SS_Upgrade_specs.pdf
PDF 375 KB Posted
- Attached to
- Station Service Upgrade and Transformer Replacement Federal contract opportunity
- Solicitation number
- W9128F-16-Q-0130
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_AMD002.pdf | ||
| PPQ.pdf | ||
| Gavins_Reference_Dwgs_Amendment.pdf | ||
| Q A.pdf | ||
| GP_Service_Switchgear_and_Transformer_Replacement_BCOE_photo_attachments.pdf | ||
| IMG_1861.jpg | JPG image | |
| AK-1-50_Nameplate.JPG | JPG image | |
| AK-1-25_cubicle_(3).JPG | JPG image | |
| AK-1-25_cubicle_(3).JPG | JPG image | |
| IMG_1856.jpg | JPG image | |
| IMG_1855.jpg | JPG image | |
| IMG_1863.jpg | JPG image | |
| AK-1-25_cubicle_(1).JPG | JPG image | |
| AK-1-25_cubicle_(2).JPG | JPG image | |
| IMG_1862.jpg | JPG image | |
| 16-Q-0130.pdf | ||
| W9128F-16-Q-0130.pdf | ||
| Gavins_Point_Station_Service_Upgrades_Contract_Drawings.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(SUPPLY AND INSTALL CONTRACT)
Solicitation No. W9128F-16-Q-0130
Station Service Upgrade and Transformer Replacement
Gavins Point Dam, SD
August 2016
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
Station Service Upgrade and Transformer Replacement
Gavins Point Dam, SD
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 01 00 CONTRACTOR'S SITE OPERATIONS FOR SUPPLY AND SERVICE
CONTRACTS
01 11 00.00 26 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
DIVISION 03 - CONCRETE
03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND
EQUIPMENT FOUNDATIONS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 26 GENERAL ELECTRICAL WORK AND EQUIPMENT
26 05 19.00 26 INSULATED WIRE AND CABLE
26 05 26.00 26 GROUNDING
26 08 01.00 26 SYSTEMS TESTING AND COMMISSIONING
26 12 16.00 26 DRY-TYPE TRANSFORMERS
26 23 10.10 26 480 VOLT SWITCHGEAR RETROFILL
26 23 15.00 26 480 VOLT HIGH RESISTANCE GROUNDING (HRG) SYSTEM
-- End of Project Table of Contents --
SS Upgrade and Transformer Replacment, Gavins Point Dam, SD GP400
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 01 00
CONTRACTOR'S SITE OPERATIONS FOR SUPPLY AND SERVICE CONTRACTS
4/07; Rev 3/11
PART 1 GENERAL
1.1 PERMITS AND RESPONSIBILITIES
1.2 WORK AREAS AND ACCESS
1.2.1 Road Restrictions
1.2.2 Access by Government Personnel
1.2.3 Contractor's Staging Area and Employee Access
1.3 SUBMITTALS
1.4 STORAGE OF EQUIPMENT AND MATERIALS
1.5 PROJECT SECURITY, HOLIDAYS AND WORKING HOURS
1.5.1 General
1.5.2 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1.5.3 Federal Holidays
1.5.4 Working Hours
1.5.5 Site Work Schedule
1.6 VEHICLES
1.6.1 Use of Private Vehicles
1.6.1.1 Identification of Vehicles
1.7 UTILITIES
1.7.1 Government Furnished Utilities
1.7.1.1 Water
1.7.1.2 Electricity
1.7.1.3 Compressed Air
1.7.2 Temporary Utility Connections
1.7.3 Use of Sanitation Facilities
1.7.3.1 Portable Toilets
1.7.4 Telephone\Cell Phone
1.8 COOPERATION WITH OTHERS
1.9 COORDINATION AND OUTAGES
1.10 GENERATING UNIT AVAILABILITY AND ACCESS
1.10.1 General
1.10.2 Request for Unit Availability
1.10.3 Access to Unit for Operational Testing
1.11 SAFE CLEARANCE PROCEDURES
1.12 USE OF POWERHOUSE LOADING / UNLOADING BAY (BRIDGE CRANE & FORKLIFT)
1.13 PLANT AND EQUIPMENT LIST
1.14 GOVERNMENT FURNISHED TOOLS AND EQUIPMENT
1.15 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS
1.16 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.17 DAILY CLEANUP AND DISPOSAL
1.18 DISPOSAL OF MATERIALS
1.19 DUST CONTROL AND REMOVAL
1.20 FIRE CONTROL
1.21 CONTRACTOR'S AGENT, WORK SUPERVISOR, AND PERSONNEL
1.21.1 Contractor's Agent(s)
1.21.2 Site Supervisor(s)
SECTION 01 01 00 Page 1
1.21.3 Contractor's General Personnel
1.22 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
1.23 PROJECT REPORTING
1.24 WEEKLY MEETINGS
-- End of Section Table of Contents --
SECTION 01 01 00 Page 2
SECTION 01 01 00
CONTRACTOR'S SITE OPERATIONS FOR SUPPLY AND SERVICE CONTRACTS
4/07; Rev 3/11
PART 1 GENERAL
1.1 PERMITS AND RESPONSIBILITIES
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, County, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence, and shall take proper safety and health precautions to protect the work, workers, public, and property of others. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
1.2 WORK AREAS AND ACCESS
The Contractor shall take steps reasonably necessary to ascertain the nature and location of the work, and investigate the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the Government. The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions that can affect the work by any of its officers or agents before the execution of this contract, unless the understanding or representation is expressly stated in this contract. Site conditions that should be investigated include, but are not limited to:
(1) Conditions bearing upon transportation, disposal, handling, and storage of materials.
