This solicitation seeks proposals to purchase and install a new backup generator and associated equipment at the Green Peter Reservoir facility. Key requirements include providing and installing a 250kW diesel engine-generator, fuel tank, manual transfer switch, and modifying electrical equipment and conduits. Proposers must also submit operations and maintenance documentation and train government personnel. Proposals are due by August 15, 2023. The award is a firm fixed-price contract scheduled for September 30, 2023. The soliciting agency is the U.S. Army Corps of Engineers Portland District.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Green Peter Dam Deep Drawdown Temporary Power Supply Contract 2
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 10 00.00 25 CONTRACT ADMINISTRATION DATA
01 10 10.00 25 CONTRACTOR'S OPERATIONS AND REQUIREMENTS
01 11 00.00 25 SUMMARY OF WORK
01 22 00.00 25 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 25 QUALITY CONTROL
01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19.00 25 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23.00 25 OPERATION AND MAINTENANCE DATA
01 78 39.00 25 PROJECT RECORD DOCUMENTS
DI VI SI ON 03 - CONCRETE
03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND
MINOR EQUIPMENT FOUNDATIONS
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 19.00 26 INSULATED WIRE AND CABLE
26 05 26.00 26 GROUNDING AND GROUND TESTING
26 08 01.00 26 SYSTEMS TESTING AND COMMISSIONING
26 32 14.00 26 DIESEL-GENERATOR SET, STATIONARY 15-500 KW, STANDBY
APPLICATIONS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00.00 25
CONTRACT ADMINISTRATION DATA
PART 1 GENERAL
1.1 REFERENCES
1.2 MEANING OF TERMS
1.3 CONTRACTING OFFICER
1.4 SERIAL LETTER CORRESPONDENCE
1.4.1 Numbering
1.4.2 Subcontractors
1.4.3 Transmittals
1.5 EM 385-1-1 SAFETY AND HEALTH REQUIREMENTS MANUAL
1.6 PROJECT-SPECIFIC MANAGEMENT PLAN
1.7 LETTERS OF AUTHORITY
1.8 LABOR STANDARDS
1.8.1 Coverage
1.8.2 Wages
1.8.3 Overtime
1.8.4 Deductions
1.8.5 Apprentices
1.8.6 Payrolls
1.8.7 Supply and Use of Electronic Software for Processing Wage Rate
Requirements
1.8.8 Records
1.8.9 Job Interviews
1.9 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.10 PARTNERING
1.11 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.12 BASIS FOR SETTLEMENT OF PROPOSALS
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 10 00.00 25 Page 1
SECTION 01 10 00.00 25
CONTRACT ADMINISTRATION DATA
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 5.5 Contract Provisions and Related Matters
1.2 MEANING OF TERMS
a. Specification Sections of this Contract are generally written in the imperative mood. In sentences using the imperative mood, the subject, "the Contractor," is implied. Also implied in this language are "shall," "shall be," "must," or similar words and phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.
b. Wherever "directed," "required," "prescribed," or other similar words are used, the "direction," "requirement," or "order" of the Contracting Officer (CO) is intended. Similarly, wherever "approved," "acceptable," "suitable," "satisfactory," or similar words are used, the words mean "approved by," "acceptable to," or "satisfactory to" the CO.
c. The word "will" generally pertains to decisions or actions of the
CO.
1.3 CONTRACTING OFFICER
The CO who signed this Contract is the primary CO for the Contract.
Nevertheless, any CO assigned to the Portland District and acting within his/her authority may take formal action on this Contract when a Contract action needs to be taken and the primary CO is unavailable. All correspondence must be through the CO or, upon notification, their authorized Representative (COR).
SECTION 01 10 00.00 25 Page 2
1.4 SERIAL LETTER CORRESPONDENCE
All letters must be electronically submitted to the Government and must be sent to designated parties via email and exported via the RMS interface.
All letters must be signed in accordance with the letters of authority.
Send any documents requiring original hardcopy/signatures to: Eugene Resident Office, 211 E 7th Avenue, Suite 220, Eugene, OR 97401.
1.4.1 Numbering
All serial letter correspondence must be independently numbered sequentially with no numbers missing or duplicated, commencing with number one. Each letter must show the Contract number, description, and subject matter. Only one subject should be covered in the same letter.
1.4.2 Subcontractors
Subcontractors must not correspond with either the Resident or District offices; the Prime Contractor must handle all correspondence.
1.4.3 Transmittals
Transmittals of signed pay estimates, payrolls, submittals, and other similar correspondence will not require a Serial Letter.
1.5 EM 385-1-1 SAFETY AND HEALTH REQUIREMENTS MANUAL
The latest version in effect on the date of the Solicitation for this Contract (in accordance with EM 385-1-1 Paragraph 4 General, will be contractually binding as part of this Contract. The latest version, including all errata and changes, must be used for this Contract and is obtainable at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals /EM_385-1-1.pdf .
1.6 PROJECT-SPECIFIC MANAGEMENT PLAN
Submit SD-01, Preconstruction Submittals (listed on the submittal register, Attachment A1, and defined in Section 01 33 00, SUBMITTAL PROCEDURES). The listed components of the Project-Specific Management Plan (PSMP) must be submitted separately under the appropriate specifications section. Upon approval, the components must be combined into a single PSMP binder that will be kept onsite. Update the PSMP whenever the plans contained within are updated or amended. The COR will periodically review the onsite copy of the PSMP. If a current version of the PSMP is not available and up to date, site work may be stopped until deficiencies are corrected. Acceptance of the PSMP is required prior to mobilization.
The PSMP must include:
a. Section I - Accident Prevention Program.
(1) Accident Prevention Plan ( EM 385-1-1 and Section 01 35 26.00 25, GOVERNMENTAL SAFETY REQUIREMENTS).
(2) Drug-free workplace policy.
(3) Global Harmonization program ( EM 385-1-1 ).
SECTION 01 10 00.00 25 Page 3
(4) Activity hazard analysis ( EM 385-1-1 ).
(5) Equipment certification.
b. Section II - Environmental Protection Plan (Section 01 57 19.00 25, TEMPORARY ENVIRONMENTAL CONTROLS).
c. Section III - Construction Quality Control System (Section 01 45 00.00 25, QUALITY CONTROL).
(1) Contractor's quality control (CQC) plan.
(2) CQC Daily Report form.
d. Project Work Plan. The following are examples:
(1) Roadway Access Agreement.
(2) Temporary electrical systems.
(3) Welder qualifications.
(4) Welding procedures.
(5) Bolt pre-tensioning procedure.
e. Schedule for Construction.
f. Submittal Register.
1.7 LETTERS OF AUTHORITY
a. To authenticate actions required under terms of this Contract, furnish a letter of authority to the CO and Resident Engineer that indicates the names of individual or individuals who are authorized to perform the following functions on behalf of the company:
(1) Sign progress payment estimates.
(2) Sign final payment estimate.
(3) Accept Government-furnished property (if applicable).
(4) Sign Contract modifications, supplemental agreements and consent of surety.
(5) Monitor and report on the environmental protection plan, management plan, quality control plan, and safety plan.
(6) Supervise the field activities.
(7) Sign Release of Claims.
(8) Sign Correspondence.
b. This letter of authority must bear the typewritten names and the handwritten signatures of each individual and be signed by the person whose signature appears on the final Contract.
SECTION 01 10 00.00 25 Page 4
1.8 LABOR STANDARDS
Comply with the following labor standards, statutes, and regulations:
Davis-Bacon Act; Contract Work Hours and Safety Standards Act; Copeland Act; Secretary of Labor's regulations (Parts 3 and 5, Subtitle A, Title 29, Code of Federal Regulations). Submit a serial letter identifying the crafts and wage rates for all Prime and subcontractor employees to whom the Contract's construction wage rate requirements apply. The Government will review these crafts and rates for conformance with the wage determination.
1.8.1 Coverage
Contract provisions relating to wages, overtime, payroll deductions, and other labor standards requirements cover foremen, laborers, and mechanics, including owner-operators of other than hauling equipment and other individual enterprises performing the duties of a laborer or mechanic.
Bona fide owner-operators of hauling equipment, such as trucks, who are independent contractors, are not covered, and the certified payrolls, including the names of such owner-operators, need not show hours worked nor rates paid, but only the notation "owner-operator".
1.8.2 Wages
Wages must be paid at least once a week and be computed at hourly rates not less than those set forth in the Contract wage schedule, as set by the Davis-Bacon Act wage determinations, for the particular classifications of work performed.
