This document is a solicitation for clamshell dredging services at six locations in Oregon and Washington. The U.S. Army Corps of Engineers, Portland District is seeking a contractor to perform dredging at Port Orford and Winchester Bay in Oregon, Depot Slough in Oregon, Baker Bay in Washington, Astoria in Oregon, and Longview in Washington. Services include mobilization, dredging to required depths, and placement of dredged materials. The bid period closes on June 22, 2023. Pricing will be on a unit price basis for dredging quantities determined by pre- and post-dredge surveys. Quality assurance surveys and payment methods are also outlined. The magnitude of work is estimated between $5-10 million. Kristel Flores and Andrea Smothers of the USACE Contracting Office are points of contact.

View the file

Other files for this federal contract opportunity

Other files attached to Oregon/Washington Clamshell Maintenance Dredging 2023, newest first.
File Type Posted
W9127N23B0011 Abstract OWCM23.pdf PDF
W9127N23B0011 OWCM23 Abstract.pdf PDF
W9127N23B0011 OWCM23_ADVERTISE_Amendment 0002_PLANS.pdf PDF
W9127N23B0011 OWCM23 Amendment 0002.pdf PDF
W9127N23B0011 OWCM23 Amendment 0001.pdf PDF
Wage Determination OR20230081.pdf PDF
Wage Determination WA20230080.pdf PDF
W9127N23B0011_OWCM23_ADVERTISE_PLANS.pdf PDF
W9127N23B0011_OWCMD23_ADV_Specs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment:

1. CLIN 0017 is an optional line item.

2. FAR 52.217-7 - Optional CLIN 0017: Any time prior to 1 August 2023

3. FAR 52.204-27 - Added clause

All other terms and conditions remain the same.

POC for this amendment: Kristel Flores, kristel.m.flores@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jun-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N23B0011

X 9B. DATED (SEE ITEM 11)

23-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jun-2023

CODE

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N23B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

CLIN 0017

The option status has changed from No Status to Option.

SUBCLIN 0017AA

SUBCLIN 0017AB

SECTION 00 72 00 - GENERAL CONDITIONS

The following have been added by full text:

52.204-27

52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)

(a) Definitions. As used in this clause— Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.

Information technology, as defined in 40 U.S.C. 11101(6)—

(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—

(i) Of that equipment; or

(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;

(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but

(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.

(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the

W9127N23B0011

Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.

(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.

(End of clause)

The following have been modified:

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor as outlined above. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

Optional CLIN 0004 and 0005: At contract award Optional CLIN 0007: Any time prior to completion of any work under CLIN 0006 Optional CLIN 0011: Any time prior 1 September 2023 Optional CLIN 0013 and 0014: Any time prior to completion of any work under CLIN 0012 Optional CLIN 0016: Any time throughout the life of the contract Optional CLIN 0017: Any time prior to 1 August 2023

(End of clause)

(End of Summary of Changes)

Oregon and Washington Clamshell Maintenance Dredging 2023

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 82

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 UNIT PRICE PAYMENT ITEMS

1.3 JOB PAYMENT ITEMS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 MEASUREMENT AND PAYMENT

3.1.1 Mobilization and Demobilization, Base CLIN 0001

3.1.2 Dredging and Placement of Materials; Port Orford, Base CLIN

0002AA & 0002AB

3.1.3 Dredging and Placement of Materials; Winchester Bay, Base CLIN

0003AA & 0003AB

3.1.4 Incremental Mobilization and Demobilation; Depot Slough, Optional CLIN 0004

3.1.5 Dredging and Placement of Materials; Depot Slough, Optional

CLIN 0005AA & 0005AB

3.1.6 Dredging and Placement of Materials; Baker Bay RM 00+10+00 to

01+50+00, Base CLIN 0006AA & 0006AB

3.1.7 Dredging and Placement of Materials; Baker Bay RM 01+50+00 to

03+10+00, Optional CLIN 0007AA & 0007AB

3.1.8 Dredging and Placement of Materials; Astoria Turning Basin, Base CLIN 0008AA & 0008AB

3.1.9 Dredging and Placement of Materials; Longview Turning Basin, Base CLIN 0009AA & 0009AB

3.1.10 Dredging and Placement of Materials; Port of Longview, Optional CLIN 0010AA & 0010AB

3.1.11 Mobilization and Demobilization of Grizzly Screen(s);

Transfer Site W-60.9-IW, Base CLIN 0011

3.1.12 Dredging and Placement of Materials; Transfer Site W-60.9-IW, Base and Optional CLINS 0012AA & 0012AB, 0013AA & 0013AB, and

