This document is a Task Request (TR) for the Essayons Ships, numbered ESS-25-012, dated 05/05/24, with a Priority 1 status. The task involves renewing the supply ductwork for HVAC system in the Pump Room on the port side, at the 35-3" to Hold Deck level. Specific requirements include providing all labor/materials to renew supply ductwork for fan S12, replacing hangers, dampers, diffusers, screens, and insulation to restore the original configuration. The ductwork has corroded, separated, and failed, hanging by insulation/friction, which poses a safety risk of potential collapse that could injure shipboard personnel, contractors, and others. The technical documentation (681-0915-304, Sheets 1-9) is available electronically from the engineering department, and a detailed fan S12 overhaul request is referenced in a separate TR ESS-25-014.

View the file

Other files

File Type Posted
70.010-5058-918.pdf PDF
681-0879-205 Combined.pdf PDF
CaptiveAire SHOP DWGS REV1.pdf PDF
Galley Exhaust Fan.pdf PDF
Radar Console 1.jpg JPG image
Radar Console 2.jpg JPG image
70.010-0342-901 Rev B.pdf PDF
Fwd Fire Suction valve.jpg JPG image
parker air actuator 2.jpg JPG image
70.010-4013-902 Hopper Doors Arrangement and Details.pdf PDF
70.010-2775-001 Hopper Overflow Systems General Dimensions.pdf PDF
70.010-4013-903 Hopper Doors.pdf PDF
Evoqua PS Drawing 05071NST and Schematic W3T346111.pdf PDF
70.010-4013-901 General Arrangement of Hopper Door and Actuating Mechanism.pdf PDF
70.010-0342-902.pdf PDF
Fwd Fire Suction valve 2.jpg JPG image
70-010-2339-050 Rev D (1 of 1) Schematic Diagram Flushing System for Sluice Valves.pdf PDF
Manual Essayons Smoke Detector 10-22-01 version.docx DOCX document
70.010-0342-901 Rev A.pdf PDF
Parker air actuator.jpg JPG image
Crane hand wheel.jpg JPG image
Smk Det Zones.doc DOC document
Switchboard Circuit Breakers.pdf PDF
681-0853-303 Combined.pdf PDF
E-1720-28 Model General Assembly of Side Dragarm.pdf PDF
681-0853-325 Rev 3 (1 of 1) Hopper Collection Sluice Valve Flushing in Eng Room.pdf PDF
70.010-5069-902 Rev C.pdf PDF
70.010-5058-901.pdf PDF
681-0919-201-3 Rev 2 (1 of 1).pdf PDF
70.010-5069-902.pdf PDF
E-2240-1 PROPELLER SHAFT ROPE GUARD 1.pdf PDF
681-0700-156 Rev 2 (1 of 1).pdf PDF
70.010-5058-902 Rev B.pdf PDF
681-0700-164 Rev 2 (1 of 1).pdf PDF
Deck shack load summary.pdf PDF
70.010-5069-902 Rev B.pdf PDF
681-0919-201-4 Rev 2 (1 of 1).pdf PDF
681-0713-102 Rev 2 (2 of 4).pdf PDF
5058-908 Rev A (1 of 1).pdf PDF
681-0700-138-1 Rev 3 (1 of 1).pdf PDF
70.010-2560-053.pdf PDF
681-0700-157 Rev 1 (1 of 1).pdf PDF
681-0700-137 Rev 2 (1 of 1).pdf PDF
681-0879-203 Combined.pdf PDF
22885-D Tail Shaft ACOE Essayons.pdf PDF
5069-907 Rev A (1 of 1).pdf PDF
390-VGR-02.pdf PDF
681-0713-201 Rev 6 (1 of 3).pdf PDF
RE_ 2417283--Essayons electrical cable upgrade.pdf PDF
Propulsion Exhaust Drawings.pdf PDF
Show 40 more

Latest 50 of 128 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TASK REQUEST - ESSAYONS SHIPS TR # ESS -11-

CONTACT(S) OFFICE TR #

INITIATOR TR DATE

PRIORITY DATE REQUESTED

ROUTING INITIALS SUPERVISORS MASTERS

SYSTEM INFORMATION

SYSTEM

COMPARTMENT LEVEL

SIDE FRAME NOTE

DESCRIPTION OF TASK

DESCRIPTION OF PROBLEM

SAFETY ISSUES

ATTACHMENTS YES NO PAGES TECH. MANUAL #

ENGINEERING

COORDINATOR DATE

PRIORITY 1 PRIORITY 2 PRIORITY 3

PROJECT ENGINEER DATE JOB ORDER

SHIP’S FORCE VENDOR CONTRACTOR SHIPYARD MOORINGS

ESTIMATED COST COMPLETION DATE

υ ENGINEERING COMMENTS υ

PROPOSAL / ACTION / DIRECTION ACCEPT MORE INFO NEEDED DEFER CANCEL

TR RECEIVED FROM VESSEL TR RETURNED TO VESSEL

g2odndmp Oval g2odndmp Typewritten Text

AREA OF FAILURE, BUT ALL

MATERIALS ARE IN THE SAME,

POOR CONDITION. REPLACE ALL

DUCTWORK HIGHLIGHTED.