1.8.3 Overtime
Pay overtime for work in excess of 40 hours in any workweek at not less than 1-1/2 times the basic rate of pay. Rates paid for fringe benefits are excluded in the computations of overtime.
1.8.4 Deductions
Deductions from wages earned may be only those that are permitted by the Copeland Act (Anti-Kickback) regulations.
1.8.5 Apprentices
Comply with the requirements of 29 CFR 5.5 (a)(4)(i) with respect to apprentices.
1.8.6 Payrolls
Prepare and submit correct Weekly Payrolls, including those of subcontractors. Incorrect and delinquent payrolls will delay processing of partial payment estimates.
1.8.7 Supply and Use of Electronic Software for Processing Wage Rate Requirements
a. Use a commercially-available electronic system to process and submit certified payrolls electronically to the Government is encouraged. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements
SECTION 01 10 00.00 25 Page 5 statute.
b. If an electronic payroll processing system, then the Contractor is responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required to comply with the Wage Rate Requirements statute. If an electronic payroll system is used, the electronic payroll service must be used to prepare, process, and maintain the relevant payrolls and basic records during all work under this contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required three years after contract completion. If an electronic payroll system is not used, then the Contractor must obtain and provide electronic system access to the Government, over the duration of this Contract.
The access must include electronic review access by the Government to the electronic payroll processing system used by the Contractor.
c. Provision and use of an electronic payroll processing system must meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation (FAR);
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's RMS;
(5) demonstrated security of data and data entry rights;
(6) ability to produce contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the date/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
d. All incurred costs related to the provision and use of an electronic payroll processing service shall be included in the price for the overall work under the Contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately bid or reimbursed item under this Contract.
SECTION 01 10 00.00 25 Page 6
1.8.8 Records
Maintain payroll and Employment Records during the course of work and for three years thereafter. They are subject to inspection by the CO and the U.S. Department of Labor.
1.8.9 Job Interviews
A Government representative will interview Contractor and subcontractor employees from time to time during working hours on the job.
1.9 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE Contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant Contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this Contract. The following resources are available to assist USACE Contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information:
www.fedshirevets.gov/index.aspx
c. Veterans' Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program:
http://benefits.va.gov/vow/
e. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
1.10 PARTNERING
a. The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. Among the objectives are effective and efficient Contract performance and are intended to achieve completion within budget, on schedule, and in accordance with the plans and specifications; and to develop a single cooperative management team focused on the success of the project to mutual benefit of all stakeholders. This partnership will be bilateral in makeup, and participation will be totally voluntary. Any cost associated with effectuating this partnership will be agreed to by both parties, and will be shared equally with no change to the Contract price. An integral aspect of partnering is the resolution of disputes in a timely, professional, and non-adversarial manner through the use of issue clarification and problem solving. Alternate Dispute Resolution (ADR) methodologies will be encouraged in place of the more formal dispute resolution procedures. ADR will assist in promoting and maintaining an amicable working relationship to preserve the partnership. ADR is a voluntary, non-binding procedure available for
SECTION 01 10 00.00 25 Page 7 use by the parties to this Contract to resolve any dispute that may arise during performance.
b. Should the Contractor elect to participate in partnering, key on-site and home office management personnel will be required to attend a full day partnering session as directed by the Government with an outside facilitator. The cost of this facilitated session is anticipated to be around $5,000 and will be shared equally between the Contractor and the Government.
1.11 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
a. This special contract requirement does not apply to terminations.
See FAR Part 49.
b. Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8 , Construction Equipment Ownership and Operating Expense Schedule, Region VIII.
Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
c. Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
d. When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
1.12 BASIS FOR SETTLEMENT OF PROPOSALS
a. Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis.
b. In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
SECTION 01 10 00.00 25 Page 8
(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(4) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation (FAR) 31.205-11).
