B.08 7N23R0006 BON 1 Lamprey Amendment 3 Specifications 01 22 00.00 25.pdf

PDF 18 KB Posted

Attached to
BON Fish Accords Lamprey Bonneville 1
Solicitation number
W9127N23R0006
Issued by

About this file

This document outlines the measurement and payment terms for a federal construction contract to complete improvements at Bonneville Powerhouse I Branch B entrance. The contract includes 10 line items for mobilization and demobilization, fabrication and installation of a variable width entrance weir, counterweight slot modifications, lamprey bollard plates, supply of a lamprey passage flume and collection tank, installation of a gravity fed water supply system, demolition in the fingerling passage, construction of a fingerling passage concrete weir, fabrication and installation of a lamprey passage trash rack and hoist, and installation of walkway handrails. Payment for each line item will be made upon completion of the specified scope of work. The solicitation was issued by the Army Corps of Engineers Portland District for fish passage improvements at the Bonneville Dam to support the requirements of the Columbia Basin Fish Accords.

View the file

Other files

File Type Posted
B.08 7N23R0006 BON 1 Lamprey Amendment 7.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 6.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Stoplog slot from above Photo.jpg JPG image
B.08 7N23R0006 BON 1 Lamprey Amendment 5.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Specification 22 00 00.00 25.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Sheet SF501.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Sheet SH505.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Finglerling Passage looking East Photo.jpg JPG image
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Dewatered Ladder Entrance Photo 1.jpg JPG image
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Dewatered Ladder Entrance Photo 2.jpg JPG image
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Specification 35 79 13.04 25.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Sheet SM502.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 5 Sheet SJ501.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 4.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 3.pdf PDF
I.01 7N23R0006 BON 1 Lamprey Amendment Site Visit Attendance Sheet.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 2.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 2 Sheet G 001.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Reference Drawings.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Amendment 1.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Site Visit Map.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Solicitation and Specifications.pdf PDF
A.08 7N23R0006 BON 1 Lamprey Plans.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Attachment B Past Performance Questionnaire.pdf PDF
B.08 7N23R0006 BON 1 Lamprey Attachment A Offeror Experience Form.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bonneville Powerhouse I B-Branch Entrance Improvements

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 JOB PAYMENT ITEMS

1.3 MEASUREMENT AND PAYMENT

1.3.1 Mobilization and Demobilization, CLIN 0001

1.3.2 Variable Width Entrance Weir, CLIN 0002

1.3.3 Counterweight Slot Modification, CLIN 0003

1.3.4 Lamprey Bollard Plates, CLIN 0004

1.3.5 Supply Lamprey Passage Flume and Collection Tank, CLIN 0005

1.3.6 Gravity Fed Water Supply, CLIN 0006

1.3.7 Demolition in the Fingerling Passage, CLIN 0007

1.3.8 Fingerling Passage Concrete Weir, CLIN 0008

1.3.9 Lamprey Passage Trash Rack and Hoist, CLIN 0009

1.3.10 Walkway Handrails, CLIN 0010

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

SECTION 01 22 00.00 25 Page 1 AMD #0003

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the Paragraphs MEASUREMENT and PAYMENT, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.

1.2 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment;

performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items prior to the first pay request. Update with each subsequent payment request.

MANDATORY I TEMS

1.3 MEASUREMENT AND PAYMENT

1.3.1 Mobilization and Demobilization, CLIN 0001

a. Measurement: Measurement will be made as a job for mobilizing and demobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site. This Contract Line Item Number (CLIN) applies to the Prime Contractor and all subcontractor mobilization and demobilization.

b. Payment: Payment will be made at the Contract amount under CLIN 0001 as stated in Contract Clause 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (Dec 1991). Submit a schedule of mobilization and demobilization costs prior to submitting the first request for payment.

SECTION 01 22 00.00 25 Page 2 AMD #0003

1.3.2 Variable Width Entrance Weir, CLIN 0002

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the fabrication and installation of the variable width entrance weir as depicted in the SL series of the Structural drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0002.

1.3.3 Counterweight Slot Modification, CLIN 0003

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the fabrication and installation of counterweight slot modifications as depicted in the SJ series of the Structural drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0003.

1.3.4 Lamprey Bollard Plates, CLIN 0004

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the fabrication and installation of lamprey bollard plates as depicted in the SH series of the Structural drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0004.

1.3.5 Supply Lamprey Passage Flume and Collection Tank, CLIN 0005

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, and incidentals required for fabrication and delivery of the lamprey passage flume, supports, and lamprey collection tank as depicted in the MH series of the Mechanical drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0005.

1.3.6 Gravity Fed Water Supply, CLIN 0006

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the gravity fed water supply system as depicted in the MP series of the Mechanical drawings and the Civil drawing.

b. Payment: Payment will be made at the Contract amount under CLIN 0006.

1.3.7 Demolition in the Fingerling Passage, CLIN 0007

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and disposal of the existing sluice gate, associated machinery, and wooden stoplogs in the fingerling passage as depicted in the demolition drawings.

SECTION 01 22 00.00 25 Page 3 AMD #0003

b. Payment: Payment will be made at the Contract amount under CLIN 0007.

1.3.8 Fingerling Passage Concrete Weir, CLIN 0008

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the fingerling passage concrete weir as depicted in the SM series of the Structural drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0008.

1.3.9 Lamprey Passage Trash Rack and Hoist, CLIN 0009

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the lamprey passage trash rack and hoist as depicted in the Structural and Mechanical drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0009.

1.3.10 Walkway Handrails, CLIN 0010

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for the walkway handrail installation as depicted in the SF series of the structural drawings.

b. Payment: Payment will be made at the Contract amount under CLIN 0010.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

SECTION 01 22 00.00 25 Page 4 AMD #0003

DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 25 - MEASUREMENT AND PAYMENT
01 22 00.00 25 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 JOB PAYMENT ITEMS
1.3 MEASUREMENT AND PAYMENT
1.3.1 Mobilization and Demobilization, CLIN 0001
1.3.2 Variable Width Entrance Weir, CLIN 0002
1.3.3 Counterweight Slot Modification, CLIN 0003
1.3.4 Lamprey Bollard Plates, CLIN 0004
1.3.5 Supply Lamprey Passage Flume and Collection Tank, CLIN 0005
1.3.6 Gravity Fed Water Supply, CLIN 0006
1.3.7 Demolition in the Fingerling Passage, CLIN 0007
1.3.8 Fingerling Passage Concrete Weir, CLIN 0008
1.3.9 Lamprey Passage Trash Rack and Hoist, CLIN 0009
1.3.10 Walkway Handrails, CLIN 0010
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED