Am_0007.pdf

PDF 1 MB Posted

Attached to
Maintenance Hangar -Fort Carson, CO Federal contract opportunity
Solicitation number
W9128F-16-R-0067
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

Amendment 7

View the file

Other files for this federal contract opportunity

Other files attached to Maintenance Hangar -Fort Carson, CO, newest first.
File Type Posted
W9128F-16-R-0067_Amend_0009.pdf PDF
Am_0008.pdf PDF
Am_0007-Drawings.pdf PDF
Am_0006.pdf PDF
Am_0006-Drawings.pdf PDF
Am_0005-Drawings.pdf PDF
Am_0005.pdf PDF
Am_0004-Drawings.pdf PDF
Am_0004.pdf PDF
Am_0003-Drawings.pdf PDF
Am_0003.pdf PDF
FCX7_CADD_Files.zip ZIP file
Am_0002-Drawings.pdf PDF
Am_0002.pdf PDF
FY15_Attack_Pre-award_Site_Visit_Sign-In_Sheet_(07JUN16).pdf PDF
Am_0001-Vol1_Drawings.pdf PDF
Am_0001-Vol3_Drawings.pdf PDF
Am_0001.pdf PDF
FCX7_Advertisement_Vol._1.PDF PDF
FCX7_Advertisement_Vol._1.PDF.7z 7Z file
FCX7_Advertisement_Vol._3.pdf PDF
FCX7_Advertisement_Vol._2.pdf PDF
Specs_W9128F-16-R-0067.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

Amendment No. 0007 21-JUL-2016

U.S ARMY CORPS OF ENGINEERS, OMAHA DISTRICT

CONTRACTING OFFICE

1616 CAPITOL AVE.

OMAHA, NE 68102-4901

See Item 6

W9128F-16-R-0067

23-MAY-2016

4th ID CAB, ATTK BN MAINTENANCE HANGAR

PN 77305, FORT CARSON, COLORADO

See attached documentation for content of the amendment revisions

Date for receipt of Proposals is 28 JUL 2016 at 1400 hours

Government Point of Contact: Denise Cramer (402) 995-2057

21-JUL-2016

Am #0007 - 2 (Continuation SF 30)

DEPARTMENT OF THE ARMY

Omaha District, Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901

:NOTICE: Failure to acknowledge : Solicitation No. W9128F 16 R 0067 :all amendments may cause rejec- :

:tion of the offer. See FAR : Date of Issue: 23 MAY 2016 :52.215-1 of Section 00 21 00 : Date of Receiving Proposals:

28 JUL 2016

Amendment No. 0007

21 JUL 2016

SUBJECT: Amendment No. 0007 to Request for Proposal Solicitation Package for Construction of 4th ID CAB, ATTK BN MAINTENANCE HANGAR, PN 77305, FORT CARSON, COLORADO

Solicitation No. W9128F 16 R 0067

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.

For convenience, on the revised specification pages (excepting general wage decision ones and where there are merely deletions), changes have been identified by highlighting. (All portions of reissued specification pages shall apply whether or not changes thereon have been indicated by highlighting.)

Pages or Sections Deleted Pages or Sections Substituted or Added 00 10 00 00 10 00 01 35 26 01 35 26 03 30 00 03 30 00 05 50 13 05 50 13 08 71 00 08 71 00 09 67 23.15 09 67 23.15 09 90 00 09 90 00 12 21 00 12 21 00 13 21 10 13 21 10 22 00 00 22 00 00 27 51 16 27 51 16 32 13 11.10 32 13 11.10

b. Drawings (Reissued). The following drawings are revised with latest revision date of 21 JUL 2016, and reissued with this amendment.

