$ 14.26 0.00

ROOFER...........................$ 13.57 0.77

TRUCK DRIVER, Includes Dump and Tandem Truck.................$ 15.34 3.22

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

(End of Summary of Changes)