6. Environmental_Monitoring_Reports (Hamer 2020).pdf

PDF 22 MB Posted

Attached to
Mouth of the Columbia River Sand Island Pile Dikes Repair
Solicitation number
W9127N22B0001
Issued by

About this file

This document provides details for a federal construction contract solicitation for rehabilitation work on four pile dikes at the Mouth of the Columbia River in Oregon. The U.S. Army Corps of Engineers seeks bids to perform work including enhanced enrockment, installation of 24-inch steel pile dikes, and enhanced pile connections based on the attached plans and specifications. The solicitation number is W9127N22B0001 and bids are due in accordance with the provided proposal instructions and terms.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MARINE MAMMAL MONITORING REPORT

Sand Island Pile Dike System Test Piles Project

Prepared for:

U.S Army Corps of Engineers 333 SW First Avenue Portland, OR 97204

Prepared by:

Hamer Environmental L.P.

P.O. Box 2561

Mount Vernon, WA 98273 Email: matt@hamerenvironmental.com

October 27, 2020

Marine Mammal Monitoring Report – Sand Island Test Piles

TABLE OF CONTENTS

MARINE MAMMAL MONITORING REPORT

INTRODUCTION

METHODS

TABLE 1. SHUTDOWN ZONES FOR MARINE MAMMALS DURING PROJECT ACTIVITIES (METERS)

TABLE 2. LEVEL B HARASSMENT MONITORING ZONES DURING PROJECT ACTIVITIES (METERS)

FIGURE 1. LEVEL B MONITORING ZONE FOR VIBRATORY INSTALLATION / REMOVAL

FIGURE 2. LEVEL B MONITORING ZONE FOR IMPACT INSTALLATION

RESULTS

TABLE 3. ACTIVE MONITORING TIMES

TABLE 4. TOTAL AND AUTHORIZED TAKE BY LEVEL A AND LEVEL B HARASSMENT

REFERENCES

APPENDIX A: PILE INSTALLATION & REMOVAL TIMES

APPENDIX B: MARINE MAMMAL OBSERVATIONS DURING SAND ISLAND TEST PROJECT

APPENDIX C: MARINE MAMMAL OBSERVATION RECORD FORMS

INTRODUCTION

In 2020, Hamer Environmental was contracted by Pacific Pile and Marine to conduct Marine Mammal

Monitoring during vibratory and impact pile driving for the Sand Island Test Piles project in the mouth of the Columbia River. Monitoring for Marine Mammals was required by the National Marine

Fisheries Service (NMFS) during pile driving and removal activities for this project as part of an

Incidental Harassment Authorization (IHA) authorized under the Marine Mammal Protection Act

(MMPA). Monitoring for Marine Mammals was conducted on 15 days between September 16 and

October 9.

METHODS

Two Protected Species Observers (PSOs) were required to monitor for marine mammals during all pile installation and removal activities. One PSO was positioned on the barge adjacent to pile installation and removal; the second PSO was stationed on a boat to more effectively search the monitoring zone. Monitoring began at least 30 minutes prior to the initiation of pile removal or installation, and continued until 30 minutes post-completion. Each observer had an unobstructed view of the shutdown and monitoring zone (Table 1 & 2, Figures 1 &2).

If any marine mammals were present within or approaching the shutdown zone during this 30-minute monitoring period, pile installation and removal would be delayed until the marine mammal voluntarily left the shutdown zone for at least 15 minutes. If no marine mammals were seen during the 30-minute monitoring period or if more than 15 minutes had passed since a marine mammal was seen within or approaching the shutdown zone, pile installation and removal was allowed to commence. If increased sea state conditions limit the observers’ ability to see the shutdown and monitoring zones, pile installation and removal would be stopped until visibility improved. If foggy conditions limit the visibility of the PSO’s, pile driving is allowed to commence as long as the PSO’s can fully monitor the shutdown zone.

At the start of any impact work, Pacific Pile and Marine would employ a “soft start” technique, consisting of an initial set of strikes at reduced energy, in order to allow marine mammals to vacate the area. Pile installation and removal was stopped if a marine mammal approached or entered the shutdown zone. In the event of a shutdown of activity resulting from marine mammals in the shutdown zone, marine mammal behavior was monitored and documented until they left of their own volition. Installation and removal work would then be delayed until the marine mammal was visually confirmed to have voluntarily left the shutdown zone or if 15 minutes had passed without the animal being seen. All marine mammal detection information was recorded separately by each observer on a

Marine Mammal Observation Record Form (APPENDIX B & C). Level A Take and Level B

Harassment were recorded according to distance, species class, and activity type as described in the

IHA and in accordance with the MMPA.

Table 1. Shutdown Zones for Marine Mammals during Project Activities (meters).

Activity

Low-

Frequency

Cetacean

Medium-

Frequency

Cetacean

High-

Frequency

Cetacean

Phocid

Pinniped

Otariid

Pinniped

24" Steel Pipe Pile

Impact Installation 890 35 1050 100* 35

24" Steel Pipe

Vibratory Installation 25 25 25 25 25

24" Steel Pipe

Vibratory Removal 25 25 25 25 25

*Level A Harassment zone for harbor seals must extend to 475m during impact driving

Table 2. Level B Harassment Monitoring Zones during Project Activities (meters).

Activity Distance

24" Steel Pipe Pile Impact Installation 1,000

24" Steel Pipe Vibratory Installation 5,420

24" Steel Pipe Vibratory Removal 5,420

24" Timber Pile Vibratory Removal 1,360

Figure 1. Level B Monitoring Zone for Vibratory Installation / Removal

Figure 2. Level B Monitoring Zone for Impact Installation

RESULTS

Marine mammal monitors were onsite for 15 days during the Sand Island Pile Dike Systems Test Piles

Project (Table 3). Vibratory work took place during all 15 of those days, while impact pile installation took place on 9 days, for a total of 40 24-inch steel piles installed. No work was stopped due to poor visibility or other weather conditions that would preclude effective monitoring. Vibratory pile installation and removal occurred for a total of 930 minutes over the 15 days of pile driving, while impact driving lasted for 107 minutes, for a total of 1037 minutes of pile driving during the project

(Appendix A).

Two-hundred eighty-five detections of marine mammals were recorded by observers, for a total of

389 individuals. A detection constituted visually seeing one or more marine mammals of the same species interacting either on their own or in a group. Most detections were of single marine mammals, though large groups of Harbor seals were occasionally seen. Harbor seals were the most common species observed, accounting for 214 of all detections (75%) and a total of 309 individuals (79%), followed by California sea lions with 56 detections (20%) and 61 individuals (16%). Humpback whale, harbor porpoise, and Steller sea lion comprised the remainder of the observations. A detailed record of all marine mammals observed is found in Appendix B.

One to two Humpback whales were seen on occasion during the project, with all but one of the detections occurring outside of pile driving operations. The whales seemed to come through the area with the incoming tides to forage for food and leave with the outgoing tides. In recent years, Humpbacks have been seen foraging in the vicinity of the Astoria-Megler Bridge and off the coast of

McGowan, Washington. One humpback whale was observed in the monitoring zone (5,420 m) during vibratory pile installation at 12:57 on 9/18. Work was immediately stopped while USACE discussed the observation with NMFS. The whale seemed to be transited through the monitoring zone when it was observed. Work re-started after confirmation that work could proceed and more than 15 minutes had passed without the individual being seen. All other observations of humpback whales occurred outside construction activity, and pile driving was delayed until either the animal was observed leaving the monitoring zone or at least 15 minutes had passed without the individual being seen. No other shutdowns occurred during this project. Take and harassment for all other species were within authorized levels (Table 4).