0014AA & 0014AB

3.1.13 Grizzly Debris Screening and Disposal; Transfer Site

W-60.9-IW, Base CLIN 0015

3.1.14 Remote Video Monitoring System; Optional CLIN 0016

3.1.15 Dredging and Placement of Materials; Old Mouth Cowlitz, Optional CLIN 0017AA & 0017AB

3.2 SUBMISSION OF INVOICES FOR PAYMENT

3.3 PAYMENT METHOD

3.3.1 Pre/Post Dredge Survey

3.3.2 Dredging Quantity Computations

3.3.3 Quality Assurance Surveys

SECTION 01 22 00.00 82 Page 1

Amendment 0003

3.3.4 Screened Debris Quantity Computations

-- End of Section Table of Contents --

SECTION 01 22 00.00 82 Page 2

SECTION 01 22 00.00 82

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance the Contract price for an item will constitute full compensation in accordance with Contract Clause 252.236-7008, CONTRACT PRICES - BIDDING SCHEDULES. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another bid item. In the event any work is required by the specifications Sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs, separate and direct payment will not be made and all costs thereof are incidental to and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of as-builts, O&M manuals, tests and reports, meeting safety requirements;

and for performing all work required for each of the unit price items.

1.3 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. Include all costs for items of work, which are not specifically mentioned to be included in a particular job item, in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment;

performing all associated Contractor quality control, environmental protection, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items prior to the start of work and submit an updated schedule with each payment request.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 MEASUREMENT AND PAYMENT

3.1.1 Mobilization and Demobilization, Base CLIN 0001

a. Measurement and payment for Mobilization and Demobilization will be considered complete and full compensation for the effort and cost to

SECTION 01 22 00.00 82 Page 3 prepare the Contractor's plant and equipment for shipment; transport to and from the job site all necessary Contractor plant including related equipment, fuel, supplies, personnel required for its operation, and Government field office setup and on-board accommodations as stated in Section 01 10 10.00 82, CONTRACTOR'S OPERATIONS AND REQUIREMENTS (DREDGING); making ready for dredging; and maintaining plant and equipment in working condition at the site during the dredging period, and will be paid for at the Contract job price for this item. Plant subject to pre-work safety inspection requirements will not be considered "mobilized" until such equipment is determined to be in compliance as determined by the floating plant inspection and verified during the joint equipment walk-through.

Criteria for equipment to be considered mobilized apply to all work locations. Demobilization must be from the final dredging area, regardless of location.

b. Mobilization will be paid once all equipment needed to commence dredging and perform material placement operations is on site in accordance with the schedule required in Section 01 10 00.00 82, CONTRACT ADMINISTRATION DATA (DREDGING). All costs associated with mobilization of all equipment for all base and optional items will be included in this bid item. No more than a total of 60 percent will be paid for mobilization; mobilization payments for multiple dredge plant will be determined by the Government and will be based on the approved project schedule. This CLIN may be separated into subitems for funding purposes. Mobilization charges will be spread throughout the subitems.

c. The remaining 40 percent will be paid upon final completion and acceptance of the minimum specification requirements at all work sites and areas of operation. Demobilization charges may be spread throughout the funding subitems.

3.1.2 Dredging and Placement of Materials; Port Orford, Base CLIN 0002AA &

0002AB

a. Measurement and payment for this bid item will be considered complete and full compensation for the effort and cost to excavate the entire dredging pay areas to not less than the required dredging depths in accordance with Section 35 20 23.00 82, DREDGING AND CHANNEL CLEARING, including water quality monitoring and placement of all dredged material within the Government furnished ocean placement site, and will be paid at the Contract unit price (cubic yards of dredged material) for this item.

b. The Government will determine cubic yard quantities for payment by taking pre-dredge and post-dredge surveys utilizing electronic depth sounding and horizontal positioning equipment. See paragraph DREDGING QUANTITY COMPUTATIONS for measurement description.

c. Some amount of non-pay yards outside of the dredging prism may be necessary to dig-in and accomplish the work at Port Orford.