(1) Sheet FCX7G-002, VOLUME 1 INDEX

(2) Sheet FCX7CD112A.1, OPTIONAL ADDITIONAL DEMOLITION AREA 112A.1

(3) Sheet FCX7CD112B.1, OPTIONAL ADDITIONAL DEMOLITION AREA

Am #0007 - 3

112B.1

(4) Sheet FCX7CD112D.1, OPTIONAL ADDITIONAL DEMOLITION AREA 112D.1

(5) Sheet FCX7CD113A.1, OPTIONAL ADDITIONAL DEMOLITION AREA 113A.1

(6) Sheet FCX7CD113C.1, OPTIONAL ADDITIONAL DEMOLITION AREA 113C.1

(7) Sheet FCX7CD123C.1, OPTIONAL ADDITIONAL DEMOLITION AREA 123C.1

(8) Sheet FCX7CD123D.1, OPTIONAL ADDITIONAL DEMOLITION AREA 123D.1

(9) Sheet FCX7A-103, FIRST FLOOR PLAN – AREA “C” - ANNOTATIVE

(10) Sheet FCX7A-201, NORTH AND SOUTH ELEVATIONS

(11) Sheet FCX7A-202, EAST AND WEST ELEVATIONS

(12) Sheet FCX7A-203, ENLARGED EXTERIOR ELEVATIONS

(13) Sheet FCX7A-204, ENLARGED SOUTH ELEVATION AREA “A”

(14) Sheet FCX7A-205, ENLARGED SOUTH ELEVATION AREA “B”

(15) Sheet FCX7A-206, ENLARGED SOUTH ELEVATION

(16) Sheet FCX7A-207, ENLARGED EAST ELEVATION

(17) Sheet FCX7A-208, ENLARGED WEST ELEVATION

(18) Sheet FCX7A-423, STORAGE SYSTEM PLAN AND DETAILS

(19) Sheet FCX7A-600, FINISH SCHEDULE FIRST FLOOR

(20) Sheet FCX7ES100A, ELECTRICAL SITE PLAN COMPOSITE

(21) Sheet FCX7ES113.1, ELECTRICAL SITE PLAN AREA 113 AIRFIELD

OPTION

(22) Sheet FCX7ES113, ELECTRICAL SITE PLAN AREA 113

(23) Sheet FCX7ES113B, ELECTRICAL SITE PLAN AREA 113B

(24) Sheet FCX7ES122, ELECTRICAL SITE PLAN AREA 122

(25) Sheet FCX7ES124.1, ELECTRICAL SITE PLAN AREA 124 AIRFIELD

OPTION

(26) Sheet FCX7ES124, ELECTRICAL SITE PLAN AREA 124

(27) Sheet FCX7ES125, ELECTRICAL SITE PLAN AREA 125

(28) Sheet FCX7ES505, ELECTRICAL SITE DETAILS UTILITY RACKS

(29) Sheet FCX7EY601, SYSTEMS RISERS

(30) Sheet FCX7TO100, COMMUNICATIONS SITE PLAN COMPOSITE

c. Drawings (New). The following new drawings dated 21 JUL 2016 are hereby added to the request for proposal drawings and are issued with this amendment.

(1) Sheet FCX7G-009, AIRFIELD GATE ACCESS

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged on the Standard Form 1442. All other conditions and requirements of the request for proposal remain unchanged. If the proposals have been mailed prior to receiving this amendment, you will notify the office where proposals are received, in the specified manner, immediately of its receipt and of any changes in your proposal occasioned thereby.

a. Hand-Carried Proposals shall be delivered to the U.S. Army Corps of Engineers, Omaha District, Contracting Division, 1616 Capitol Avenue, Omaha, Nebraska 68102-4901.

b. Mailed Proposals shall be addressed as noted in Item 8 on Page 00 10 00-1 of Standard Form 1442.

3. Offers will be received until 2:00 p.m., local time at place of

Am #0007 - 4 receiving proposals, 28 JUL 2016.

Attachments:

Spec Pages listed in 1.a. above Dwgs. listed in 1.b. above (under separate cover)

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

21 JUL 2016

jlb/2099

00 10 00 - 1

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W9128F-16-R-0067

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

23 MAY 2016

PAGES OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY CODE CT 8. ADDRESS OFFER TO

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Contracting Division (CENWO-CT) 1616 Capitol Ave Omaha, Nebraska 68102-4901

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Attn: CONTRACTING DIVISION (CENWO-CT) 1616 Capitol Ave Omaha, Nebraska 68102-4901

9. FOR INFORMATION

CALL:

A. NAME

Denise Cramer

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(402) 995-2057

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

The offeror hereby agrees to do all work described in the documents entitled:

4th ID CAB, ATTK BN MAINTENANCE HANGAR

PN 77305

FORT CARSON, COLORADO

RETURN WITH OFFER: INFORMATION REQUIRED BY SECTION 00 10 00 (SF1442 AND CLIN BIDDING SCHEDULE), SECTION 00 22 00, AND SECTION 00 45 00.