Table 3. Active Monitoring Times.

Date Monitoring Times Wind Speed

(Beaufort Marine Scale)

9/16/2020 1500 - 1645 2

9/17/2020 0758 - 1519 1

9/18/2020 0811 - 1642 1 - 2

9/19/2020 0949 - 1303 2

9/21/2020 0930 - 1130;

1400 - 1600

1 - 2

9/22/2020 0740 - 1727 1 - 2

9/27/2020 0924 - 1749 1

9/28/2020 0740 - 1640 1 - 2

9/29/2020 1300 - 1613 2

9/30/2020 0906 - 1446 1

10/5/2020 0745 - 1715 1

10/6/2020 0850 - 1707 1 - 2

10/7/2020 0815 - 1818 0 - 1

10/8/2020 0750 - 1712 1 - 2

10/9/2020 0744 - 1427 1 - 2

Table 4. Total and Authorized Take by Level A and Level B Harassment.

Species Authorized Level A Take

Total Level A Take

Authorized Level B Take

Total Level B Take

Harbor porpoise 20 0 42 0

California Sea Lion

0 0 3,119 13

Steller Sea Lion 0 0 3,563 0

Harbor Seal 76 2 2,337 106

Humpback Whale

0 0 0 1

REFERENCES

National Marine Fisheries Service. 2007. Marine Mammal Protection Act of 1972 as Amended.