(2) The availability of labor, water, electrical power, and roads.
(3) Uncertainties of weather, river stages, tides, or similar physical conditions at the site.
(4) The conformation and conditions of the ground and equipment and facilities to be replaced and/or rehabilitated.
(5) The character of equipment and facilities needed preliminary to and during work performance.
(6) Amount of work space, accessibility, lighting, etc.
SECTION 01 01 00 Page 3
1.2.1 Road Restrictions
No new access roads are required for this work. Any damage to existing roadways that are used for access purposes shall be repaired and the surface shall be restored to its "as found" condition. The Contractor shall comply with any special requirements of the State, County, Local authorities and Corps of Engineers for use of existing roadways. These special requirements include, but are not limited to, traffic regulations and load limits. The Contractor is responsible for investigating and understanding these restrictions. No time extensions or cost claims will be allowed due to road restrictions.
1.2.2 Access by Government Personnel
Clear access shall be maintained for Government personnel and equipment through all work areas.
1.2.3 Contractor's Staging Area and Employee Access
The Contractor's staging area shall be restricted to the area designated by the Government. The contractor's job-site office may be in the staging area, as approved. The project areas off-limits to Contractor shall be all areas other than direct work areas. Power plant elevators shall not be used by Contractor personnel unless needed to transport small tools and materials. Salespersons or personnel seeking employment will not be permitted inside the powerhouse. Signs may be erected outside the powerhouse containing instructions for personnel seeking the Contractor.
The content and location of the signs must be approved. All buildings and facilities constructed or brought on site by the Contractor shall be maintained in a satisfactory condition with strict observance of the rules of sanitation, safety and order as may be established by the Contracting Officer. Prior to final payment under the contract, all buildings and facilities constructed by the Contractor for his own use shall be removed from the site by the Contractor.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
AT Level I Training Sign In Sheets;
Sign In Sheets for all employee training required for AT Level I Training, see paragraph 1.5.2.1
Security Personnel List; G-AO
Security Personnel list as described in Access and General Protection/Security Policy and Procedures paragraph 1.5.2.3
Suspicious Activity Reporting Training;
Sign In Sheets for all employee training required for iWATCH and/or CorpsWatch Training, see paragraphs 1.5.2.4
SECTION 01 01 00 Page 4
OPSEC Training Sign In Sheets;
Sign In Sheets for all employee training required for OPSEC Training, see paragraphs 1.5.2.7
Site Work Schedule;
Site Work Schedule required as described in paragraph 1.5.5
Special Instructions for Progress Charts;
To be submitted in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Schedules for Construction Contracts", see paragraph 1.26
SD-06 Test Reports
Contractor's Agent(s);
A daily log shall be made of the accomplished work, and shall be submitted at the completion of the contract, see paragraph 1.25.1
Site Supervisor(s);
A daily log shall be made of the accomplished work, and shall be submitted at the completion of the contract, see paragraph 1.25.2
Project Reporting;
Weekly reports shall be submitted by the Contractor giving project status and activities information, see paragraph 1.27
Weekly Meetings;
Daily reports shall be completed and submitted to the Contracting Officer or Representative within 24 hours of work, see paragraph 1.28
1.4 STORAGE OF EQUIPMENT AND MATERIALS
Indoor and outdoor storage of equipment and materials will be permitted only at designated storage areas in the vicinity of the powerplant which will be coordinated with the Government Representative during the pre-work conference. A minimum access space of three feet shall be maintained between stored items and the existing powerhouse equipment. Due to high winds at the site, everything in the outside storage area(s) shall be securely tied down so it will not be blown into the tailrace.
1.5 PROJECT SECURITY, HOLIDAYS AND WORKING HOURS
1.5.1 General
A procedure shall be prepared and submitted for approval for the identification and control of employees entering or leaving the project during the hours of closure. The security of the Contractor's property and items furnished under this contract are the Contractors responsibility, until accepted, whether stored inside or outside the powerhouse.
SECTION 01 01 00 Page 5
1.5.2 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1.5.3 Federal Holidays
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
1.5.4 Working Hours
The contractor will have access to the powerhouse for work during normal plant business hours from 0600 to 1630 hrs Monday thru Thursday excluding any federally recognized holiday that it is observed on and the contractor shall plan all work accordingly to this work schedule. These hours will be strictly adhered to unless government determines work outside this time is beneficial to the government.