3.1.3 Dredging and Placement of Materials; Winchester Bay, Base CLIN

0003AA & 0003AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

SECTION 01 22 00.00 82 Page 4

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.4 Incremental Mobilization and Demobilation; Depot Slough, Optional

CLIN 0004

a. Measurement and payment for mobilization and demobilization will be considered complete and full compensation and will be paid at the Contract job price, for the effort and cost, above and beyond the initial mobilization associated with CLIN 0001, to transport to and from the Depot Slough project all necessary serviceable Contractor plant including related equipment, fuel, supplies, and personnel required for its operation.

b. Mobilization will be paid once all equipment needed to commence dredging and perform material placement operations is on site in accordance with the schedule required in Section 01 10 00.00 82, CONTRACT ADMINISTRATION DATA (DREDGING). All costs associated with mobilization of all equipment for this item will be included in this bid item. No more than a total of 60 percent will be paid for mobilization; mobilization payments for multiple dredge plant will be determined by the Government and will be based on the approved project schedule.

c. The remaining 40 percent will be paid upon final completion and acceptance of the minimum specification requirements at the Depot Slough work sites.

d. It is the Government's intent that work at the Depot Slough project be completetd while transitting between the Winchester Bay and various Columbia River projects. As such, for bidding purposes, should not be considered as a separate molbilization to or from the Columbia River Projects.

3.1.5 Dredging and Placement of Materials; Depot Slough, Optional CLIN

0005AA & 0005AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.6 Dredging and Placement of Materials; Baker Bay RM 00+10+00 to 01+50+00, Base CLIN 0006AA & 0006AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.7 Dredging and Placement of Materials; Baker Bay RM 0 0+10 1+50 +00 to 03+10+00, Optional CLIN 0007AA & 0007AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of

SECTION 01 22 00.00 82 Page 5

Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.8 Dredging and Placement of Materials; Astoria Turning Basin, Base

CLIN 0008AA & 0008AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.9 Dredging and Placement of Materials; Longview Turning Basin, Base

CLIN 0009AA & 0009AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

c. The remaining 40 percent will be paid upon final completion and acceptance of the minimum specification requirements for this work site.

3.1.10 Dredging and Placement of Materials; Port of Longview, Optional

CLIN 0010AA & 0010AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

c. The Government intends for work under this CLIN to be completed under the same mobilization/demobilization for CLIN 0009 Dredging and Placement of Material; Longview Turning Basin. No additional payment will be made for mobilization/demobilization upon award of this CLIN.

3.1.11 Mobilization and Demobilization of Grizzly Screen(s); Transfer Site W-60.9-IW, Base CLIN 0011

a. Measurement and payment for mobilization and demobilization will be considered complete and full compensation and will be paid at the Contract job price, for the effort and cost to transport to and from the Transfer Site W-60.9-IW project, and prepare for use, all necessary equipment, supplies, and personnel required for the operations of screening all dredged material at the site, in accordance with Section 35 20 23.00 82 Subpart DREDGING, Paragraph Equipment. This item does not cover the efforts associated with use of the grizzly screeen(s) during dredging. Reference Subpart Grizzly Debris Screening and Disposal; Transfer Site W-60.9-IW of this Section.

b. Mobilization will be paid once all equipment needed to commence dredging and perform material placement operations is on site in accordance with the schedule required in Section 01 10 00.00 82, CONTRACT ADMINISTRATION DATA (DREDGING). All costs associated with mobilization of all equipment for this item will be included in this bid item. No more than a total of 60 percent will be paid for mobilization; mobilization payments for multiple dredge plant will be

SECTION 01 22 00.00 82 Page 6 determined by the Government and will be based on the approved project schedule.

c. The remaining 40 percent will be paid upon final completion and acceptance of the minimum specification requirements at the Transfer Site W-60.9-IW work sites.

3.1.12 Dredging and Placement of Materials; Transfer Site W-60.9-IW, Base and Optional CLINS 0012AA & 0012AB, 0013AA & 0013AB, and 0014AA & 0014AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

3.1.13 Grizzly Debris Screening and Disposal; Transfer Site W-60.9-IW, Base CLIN 0015

a. Measurement and payment for this bid item will be considered complete and full compensation for the effort and cost to implement the use of the grizzly device, as well as dispose of all debris that is screened during use of the required grizzly device in accordance with Section 35 20 23.00 82, DREDGING AND CHANNEL CLEARING. Efforts and Costs to be considered are, but are not limited to, use of the screen(s) during dredging, the removal of the debris from the grizzly device during use, the temporary storage of the debris until it is to be hauled to the appropriate disposal facility, transporting the debris from the temporary storage area to the disposal facility, costs associated weighing the debris, and costs incurred at the disposal facility. This item will be paid at the Contract unit price (tons of screened debris) for this item.

b. Material weight in tons will be determined by certified scale in accordance with Subpart Screened Debris Quantity Computations of this Section. A Government representative must be present to witness the measurement(s).

3.1.14 Remote Video Monitoring System; Optional CLIN 0016

a. Measurement and payment for this bid item will be considered complete and full compensation for the effort and cost to provide and maintain the operation for two cameras used for video monitoring, as well as data management until the project is complete. Camera requirements are outlined in Section 01 10 10.00 82, CONTRACT

ADMINISTRATION DATA (DREDGING).

b. Payment will made as a percentage of the Contract amount prorated by overall contract work completed at the time of the pay request based on the most recent schedule update provided.

3.1.15 Dredging and Placement of Materials; Old Mouth Cowlitz, Optional

CLIN 0017AA & 0017AB

a. Measurement and Payment: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem a.

b. Quantity measurement: Reference paragraph Dredging and Placement of Materials; Port Orford, Base CLIN 0002 Subitem b.

SECTION 01 22 00.00 82 Page 7

c. The Government intends for work under this CLIN to be completed under the same mobilization/demobilization for CLIN 0009 Dredging and Placement of Material; Longview Turning Basin. No additional payment will be made for mobilization/demobilization upon award of this CLIN

3.2 SUBMISSION OF INVOICES FOR PAYMENT

Submit invoices for payment as required in Section 00 73 00, Special Contract Clause INVOICE SUBMITTAL. Progress payments for work accomplished will be made monthly.

3.3 PAYMENT METHOD

3.3.1 Pre/Post Dredge Survey

a. In Pre/Post Dredge Survey work areas, the Government will provide a required channel depth, with a maximum pay depth of 1 or 2 feet beyond the required channel depth, unless otherwise noted on the associated Contact drawings.

b. The Government will determine cubic yard quantities for payment and acceptance by utilizing electronic depth sounding and horizontal positioning equipment. Sounding depths used for determination of pay quantity volumes will generally be derived from surveys utilizing 200 kHz single-beam, or multi-beam acoustic methods. However, the Government reserves the right to take soundings by any method, including: leadline, or trigonometric leveling (total station)/differential leveling; the same method will be used for the pre and post survey of a given reach.

c. Accuracy(ies) will be in accordance with stated quality control values in EM-1110-2-1003. Upon request, the Government will provide the survey line files by which surveys are run.

d. Government Equipment: The following survey equipment (or comparable) will be used by the Government Survey Crew during the collection of sounding data and will be considered the standard for which data is obtained:

Positioning and Attitude System: Applanix POS MV V5 Wavemaster Multibeam Echosounder: Teledyne RESON T-50 Singlebeam Echosounder: Teledyne ODOM CV-100 with a 3 degree 200khz transducer Sound Velocity Profiler: AML BaseX

Note: The Government will be available by request to run check surveys between the Contractor's and Government's survey vessels prior to the start of work. The Contractor must request any side-by-side survey checks at least seven days in advance.

e. All Contractor owned equipment including all attendant plant and anchor lines must be removed from the acceptance area prior to the initiation of a survey. If equipment remains in the acceptance area at the time of survey, the survey will be cancelled and the full daily rate of $5,800 will be charged.

f. For all Contractor surveys, furnish the originals of all field notes, sounding plots, and electronic survey data described in Section

SECTION 01 22 00.00 82 Page 8

01 45 00.00 82, QUALITY CONTROL (DREDGING), along with all other records relating to the survey or to the layout of the work, to the Government, who may consider them to the extent necessary to determine the amount of progress payments. Retain copies of all such material furnished to the Government.

g. Survey Time Frames

(1) All requests for Government surveys must be made by submission of a Hydrographic Survey Request Form (Attachment A6). The request must be submitted to the Government representative(s) identified at the pre-construction conference. The dredge, including all attendant plant and anchor lines must be clear of the acceptance area(s) before a survey is made. The Government Survey periods stated below are contingent on weather and sea conditions.