(5) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 10 00.00 25 Page 9
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 10.00 25
CONTRACTOR'S OPERATIONS AND REQUIREMENTS
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.2 REFERENCES
1.3 SUBMITTALS
1.4 SCHEDULE FOR CONSTRUCTION
1.5 INCLEMENT WEATHER CONSTRUCTION
1.6 NOTIFICATION OF EQUIPMENT OUTAGE
1.7 NOTIFICATION OF EQUIPMENT OUTAGE TO BPA
1.8 UTILITY OUTAGE REQUEST AND UTILITY CONNECTION REQUEST
1.9 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
1.10 WEEKLY COORDINATION MEETINGS
1.11 CONTRACTOR EMPLOYEES
1.12 ACCESS AGREEMENTS AND WORK AREAS
1.12.1 Access Agreements
1.12.2 Employee Access and Parking
1.13 GOVERNMENT PROJECT ENGINEER'S OFFICE
1.14 SECURITY PROCEDURES
1.14.1 Project Security
1.14.2 Contractor's General Personnel
1.14.3 Verification of Employment Eligibility
1.14.4 Identification of Employees
1.14.5 Non-US Citizens
1.15 SUPPLEMENTAL SECURITY REQUIREMENTS
1.15.1 Seven Year Criminal Background Check
1.15.2 NERC Critical Infrastructure Protection (CIP) Training
1.15.3 Quarterly NERC CIP Security Awareness Program
1.15.4 Personnel Requiring Electronic Access to Cyber Assets
1.16 SECURITY TRAINING
1.17 CONSTRUCTION PROJECT IDENTIFICATION SIGN
1.18 UTILITIES
1.18.1 Sanitary Facilities
1.18.2 Electrical Power
1.18.2.1 General
1.18.2.2 Temporary Electrical Wiring
1.18.3 Water
1.19 CONTRACTOR'S EQUIPMENT
1.19.1 Contractor's Planned Equipment Methods
1.19.2 Plant and Equipment List
1.19.3 Movement of Equipment by the Contractor
1.20 CONTRACTOR USE OF GOVERNMENT CRANES
1.21 DAMAGED EQUIPMENT OR ABNORMAL CONDITIONS
1.22 GAS, VAPOR, FUME, DUST, AND MIST CONTROL IN POWERHOUSE
1.22.1 General
1.22.2 Additional Provisions
1.23 USE OF EXPLOSIVES
1.24 DAILY CLEANUP AND DISPOSAL
1.25 DISPOSAL AND SALVAGE OF EQUIPMENT AND MISCELLANEOUS MATERIALS
SECTION 01 10 10.00 25 Page 1
1.26 PROTECTION OF MATERIAL AND WORK
1.27 PROTECTION OF EXISTING UTILITIES
1.28 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.29 RESTORATION OF PROJECT ROADS
1.30 COMMISSIONING PLAN
1.30.1 Description
1.30.2 Team
1.30.3 Safety
1.30.4 Environmental
1.30.5 Safe Clearance Procedures
1.30.6 Steps
1.30.7 Contingency Plans
1.30.8 Documentation
1.30.9 Operation and Maintenance (O&M) Manuals and As-Built Drawings
1.31 COMMISSIONING REPORT
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 10 10.00 25 Page 2
SECTION 01 10 10.00 25
CONTRACTOR'S OPERATIONS AND REQUIREMENTS
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
This Section covers general requirements applicable to specific Contractor's operations and equipment.
1.2 REFERENCES
The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
EP 310-1-6A (2006; 2019 Change 2) Project Operation -- Sign Standards Manual, VOL 1
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO LRFD (8th Edition; 2017) Bridge Design Specifications
U.S. ARMY (DA)
DA AR 25-2 (2019) Army Cybersecurity
DA AR 380-67 (2014) Personnel Security Program
U.S. DEPARTMENT OF DEFENSE (DOD)
DoD 8570.01 (2004) Information Assurance Training, Certification, and Workforce Management
DoD 8570.01-M (2012) Information Assurance Workforce Improvement Program
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.94 Ventilation
29 CFR 1926.52 Occupational Noise Exposure
29 CFR 1910.1000 Air Contaminants
29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists
29 CFR 1926.57 Ventilation
SECTION 01 10 10.00 25 Page 3
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule for Construction; G
Utility Outage Request
Utility Connection Request
Access Agreements and Work Areas ; G
Security Procedures; G
Security Training; G
Temporary Electrical Wiring Plan; G
Contractor's Planned Equipment Methods; G
Plant and Equipment List; G
Loading Diagram; G
Gas, Vapor, Fume, Dust, and Mist Control Program; G
Commissioning Plan; G
Notification Of Equipment Outage To BPA; G
Notification Of Equipment Outage
Procedure For Approval For Identification
SD-06 Test Reports
Commissioning Report; G
SD-07 Certificates
Information Assurance/Information Technology Training And Certification; G
1.4 SCHEDULE FOR CONSTRUCTION
Submit an updated schedule for Government approval on a monthly basis.