In addition to the work business hours listed previously all clearance (Lock Out - Tag Out) and crane operations needed to be performed by the government shall take place during powerhouse maintenance personnel work schedule Monday through Thursday 0630 to 1600.
1.5.5 Site Work Schedule
A site work schedule shall be prepared and submitted. The schedule shall include major and minor work elements and stages of the work. These documents shall be updated and submitted to reflect the actual work elements and progress anticipated in the future.
SECTION 01 01 00 Page 6
1.6 VEHICLES
1.6.1 Use of Private Vehicles
Private vehicles of the Contractor and Contractor's employees shall park outside the fence as designated. The Contractor shall follow all Contracting officer requirements regarding vehicle access to the project.
Parking of private vehicles shall be restricted to the areas designated by the Contracting Officer. Additional parking will be designated upon request, but may be located up to ½ mile from the powerhouse. The Contractor shall maintain the designated parking areas.
1.6.1.1 Identification of Vehicles
All Contractor's vehicles shall display approved permanent identification of such size and color to allow Government personnel to identify the vehicle.
1.7 UTILITIES
1.7.1 Government Furnished Utilities
All utilities that are required for use in performance of the work under this contract shall be Contractor-furnished except as noted below:
1.7.1.1 Water
All reasonable amounts of non-potable water will be made available from existing outlets. The Contractor will be responsible for freeze proofing all accessed water sources. Full responsibility for care of water shall be borne by the Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate construction and to protect the work from damage by water. The Contractor shall make his own investigations and determinations of conditions, both existing and anticipated concerning care of water.
Plans for care of water are subject to approval by the Contracting Officer prior to construction. Facilities shall be removed upon completion of the work.
1.7.1.2 Electricity
Electric power may be obtained from existing sources located at various locations near the work areas unless otherwise approved:
(1) 120-volt
(2) 480-volt
Note: Many of the receptacles in the powerhouse are the twist-lock type, the Contractor shall investigate the available power sources and provide all necessary adapters. The Contractor may provide his own temporary electrical power distribution panel and connect a power cable from a 480-volt outlet to this temporary panel.
1.7.1.3 Compressed Air
Reasonable amounts of compressed air will be available to the Contractor.
1.7.2 Temporary Utility Connections
All utilities provided by the Government shall be at no cost. Care shall
SECTION 01 01 00 Page 7 be exercised in conserving all utilities. The contractor shall at his own expense and in a workman like manner satisfactory to the CONTRACTING OFFICER provide all necessary hoses, cords, couplings, plugs, GFI's and other appurtenances as required to connect to the system(s). All temporary connections shall be subject to approval. The location of all power lines and all temporary connections for electricity shall be coordinated with the CONTRACTING OFFICER. All temporary circuits and devices shall be provided, connected, and maintained and removed prior to final acceptance. Ground fault protection shall be provided for all circuits used, inside and outside, and shall be Contractor-furnished. The temporary panel shall conform to current NEC standards in EM 385-1-1.
1.7.3 Use of Sanitation Facilities
1.7.3.1 Portable Toilets
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff [and Government staff]. Toilet(s) shall be placed at the location directed by the Contracting Officer.[ To prevent overturning by high winds, all portable toilets shall be anchored down.]
1.7.4 Telephone\Cell Phone
The Contractor may use his personal cellular phone if service is available and functional. Cellular phones typically do not work inside the powerhouse. Telephones (landlines) within the facility are for Government use only.
1.8 COOPERATION WITH OTHERS
The Contractor shall cooperate and coordinate his work with that of others as required for orderly completion of all work. In the event of disagreement between the Contractor and others, the decision of the Contracting Officer shall be final.
1.9 COORDINATION AND OUTAGES
The Government shall approve outages after coordination with power marketing agency. The Government will limit interference with the Contractor's work to the extent possible. The Government and Contractor shall coordinate work activities as necessary. The Contractor's employees shall not open, close or tamper with switches, valves or control devices for existing installed equipment. Only Government operating personnel will be authorized to open or close existing switches, valves and control devices to enable the Contractor to make connections or modifications to existing equipment. Work shall be coordinated and scheduled to reduce the "Outage" time of operating equipment or systems to a minimum. Work in the proximity of exposed energized equipment or work involving connections to existing energized or operating equipment or systems shall perform only under the Safe Clearance Procedures. The Contractor will be instructed by the Contracting Officer in the proper procedure for requesting clearances.
Only qualified supervisory personnel will be permitted to request clearances. Request for "Outage" shall be made by the Contractor to the Contracting Officer in each instance and in sufficient time to permit adjusting power plant operations, and to coordinate outages with the dispatching agency. Scheduling of "Outage" will be subject to the approval of the Contracting Officer.