APPENDIX A: PILE INSTALLATION & REMOVAL TIMES

Date Time Activity

9/16/2020 15:35 - 15:39 Vibratory Installation

9/16/2020 15:45 - 15:48 Vibratory Installation

9/17/2020 08:28 - 08:32 Vibratory Removal

9/17/2020 12:56 - 13:14 Vibratory Installation

9/17/2020 13:17 - 13:19 Vibratory Removal

9/17/2020 14:36 - 14:39 Vibratory Installation

9/17/2020 14:41 - 14:43 Vibratory Removal

9/17/2020 14:45 - 14:48 Vibratory Removal

9/18/2020 09:06 - 09:07 Vibratory Installation

9/18/2020 09:08 - 09:23 Vibratory Installation

9/18/2020 09:28 - 09:29 Vibratory Removal

9/18/2020 12:00 - 12:57 Vibratory Installation

9/18/2020 14:24 - 14:34 Vibratory Installation

9/18/2020 14:35 - 14:39 Vibratory Removal

9/18/2020 15:33 - 16:10 Vibratory Installation

9/18/2020 16:10 - 16:11 Vibratory Removal

9/19/2020 10:39 - 10:41 Vibratory Installation

9/19/2020 10:46 - 10:52 Vibratory Installation

9/19/2020 10:57 - 11:03 Vibratory Installation

9/19/2020 11:07 - 11:10 Vibratory Installation

9/21/2020 10:15 - 10:31 Vibratory Installation

9/22/2020 08:27 - 08:29 Vibratory Installation

9/22/2020 08:34 - 08:35 Vibratory Installation

9/22/2020 08:37 - 08:41 Vibratory Installation

9/22/2020 08:43 - 08:54 Vibratory Installation

9/22/2020 08:58 - 09:08 Impact Installation

9/22/2020 09:58 - 09:59 Impact Installation

9/22/2020 10:02 Impact Installation

9/22/2020 10:07 Impact Installation

9/22/2020 10:13 - 10:15 Impact Installation

9/22/2020 10:21 Impact Installation

9/22/2020 11:11 - 11:17 Vibratory Removal

9/22/2020 11:57 - 12:13 Vibratory Installation

9/22/2020 12:37 Impact Installation

9/22/2020 12:58 - 13:01 Impact Installation

9/22/2020 14:55 - 15:39 Vibratory Installation

9/22/2020 16:22 - 16:26 Impact Installation

9/22/2020 16:32 - 16:35 Impact Installation

9/22/2020 16:52 - 16:57 Vibratory Removal

9/27/2020 10:26 - 10:29 Vibratory Removal

9/27/2020 10:45 - 10:57 Vibratory Installation

9/27/2020 12:02 - 12:34 Vibratory Installation

9/27/2020 14:13 - 14:16 Impact Installation

9/27/2020 14:46 Vibratory Removal

9/27/2020 15:19 - 15:24 Vibratory Removal

9/27/2020 15:28 - 15:36 Vibratory Removal

9/27/2020 17:01 - 17:19 Vibratory Installation

9/28/2020 09:29 - 10:12 Vibratory Installation

9/28/2020 12:00 - 12:28 Vibratory Installation

9/28/2020 14:14 - 14:15 Impact Installation

9/28/2020 14:22 - 14:23 Impact Installation

9/28/2020 14:39 Impact Installation

9/28/2020 15:19 - 15:21 Impact Installation

9/28/2020 15:40 - 15:41 Vibratory Removal

9/28/2020 15:49 - 15:51 Vibratory Removal

9/28/2020 16:03 - 16:07 Vibratory Removal

9/29/2020 13:58 - 14:56 Vibratory Installation

9/29/2020 15:06 - 15:23 Vibratory Installation

9/30/2020 09:43 - 09:48 Vibratory Installation

9/30/2020 09:52 - 10:09 Vibratory Installation

9/30/2020 10:49 Impact Installation

9/30/2020 10:52 - 10:54 Impact Installation

9/30/2020 11:07 Impact Installation

9/30/2020 11:21 - 11:22 Impact Installation

9/30/2020 11:41 - 11:43 Vibratory Removal

9/30/2020 11:47 Vibratory Removal

9/30/2020 13:14 - 13:24 Vibratory Installation

9/30/2020 13:59 Impact Installation

9/30/2020 14:12 - 14:14 Impact Installation

10/5/2020 09:13 - 09:37 Vibratory Installation

10/5/2020 10:18 Impact Installation

10/5/2020 10:19 - 10:20 Impact Installation

10/5/2020 11:25 - 11:26 Vibratory Removal

10/5/2020 12:12 - 12:25 Vibratory Installation

10/5/2020 13:27 - 13:29 Impact Installation

10/5/2020 13:44 Impact Installation

10/5/2020 13:50 Impact Installation

10/5/2020 14:04 - 14:05 Vibratory Removal

10/5/2020 16:16 - 16:17 Impact Installation

10/5/2020 16:22 - 16:25 Impact Installation

10/5/2020 16:41 - 16:44 Vibratory Removal

10/6/2020 10:44 Vibratory Installation

10/6/2020 10:54 - 11:08 Vibratory Installation

10/6/2020 11:15 Vibratory Removal

10/6/2020 12:12 - 12:17 Vibratory Installation

10/6/2020 13:57 - 14:03 Vibratory Installation

10/6/2020 15:42 - 15:44 Vibratory Installation

10/6/2020 15:48 - 15:51 Vibratory Removal

10/6/2020 16:34 - 16:37 Impact Installation

10/7/2020 08:47 - 08:49 Vibratory Removal

10/7/2020 08:51 Vibratory Removal

10/7/2020 08:57 - 09:11 Vibratory Installation

10/7/2020 09:14 Vibratory Removal

10/7/2020 15:00 Vibratory Installation

10/7/2020 15:05 Vibratory Installation

10/7/2020 15:09 - 15:19 Vibratory Installation

10/7/2020 15:37 - 15:41 Impact Installation

10/7/2020 15:47 - 15:48 Impact Installation

10/7/2020 17:09 - 17:12 Vibratory Removal

10/7/2020 17:23 - 17:25 Vibratory Removal

10/7/2020 17:37 - 17:48 Vibratory Removal

10/8/2020 08:29 - 08:37 Vibratory Installation

10/8/2020 08:40 - 08:41 Vibratory Installation

10/8/2020 08:55 - 09:02 Vibratory Installation

10/8/2020 09:04 - 09:07 Vibratory Installation

10/8/2020 09:15 - 09:20 Vibratory Installation

10/8/2020 10:01 - 10:03 Impact Installation

10/8/2020 10:11 - 10:13 Impact Installation

10/8/2020 10:58 - 11:01 Vibratory Removal

10/8/2020 11:08 - 11:25 Vibratory Installation

10/8/2020 11:55 - 11:57 Impact Installation

10/8/2020 12:29 - 12:50 Vibratory Installation

10/8/2020 13:50 - 13:51 Impact Installation

10/8/2020 13:58 Impact Installation

10/8/2020 14:15 - 14:17 Vibratory Removal

10/8/2020 14:20 Vibratory Removal

10/8/2020 14:25 - 14:27 Vibratory Removal

10/8/2020 14:31 Vibratory Removal

10/8/2020 15:35 - 16:06 Vibratory Installation

10/8/2020 16:36 - 16:38 Impact Installation

10/8/2020 16:42 Impact Installation

10/9/2020 08:14 - 08:43 Vibratory Installation

10/9/2020 09:11 Impact Installation

10/9/2020 09:14 - 09:16 Impact Installation

10/9/2020 09:20 - 09:22 Impact Installation

10/9/2020 09:37 - 09:39 Vibratory Removal

10/9/2020 09:41 Vibratory Removal

10/9/2020 09:44 - 09:47 Vibratory Removal

10/9/2020 09:50 Vibratory Removal

10/9/2020 11:00 - 11:08 Vibratory Installation

10/9/2020 11:36 - 11:37 Impact Installation

10/9/2020 12:11 - 12:38 Vibratory Installation

10/9/2020 13:10 Impact Installation

10/9/2020 13:45 Vibratory Removal

10/9/2020 13:49 Vibratory Removal

10/9/2020 13:53 - 13:54 Vibratory Removal

10/9/2020 13:57 Vibratory Removal

APPENDIX B: MARINE MAMMAL OBSERVATIONS DURING SAND

ISLAND TEST PROJECT.

Date Observer Species Time Number of Individuals

Direction/ Bearing

Distance (meters)

Construction Activity

9/16/2020 Case Wyatt Harbor Seal 15:06 1 SSW 250 no construction

9/16/2020 Kerry Lyons California Sea

Lion 15:10 2 160 50 no construction

9/16/2020 Case Wyatt Harbor Seal 15:16 1 NW 120 no construction

9/16/2020 Kerry Lyons Harbor

Porpoise 15:19 1 240 150 no construction

9/16/2020 Case Wyatt Harbor Seal 15:23 1 N 100 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:23 1 240 150 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:23 1 180 100 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:29 1 100 120 no construction

9/16/2020 Case Wyatt Harbor Seal 15:30 1 ESE 110 no construction

9/16/2020 Case Wyatt California Sea

Lion 15:31 1 N 100 no construction

9/16/2020 Case Wyatt California Sea

Lion 15:32 1 W 220 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:32 1 160 250 no construction

9/16/2020 Kerry Lyons California Sea

Lion 15:34 1 180 250 no construction

9/16/2020 Case Wyatt Harbor Seal 15:37 1 NE 85 vibratory installation

9/16/2020 Case Wyatt Harbor Seal 15:43 1 N 80 no construction

9/16/2020 Case Wyatt Harbor Seal 15:46 1 N 300 vibratory installation

9/16/2020 Case Wyatt California Sea

Lion 15:55 1 E 400 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:03 1 340 150 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:06 1 200 200 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:15 1 270 250 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:01 1 90 80 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:04 1 60 120 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:11 1 290 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 8:26 1 W 50 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:28 1 330 150 vibratory removal

9/17/2020 Kendra Ritchie

Harbor Seal 8:50 1 NW 30 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:54 1 270 150 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:00 1 250 350 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:08 1 190 200 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:17 1 220 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 9:21 1 ESE 40 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:48 1 180 80 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:08 1 340 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 10:14 1 SW 60 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:18 1 120 400 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 10:21 1 S 70 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:23 2 140 400 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 10:27 6 WNW 200 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 10:32 1 SSE 40 no construction

9/17/2020 Kerry Lyons Humpback

Whale 10:36 2 160 500 no construction

9/17/2020 Kendra Ritchie

Humpback Whale

10:40 2 SE 180 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:41 2 150 600 no construction

9/17/2020 Kendra Ritchie

Harbor Porpoise

11:10 2 S 20 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 12:15 1 W 60 no construction

9/17/2020 Kendra Ritchie

California Sea Lion

12:20 1 SW 40 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 12:49 2 SW 40 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 12:51 3 W 50 no construction

9/17/2020 Kerry Lyons Harbor Seal 13:00 1 200 200 vibratory installation

9/17/2020 Kerry Lyons Harbor Seal 13:30 1 120 150 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 13:32 2 NNW 60 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 13:39 1 S 150 no construction

9/17/2020 Kerry Lyons Harbor Seal 13:52 2 45 150 no construction

9/17/2020 Kerry Lyons Harbor Seal 13:56 1 120 150 no construction

9/17/2020 Kerry Lyons Harbor Seal 14:18 1 170 200 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 14:21 1 W 40 no construction

9/17/2020 Kerry Lyons California Sea

Lion 14:58 1 200 200 no construction

9/17/2020 Kendra Ritchie

California Sea Lion

15:00 1 W 100 no construction

9/17/2020 Kerry Lyons Harbor Seal 15:00 1 180 200 no construction

9/17/2020 Kerry Lyons Harbor Seal 15:07 1 0 300 no construction

9/18/2020 Case Wyatt California Sea

Lion 8:07 1 SW 110 no construction

9/18/2020 Case Wyatt Harbor Seal 8:18 1 W 120 no construction

9/18/2020 Case Wyatt California Sea

Lion 8:21 1 E 10 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 8:22 1 ESE 300 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 8:30 1 SSW 400 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 8:34 1 SSW 600 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 8:37 1 SW 800 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 8:44 2 SE 550 no construction

9/18/2020 Kendra Ritchie

California Sea Lion

8:59 1 W 300 no construction

9/18/2020 Case Wyatt California Sea

Lion

9:06 1 SSE 40

vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 9:19 1 SE 300 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 9:26 1 S 150 no construction

9/18/2020 Case Wyatt Harbor Seal 10:14 1 E 35 no construction

9/18/2020 Case Wyatt Harbor Seal 10:22 1 ESE 150 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 10:29 1 SE 300 no construction

9/18/2020 Kendra Ritchie

Humpback Whale

10:36 1 W 500 no construction

9/18/2020 Case Wyatt Harbor Seal 10:39 2 WSW 180 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 10:43 1 W 600 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 10:51 1 W 500 no construction

9/18/2020 Kendra Ritchie

California Sea Lion

11:27 1 S 30 no construction

9/18/2020 Case Wyatt Harbor Seal 11:56 3 NW 40 no construction

9/18/2020 Case Wyatt Harbor Seal 11:56 3 SW 40 no construction

9/18/2020 Case Wyatt Harbor Seal 12:00 1 NE 150 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:02 3 SE 250 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 12:09 1 WSW 70 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:12 1 E 215 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 12:16 1 NW 90 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:17 1 NE 200 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:17 1 NE 110 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:19 1 SW 100 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 12:23 1 SE 200 vibratory installation