The updated schedule will be used as a basis to evaluate the Contractor's progress for purposes of payment. Lack of an updated schedule will result in an inability of the Contracting Officer (CO) to perform a full evaluation of the Contractor's progress and will result in the CO withholding payment until an updated schedule has been submitted and approved.
SECTION 01 10 10.00 25 Page 4
1.5 INCLEMENT WEATHER CONSTRUCTION
No time extensions will be authorized for materials, or equipment damaged due to negligence during periods of inclement weather.
1.6 NOTIFICATION OF EQUIPMENT OUTAGE
Where an equipment outage is required to accomplish the work outlined in this Contract, notify the Government 14 days in advance. This will allow the Government to de-energize the equipment for Contractor access.
1.7 NOTIFICATION OF EQUIPMENT OUTAGE TO BPA
For outages required to a generator or line, submit a request in writing to the CO at least 100 calendar days in advance of the time required.
1.8 UTILITY OUTAGE REQUEST AND UTILITY CONNECTION REQUEST
a. Obtain digging permits prior to start of excavation. Notify the CO (CO) at least 72 hours prior to starting excavation work. Verify and mark all utilities not shown.
b. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated or specified to be removed but indicated in locations to be traversed by piping, ducts, and other work to be conducted or installed.
c. Schedule work to hold outages to a minimum. Coordinate with CO and Project POC to schedule outages during work windows.
d. Arrange utility outages and connections required during the prosecution of work that affect existing systems, at the convenience of the Government, and outside of regular working hours or on weekends.
e. Requests for utility outages and connections must be made in writing to the CO at least 14 calendar days in advance of the time required. Each request must include the system involved, location involved, utilities being affected, approximate duration of outage, and the nature of work involved.
1.9 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK
The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor will coordinate as necessary.
1.10 WEEKLY COORDINATION MEETINGS
Weekly coordination meetings must be held between the Contractor and the Government. This meeting will be used to discuss Contractor's safety, Quality Control Program, joint risk management, submittals, deficiencies, Contract administration, schedule, actual progress in the last week, and work planned in the upcoming two weeks. Any work requiring Project support or potential impacts to Project operations or maintenance must be noted. During the Preconstruction Meeting, the Government will determine responsibility of running this meeting. If the Government elects to run the coordination meeting, the Contractor must provide a two week look ahead, with the previous week progress, 48 hours before each weekly meeting to the Government representative. The responsible party must
SECTION 01 10 10.00 25 Page 5 prepare and distribute, by e-mail, the coordination meeting agenda with a two week look ahead no later than 24 hours before each meeting. A meeting time and place will be mutually agreed upon for the same time each week.
Distribute weekly coordination meeting minutes no later than the close of business the next business day.
1.11 CONTRACTOR EMPLOYEES
Ensure that all employees are capable of demonstrating adequate knowledge of tools, supplies, equipment, and techniques necessary to competently perform the work. All personnel employed by the Contractor must be fully qualified in their respective fields to render the services necessary.
The Government may require the Contractor to discontinue using any employee in the performance of the work specified in this Contract determined by the Government to be unsatisfactory. Contractor employees will not be permitted to bring guests, family members, or non-employees to the job site at any time.
1.12 ACCESS AGREEMENTS AND WORK AREAS
1.12.1 Access Agreements
a. Submit access procedures to and from the work site after the Contractor, the CO, and the Project's Representative have coordinated and determined the most advantageous access to, and staging of, the Contractor's assets deployed to the work site.
b. The right-of-way for the work (or delivery site) and access thereto will be furnished as stated in this Paragraph subject to mutual agreement between the Contractor and the Government concerning the specific route the Contractor is to use. Such mutual agreement must be reached prior to initiation, construction, or delivery.
c. The existing access roadway and any associated access roads on the Project, must not be closed as a result of construction or delivery activities associated with this Contract unless previously coordinated and approved by the Government. Traffic delays will only be permitted in accordance with the provisions of this Section.
d. When necessary to operate on or to cross existing highways or roads, all necessary permits must be obtained from the appropriate private or public authority.
e. In accordance with EM 385-1-1 , flaggers, signs, lights, and other safeguards must be provided to safely control and direct the flow of traffic when necessary for equipment to operate on or to cross access roads, arterial roads, or highways.
f. Spillage on Project roads and state or county roads will not be permitted, and the spillage must be immediately cleaned up at the expense of the Contractor.
g. No cleated or crawler-type equipment can be operated on paved surfaces.
h. Damage to all roads caused by the Contractor's operations must be repaired to pre-existing conditions at the expense of the Contractor.
i. Photograph the existing condition of all staging areas prior to
SECTION 01 10 10.00 25 Page 6 mobilization and submit all photographs in the Access Agreements submittal. Failure to properly document existing conditions will result in a Government determination of necessary repairs.