SECTION 01 01 00 Page 8
1.10 GENERATING UNIT AVAILABILITY AND ACCESS
1.10.1 General
Not later than 90 days notice to proceed, the Contractor shall provide a proposed generator outage schedule for approval. Generator outages are only permitted as Spring Outages (15 February through 15 June) and Fall Outage (01 September through 30 December). Unless otherwise notified by the Contracting Officer, at any given time, only one generator shall be allowed under outage for exciter replacement. A unit receiving an exciter replacement shall be complete and accepted prior to the outage of the next unit. Paired units will be completed during outage seasons. The Government will arrange for the unit outages. The Government reserves the right to require changes to the Contractor's Proposed Outages Schedule. Power demands and emergency maintenance requirements may limit unit availability.
Should this occur, the Contractor will be notified. The first day of availability shall not be a weekend day or on a Friday. Contractor personnel shall not enter the unit until given assurance in writing by the Government that all Safe Clearance steps have been completed.
1.10.2 Request for Unit Availability
Request to accelerate or modify the Outage Schedule shall be made in writing to the Contracting Officer. The Contractor shall request a unit outage time and date for exciter replacement as early as possible but at least 10 days in advance. The Government will inform the Contractor in writing as to unit availability and verify the time and date of availability.
1.10.3 Access to Unit for Operational Testing
The Contractor and Government shall jointly assist each other in checking out the unit and its auxiliaries, and readying the generator for special field tests. During preparation for operational testing, Contractor personnel shall fully comply with Safe Clearance procedures, clearances tagged on equipment, and requests from the Government to vacate areas or stop work temporarily during this period.
1.11 SAFE CLEARANCE PROCEDURES
A Hazardous Energy Control (HEC) procedures are implemented for all the maintenance and construction activities on Corps property. These procedures are in accordance with OSHA regulation 29 CFR 1910.147, 1910.333, 1910.269 and USACE ER 385-1-31, The Control of Hazardous Energy (safe clearance). Any work performed at the Big Bend project will be performed under safe clearance. The contractor shall request clearance on a piece of equipment or system before any work may begin. The Corps will establish the limits of the clearance, tag and lock the equipment or systems. The Contractor will be required to institute their own safe clearance procedures in accordance with OSHA and USACE regulations, within the perimeter or the Corps clearance. The Contractor's clearance shall not inhibit or interfere with the Corps operation of the plant. The clearances shall not be violated. Any violation of Hazardous Energy Control procedure (Safe Clearance Procedures) will be grounds for removal of the offender(s).
1.12 USE OF POWERHOUSE LOADING / UNLOADING BAY (BRIDGE CRANE & FORKLIFT)
The Government will operate the bridge crane or forklift at the powerhouse
SECTION 01 01 00 Page 9 loading bay for loading and off-loading of Contractor equipment and materials only. All other material movement is the responsibility of the Contractor. The powerhouse crane and fork lift will be made available on an as needed basis for work under this contract. The Contractor shall cooperate with the Government in the use of the crane for scheduled and emergency project maintenance. The Government will have priority use of the crane in emergency conditions, e.g., for needed use that could not be foreseen or scheduled. The Contractor shall provide riggers responsible for preparing loads for lifting. The Contractor shall be responsible for providing appropriate lifting devices, slings, shackles, and appurtenances. Use of Government slings, etc. is not permitted. The Contractor will be held liable for all damages incurred as the result of negligent rigging.
1.13 PLANT AND EQUIPMENT LIST
A complete list of all plant and equipment, exclusive of shop equipment, to be used on the project shall be furnished. An up-to-date plant and equipment list shall be submitted with all other end-of-the-month requests, throughout the life of the contract. The lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised monthly lists shall indicate dates equipment is assigned to, or removed from, the project, dates deadlined for repairs and returned for use, and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.14 GOVERNMENT FURNISHED TOOLS AND EQUIPMENT
Government tools and equipment at the project, i.e., lathes, drill presses, hand tools, etc., are not available for use.
1.15 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS
The Government shall be informed immediately upon finding any damaged equipment or other abnormal conditions involving additional work. The failure or abnormality shall not be disturbed until witnessed by the CONTRACTING OFFICER. Prior to proceeding further with work, the Contractor and the Government shall agree in writing as to the responsibility for the damage or abnormality.
1.16 PROTECTION AND RESTORATION OF EXISTING FACILITIES
The Contractor shall be responsible for the protection of the work area from damage. All existing grounds, property and facilities shall be protected whether or not shown on the drawings. Upon completion of the work, all the existing grounds, property and facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price. All work, storage of materials, and construction plant shall be kept within the limits of the areas assigned. Prior to construction operations, the Contractor shall confer with the Contracting Officer's representative to determine the proximity of any possible obstructions, pipe or equipment which could be damaged as a result of
SECTION 01 01 00 Page 10 construction operations. Existing utility lines shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines report thereof shall be made immediately to the Contracting Officer. The Contractor will be responsible for the protection of structures from any structural damage during the construction operations. At all times the plant and work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the construction areas.