9/18/2020 Case Wyatt Harbor Seal 12:36 2 S 200 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 12:45 2 W 60 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 12:53 1 S 90 vibratory installation

9/18/2020 Kendra Ritchie

Humpback Whale

12:57 1 SW 700

vibratory installation

9/18/2020 Case Wyatt California Sea

Lion 13:05 1 S 165 no construction

9/18/2020 Case Wyatt California Sea

Lion 13:52 1 SW 300 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 14:32 1 S 300 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 14:35 2 SW 300 vibratory removal

9/18/2020 Case Wyatt Harbor Seal 14:39 10 NW 100 vibratory removal

9/18/2020 Kendra Ritchie

Harbor Seal 14:39 43 SSW 60 vibratory removal

9/18/2020 Kendra Ritchie

Harbor Porpoise

14:56 1 SW 100 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:01 2 NE 90 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:05 3 NW 150 no construction

9/18/2020 Kendra

Harbor Seal 15:13 1 W 120 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:15 2 S 90 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:22 1 E 200 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:24 3 SE 150 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:28 1 E 90 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 15:45 1 SE 200 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 16:02 1 E 300 vibratory installation

9/18/2020 Kendra Ritchie

Harbor Seal 16:15 1 SE 400 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 16:19 1 NW 400 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 16:27 1 SW 150 no construction