(2) All survey requests must be submitted a minimum of four calendar days prior to the date on which the survey is required, or immediately upon receiving the pre-dredge survey layout if the post-dredge survey will be needed in less than four calendar days.

(3) The Government will perform all post dredge surveys within five calendar days of the requested date and will provide acceptance or rejection of each area within one day following the survey. The complete layout or post dredge package (i.e.

electronic survey data, layout chart, and quantity computations) will be available two calendar days thereafter. For the final acceptance area within a specific work location, once that acceptance area has been completed, and a post dredge survey has been requested, the Contractor may move to the next work location and begin work. However, if the results of the post dredge survey show that additional dredging is required at the previous acceptance area the Contractor will be required to return at no additional cost to the Government.

(4) The Government may conduct periodic progress surveys at all work locations.

(5) Notify the GQAR in advance of any surveys conducted and the GQAR will have the option of attending these surveys. Conduct all surveys in accordance with EM-1110-2-1003.

h. Request in writing for additional information for each survey, to include:

(1) Daily Report of Hydrographic Survey Operations

(2) Metadata

(3) Type of Survey: Multi- or Single-Beam

(4) Bar Check Calibration

(5) Sound Velocity Profile Report

(6) Survey Tide File Log

(7) Lead Line Report (when applicable)

SECTION 01 22 00.00 82 Page 9

(8) Copy of Field Book (scanned)

(9) Computation Report: The computation report will indicate the surveys used (identified by location and date) and the program and computation method used.

i. In the event it becomes necessary to reschedule a request for survey, notify the Government at least one calendar day prior to the first day of the scheduled survey period. Failure to provide such notification will result in a charge of one-half the daily rate for a Government survey crew. If the survey party mobilizes to the site before the survey is cancelled, the full daily rate for a Government survey crew of $5,800 will be charged.

j. Several work areas within this contract will have a vertical slope on one or more side due to the close proximity of obstructions, and the inability to collect adequate survey data outside of the channel limits. In work areas with vertical slopes, bidders should consider the potential of non-pay material outside the toe line moving into the dredging prism.

k. See Attachment A13 Survey Acceptance Criteria for survey methods and acceptance language for each work location. A work area will be accepted when all of the survey values inside the channel limits are equal to or deeper than the required channel depth. There is one exception to this requirement, per the note below.

Note:

(1) For Baker Bay areas, as identified on the contract drawings, certain parts of the channel will not be evaluated for depth clearance, and rather will be only be evaluated for clearance of the prescribed slope.

(2) For Port of Longview dredge areas, acceptance will be based on multibeam survey data processed using a median sort with a 5x5 foot matrix. Post-dredge survey soundings will be clipped to the dredge prism prior to median sorting to remove soundings outside of the dredge prism. All median sorted soundings within the dredge prism will be evaluated for acceptance.

l. The cross sections shown on the Contract drawing(s) represent the anticipated pre-dredge condition prior to start of work and are not necessarily derived from the latest available survey data.

m. Should more than one sounding or sweeping operation by the Government over an area be necessary by reason of work for the removal of shoals disclosed at a prior sounding or sweeping, the cost of such second and any subsequent sounding or sweeping operation will be charged at the rate of $5,800 per day for each day in which the Government plant is engaged in sounding or sweeping and/or is enroute to or from the site or held at or near the said site for such operations.

NOTE: The Contractor should consider conducting some means of hydrosurvey prior to requesting a government post dredge survey for acceptance of a work area so as to avoid being assessed the fee prescribed in the paragraph above.

SECTION 01 22 00.00 82 Page 10

n. The most recent hydrographic surveys performed by the Portland District may be obtained at the following link:

http://www.nwp.usace.army.mil/Missions/Navigation.aspx.