1.17 DAILY CLEANUP AND DISPOSAL
All debris resulting from the work, such as waste metalwork, packing cases, scrap lumber, oil and grease, and other debris shall be collected, removed, and disposed of off site at least once per shift. Disposal shall be in accordance with Federal, State and Local regulations. The location of the Contractor's off-site disposal area and a plan for safe disposal of material shall be approved. The Government's trash cans, dumpsters, etc.
shall not be used. Liquid waste shall not be disposed of in powerhouse drains. All costs of removing debris shall be incidental to the work, and no separate payment will be made therefore. All temporary structures used by the Contractor in the course of the work shall leave the area looking "broom clean".
1.18 DISPOSAL OF MATERIALS
Title to all materials and equipment to be disposed of, except salvage items and hazardous waste, is vested in the Contractor upon receipt of signed contract and such materials and equipment are designated scrap only as directed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed. The Contractor may retain these items in usable form and take possession of them providing that there is no subsequent cost or inconvenience to the Government. The Government does not guarantee that these items are complete or in working order, and the Contractor shall assume responsibility for any damages caused by their use immediately upon taking possession of them. Scrap materials shall be removed from the Government's property within 14 days.
Scrap shall not be sold on the site.
1.19 DUST CONTROL AND REMOVAL
Special measures shall be taken to minimize air-borne dust in work areas.
Dust shall not be allowed to accumulate about the powerhouse in general.
Return air ducts for heating, ventilating and air conditioning shall be blocked, where practicable, or equipped with filters in areas where dust is being produced or agitated. Removal of dust shall be by sweeping with dust wetted down or overlain with sweeping compound, or by vacuum cleaner as approved. Where air-borne dust in objectionable amount is unavoidable, equipment containing commutators, contactors, bearing, etc., shall be covered. Adequate air filters shall be provided in covers over equipment which requires circulation of air while operating. Dust shall be removed daily on a continuing basis during the life of this contract. Dust shall be removed as directed from the interior of equipment housed in cabinets by method approved by the Contracting Officer.
SECTION 01 01 00 Page 11
1.20 FIRE CONTROL
All fire fighting equipment, supplies, and personnel shall be supplied in accordance with EM-385-1-1. Delays due to fire will not be acceptable as the basis of a claim for additional compensation.
1.21 CONTRACTOR'S AGENT, WORK SUPERVISOR, AND PERSONNEL
1.21.1 Contractor's Agent(s)
The Contractor shall give personal attention to the faithful execution and completion of this work and shall be present either in person or by duly authorized representative(s) on the site of the work continually during its progress. The agent shall be fluent in the spoken and written English language. The agent's qualifications and identification shall be provided. The agent shall be fully authorized to act for the Contractor and to receive such orders as may be given for the proper continuance of the work. Written notice to do any work, to alter any work, or to cease work which the Contractor is obligated to do, or concerning any imperfections in work or any material furnished, when given to the agent shall be considered as notice to the Contractor. A daily log shall be made of the accomplished work, and shall be submitted at the completion of the contract. The agent shall have been engaged in similar work at a minimum of two different powerhouses. A verifying contact, with name and phone number, shall be provided for at least two such facilities.
1.21.2 Site Supervisor(s)
At least one full-time employee of the Contractor shall be available at the work site anytime other Contractor personnel are working on the site to supervise and direct the work specified herein. The Contractor's Agent and Site Supervisor can be the same person, provided that all qualifications are met. The supervisor(s) shall be fluent in the spoken and written English language. The supervisor shall be technically qualified to supervise the site work and commissioning and all other aspects related to completing this work. The supervisor shall report immediately in writing to the Government any work not in accordance with the manufacturer's recommendations, or any special conditions which may result in an unsatisfactory job. A daily log shall be made of the accomplished work, and shall be submitted at the completion of the contract.
1.21.3 Contractor's General Personnel
The Contractor shall prepare and keep updated, as a minimum weekly, a project organization chart reflecting at least those positions described herein and defining their work relationships, etc. All personnel employed by the Contractor shall be fully qualified in their respective fields to render the services necessary.
1.22 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
To be submitted in accordance with the CONTRACT CLAUSES clause entitled "Schedule for Construction Contracts" shall indicate the required data for each of the principal features of the work. Contract changes or modifications will not include extensions of time unless the updated progress chart shows that the contract completion date is delayed due to the affect of the change on one or more principal features of the work.
SECTION 01 01 00 Page 12
1.23 PROJECT REPORTING
Weekly reports shall be submitted by the Contractor giving project status and activities information. An updated CPM should be included in this report, if appropriate. This report shall include a written summary, accompanied with detailed information relating to current status of procurement, construction, and delivery activities compared to both the current project schedules and the schedule submitted at the time of the Request for Technical Proposal.
1.24 WEEKLY MEETINGS
Once each week, while on site, a general meeting will be held between the Contractor and the Government. This meeting will be used to discuss progress in the last week and work planned in the upcoming week. A meeting time and place shall be mutually agreed upon.