*BLOCK 13A. – REFER TO SECTION 00 22 00 FOR THE NUMBER OF COPIES TO BE SUBMITTED WITH THE ORIGINAL OFFER.

THIS SOLICITATION IS UNRESTRICTED AND OPEN TO PARTICIPATION BY SMALL AND OTHER THAN SMALL BUSINESS INTERESTS. SOURCE SELECTION PREFERENCE WILL BE GIVEN TO THE PROPOSAL REPRESENTING THE OVERALL BEST VALUE TO THE GOVERNMENT.

11. The Contractor shall begin performance within 10 calendar days and complete it within 600 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable.

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and * copies to perform the work required are due at the place specified in Item 8 by 1400 (hour) local time 28 JUL 2016. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101

STANDARD FORM 1442(REV. 4-85)

Prescribed by GSA FAR(48 CFR) 53.236-1(d)

Am_0007

00 10 00 - 2

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

DUNS Number:

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within 60 calendar days after the date offers are due.

AMOUNTS

SEE ATTACHED CLIN BIDDING SCHEDULE

Contractor’s Fax No.____________ CAGE CODE ________________ Contractor’s E-Mail address_______________

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

U.S. Army Engineer District, Omaha 1616 Capitol Ave.

Omaha, Nebraska 68102-4901

USAED Omaha c/o USACE Finance Center 5722 Integrity Drive Millington, TN 38054-5005

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (contractor is required to sign this document and return _______ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,

(b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

STANDARD FORM 1442 BACK (REV. 4-85)

Section 00 10 00 W9128F-16-R-0067

CLIN SCHEDULE 00 10 00 - 3

OFFEROR'S NAME:____________________________

CONTRACT LINE ITEM (CLIN) BIDDING SCHEDULE

ITEM

NO.

DESCRIPTION QUANTITY UNIT UNIT

PRICE

LINE ITEM AMOUNT

BASIC ITEMS

0001 All work complete to Construct the ATTK BN Maintenance Hangar, up to 5 feet outside of the building.

1 Job XXX $_______________________

0002 All work complete to Construct Sitework, Utilities, and Pavements (excluding road work in Item 0003 below), complete from the five-foot line to the limits of construction of the ATTK BN Maintenance Hangar.

1 Job XXX $_______________________

0003 All work complete to Construct Improvements and realignment of Essayons Road (STA 61+50 to STA 101+50) and Tank Trail (STA 200+00 to 206+00). See Sheets CG808- CG814, CS808-CS814, and CT808-

CT814.

1 Job XXX $_______________________

0004 All work complete for Demolition of Building 9604, Building 9609, and other structures shown on demolition plans, as well as foundations, pavements, and utilities not listed in CLIN Option 0010 (Item 0014).

1 Job XXX $_______________________

TOTAL BASIC AMOUNT $_______________________

OPTION ITEMS

[Option 1]

All work complete to Provide Foam Pumps, Controllers, Atmospheric Tank, Relief Valves, Fire Alarm equipment, In-line Balance Proportioners, and any additional equipment, labor, programming, or design effort to meet the requirements of Engineering and Construction Bulletin No. 2015-17.

1 Job XXX $_______________________

[Option 2]

All work complete to Construct Pedestrian Bridge in accordance with the plans and specifications.

1 Job XXX $_______________________

CLIN SCHEDULE 00 10 00 - 4

[Option 3]

All work complete to Construct PT Pits in accordance with the plans and specifications.

1 Job XXX $_______________________

[Option 4]

All work complete to Construct Airfield Paving in accordance with the plans and specifications.

1 Job XXX $_______________________

[Option 5]

All work complete to Demolish the 9600/9601/9602 Building Complex including abatement and disposal of lead-based paint (LBP) and asbestos containing materials (ACM).

1 Job XXX $_______________________

[Option 6]

All work complete to Demolish Building 9610 including abatement and disposal of lead-based paint (LBP) and asbestos containing materials (ACM).