9/18/2020 Kendra Ritchie

Harbor Seal 16:36 1 SSW 100 no construction

9/19/2020 Case Wyatt Harbor Seal 10:11 1 NE 60 no construction

9/19/2020 Case Wyatt California Sea

Lion 10:23 1 W 280 no construction

9/19/2020 Kendra Ritchie

Harbor Seal 10:32 1 E 150 no construction

9/19/2020 Kendra Ritchie

Humpback Whale

11:15 1 SSE 700 no construction

9/19/2020 Kendra Ritchie

Harbor Seal 11:50 1 NE 400 no construction

9/19/2020 Case Wyatt Harbor Seal 11:51 1 NE 100 no construction

9/19/2020 Case Wyatt Harbor Seal 12:47 1 ESE 100 no construction

9/21/2020 Case Wyatt Harbor Seal 9:29 1 E 170 no construction

9/21/2020 Kerry Lyons Harbor Seal 10:15 1 100 250 vibratory installation

9/21/2020 Case Wyatt Harbor Seal 10:39 1 N 230 no construction

9/21/2020 Kerry Lyons Harbor Seal 11:02 1 220 450 no construction

9/21/2020 Kerry Lyons Harbor Seal 11:37 1 180 300 no construction

9/21/2020 Case Wyatt Harbor Seal 13:18 1 S 100 no construction

9/21/2020 Case Wyatt Humpback

Whale 13:39 1 SW 220 no construction

9/21/2020 Case Wyatt California Sea

Lion 14:09 1 N 275 no construction

9/21/2020 Kerry Lyons California Sea

Lion 14:23 1 30 80 no construction

9/21/2020 Kerry Lyons Harbor Seal 15:00 1 100 100 no construction

9/22/2020 Kerry Lyons Harbor Seal 8:22 1 110 100 no construction

9/22/2020 Case Wyatt Harbor Seal 8:28 1 SW 120 vibratory installation

9/22/2020 Kerry Lyons Harbor Seal 8:33 1 180 300 no construction

9/22/2020 Kerry Lyons Harbor Seal 8:49 1 160 100 vibratory installation

9/22/2020 Case Wyatt Harbor Seal 8:52 1 SE 110 vibratory installation

9/22/2020 Kerry Lyons California Sea

Lion 9:00 1 270 200 impact installation

9/22/2020 Kerry Lyons Harbor Seal 9:08 1 220 250 no construction

9/22/2020 Kerry Lyons Harbor Seal 9:14 1 160 250 no construction

9/22/2020 Kerry Lyons Harbor Seal 9:34 1 170 240 no construction

9/22/2020 Kerry Lyons Humpback

Whale 9:35 1 180 650 no construction

9/22/2020 Case Wyatt Harbor Seal 9:48 2 SE 475 no construction

9/22/2020 Case Wyatt Harbor Seal 9:51 1 ESE 150 no construction

9/22/2020 Case Wyatt Harbor Seal 9:56 1 ESE 460 no construction

9/22/2020 Kerry Lyons Harbor Seal 9:58 1 210 450 no construction

9/22/2020 Kerry Lyons Harbor Seal 10:02 1 190 600 impact installation

9/22/2020 Kerry Lyons Harbor Seal 10:07 1 120 550 impact installation

9/22/2020 Case Wyatt California Sea

Lion 10:39 1 NW 175 no construction

9/22/2020 Case Wyatt Harbor Seal 10:44 1 N 190 no construction

9/22/2020 Kerry Lyons Harbor Seal 11:00 2 200 300 no construction

9/22/2020 Case Wyatt Harbor Seal 11:08 1 WNW 100 no construction

9/22/2020 Case Wyatt Harbor Seal 11:12 1 S 100 vibratory removal

9/22/2020 Case Wyatt California Sea

Lion 11:45 1 SE 280 no construction

9/22/2020 Kerry Lyons California Sea

Lion 12:24 1 220 300 no construction

9/22/2020 Case Wyatt Harbor Seal 12:28 1 WSW 190 no construction

9/22/2020 Kerry Lyons Harbor Seal 12:30 1 190 500 no construction

9/22/2020 Kerry Lyons Harbor Seal 12:36 1 220 300 no construction

9/22/2020 Case Wyatt Harbor Seal 14:07 1 WWS 65 no construction

9/22/2020 Kerry Lyons Harbor Seal 14:51 1 270 100 no construction

9/22/2020 Kerry Lyons Harbor Seal 15:09 1 180 250 vibratory installation

9/22/2020 Case Wyatt California Sea

Lion 15:22 1 N 300 vibratory installation

9/22/2020 Kerry Lyons California Sea

Lion 15:38 1 200 200 vibratory installation

9/22/2020 Case Wyatt Harbor Seal 15:43 1 NE 300 no construction

9/22/2020 Case Wyatt Harbor Seal 15:48 1 WSW 200 no construction

9/22/2020 Kerry Lyons Harbor Seal 15:55 1 180 500 no construction

9/22/2020 Kerry Lyons Harbor Seal 16:11 1 180 250 no construction

9/22/2020 Case Wyatt Harbor Seal 16:46 1 ENE 450 no construction

9/27/2020 Case Wyatt Harbor Seal 9:43 2 W 190 no construction

9/27/2020 Case Wyatt Harbor Seal 9:46 1 ESE 120 no construction

9/27/2020 Case Wyatt Harbor Seal 9:59 2 S 120 no construction

9/27/2020 Case Wyatt Harbor Seal 10:28 1 SW 210 vibratory removal

9/27/2020 Case Wyatt Harbor Seal 10:29 1 S 230 vibratory removal

9/27/2020 Case Wyatt Harbor Seal 10:38 1 WSW 220 no construction

9/27/2020 Kerry Lyons Harbor Seal 10:38 1 160 250 no construction

9/27/2020 Kerry Lyons Harbor Seal 10:42 1 200 400 no construction

9/27/2020 Kerry Lyons Harbor Seal 10:50 1 170 200 vibratory installation

9/27/2020 Kerry Lyons Harbor Seal 11:05 1 220 400 no construction

9/27/2020 Kerry Lyons Harbor Seal 11:20 1 180 400 no construction

9/27/2020 Kerry Lyons Harbor Seal 11:45 2 160 350 no construction

9/27/2020 Case Wyatt California Sea

Lion 11:57 1 ESE 60 no construction

9/27/2020 Kerry Lyons Harbor Seal 12:00 1 220 500 no construction

9/27/2020 Case Wyatt Harbor Seal 12:04 1 E 50 vibratory installation

9/27/2020 Kerry Lyons Harbor Seal 12:30 1 300 75 vibratory installation

9/27/2020 Case Wyatt Harbor Seal 12:47 1 SW 185 no construction

9/27/2020 Kerry Lyons Harbor Seal 13:37 1 270 100 no construction

9/27/2020 Case Wyatt California Sea

Lion 13:54 1 S 100 no construction

9/27/2020 Kerry Lyons Harbor Seal 15:32 1 160 150 vibratory removal

9/27/2020 Kerry Lyons Harbor Seal 15:51 1 280 150 no construction

9/28/2020 Case Wyatt Harbor Seal 9:08 1 N 120 no construction

9/28/2020 Case Wyatt Harbor Seal 9:35 1 ENE 50 vibratory installation

9/28/2020 Case Wyatt California Sea

Lion 9:50 1 N 125 vibratory installation

9/28/2020 Kerry Lyons Harbor Seal 10:05 1 120 150 vibratory installation

9/28/2020 Kerry Lyons Harbor Seal 10:12 1 150 200 vibratory installation

9/28/2020 Kerry Lyons Harbor Seal 11:28 2 10 50 no construction

9/28/2020 Kerry Lyons California Sea

Lion 11:30 1 10 150 no construction

9/28/2020 Case Wyatt Harbor Seal 12:57 1 SW 110 no construction

9/28/2020 Case Wyatt California Sea

Lion 13:44 1 SW 250 no construction

9/28/2020 Case Wyatt Harbor Seal 13:51 1 S 110 no construction

9/28/2020 Kerry Lyons Harbor Seal 14:10 1 160 250 no construction

9/28/2020 Case Wyatt Harbor Seal 14:15 1 NE 275 impact installation

9/28/2020 Kerry Lyons Harbor Seal 15:11 1 200 300 no construction

9/28/2020 Kerry Lyons Harbor Seal 15:15 1 200 100 no construction

9/28/2020 Kerry Lyons Harbor Seal 15:31 1 200 200 no construction

9/28/2020 Case Wyatt California Sea

Lion 16:26 1 WNW 180 no construction

9/29/2020 Case Wyatt California Sea

Lion 13:47 1 SE 180 no construction

9/29/2020 Kerry Lyons Harbor Seal 14:08 1 200 200 vibratory installation

9/29/2020 Case Wyatt California Sea

Lion 16:00 1 W 300 no construction

9/30/2020 Kendra Ritchie

Harbor Seal 9:13 1 SE 60 no construction

9/30/2020 Steve Crane Harbor

Porpoise 9:29 1 S 125 no construction

9/30/2020 Kendra Ritchie

Harbor Seal 11:14 1 ESE 400 no construction

9/30/2020 Steve Crane California Sea

Lion 11:17 1 S 100 no construction

9/30/2020 Kendra Ritchie

California Sea Lion

11:24 1 WSW 400 no construction

9/30/2020 Kendra Ritchie

Harbor Seal 11:26 1 ESE 500 no construction

9/30/2020 Steve Crane Harbor Seal 11:39 1 E 125 no construction

9/30/2020 Steve Crane Harbor Seal 12:06 1 SE 175 no construction

9/30/2020 Steve Crane California Sea

Lion 12:10 1 E 150 no construction

9/30/2020 Steve Crane Harbor Seal 12:23 1 W 300 no construction

9/30/2020 Steve Crane California Sea

Lion 12:24 1 S 50 no construction

9/30/2020 Steve Crane Harbor Seal 12:54 1 SE 250 no construction

9/30/2020 Steve Crane Harbor Seal 13:11 2 N 150 no construction

9/30/2020 Kendra Ritchie

Harbor Seal 13:36 1 W 300 no construction

9/30/2020 Kendra Ritchie

Harbor Seal 13:46 1 S 400 no construction

10/5/2020 Case Wyatt Harbor Seal 9:06 1 NE 100 no construction

10/5/2020 Case Wyatt Harbor Seal 9:15 1 NE 200 vibratory installation

10/5/2020 Kerry Lyons Harbor Seal 11:47 1 200 500 no construction

10/5/2020 Kerry Lyons Harbor Seal 12:04 1 200 400 no construction

10/5/2020 Case Wyatt Harbor Seal 12:08 1 SE 320 no construction

10/6/2020 Kerry Lyons Harbor Seal 10:52 1 150 150 no construction

10/6/2020 Case Wyatt California Sea

Lion

10:56 1 ENE 300

vibratory installation

10/6/2020 Case Wyatt California Sea

Lion

11:04 1 NNE 230

vibratory installation

10/6/2020 Kerry Lyons California Sea