In order to closely coordinate work under this contract, the Contractor shall prepare a written agenda/meeting minutes at the weekly coordination meeting with the Contracting Officer at which time the Contractor shall submit for coordination and approval, his proposed daily work schedule for the next two week period. The Contractor shall provide a copy of modifications (MODs), Serial Letters, Requests for Information (RFIs)and any other information that is needed in the minutes of the meeting.
Required temporary utility services, time and duration of interruptions, and protection of adjoining areas shall be included with the Contractor's proposed 2-week work schedule. At this meeting, the Contractor shall also submit his schedule of proposed dates and times of all preparatory inspections to be performed during the next 2 weeks. Coordination action by the Contracting Officer relative to these schedules will be accomplished during these weekly meetings. Daily reports shall be completed and given to the Contracting Officer or Representative within 24 hours of work.
-- End of Section --
SECTION 01 01 00 Page 13
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00.00 26
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.2 CHANGES IN SPECIFICATIONS AND DRAWINGS
1.3 DEFINITIONS
PART 2 - PRODUCTS - NOT USED
PART 3 - PRODUCTS - NOT USED
SECTION 01 11 00.00 26 Page 1
SECTION 01 11 00.00 26
SUMMARY OF WORK
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
This section covers the technical specifications to perform all work required for Gavin's Point Station Service Switchgear Upgrade & Transformer Replacement. This section is a general summary of the required work and is not all-inclusive. The work described within these specifications include, but not necessarily be limited to the following:
a. Provide new Retro-Fill Power Circuit Breakers for the Existing 480 VAC Switchgear.
b. Provide a complete bracing Study for the existing 480 VAC Switchgear to rerate for 65 KA.
c. Test all existing feeder cables from the existing 480 VAC switchgear to the first point of termination.
d. Provide new 1000 KVA 13.8kV/480V dry type transformers and new High Resistance Grounding Systems for both transformers and the existing Diesel Generator.
e. (OPTIONAL)Provide any and all bracing needed to rerate the existing 480 VAC Switchgear Bus to 65 KA.
f. (OPTIONAL) Provide a complete bracing study of the existing 13.8 kV Switchgear to rerate to 73kA
g. (OPTIONAL)Provide any and all bracing needed to rerate the existing
13.8 kV Switchgear Bus to 73 kA.
h. (OPTIONAL)Provide new 480 VAC feeder cables where directed.
i. Prepare and furnish as-built drawings for the completed installation.
j. Provide all necessary contractor commissioning activities and support Government Commissioning activities.
1.2 CHANGES IN SPECIFICATIONS AND DRAWINGS
The Government reserves the right to revise or amend the specifications and/or drawings prior to the date set for opening bids. Copies of such amendments will be furnished to all prospective bidders. If the revisions and amendments require material changes in quantities or prices bid, or both, the date set for bid opening may be extended to enable bidders the opportunity to revise their bids. The amendment will include an announcement of the new date for opening bids.
SECTION 01 11 00.00 26 Page 2
1.3 DEFINITIONS
a. Wherever in the specifications, or upon the drawings, the words "directed", "required", "ordered", "designated", "prescribed", or words of like import are used, it shall be understood that the "direction", "requirement", "order", "designation", or "prescription" of the Contracting Officer is intended, and similarly the words "approved", "acceptable", "satisfactory", or words of like import shall mean "approved by" or "acceptable to" or "satisfactory to" the Contracting Officer unless otherwise expressly stated.
b. Where "as shown", "as indicated", "as detailed", or words of like import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean "provided complete in place", that is, "furnished and installed". (FAR 52.236.21(b) and (c)).
c. Wherever in these specifications or upon the drawings, the words "Contracting Officer" (CO) or "Contracting Officer's Representative" (COR) are used, it shall be understood to also mean "Government" unless otherwise expressly stated.
d. Wherever in these specifications the word "weekend(s)" is used, it shall be understood to mean "Saturday, Sunday, and Federal Holidays", unless otherwise expressly stated.
e. Whenever in these specifications the word "Project" is used, it shall be understood to mean Gavin's Point Dam.Text
PART 2 - PRODUCTS - NOT USED
PART 3 - PRODUCTS - NOT USED
SECTION 01 11 00.00 26 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 MEASUREMENT
1.2.1 JOB PAYMENT ITEMS
1.3 PAYMENT
1.3.1 ITEM 0001 MOBILIZATION AND DEMOBILIZATION
1.3.2 ITEM 0002 Provide Low Voltage Retro-Fill Power Circuit Breakers
1.3.3 ITEM 0003 Provide Bus Bracing Study for 480 VAC Switchgear
1.3.4 ITEM 0004 Provide Commissioning Services
1.3.5 ITEM 0005 Provide New Station Service Transformers and High
Resistance Grounding Systems
1.3.6 ITEM 0006 Test the Existing Feeder Cables from the 480VAC
Switchgear
1.3.7 ITEM 0007 Provide Remote Racking Device and Spare Parts for
New Retrofill Breakers
1.3.7 ITEM 0008 Provide 13.8 kV Bus Bracing Study (Optional)
1.3.8 ITEM 0009 13.8 kV Bus Bracing Activities (Optional)
1.3.9 ITEM 0010 Provide 13.8 kV Bus Bracing (Optional)
1.3.10 ITEM 0011 480 VAC Bus Bracing Activities (Optional)
1.3.11 ITEM 0012 Provide 480 VAC Bus Bracing (Optional)
1.3.12 ITEM 0013 Provide New Feeder Cables (Optional)
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
In each instance the contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another bid item. In the event any work is required by the specification sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to and included in the contract prices and payments for all items listed in the bid schedule.
1.2 MEASUREMENT
1.2.1 JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00010, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job payment item, must be included in the listed job payment item most closely associated with the work involved.
The job payment price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of as-builts, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. A schedule of values for job payment items shall be provided with each payment request.
1.3 PAYMENT
Payment for all work specified, shown, or incidental to complete the work will be made as follows:
1.3.1 ITEM 0001 MOBILIZATION AND DEMOBILIZATION
Measurement shall be made for mobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site and includes all options exercised by the Government. This Line item applies to the Prime Contractor and all subcontractors' mobilization work unless noted otherwise. Payment must be made in the Contract amount for Mobilization and must be paid as a JOB under Line Item No. 0001. The Contractor is required to submit a schedule of mobilization costs prior to submitting the first request for payment. Mobilization is to be considered complete after all of the Contractor's equipment and site personnel have arrived and equipment has been set up to accomplish the work. Demobilization is considered complete after all contractor's equipment has been removed and site personnel have departed following all work complete. There will be
SECTION 01 22 00 Page 2 only one mobilization/demobilization paid under this contract. Any contractor personnel or equipment movements between the initial mobilization and final demobilization shall be considered incidental to and included in this payment item. Additional cost for Contractors mobilization and demobilization for the bus bracing activities are paid under job payment items 0009 and 0010
1.3.2 ITEM 0002 Provide Low Voltage Retro-Fill Power Circuit Breakers
Payment for providing the Low Voltage Retro-Fill Power Circuit Breakers will be paid for under line Item 0002. Payment is to be paid as a JOB under Line Item No. 0002. Price and payment must constitute full compensation for all material, labor, equipment, and engineering to furnish and install the Low Voltage Retro-Fill Power Circuit Breakers.
1.3.3 ITEM 0003 Provide Bus Bracing Study for 480 VAC Switchgear
Payment for providing a Bus Bracing Study for 480 VAC Switchgear will be paid for under line Item 0003. Payment is to be paid as a JOB under Line Item No. 0003. Price and payment must constitute full compensation for the providing of a Government approved Bus Bracing Study for 480 VAC Switchgear.
1.3.4 ITEM 0004 Provide Commissioning Services
Payment for providing Commissioning Services will be paid for under line Item 0004. Payment is to be paid as a JOB under Line Item No. 0004. Price and payment must constitute full compensation for the providing of all material, labor, equipment, and engineering to provide Commissioning Services.
1.3.5 ITEM 0005 Provide New Station Service Transformers and High Resistance Grounding Systems
Payment for providing New Station Service Transformers and High Resistance Grounding Systems will be paid for under line Item 0005. Payment is to be paid as a JOB under Line Item No. 0005. Price and payment must constitute full compensation for the providing of all material, labor, equipment, factory testing, site testing, and engineering to furnish and install New Station Service Transformers and High Resistance Grounding Systems.
1.3.6 ITEM 0006 Test the Existing Feeder Cables from the 480VAC Switchgear
Payment for Testing the Existing Feeder Cables from the 480VAC Switchgear will be paid for under line Item 0006. Payment is to be paid as a JOB under Line Item No. 0006. Price and payment must constitute full compensation for the providing of all material, labor, equipment, site testing, and engineering to Test the Existing Feeder Cables from the 480VAC Switchgear.
1.3.7 ITEM 0007 Provide Remote Racking Device and Spare Parts for New Retrofill Breakers
Payment for Providing Remote Racking Device and Spare Parts for New Retrofill Breakers will be paid for under line Item 0007. Payment is to be
SECTION 01 22 00 Page 3 paid as a JOB under Line Item No. 0007. Price and payment must constitute full compensation for the providing of all material, labor, equipment, site testing, and engineering to Provide Remote Racking Device and Spare Parts for New Retrofill Breakers.
1.3.7 ITEM 0008 Provide 13.8 kV Bus Bracing Study (Optional)
Payment for providing the 13.8 kV Bus Bracing Study will be paid for under line Item 0008. Payment is to be paid as a JOB under Line Item No. 0008.
Price and payment must constitute full compensation for the providing of all material, labor, equipment, and engineering to provide the Government approved 13.8 kV Bus Bracing Study.
