CFR - Allied Crane Dredge Yaquina.pdf
PDF 86 KB Posted
- Attached to
- USACE; Portland District Dredge Yaquina Overhaul
- Solicitation number
- W9127N25BA012
About this file
This is an Onsite Corrective and Functional Report (CFR) from Allied Marine Crane documenting a mechanical issue with equipment. The report identifies a problem with the boom luffing cylinder, which is leaking from the packing gland. The recommended resolution is to remove the cylinder and rebuild it using seal kit #37843. The document was completed by an inspector named Lloyd Hoots on 07/11/2025, and contains the company's contact information at 21433 SW Oregon Street in Sherwood, Oregon.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Onsite CFR report 001
Define issue as found or problem during operation:
Boom luffing cylinder is leaking out of the packing gland
Provide resolution, include any parts required:
Remove the boom luffing cylinder and have it rebuilt with seal kit #37843
Additional notes:
Inspector Signature ________Lloyd Hoots___________________ Date ____07/11/2025____