1.12.2 Employee Access and Parking
Contractor's employee private vehicle parking areas must be restricted to the area as agreed upon before construction or delivery. All Contractor vehicles used for prosecuting the work must have a Contractor sign or other permanent identification and must carry the required insurance.
Private vehicles not owned by the Prime Contractor or subcontractors must not be used for prosecuting the work. Private vehicles of the Contractor and its employees must enter and leave the project as directed. Keep the parking areas free of litter and debris. An adequate number and size of trash receptacles must be placed in the parking areas and emptied, as necessary to avoid overflowing. Trash receptacles must be adequately secured to provide protection from the wind and animals.
1.13 GOVERNMENT PROJECT ENGINEER'S OFFICE
Provide the Government Project Engineer with a temporary office, approximately 200 square feet in floor area; locate where directed and provide space heat, cooling, electric light, and power. Provide a mail slot in the door or a lockable mail box mounted on the surface of the door. Include a four by eight foot plan table, a standard size office desk, and a five-wheeled, padded, ergonomic desk chair with lumbar support and armrests. All furniture must be in good, working condition. If the Contractor has internet access installed in the trailer a minimum of one access point must be provided to the Government's office with an ethernet cable. The office must have a minimum of one window with operable window blinds. The Contractor's drinking water must be available for consumption by onsite Government employees. Provide janitorial services at a minimum of once per week, including emptying of trash cans and sweeping and mopping of floors. Dedicate a minimum of two parking spots as "Government Parking Only" in the office parking area. At completion of the work, the office will remain the property of the Contractor and must be removed from the site. Utilities must be connected and disconnected in accordance with local codes and to the satisfaction of the CO and all utility costs must be borne by the Contractor.
1.14 SECURITY PROCEDURES
a. General security requirements and guidance: The security requirements described below apply to all Contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this Contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters must be addressed to the COR. Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable Contract personnel must complete initial training within 30 days of Contract award or the date new Contract personnel begin performance on the Contract.
b. Within five business days from the completion of training, provide
SECTION 01 10 10.00 25 Page 7 written documentation (e.g., email or memorandum) to the Government representative. The documentation must include the names of Contract personnel trained and which training they completed. Maintain training records as part of Contract files and be prepared to provide copies of training certificates to the Government representative.
Contractor personnel and vehicles are subject to search when entering Federal installations. Additionally, all Contract personnel must comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this Contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect Contract personnel. Ensure all Contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.14.1 Project Security
a. The Project is not open to the public during daylight hours. After dusk the security gates are locked and unmanned. Submit a procedure for approval for identification and control of employees entering or leaving the Project during the hours of closure.
b. Arrangement and scheduling of working hours and crews must be coordinated through the CO with the Project Staff. The working hours of the Project Staff are Mondays through Thursdays from 6:30 a.m.
until 5:00 p.m. Fridays are non-working days. Green Peter Dam is a remotely operated facility, Project Staff availability may be limited to 7:00 AM to 3:30 PM to allow for travel time. Working hours that extend past 5:00 p.m. weekdays or on weekends and holidays must be coordinated through the CO. Submit the intended working hours of staff on site and identify any employees working in any capacity in accordance with Subparagraph IDENTIFICATION OF EMPLOYEES .
c. Security of the Contractor's property and items furnished under this Contract, until the Government accepts items, are the Contractor's responsibility . Salespersons, personnel seeking employment, and personal visitors are not authorized to enter non-public areas of the Project.
d. Signs may be erected outside the project containing instructions for personnel seeking the Contractor. The content and location of the signs will be approved by the CO prior to erection. Posts or other means of support, if required, must be provided by the Contractor and removed when the Contract is completed. Any open post holes must be suitably backfilled, prior to the end of the shift in which posts are removed, and any other damage must be repaired to preconstruction conditions.
e. All Contract personnel requiring physical access to a Federal installation or facility must comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet Contract performance requirements on a DoD installation in the US must be vetted by the Government using the National Crime
SECTION 01 10 10.00 25 Page 8
Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel must comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to Government facilities must coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property must comply with key and lock control procedures of the RA.