Line

Oval

SHIPS TR #
CONTACT(S)
TASK REQUEST - ESSAYONS
OFFICE TR #
INITIATOR
TR DATE
PRIORITY
DATE REQUESTED
MASTERS
SUPERVISORS
ROUTING INITIALS
SYSTEM INFORMATION
NOTE
DESCRIPTION OF TASK
DESCRIPTION OF PROBLEM
SAFETY ISSUES
ATTACHMENTS
YES NO
PAGES
TECH. MANUAL #
ENGINEERING
COORDINATOR
DATE
PRIORITY 1
PRIORITY 2
PRIORITY 3
PROJECT ENGINEER
DATE
JOB ORDER
ESTIMATED COST
COMPLETION DATE
( ENGINEERING COMMENTS (
PROPOSAL / ACTION / DIRECTION
TR RECEIVED FROM VESSEL
TR RETURNED TO VESSEL
ESS-15-083 - ICMS-Wonderware CorrectionsJOH.pdf
ESS-15-083 - ICMS-Wonderware Corrections
SHIPS TR #
CONTACT(S)
TASK REQUEST - ESSAYONS
OFFICE TR #
INITIATOR
TR DATE
PRIORITY
DATE REQUESTED
MASTERS
SUPERVISORS
ROUTING INITIALS
SYSTEM INFORMATION
NOTE
DESCRIPTION OF TASK
DESCRIPTION OF PROBLEM
SAFETY ISSUES
ATTACHMENTS
YES NO
PAGES
TECH. MANUAL #
ENGINEERING
COORDINATOR
DATE
PRIORITY 1
PRIORITY 2
PRIORITY 3
PROJECT ENGINEER
DATE
JOB ORDER
ESTIMATED COST
COMPLETION DATE
( ENGINEERING COMMENTS (
PROPOSAL / ACTION / DIRECTION
TR RECEIVED FROM VESSEL
TR RETURNED TO VESSEL

Wonderware Task Request support doc 2014

TR 012 DWG 681-0915-304.pdf
681-0915-304 Rev 5 (1 of 9)
681-0915-304 Rev 5 (2 of 9)
681-0915-304 Rev 5 (3 of 9)
681-0915-304 Rev 5 (4 of 9)
681-0915-304 Rev 5 (5 of 9)
681-0915-304 Rev 5 (6 of 9)
681-0915-304 Rev 5 (7 of 9)
681-0915-304 Rev 5 (8 of 9) Fr1
681-0915-304 Rev 5 (8 of 9) Fr2
681-0915-304 Rev 5 (9 of 9)
Paquet/Rolle Chief Engineers: PAQUET
Joe Bateman:
SY 15/16: M&R 24-25
Point of Contact: PAQUET/YELACA
tr#: ESS-25-012
MM/DD/YY: 5/5/2024
1,2,3: 1
SYSTEM: HVAC
COMPARTMENT: PUMP ROOM
LEVEL: 35-3" to HOLD DECK
SIDE: PORT
FRAME: 46
NOTE:
Task Description: PROVIDE ALL LABOR/MATERIALS TO RENEW SUPPLY DUCTWORK IAW FAN S12. RENEW ALL HANGERS, DAMPERS, DIFFUSERS, SCREENS, INSULATION, ETC. TO RESTORE TO ORIGINAL CONFIGUATION. INSPECT/REPLACE AS NECESSARY THE REMAINING DUCTWORK FOR THIS FAN AND FAN E11. ALL DUCTWORK IS OF THE SAME AGE/CONDITION. FAN S12 OVERHAUL REQUEST IS DETAILED ON TR ESS-25-014.
Description of Problem: DUCT WORK HAS CORRODED/SEPARATED/FAILED AND IS HANGING BY INSULATION/FRICTION. REQUEST NEEDS TO BE COMPLETED THIS M&R. SEE PAGE 3 FOR PICTURE. SEE PAGE 2 FOR SNIPET OF DWG 681-0915-304, SHEET 8 of 9.
Safety Issues: COMPLETE DUCTWORK COLLAPSE/INJURING SHIPBOARD PERSONNEL, CONTRACTORS, ETC.
Y: Yes
No: Off
PAGES:
TECH MANUAL:
Comments: 681-0915-304, SHEETS 1-9 AVAILABLE FROM C/E ELECTRONICALLY.
COORDINATOR:
DATE:
PRIORITY 1: Off
PRIORITY 2: Off
PRIORITY 3: Off
PROJECT ENGINEER:
DATE_2:
JOB ORDER:
ship's force: Off
vendor: Off
contractor: Off
shipyard: Off
moorings: Off
ESTIMATED COST:
COMPLETION DATE:
engineering comments:
accept: Off
more info: Off
defer: Off
cancel: Off
TR RECEIVED FROM VESSEL:
TR RETURNED TO VESSEL:
2024-05-05T19:35:03-0700