1 Job XXX $_______________________

[Option 7]

All work complete to Demolish Building 9611 including abatement and disposal of lead-based paint (LBP) and asbestos containing materials (ACM).

1 Job XXX $_______________________

[Option 8]

All work complete to Demolish Building 9634A including abatement and disposal of lead-based paint (LBP) and asbestos containing materials (ACM).

1 Job XXX $_______________________

[Option 9]

All work complete to Demolish Building 9635A including abatement and disposal of lead-based paint (LBP) and asbestos containing materials (ACM).

1 Job XXX $_______________________

[Option 10]

All work complete to Demolish Underground Utility Lines, Pavements, Slabs, Foundations, and other site features shown on Optional Additional Demolition plan sheets.

1 Job XXX $_______________________

TOTAL AMOUNT (BASIC PLUS OPTIONS) $_______________________

NOTES:

1. The government intends to issue a limited notice to proceed at time of award to begin work as described in Section 01 30 00.24, paragraph 1.7.

All work complete to Demolish p Underground Utility Lines, g y , Pavements, Slabs, Foundations, and , , , other site features shown on Optionalp Additional Demolition plan sheets.

CLIN SCHEDULE 00 10 00 - 5

2. See 00 21 00, INSTRUCTIONS TO OFFERORS, for evaluation of options. The Government reserves the right to exercise options within 180 calendar days after issuance of Notice to Proceed.

3. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. In case of variation between the lump-sum prices and the total amount, the lump-sum prices will be considered the price submitted.

4. A modification to a bid which provides for a single adjustment to the total amounts, should state the application of the adjustment to each respective lump-sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item No. 0001.

4th ID CAB Attack BN Maintenance Hangar, PN77305 Fort Carson, CO FCX7

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

02/12

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.3 SUBMITTALS

1.4 REGULATORY REQUIREMENTS

1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.5.1 Personnel Qualifications

1.5.1.1 Site Safety and Health Officer (SSHO)

1.5.1.1.1 Contractor Quality Control (QC) Person:

1.5.1.2 Alternate SSHO

1.5.1.3 Crane Operators

1.5.2 Personnel Duties

1.5.2.1 Site Safety and Health Officer (SSHO)

1.5.3 Meetings

1.5.3.1 Preconstruction Conference

1.6 ACCIDENT PREVENTION PLAN (APP)

1.6.1 EM 385-1-1 Contents

1.7 ACTIVITY HAZARD ANALYSIS (AHA)

1.8 DISPLAY OF SAFETY INFORMATION

1.9 SITE SAFETY REFERENCE MATERIALS

1.10 EMERGENCY MEDICAL TREATMENT

1.11 NOTIFICATIONS and REPORTS

1.11.1 Accident Notification

1.11.2 Accident Reports

1.11.3 Crane Reports

1.11.4 Certificate of Compliance

1.12 HOT WORK

1.13 FACILITY OCCUPANCY CLOSURE

1.14 SEVERE STORM PLAN

1.15 CONFINED SPACE ENTRY REQUIREMENTS.

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION

3.1 CONSTRUCTION AND OTHER WORK

3.1.1 Hazardous Material Exclusions

3.1.2 Unforeseen Hazardous Material

3.2 PRE-OUTAGE COORDINATION MEETING

3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)

3.4 FALL HAZARD PROTECTION AND PREVENTION PROGRAM

3.4.1 Training

3.4.2 Fall Protection Equipment and Systems

3.4.2.1 Personal Fall Arrest Equipment

SECTION 01 35 26 Page 1

3.5 EQUIPMENT

3.5.1 Crane Equipment

3.5.2 Crane Equipment

3.6 EXCAVATIONS

3.6.1 Utility Locations

3.6.2 Utility Location Verification

3.6.3 Utilities Within and Under Concrete, Bituminous Asphalt, and

Other Impervious Surfaces

3.7 ELECTRICAL

3.9.1 Portable Extension Cords

3.8 WORK IN CONFINED SPACES

3.9 AIRFIELD SAFETY PRECAUTIONS (DEC 1991)

3.9.1 Definitions

3.9.2 General

3.9.3 The Contractor shall

3.9.4 Landing Areas

3.9.5 Safety Precaution Areas

-- End of Section Table of Contents --

SECTION 01 35 26 Page 2

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

02/12

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.32 (2004) Fall Protection

ASSE/SAFE A10.34 (2001; R 2005) Protection of the Public on or Adjacent to Construction Sites