1.14.2 Contractor's General Personnel
Prepare an organizational chart and revise whatever organizational changes occur. Maintain a complete organizational chart of all positions that will be working on the project.
1.14.3 Verification of Employment Eligibility
Contractors must comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at https://www.e-verify.gov/ to meet the Contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates must be provided to the COR no later than three business days after the initial Contract award. When Contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official Contract file.
1.14.4 Identification of Employees
a. Submit a complete, dated and signed, list of all Contractor and subcontractor personnel and their titles who will be working on the project at the Weekly Coordination Meeting. This listing must be revised and resubmitted when personnel changes occur.
b. Government-prescribed cards/keys: Obtain the Government-prescribed cards/keys from the Project Security Office prior to engaging in work on the project. For each employee requiring Government-prescribed card/key, submit a written request to the CO at least 15 days prior to site mobilization including, but not limited to the following:
(1) Name of Contractor
(2) Name of Employee
(3) Employee's birth date
(4) Employee's place of birth
(5) Employee's valid identification with photo
(6) Other employee information as needed based on security level
c. Return of Government-prescribed cards/keys:
SECTION 01 10 10.00 25 Page 9
(1) Notify the Project security office immediately in the event of a termination for cause, reassignment, or a lost or stolen security item.
(2) Within 24 hours of personnel changes or the release of any employee and within seven days of the end of construction completion or termination of Contract, collect and return all Government-prescribed cards/keys to the Project Security Office.
Failure to return any Government-prescribed cards or keys will result in a $1000 per item charge to the Contractor and may delay final payment. These fees will be deducted from the Contractor's monthly payment at no additional cost to the Government.
(3) Contractor personnel who will be on site intermittently (less than once per week) must return their security items to the Project security office for safekeeping when offsite.
d. Personnel Identity Verification (PIV) - All personnel, including visitors, must provide positive verification of individual identity, in the form of a valid Government-issued photo ID prior to being granted access to non-public areas. Driver licenses that do not comply with the REAL ID Act of 2005 cannot be used as the sole source for identity proofing, and a second form of photo ID will be required. For details and current information, see the Department of Homeland Security website https://www.dhs.gov/secure-drivers-licenses .
e. Personally Identifiable Information (PII) - Encrypt or password protect all transmissions containing PII must be encrypted or the document(s) containing PII must be encrypted or password protected.
Send all documents containing PII ll directly to the Project RCC and Security Specialist.
1.14.5 Non-US Citizens
Submit a scanned legible color copy of the Permanent Resident Card and passport to the CO of all personnel who are non-US citizens working on this Contract. If a passport is not available, a minimum of a seven year criminal background check with the state patrol office must be performed from all states of residence and employment, for the past seven years must be submitted. The CO will provide the Portland District Security Office the submitted copies at least one month (30 calendar days) in advance of the start of work by the employees. Contractor personnel who are non-US citizens will not be permitted access to the Project until the Foreign Visitor Authorization is received from U.S. Army Corps of Engineers Headquarters. Contractor personnel who are non-US citizens will not be permitted to work on the Contract at all until Foreign Visitor Authorization is received.
1.15 SUPPLEMENTAL SECURITY REQUIREMENTS
Powerhouses, security badging, and security monitoring areas are subject to additional security requirements, including those in North American Electric Reliability Corporation Critical Infrastructure Protection (NERC CIP)-004, Personnel and Training. The following additional requirements apply where unescorted access to any of these areas is required.
Documents specified below must be submitted along with the Project approved access request forms, not less than one week before the date when access is required. If unescorted access to these areas is required, the access request will not be processed until all required documentation has
SECTION 01 10 10.00 25 Page 10 been provided. In accordance with applicable regulations, all Contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
1.15.1 Seven Year Criminal Background Check
a. For each person requiring unescorted access to the Powerhouse or to designated security areas, provide a seven year criminal background check. All costs associated with obtaining the criminal background report will be at the expense of the Contractor. The Project RCC or Security Specialist will review the report, and Project management will approve, disapprove, or revoke authorization for unescorted access based on the findings of the report.
b. Base the report on a positive ID match using Social Security Number and fingerprints, and include all of the following:
(1) State and county check for the current residence, regardless of duration, and for each jurisdiction where the subject has lived or worked for six months or longer during the seven years immediately preceding the investigation.
(2) A search of Federal criminal records, a national crime index search of all US states and territories, and (where possible) an Office of Foreign Assets Control (OFAC) search for terrorists, narcotics traffickers, and blocked persons.
(3) For Contracts extending beyond seven years, the seven year criminal background check must be updated at least once every seven years for personnel requiring unescorted access to Powerhouses or other areas subject to NERC CIP regulations.
1.15.2 NERC Critical Infrastructure Protection (CIP) Training
Prior to being authorized for unescorted access, and annually thereafter, each person requiring unescorted access to the Powerhouse or to designated security areas must review the Government-provided NERC CIP training material, and must complete the quiz with a passing score of not less than 70 percent. The Project RCC will provide the training, curriculum, and materials. Costs associated with the execution of this training are be at the expense of the Contractor.
1.15.3 Quarterly NERC CIP Security Awareness Program
The Project maintains a quarterly awareness program for personnel requiring unescorted access to areas subject to NERC CIP regulations.
Awareness materials will be furnished by the Project Reliability Compliance Coordinator, and will be distributed to Contractor personnel by the Contractor. Costs associated with the distribution of the security awareness documents are at the expense of the Contractor.
1.15.4 Personnel Requiring Electronic Access to Cyber Assets
In addition to meeting all of the above requirements for unescorted PHYSICAL access, personnel requiring ELECTRONIC access to cyber assets subject to NERC CIP regulations must complete additional NERC CIP training for electronic access, must submit the Government-provided electronic
SECTION 01 10 10.00 25 Page 11 access request form, and must be authorized for electronic access. Each person requiring electronic access must complete the quiz with a passing score of not less than 70 percent. The Project RCC will provide the training, curriculum, and materials. Costs associated with the execution of this training must be at the expense of the Contractor.
1.16 SECURITY TRAINING
Costs associated with the following execution of training and verification requirements must be at the expense of the Contractor. Facilitate the following training and submit the following:
a. AT Level 1 Training - Thirty calendar days prior to mobilization, All Contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access must complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change). Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel. Obtain training DVD from the CO through the Portland District Security Office.
(Estimated training time is ten minutes per individual).
b. iWATCH or CorpsWatch Training - Thirty calendar days prior to mobilization, all Contract personnel must receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides Contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity. Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel. Obtain training DVD from the CO through the Portland District Security Office. (Estimated training time is five minutes per individual).
c. Operations Security (OPSEC) Training - Thirty calendar days prior to mobilization, all Contractor employees, to include subcontractor employees, requiring access to army installations, facilities, and controlled access areas must complete OPSEC Training. Submit a roster of training completion for each Contractor employee and subcontractor employee to the CO within five calendar days after completion of training of all employees and subcontractor personnel. Obtain training DVD from the CO through the Portland District Security Office. (Estimated training time is 15 minutes per individual).
d. Access to Government Information Systems - Register all Contractor, to include subcontractor, employees with access to a Government info system in the ATCTS (Army Training Certification Tracking System) at commencement of services. Each employee and Contractor personnel must complete the following items prior to access to the information systems and annually thereafter in accordance with DA AR 380-67 (Personnel Security Program) and Homeland Security Presidential Directive 12 (Policy for a Common Identification Standard for Federal Employees and Contractors).
(1) Obtain written permission from the Project.
SECTION 01 10 10.00 25 Page 12
(2) A minimum of seven days prior to engaging in work submit, to the CO or Project POC, a Personnel Risk Assessment (PRA) for each employee.
(a) Have a PRA performed which includes a personnel identity verification and local agency criminal check for the prior seven years. A minimum of a seven year criminal background check with the state patrol office must be performed from all States of residence and employment, for the past seven years.
(b) Identity Verification - Contractor employees must provide positive verification of individual identity prior to authorized unescorted access to the Powerhouse. Acceptable forms of identity verification are documents issued by a Federal Government agency that include: the individual's photograph, name, and date of birth, such as a passport or military identification (ID) card.