Lion 11:06 1 190 200 vibratory installation

10/6/2020 Case Wyatt California Sea

Lion 11:20 1 S 200 no construction

10/6/2020 Kerry Lyons Harbor Seal 11:45 1 180 100 no construction

10/6/2020 Kerry Lyons Harbor Seal 12:17 1 120 250 no construction

10/6/2020 Case Wyatt Harbor Seal 12:30 1 SE 250 no construction

10/6/2020 Case Wyatt Harbor Seal 13:30 1 S 180 no construction

10/6/2020 Case Wyatt California Sea

Lion 13:37 1 S 220 no construction

10/6/2020 Kerry Lyons California Sea

Lion 13:46 1 200 100 no construction

10/6/2020 Case Wyatt Harbor Seal 13:59 1 SE 400 vibratory installation

10/6/2020 Case Wyatt Harbor Seal 14:17 1 WSW 200 no construction

10/6/2020 Kerry Lyons Harbor Seal 14:24 1 100 300 no construction

10/6/2020 Kerry Lyons California Sea

Lion 14:45 2 200 600 no construction

10/6/2020 Kerry Lyons Harbor Seal 16:01 1 260 500 no construction

10/7/2020 Kerry Lyons California Sea

Lion 10:11 1 240 150 no construction

10/7/2020 Kerry Lyons California Sea

Lion 12:28 1 180 70 no construction

10/7/2020 Case Wyatt California Sea

Lion 13:45 1 S 110 no construction

10/7/2020 Case Wyatt California Sea

Lion 13:45 2 NNE 250 no construction

10/7/2020 Kerry Lyons Harbor

Porpoise 13:52 1 200 150 no construction

10/7/2020 Case Wyatt Stellar's Sea

Lion 14:12 1 NW 220 no construction

10/7/2020 Case Wyatt Harbor Seal 14:40 1 NE 60 no construction

10/7/2020 Case Wyatt Stellar's Sea

Lion 14:42 1 NNE 30 no construction

10/7/2020 Case Wyatt California Sea

Lion

15:00 2 NNE 200

vibratory installation

10/7/2020 Case Wyatt Harbor Seal 16:14 1 NW 220 no construction

10/7/2020 Case Wyatt Harbor Seal 17:03 1 SE 80 no construction

10/7/2020 Case Wyatt Harbor Seal 17:09 1 SE 80 vibratory installation

10/7/2020 Case Wyatt California Sea

Lion 17:23 1 E 75 vibratory installation

10/7/2020 Case Wyatt Harbor Seal 18:10 1 SSW 180 no construction

10/8/2020 Steve Crane Harbor Seal 7:51 1 SW 60 no construction

10/8/2020 Kendra Ritchie

Harbor Seal 7:58 1 S 600 no construction

10/8/2020 Steve Crane Harbor Seal 8:02 3 S 100 no construction

10/8/2020 Kendra Ritchie

Harbor Porpoise

8:07 2 W 500 no construction

10/8/2020 Steve Crane California Sea

Lion 8:15 1 N 125 no construction

10/8/2020 Kendra Ritchie

Harbor Seal 8:23 1 E 300 no construction

10/8/2020 Kendra Ritchie

Harbor Seal 8:34 1 NW 600 vibratory installation

10/8/2020 Kendra Ritchie

Harbor Seal 9:15 1 N 700 vibratory installation

10/8/2020 Kendra Ritchie

California Sea Lion

10:17 1 W 600 no construction

10/8/2020 Kendra Ritchie

California Sea Lion

12:05 1 SSW 700 no construction

10/8/2020 Steve Crane California Sea

Lion 13:26 2 N 100 no construction

10/8/2020 Kendra Ritchie

California Sea Lion

16:37 1 SSE 500 impact installation

10/8/2020 Steve Crane California Sea

Lion 16:38 1 SE 250 impact installation

10/9/2020 Kendra Ritchie

Harbor Seal 8:06 5 ESE 40 no construction

10/9/2020 Kerry Lyons Harbor Seal 8:12 2 180 150 no construction

10/9/2020 Kerry Lyons Harbor Seal 8:13 1 100 100 no construction

10/9/2020 Kendra Ritchie

Harbor Seal 8:23 1 ESE 70 vibratory installation

10/9/2020 Kerry Lyons Harbor Seal 8:30 1 180 100 vibratory installation

10/9/2020 Kerry Lyons Harbor Seal 8:52 1 240 200 no construction

10/9/2020 Kendra Ritchie

Harbor Seal 8:52 1 S 50 no construction

10/9/2020 Kerry Lyons Harbor Seal 9:14 1 260 250 impact installation

10/9/2020 Kendra Ritchie

California Sea Lion

10:05 1 N 75 no construction

10/9/2020 Kendra Ritchie

Harbor Seal 10:36 1 N 400 no construction

10/9/2020 Kerry Lyons Harbor Seal 11:21 1 70 100 no construction

10/9/2020 Kerry Lyons Harbor Seal 12:13 1 300 150 vibratory installation

10/9/2020 Kendra Ritchie

Harbor Seal 13:49 1 NNE 250 vibratory removal

10/9/2020 Kendra Ritchie

Harbor Seal 14:12 1 ESE 100 no construction

10/9/2020 Kerry Lyons Harbor Seal 14:22 2 260 50 no construction

APPENDIX C: MARINE MAMMAL OBSERVATION RECORD FORMS.

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-0; the proponent agency is CECW-CE

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO: FROM: CONTRACT NO. THIS IS A:

PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal) THIS TRANSMITTAL IS FOR: (Check one)

DATE TRANSMITTAL NO.

RESUBMITTAL OF

TRANSMITTAL 01 57 19.00 25-2

11/16/2020 01 57 19.00 25-2.1

MCR Sand Island Test Piles, Mouth of the Columbia River, Clatsop County OR

01 57 19.00 25-

W9127N20C0018

VANCOUVER RESIDENT OFFICE

4480 SE COLUMBIA WAY

VANCOUVER, WA 98661-5570

Duwamish-Pacific Joint Venture 6627 Ellis Ave S Seattle WA98108-3521

FIO GA DA CR DA/CR DA/GA S

ITEM NO.

(See Note

3) a.

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc) b.

SUBMITTAL TYPE CODE

(See Note 8) c.

NO. OF

COPIES

d.

CONTRACT REFERENCE

DOCUMENT

SPEC. PARA

NO.

e.

DRAWING

SHEET NO.

f.

FOR

CONTRACTOR

USE

g.

VARIATION

(See

Instruction No.

6) h.

FOR CE USE

CODE

(Note 9) i.

2 Marine Mammal Observation Sheet 06 - TEST REPORTS 0 3.1.2 A No Remarks from Contractor

ENCLOSURES RETURNED (List by item No.) DATE

SECTION II - APPROVAL ACTION

NAME, TITLE AND SIGNATURE OF APPROVING AUTHORITY

I certify that the above submitted items have been reviewed in detail and are correct and in the strict conformance with the contract drawings and specifications except as otherwise stated.

NAME AND SIGNATURE OF CONTRACTOR

ENG FORM 4025-R, JUL 2015 REPLACES EDITION OF MAR 2012, WHICH IS OBSOLETEPage 1 of 1

Digitally signed by zachm@duwamishservices.com Date: 2020.11.16 08:47:12 -08:00

P.O. Box 2561

Mount Vernon, WA 98273

MARINE MAMMAL MONITORING REPORT

INTRODUCTION

METHODS

TABLE 1. SHUTDOWN ZONES FOR MARINE MAMMALS DURING PROJECT ACTIVITIES (METERS)

TABLE 2. LEVEL B HARASSMENT MONITORING ZONES DURING PROJECT ACTIVITIES (METERS)

FIGURE 1. LEVEL B MONITORING ZONE FOR VIBRATORY INSTALLATION / REMOVAL

FIGURE 2. LEVEL B MONITORING ZONE FOR IMPACT INSTALLATION

RESULTS

TABLE 3. ACTIVE MONITORING TIMES

TABLE 4. TOTAL AND AUTHORIZED TAKE BY LEVEL A AND LEVEL B HARASSMENT

REFERENCES

APPENDIX A: PILE INSTALLATION & REMOVAL TIMES

APPENDIX B: MARINE MAMMAL OBSERVATIONS DURING SAND ISLAND TEST PROJECT

APPENDIX C: MARINE MAMMAL OBSERVATION RECORD FORMS

In 2020, Hamer Environmental was contracted by Pacific Pile and Marine to conduct Marine Mammal

Monitoring during vibratory and impact pile driving for the Sand Island Test Piles project in the mouth of the Columbia River. Monitoring for Marine Mammals was required by the National Marine

Fisheries Service (NMFS) during pile driving and removal activities for this project as part of an

Incidental Harassment Authorization (IHA) authorized under the Marine Mammal Protection Act

(MMPA). Monitoring for Marine Mammals was conducted on 15 days between September 16 and

October 9.

METHODS

Two Protected Species Observers (PSOs) were required to monitor for marine mammals during all pile installation and removal activities. One PSO was positioned on the barge adjacent to pile installation and removal; the second PSO was stationed on a boat to more effectively search the monitoring zone. Monitoring began at least 30 minutes prior to the initiation of pile removal or installation, and continued until 30 minutes post-completion. Each observer had an unobstructed view of the shutdown and monitoring zone (Table 1 & 2, Figures 1 &2).

If any marine mammals were present within or approaching the shutdown zone during this 30-minute monitoring period, pile installation and removal would be delayed until the marine mammal voluntarily left the shutdown zone for at least 15 minutes. If no marine mammals were seen during the 30-minute monitoring period or if more than 15 minutes had passed since a marine mammal was seen within or approaching the shutdown zone, pile installation and removal was allowed to commence. If increased sea state conditions limit the observers’ ability to see the shutdown and monitoring zones, pile installation and removal would be stopped until visibility improved. If foggy conditions limit the visibility of the PSO’s, pile driving is allowed to commence as long as the PSO’s can fully monitor the shutdown zone.

At the start of any impact work, Pacific Pile and Marine would employ a “soft start” technique, consisting of an initial set of strikes at reduced energy, in order to allow marine mammals to vacate the area. Pile installation and removal was stopped if a marine mammal approached or entered the shutdown zone. In the event of a shutdown of activity resulting from marine mammals in the shutdown zone, marine mammal behavior was monitored and documented until they left of their own volition. Installation and removal work would then be delayed until the marine mammal was visually confirmed to have voluntarily left the shutdown zone or if 15 minutes had passed without the animal being seen. All marine mammal detection information was recorded separately by each observer on a

Marine Mammal Observation Record Form (APPENDIX B & C). Level A Take and Level B

Harassment were recorded according to distance, species class, and activity type as described in the

IHA and in accordance with the MMPA.

Low-

Frequency

Cetacean

Medium-

Frequency

Cetacean

High-

Frequency

Cetacean

Phocid

Pinniped

Otariid

Pinniped

24" Steel Pipe Pile

Impact Installation 890 35 1050 100* 35

24" Steel Pipe

Vibratory Installation 25 25 25 25 25

24" Steel Pipe

Vibratory Removal

24" Steel Pipe Pile Impact Installation 1,000

24" Steel Pipe Vibratory Installation 5,420

Marine mammal monitors were onsite for 15 days during the Sand Island Pile Dike Systems Test Piles

Project (Table 3). Vibratory work took place during all 15 of those days, while impact pile installation took place on 9 days, for a total of 40 24-inch steel piles installed. No work was stopped due to poor visibility or other weather conditions that would preclude effective monitoring. Vibratory pile installation and removal occurred for a total of 930 minutes over the 15 days of pile driving, while impact driving lasted for 107 minutes, for a total of 1037 minutes of pile driving during the project

(Appendix A).

Two-hundred eighty-five detections of marine mammals were recorded by observers, for a total of

389 individuals. A detection constituted visually seeing one or more marine mammals of the same species interacting either on their own or in a group. Most detections were of single marine mammals, though large groups of Harbor seals were occasionally seen. Harbor seals were the most common species observed, accounting for 214 of all detections (75%) and a total of 309 individuals (79%), followed by California sea lions with 56 detections (20%) and 61 individuals (16%). Humpback whale, harbor porpoise, and Steller sea lion comprised the remainder of the observations. A detailed record of all marine mammals observed is found in Appendix B.

One to two Humpback whales were seen on occasion during the project, with all but one of the detections occurring outside of pile driving operations. The whales seemed to come through the area with the incoming tides to forage for food and leave with the outgoing tides. In recent years, Humpbacks have been seen foraging in the vicinity of the Astoria-Megler Bridge and off the coast of

McGowan, Washington. One humpback whale was observed in the monitoring zone (5,420 m) during vibratory pile installation at 12:57 on 9/18. Work was immediately stopped while USACE discussed the observation with NMFS. The whale seemed to be transited through the monitoring zone when it was observed. Work re-started after confirmation that work could proceed and more than 15 minutes had passed without the individual being seen. All other observations of humpback whales occurred outside construction activity, and pile driving was delayed until either the animal was observed leaving the monitoring zone or at least 15 minutes had passed without the individual being seen. No other shutdowns occurred during this project. Take and harassment for all other species were within authorized levels (Table 4).

Date Monitoring Times Wind Speed

(Beaufort Marine Scale)

9/16/2020 1500 - 1645 2

9/17/2020 0758 - 1519 1

9/18/2020 0811 - 1642 1 - 2

9/19/2020 0949 - 1303 2

9/21/2020 0930 - 1130;

1400 - 1600

1 - 2

9/22/2020 0740 - 1727 1 - 2

9/27/2020 0924 - 1749 1

9/28/2020 0740 - 1640 1 - 2

9/29/2020 1300 - 1613 2

9/30/2020 0906 - 1446 1

10/5/2020 0745 - 1715 1

10/6/2020 0850 - 1707 1 - 2

10/7/2020 0815 - 1818 0 - 1

Species Authorized Level A Take

Total Level A Take

Authorized Level B Take

Total Level B Take

Harbor porpoise 20 0 42 0

California Sea Lion

0 0 3,119 13

Steller Sea Lion 0 0 3,563 0

Harbor Seal 76 2 2,337 106

Humpback

Date Time Activity

9/16/2020 15:35 - 15:39 Vibratory Installation

9/16/2020 15:45 - 15:48 Vibratory Installation

9/17/2020 08:28 - 08:32 Vibratory Removal

9/17/2020 12:56 - 13:14 Vibratory Installation

9/17/2020 13:17 - 13:19 Vibratory Removal

9/17/2020 14:36 - 14:39 Vibratory Installation

9/17/2020 14:41 - 14:43 Vibratory Removal

9/17/2020 14:45 - 14:48 Vibratory Removal

9/18/2020 09:06 - 09:07 Vibratory Installation

9/18/2020 09:08 - 09:23 Vibratory Installation

9/18/2020 09:28 - 09:29 Vibratory Removal

9/18/2020 12:00 - 12:57 Vibratory Installation

9/18/2020 14:24 - 14:34 Vibratory Installation

9/18/2020 14:35 - 14:39 Vibratory Removal

9/18/2020 15:33 - 16:10 Vibratory Installation

9/18/2020 16:10 - 16:11 Vibratory Removal

9/19/2020 10:39 - 10:41 Vibratory Installation

9/19/2020 10:46 - 10:52 Vibratory Installation

9/19/2020 10:57 - 11:03 Vibratory Installation

9/19/2020 11:07 - 11:10 Vibratory Installation

9/21/2020 10:15 - 10:31 Vibratory Installation

9/22/2020 08:27 - 08:29 Vibratory Installation

9/22/2020 08:34 - 08:35 Vibratory Installation

9/22/2020 08:37 - 08:41 Vibratory Installation

9/22/2020 08:43 - 08:54 Vibratory Installation

9/22/2020 08:58 - 09:08 Impact Installation

9/22/2020 09:58 - 09:59 Impact Installation

9/22/2020 10:02 Impact Installation

9/22/2020 10:07 Impact Installation

9/22/2020 10:13 - 10:15 Impact Installation

9/22/2020 10:21 Impact Installation

9/22/2020 11:11 - 11:17 Vibratory Removal

9/22/2020 11:57 - 12:13 Vibratory Installation

9/22/2020 12:37 Impact Installation

9/22/2020 12:58 - 13:01 Impact Installation

9/22/2020 14:55 - 15:39 Vibratory Installation

9/27/2020 10:26 - 10:29 Vibratory Removal

9/27/2020 10:45 - 10:57 Vibratory Installation

9/27/2020 12:02 - 12:34 Vibratory Installation

9/27/2020 14:13 - 14:16 Impact Installation

9/27/2020 14:46 Vibratory Removal

9/27/2020 15:19 - 15:24 Vibratory Removal

9/27/2020 15:28 - 15:36 Vibratory Removal

9/27/2020 17:01 - 17:19 Vibratory Installation

9/28/2020 09:29 - 10:12 Vibratory Installation

9/28/2020 12:00 - 12:28 Vibratory Installation

9/28/2020 14:14 - 14:15 Impact Installation

9/28/2020 14:22 - 14:23 Impact Installation

9/28/2020 14:39 Impact Installation

9/28/2020 15:19 - 15:21 Impact Installation

9/28/2020 15:40 - 15:41 Vibratory Removal

9/28/2020 15:49 - 15:51 Vibratory Removal

9/28/2020 16:03 - 16:07 Vibratory Removal

9/29/2020 13:58 - 14:56 Vibratory Installation

9/29/2020 15:06 - 15:23 Vibratory Installation

9/30/2020 09:43 - 09:48 Vibratory Installation

9/30/2020 09:52 - 10:09 Vibratory Installation

9/30/2020 10:49 Impact Installation

9/30/2020 10:52 - 10:54 Impact Installation

9/30/2020 11:07 Impact Installation

9/30/2020 11:21 - 11:22 Impact Installation

9/30/2020 11:41 - 11:43 Vibratory Removal

9/30/2020 11:47 Vibratory Removal

9/30/2020 13:14 - 13:24 Vibratory Installation

9/30/2020 13:59 Impact Installation

9/30/2020 14:12 - 14:14 Impact Installation

10/5/2020 09:13 - 09:37 Vibratory Installation

10/5/2020 10:18 Impact Installation

10/5/2020 10:19 - 10:20 Impact Installation

10/5/2020 11:25 - 11:26 Vibratory Removal

10/5/2020 12:12 - 12:25 Vibratory Installation

10/5/2020 13:27 - 13:29 Impact Installation

10/5/2020 13:44 Impact Installation

10/5/2020 13:50 Impact Installation

10/5/2020 14:04 - 14:05 Vibratory Removal

10/5/2020 16:16 - 16:17 Impact Installation

10/5/2020 16:22 - 16:25 Impact Installation

10/5/2020 16:41 - 16:44 Vibratory Removal

10/6/2020 10:44 Vibratory Installation

10/6/2020 10:54 - 11:08 Vibratory Installation

10/6/2020 11:15 Vibratory Removal

10/6/2020 12:12 - 12:17 Vibratory Installation

10/6/2020 13:57 - 14:03 Vibratory Installation

10/6/2020 15:42 - 15:44 Vibratory Installation

10/6/2020 15:48 - 15:51 Vibratory Removal

10/6/2020 16:34 - 16:37 Impact Installation

10/7/2020 08:47 - 08:49 Vibratory Removal

10/7/2020 08:51 Vibratory Removal

10/7/2020 08:57 - 09:11 Vibratory Installation

10/7/2020 09:14 Vibratory Removal

10/7/2020 15:00 Vibratory Installation

10/7/2020 15:05 Vibratory Installation

10/7/2020 15:09 - 15:19 Vibratory Installation

10/7/2020 15:37 - 15:41 Impact Installation

10/7/2020 15:47 - 15:48 Impact Installation

10/7/2020 17:09 - 17:12 Vibratory Removal

10/7/2020 17:23 - 17:25 Vibratory Removal

10/7/2020 17:37 - 17:48 Vibratory Removal

10/8/2020 08:29 - 08:37 Vibratory Installation

10/8/2020 08:40 - 08:41 Vibratory Installation

10/8/2020 08:55 - 09:02 Vibratory Installation

10/8/2020 09:04 - 09:07 Vibratory Installation

10/8/2020 09:15 - 09:20 Vibratory Installation

10/8/2020 10:01 - 10:03 Impact Installation

10/8/2020 10:11 - 10:13 Impact Installation

10/8/2020 10:58 - 11:01 Vibratory Removal

10/8/2020 11:08 - 11:25 Vibratory Installation

10/8/2020 11:55 - 11:57 Impact Installation

10/8/2020 12:29 - 12:50 Vibratory Installation

10/8/2020 13:50 - 13:51 Impact Installation

10/8/2020 13:58 Impact Installation

10/8/2020 14:15 - 14:17 Vibratory Removal

10/8/2020 14:20 Vibratory Removal

10/8/2020 14:25 - 14:27 Vibratory Removal

10/8/2020 14:31 Vibratory Removal

10/8/2020 15:35 - 16:06 Vibratory Installation

10/8/2020 16:36 - 16:38 Impact Installation

10/8/2020 16:42 Impact Installation

10/9/2020 08:14 - 08:43 Vibratory Installation

10/9/2020 09:11 Impact Installation

10/9/2020 09:14 - 09:16 Impact Installation

10/9/2020 09:20 - 09:22 Impact Installation

10/9/2020 09:37 - 09:39 Vibratory Removal

10/9/2020 09:41 Vibratory Removal

10/9/2020 09:44 - 09:47 Vibratory Removal

10/9/2020 09:50 Vibratory Removal

10/9/2020 11:00 - 11:08 Vibratory Installation

10/9/2020 11:36 - 11:37 Impact Installation

10/9/2020 12:11 - 12:38 Vibratory Installation

10/9/2020 13:10 Impact Installation

10/9/2020 13:45 Vibratory Removal

10/9/2020 13:49 Vibratory Removal

10/9/2020 13:53 - 13:54 Vibratory Removal

10/9/2020 13:57 Vibratory Removal

APPENDIX B: MARINE MAMMAL OBSERVATIONS DURING SAND

ISLAND TEST PROJECT.

Date Observer Species Time Number of Individuals

Direction/ Bearing

Distance (meters)

Construction Activity

9/16/2020 Case Wyatt Harbor Seal 15:06 1 SSW 250 no construction

9/16/2020 Kerry Lyons California Sea

Lion 15:10 2 160 50 no construction

9/16/2020 Case Wyatt Harbor Seal 15:16 1 NW 120 no construction

9/16/2020 Kerry Lyons Harbor

Porpoise 15:19 1 240 150 no construction

9/16/2020 Case Wyatt Harbor Seal 15:23 1 N 100 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:23 1 240 150 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:23 1 180 100 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:29 1 100 120 no construction

9/16/2020 Case Wyatt Harbor Seal 15:30 1 ESE 110 no construction

9/16/2020 Case Wyatt California Sea

Lion 15:31 1 N 100 no construction

9/16/2020 Case Wyatt California Sea

Lion 15:32 1 W 220 no construction

9/16/2020 Kerry Lyons Harbor Seal 15:32 1 160 250 no construction

9/16/2020 Kerry Lyons California Sea

Lion 15:34 1 180 250 no construction

9/16/2020 Case Wyatt Harbor Seal 15:37 1 NE 85 vibratory installation

9/16/2020 Case Wyatt Harbor Seal 15:43 1 N 80 no construction

9/16/2020 Case Wyatt Harbor Seal 15:46 1 N 300 vibratory installation

9/16/2020 Case Wyatt California Sea

Lion 15:55 1 E 400 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:03 1 340 150 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:06 1 200 200 no construction

9/16/2020 Kerry Lyons Harbor Seal 16:15 1 270 250 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:01 1 90 80 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:04 1 60 120 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:11 1 290 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 8:26 1 W 50 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:28 1 330 150 vibratory removal

9/17/2020 Kendra Ritchie

Harbor Seal 8:50 1 NW 30 no construction

9/17/2020 Kerry Lyons Harbor Seal 8:54 1 270 150 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:00 1 250 350 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:08 1 190 200 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:17 1 220 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 9:21 1 ESE 40 no construction

9/17/2020 Kerry Lyons Harbor Seal 9:48 1 180 80 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:08 1 340 300 no construction

9/17/2020 Kendra Ritchie

Harbor Seal 10:14 1 SW 60 no construction

9/17/2020 Kerry Lyons Harbor Seal 10:18 1 120 400 no construction

9/17/2020 Kendra…