3.3.2 Dredging Quantity Computations

a. As prescribed in paragraph Pre/Post Dredge Survey of this Subpart, the Government will determine cubic yard quantities for payment and acceptance by utilizing electronic depth sounding and horizontal positioning equipment.

b. As required, data from land surveys will be obtained and incorporated into the volume computation.

c. The dredging pay prism is defined by the intersection of the maximum pay depth and the pay slope, as shown by Attachment A3, Descriptive Sketch. Slopes are assumed to project upward from the maximum pay depth at 1-vertical to 3-horizontal, unless noted otherwise on the Contract drawings, regardless of whether it is found to be representative of the actual side slope conditions. Material removed from outside of the maximum pay prism will not be considered for payment. Actual material removed from the side slope is considered payable as long as it is within the maximum pay prism as determined by the pre-survey data.

d. Cubic yard volumes will be computed by comparing the Government's pre-dredge and post-dredge soundings against the advanced channel design template. The Government intends to use Hypack software to compute pay volumes using the Triangulated Irregular Network (TIN) surface volume computation method. Computed pay volumes will be the difference between the TIN to CHANNEL computation of the post-dredge survey, and the TIN to CHANNEL computation of the pre-dredge survey.

No adjustments will be made for infill material (Y1) from any cause.

See Section 35 20 23.00 82, DREDGING AND CHANNEL CLEARING, regarding estimation of non-payable material.

e. Material removed from the projected side slope areas that is within the maximum dredging pay prism is considered payable. No payment will be made for material removed from outside the slope projection shown on the Contract drawings.

3.3.3 Quality Assurance Surveys

A high frequency of Government performed surveys must be anticipated. The Government may elect to perform, for the Government's use, up to two quality assurance surveys in each acceptance area. These surveys are not intended to supplement or replace the Contractor's QC/progress surveys.

The Government will provide 48 hour notice prior to initiating a quality assurance survey. The Government quality assurance surveys will be conducted without impact to Contractor's operations. Government quality assurance surveys will not be used for the basis of progress payments.

3.3.4 Screened Debris Quantity Computations

a. This Subpart applies only to work associated with Transfer Site W-60.9-IW work, specifically CLINs 0010AA and 0010, 0011AA and 0011AB, and 0012AA and 0012AB.

SECTION 01 22 00.00 82 Page 11

b. As part of the PSMP, submit a Debris Measurement Plan for approval that identifies the certified scale to be used for weighing removed debris and the manner in which the debris will be transported to the scale(s), and include a copy of the weigh scale certification.

c. Notify the Government by email to the COR at least five days prior to transporting any debris for measurement to the certified scale(s).

A Government representative must be present for the measurement(s).

d. Submit the weigh ticket(s) to the Government within 24 hours of the measurement(s).

-- End of Section --

SECTION 01 22 00.00 82 Page 12

23B0011 OWCM23 Amendment 0003
Amd 0003
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 82 - MEASUREMENT AND PAYMENT
01 22 00.00 82 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 UNIT PRICE PAYMENT ITEMS
1.3 JOB PAYMENT ITEMS
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 MEASUREMENT AND PAYMENT
3.1.1 Mobilization and Demobilization, Base CLIN 0001
3.1.2 Dredging and Placement of Materials; Port Orford, Base CLIN 0002AA &
3.1.3 Dredging and Placement of Materials; Winchester Bay, Base CLIN
3.1.4 Incremental Mobilization and Demobilation; Depot Slough, Optional
3.1.5 Dredging and Placement of Materials; Depot Slough, Optional CLIN
3.1.6 Dredging and Placement of Materials; Baker Bay RM 00+10+00 to
3.1.7 Dredging and Placement of Materials; Baker Bay RM 00+101+50+00 to
3.1.8 Dredging and Placement of Materials; Astoria Turning Basin, Base
3.1.9 Dredging and Placement of Materials; Longview Turning Basin, Base
3.1.10 Dredging and Placement of Materials; Port of Longview, Optional
3.1.11 Mobilization and Demobilization of Grizzly Screens; Transfer Site
3.1.12 Dredging and Placement of Materials; Transfer Site W-60.9-IW, Base
3.1.13 Grizzly Debris Screening and Disposal; Transfer Site W-60.9-IW,
3.1.14 Remote Video Monitoring System; Optional CLIN 0016
3.1.15 Dredging and Placement of Materials; Old Mouth Cowlitz, Optional
3.2 SUBMISSION OF INVOICES FOR PAYMENT
3.3 PAYMENT METHOD
3.3.1 Pre/Post Dredge Survey
3.3.2 Dredging Quantity Computations
3.3.3 Quality Assurance Surveys
3.3.4 Screened Debris Quantity Computations