1.3.8 ITEM 0009 13.8 kV Bus Bracing Activities (Optional)
Payment for the 13.8 kV Bus Bracing Activities will be paid for under line Item 0009. Payment is to be paid as a JOB under Line Item No. 0009 and shall include the costs to travel to/from the site, and subsistence costs to perform all setup to install the bracing. Costs of installing the Bracing will paid under Bid Item 0010. Subsistence should be based on the installation of the total quantity (not to exceed amount) of bid item 0008a. If no additional bracing is required per the study results under Bid Item No. 0008, no payment will be made for this Bid Item.
1.3.9 ITEM 0010 Provide 13.8 kV Bus Bracing (Optional)
Payment for providing the 13.8 kV Bus Bracing will be paid for under line Item 0010. Payment is to be paid per brace under Line Item No. 0010. Price and payment must constitute full compensation for the providing of all material, labor, equipment, and engineering to provide the 13.8 kV Bus Bracing if required based on the results of the bracing study.
1.3.10 ITEM 0011 480 VAC Bus Bracing Activities (Optional)
Payment for the 480 VAC Bus Bracing Activities will be paid for under line Item 0011. Payment is to be paid as a JOB under Line Item No. 0011 and shall include the costs to travel to/from the site, and subsistence costs to perform all setup to install the bracing. Costs of installing the Bracing will paid under Bid Item 0010. Subsistence should be based on the installation of the total quantity (not to exceed amount) of bid item 0010.
If no additional bracing is required per the study results under Bid Item No. 0003, no payment will be made for this Bid Item.
1.3.11 ITEM 0012 Provide 480 VAC Bus Bracing (Optional)
Payment for providing the 480 VAC Bus Bracing will be paid for under line Item 0012. Payment is to be paid per brace under Line Item No. 0012. Price and payment must constitute full compensation for the providing of all material, labor, equipment, and engineering to provide the 480 VAC Bus Bracing if required based on the results of the bracing study.
1.3.12 ITEM 0013 Provide New Feeder Cables (Optional)
Payment for providing the New Feeder Cables will be paid for under line Item 0013 per 26 23 10.10 26 480 VOLT SWITCHGEAR RETROFILL Paragraph:
FEEDER CABLE REPLACEMENT. Payment is to be paid as a JOB under Line Item No. 0013. Price and payment must constitute full compensation for the providing of all material, labor, equipment, and engineering to furnish and
SECTION 01 22 00 Page 4 install the New Feeder Cables.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 22 00 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11; OMA 1/15
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.2.4 Administrative Submittals
1.3 SUBMITTALS
1.4 ELECTRONIC SUBMITTALS
1.4.1 Exceptions
1.4.2 File Format
1.4.3 Digital File Naming
1.4.4 Content
1.4.5 Delivery
1.5 SUBMITTAL CLASSIFICATION
1.5.1 Government Approved G
1.5.2 Information Only
1.6 PREPARATION
1.6.1 Transmittal Form
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Contractor Action Code and Action Code
1.9.5 Copies Delivered to the Government
1.10 SUBMITTAL ITEM PROCEDURES
1.10.1 "G-DO" or "G-HDC" Submittals
1.10.2 Government Approved (G-AO/G-RO) and FIO Submittals
1.10.3 Certificates of Compliance
1.10.4 Purchase Orders
1.10.5 Operation and Maintenance Data/Manuals
1.11 SCHEDULING
1.12 GOVERNMENT APPROVING AUTHORITY
1.13 DISAPPROVED OR REJECTED SUBMITTALS
1.14 APPROVED/ACCEPTED SUBMITTALS
1.15 APPROVED SAMPLES
1.16 WITHHOLDING OF PAYMENT
1.17 STAMPS
SECTION 01 33 00 Page 1
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11; OMA 1/15
PART 1 GENERAL
Attachments: Submittal Register ENG Form 4025, Transmittal Form
1.1 SUMMARY
The Contractor is responsible for total management of his work including approval, scheduling, control, certification of all submittals and compliance with all applicable Buy-American Act and Trade Agreement Act clauses. The submittal management system provided in these specifications is intended to be a complete system for the Contractor to use to control the quality of materials, equipment and workmanship provided by manufacturers, fabricators, suppliers and subcontractors. Review each submittal for contract compliance. This review is based on the contract drawings and specifications. Compliance with all applicable Buy American Act and Trade Agreement Clauses is to be included in this review. The Contractor must provide the country of origin on ENG Form 4025 for each item submitted. Submittals that comply will be forwarded to the Government. Submittals that do not conform will be returned to the originator to be corrected. The Submittal Register (ENG Form 4288) will be utilized to log and monitor all submittal activities. No construction or installation activities are to be performed until required approvals of applicable submittals have been made. Check to assure that all materials and/or equipment have been tested, submitted and approved during the preparatory phase of quality control inspections.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal; and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
SECTION 01 33 00 Page 3
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Unless otherwise designated, the submittals listed below will be handled as Administrative Submittals.
Certificates of insurance
Surety bonds
List…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .