JFHQ Q A.r.1.docx

DOCX document 12 KB Posted

Attached to
Joint Force Readiness Headquarters
Solicitation number
W9127P-11-B-0001
Issued by

About this file

Questions and Answers Round 1

View the file

Other files

File Type Posted
JFHQ Bid Sign-in.pdf PDF
Optional Form 1419 - Abstract of Bids.pdf PDF
VI-JFHQ-E-601.pdf PDF
VI_JFHQ_Bid_Questions Set 7.V.3 Aug 3.pdf PDF
VI_JFHQ_Bid_Questions Set 7.V.2 Aug 1.pdf PDF
SF 30 MOD 0002 to Solicitation.pdf PDF
JFHQ Question Sets 7.v.1 Aug 1.pdf PDF
SF 30 MOD 0002 to Solicitation.pdf PDF
JFHQ Question Sets 1-6.v.1 Aug 1.pdf PDF
SF 30 MOD 0001 to Solicitation.pdf PDF
vi-jfhq-c-101 —
vi-jfhq-c-101.zip ZIP file
vi-jfhq-c-102.zip ZIP file
vi-jfhq-c-102 —
VI_JFHQ_Bid_Questions Set 3.pdf PDF
vi-jfhq-c-131.zip ZIP file
vi-jfhq-c-102.zip ZIP file
vi-jfhq-c-101.zip ZIP file
VIARNG JFHQ - Jacobs ELECTRONIC DATA DISCLAIMER.pdf PDF
VI-JFHQ-C-101 —
VI-JFHQ-C-102 —
JFHQ Q A.r.2.pdf PDF
Attendance Sheet.PDF PDF
Pre-Bid JFHQ.ppt PPT presentation
JFHQ 1442 - IFB Document-30June.pdf PDF
VIARNG JFHQ Specifications Volume 2_Bid-Final 100 _re-issue to Guard 060311.pdf PDF
JFHQ 1442 - IFB Document.PDF PDF
Telecom-Drawings.zip ZIP file
Arch-Drawings.zip ZIP file
Life-Safety-Drawings.zip ZIP file
Electrical-Drawings.zip ZIP file
General-Drawings.zip ZIP file
Fire-Drawings.zip ZIP file
Landscaping-Drawings.zip ZIP file
Plumbing-Drawings.zip ZIP file
Civil-Drawings.zip ZIP file
Mech-Drawings.zip ZIP file
Structural-Drawings.zip ZIP file
JFHQ 1442 - IFB Document.PDF PDF
VIARNG JFHQ Specifications Volume 1_Bid-Final 100 _re-issue to Guard 060311.pdf PDF
Bid Package JFHQ.pdf PDF
VIARNG JFHQ_Geotechnical Report_Bid Final 100 _050611.pdf PDF
VIARNG JFHQ Commissioning Plan_Bid-Final 100 _re-issue to Guard 060311.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint Force Headquarters – USVI Tuesday, July 05, 2011 Questions and Answers Version 1

IFB # W9127P-11-B-0001

"In reading the solicitation and specifications for division 14, I note that there is a restricted field of identified manufacturers for the hydraulic elevator. Is this an intentional restriction (with defined basis) or was there an administrative oversight in failing to add to the specification that "or equal" would be acceptable?"

Response: Division 14 Specification is correct. For multiple reasons evaluated during the design phase, the number of acceptable elevator manufacturers was limited to the ones listed and will be the only ones to be accepted. In this particular case no manufacturers outside the list will be allowed.