ASSE/SAFE Z359.1 (2007) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components

ASME INTERNATIONAL (ASME)

ASME B30.22 (2010) Articulating Boom Cranes

ASME B30.3 (2009) Tower Cranes

ASME B30.5 (2007) Mobile and Locomotive Cranes

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2010) Standard for Portable Fire Extinguishers

NFPA 51B (2009; TIA 09-1) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70E (2012) Standard for Electrical Safety in the Workplace

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1926 Safety and Health Regulations for Construction

SECTION 01 35 26 Page 3

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

29 CFR 1926.1400 Cranes & Derricks in Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.500 Fall Protection

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146

1.2 DEFINITIONS

a. High Visibility Accident. Any mishap which may generate publicity or high visibility.

b. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

c. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:

(1) Death, regardless of the time between the injury and death, or the length of the illness;

(2) Days away from work (any time lost after day of injury/illness onset);

(3) Restricted work;

(4) Transfer to another job;

(5) Medical treatment beyond first aid;

(6) Loss of consciousness; or

(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in

(1) through (6) above.

f. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.

g. Crane Accident. A crane accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage;

dropped load; derailment; two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects.

A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs.

A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.)

SECTION 01 35 26 Page 4

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

Government acceptance, as defined in EM 385-1-1, is required for submittals with a "G, A" designation.

SD-01 Preconstruction Submittals

Accident Prevention Plan (APP); G, RO

Activity Hazard Analysis (AHA); G, RO

Crane Critical Lift Plan; G, RO

Proof of qualification for Crane Operators; G, RO

SD-06 Test Reports

Notifications and Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph, "Notifications and Reports."

Accident Reports

Crane Reports

SD-07 Certificates

Confined Space Entry Permit

Hot work permit

License Certificates

1.4 REGULATORY REQUIREMENTS

In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations 15. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.

Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.

1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.5.1 Personnel Qualifications

1.5.1.1 Site Safety and Health Officer (SSHO)

a. Designate an individual as the Site Safety and Health Officer (SSHO).

SECTION 01 35 26 Page 5

The name, qualifications (education and training summary and documentation), and include work experience of the Site Safety and Health Officer in the APP. Responsibilities listed within this section and qualifications shall be in accordance with EM 385-1-1 Section 01.A.17.

b. The SSHO must meet the requirements of EM 385-1-1 section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

c. A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the the Contracting Officer for acceptance in consultation with the Safety Office.

1.5.1.1.1 Contractor Quality Control (QC) Person:

The Contractor Quality Control Person cannot be the SSHO on this project, even though the QC has safety inspection responsibilities as part of the QC duties.

1.5.1.2 Alternate SSHO

a. The SSHO, Alternate SSHO, and Designated Representatives contracts shall take either the OSHA 30-hour Construction Safety Course or an equivalent 30 hours of formal safety and health training covering the subjects of the OSHA 30-hour Course (see EM 385-1-1 Appendix A, paragraph 4.b) applicable to construction work and given by qualified instructors.

b. The SSHOs shall also have taken 24 hours of formal classroom or online safety and health related coursework in the past four (4) years. Hours spent as an instructor in such courses will be considered the same as attending them, but each course only gets credit once (ie. Instructing a 1-hour asbestos awareness course 5 times in the past 4 years provides one hour credit for training).

c. The SSHO, Alternate SSHO, and Designated Representatives shall have a minimum of three years' continuous experience within the past 5 years in supervising/ managing land-based construction, work managing safety programs or processes, or conducting hazard analyses and developing controls in activities or environments with similar hazards. This is in lieu of the construction experience required by paragraph 01.A.17.b, EM 385-1-1.

d. In addition to requirements stated elsewhere in this specification, the SSHO shall be present at the project site, located so they have full mobility and reasonable access to all major work operations, for at least one shift in each 24 hour period when work is being done.

The SSHO, or Alternate SSHO, shall be available during all shifts for

SECTION 01 35 26 Page 6 immediate verbal consultation and notification, either by phone or radio. The SSHO shall be a full-time, dedicated position, except as noted above. The SSHO shall report to a senior project (or corporate) officials.

1.5.1.3 Crane Operators

Meet the crane operators requirements in USACE EM 385-1-1.

1.5.2 Personnel Duties

1.5.2.1 Site Safety and Health Officer (SSHO)

The SSHO shall:

a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily quality control report.

b. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors.

c. Maintain applicable safety reference material on the job site.

d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.

e. Implement and enforce accepted APPS and AHAs.

f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.

g. Ensure sub-contractor compliance with safety and health requirements.

h. Maintain a list of hazardous chemicals on site and their material safety data sheets.

Failure to perform the above duties will result in dismissal of the Superintendent, QC Manager, and/or SSHO, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.

1.5.3 Meetings

1.5.3.1 Preconstruction Conference

a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).

b. Discuss the details of the submitted APP to include incorporated plans, SECTION 01 35 26 Page 7 programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis.

In addition, establish a schedule for the preparation, submittal, review, and acceptance of AHAs to preclude project delays.

c. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted APP.

1.6 ACCIDENT PREVENTION PLAN (APP)

Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program.

Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site-specific.

The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors.

Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer, the Contractor Quality control Manager, and any designated CSP or CIH.

Submit the APP to the Contracting Officer 30 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.

Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified.

Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control manager. Should any severe hazard exposure, i.e. imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery.

Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.

Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site. Continuously reviewed and amended the APP, as

SECTION 01 35 26 Page 8 necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.

1.6.1 EM 385-1-1 Contents

In addition to the requirements outlined in Appendix A of USACE EM 385-1-1, the following is required:

a. Personnel Qualifications.

Names and qualifications (resumes including education, training, experience and certifications) of all site safety and health personnel designated to perform work on this project to include the designated site safety and health officer and other competent and qualified personnel to be used such as CSPs, CIHs, STSs, CHSTs. Specify the duties of each position.

b. Competent Persons.

Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.

c. Confined Space Entry Plan.

Develop a confined and/or enclosed space entry plan in accordance with USACE EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, OSHA Directive CPL 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience.

Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)

d. Crane Critical Lift Plan.

Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist (or lifts over 50 percent of the capacity of a barge mounted mobile crane's hoists) at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel; and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. Submit 15 calendar days prior to on-site work and include the requirements of USACE EM 385-1-1, paragraph 16.H. and the following:

(1) For lifts of personnel, demonstrate compliance with the requirements of

29 CFR 1926.1400.

e. Fall Protection and Prevention Plan (FP&P).

The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction.

Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person for fall protection shall prepare and sign the program documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods.

Review the Fall Protection and Prevention Program documentation every six

SECTION 01 35 26 Page 9 months for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Program documentation at the job site for the duration of the project.

Include the Fall Protection and Prevention Program documentation in the Accident Prevention Plan.

The FP&P Plan shall include a Rescue and Evacuation Plan in accordance with USACE EM 385-1-1, Section 21.M. The plan shall include a detailed discussion of the following: methods of rescue; methods of self-rescue;

equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility. Include the Rescue and Evacuation Plan in the Fall Protection and Prevention (FP&P) Plan, and as part of the Accident Prevention Plan (APP).

f. Lead Compliance Plan.

The safety and health aspects of lead work, prepared in accordance with Section 02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD.

g. Asbestos Hazard Abatement Plan.

The safety and health aspects of asbestos work, prepared in accordance with Section 02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES.

h. Site Safety and Health Plan.

The safety and health aspects prepared in accordance with Section

01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES.

i. Site Demolition Plan.

The safety and health aspects prepared in accordance with Section 02 41 00 DEMOLITION and referenced sources.

j. Excavation Plan.

The safety and health aspects prepared in accordance with Section 31 00 00

EARTHWORK.

k. PCB Plan Identify the safety and health aspects of Polychlorinated Biphenyls work, and prepare in accordance with Sections 02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs) and 02 61 23 REMOVAL AND DISPOSAL OF PCB

CONTAMINATED SOILS.

1.7 ACTIVITY HAZARD ANALYSIS (AHA)

The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1, Section 1. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.

The AHA list will be reviewed periodically and at the Contractor supervisory safety meeting then updated as necessary when procedures, scheduling, or hazards change.

Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the

SECTION 01 35 26 Page 10 contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.

1.8 DISPLAY OF SAFETY INFORMATION

Within 7 calendar day(s) after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.06. Additional items required to be posted include:

a. Confined space entry permit.

b. Hot work permit.

1.9 SITE SAFETY REFERENCE MATERIALS

Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.

1.10 EMERGENCY MEDICAL TREATMENT

Contractors will arrange for their own emergency medical treatment.

Government has no responsibility to provide emergency medical treatment.

1.11 NOTIFICATIONS and REPORTS

1.11.1 Accident Notification

Notify the Contracting Officer as soon as practical, but no more than four hours after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000, or any weight handling equipment accident. Within notification include contractor name; contract title; type of contract;

name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.).

Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.

1.11.2 Accident Reports

a. Conduct an accident investigation for recordable injuries and illnesses, for Medical Treatment defined in paragraph DEFINITIONS, property damage accidents resulting in at least $20,000 in damages, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident.

b. Conduct an accident investigation for any crane equipment accident (including rigging gear accidents) to establish the root cause(s) of the accident. Do not proceed with crane operations until cause is determined and corrective actions have been implemented to the satisfaction of the contracting officer.

SECTION 01 35 26 Page 11

1.11.3 Crane Reports

Submit crane inspection reports required in accordance with USACE EM 385-1-1, with Daily Reports of Inspections.

1.11.4 Certificate of Compliance

Provide a Certificate of Compliance for each crane entering an activity under this contract. State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926 and USACE EM 385-1-1.

Certify that the crane operator(s) is qualified and trained in the operation of the crane to be used. Also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices).

1.12 HOT WORK

Submit and obtain a written permit prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, from the Edwards AFB Fire Department via Contracting Officer. Provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.

When starting work in the facility, require personnel to familiarize themselves the Fire Prevention Plan as required by the EM 385-1-1. ANY

FIRE, NO MATTER HOW SMALL, SHALL BE REPORTED IMMEDIATELY.

1.13 FACILITY OCCUPANCY CLOSURE

Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.

1.14 SEVERE STORM PLAN

In the event of a severe storm warning, the Contractor must:

a. Secure outside equipment and materials and place materials that could be damaged in protected areas.

b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.

c. Ensure that temporary erosion controls are adequate.

1.15 CONFINED SPACE ENTRY REQUIREMENTS.

Contractors entering and working in confined spaces while performing general industry work are required to follow the requirements of OSHA 29 CFR 1926 and comply with the requirements in Section 34 of EM 385-1-1, SECTION 01 35 26 Page 12

OSHA 29 CFR 1910, and OSHA 29 CFR 1910.146.

PART 2 PRODUCTS Not Used.

PART 3 EXECUTION

3.1 CONSTRUCTION AND OTHER WORK

3.1.1 Hazardous Material Exclusions

Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. Low mercury lamps used within fluorescent lighting fixtures are allowed as an exception without further Contracting Officer approval.

Notify the Radiation Safety Officer (RSO) prior to excepted items of radioactive material and devices being brought on base.

3.1.2 Unforeseen Hazardous Material

The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e.

29 CFR Part 1910.1000). If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2 PRE-OUTAGE COORDINATION MEETING

Apply for utility outages at least 15 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer and the Installation representative to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)

Ensure that each employee is familiar with and complies with these procedures and USACE EM 385-1-1, Section 12, Control of Hazardous Energy.

3.4 FALL HAZARD PROTECTION AND PREVENTION PROGRAM

Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Within the program include company

SECTION 01 35 26 Page 13 policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.

3.4.1 Training

Institute a fall protection training program. As part of the Fall Hazard Protection and Prevention Program, provide training for each employee who might be exposed to fall hazards. Provide training by a competent person for fall protection in accordance with USACE EM 385-1-1, Section 21.B.

3.4.2 Fall Protection Equipment and Systems

Enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard.

Protect employees from fall hazards as specified in EM 385-1-1, Section

21. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Paragraphs 21.N through 21.N.04. Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE A10.32.

3.4.2.1 Personal Fall Arrest Equipment

Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE Z359.1. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to an approved fall arrest system).