This document outlines a federal contract opportunity from the Department of the Army Corps of Engineers Engineering District Portland. The solicitation seeks replacement of the 480V SU and CQ feederboards in Powerhouse II at Bonneville Lock & Dam, which are original equipment in marginal condition. Powerhouse II was completed in 1982 and has eight main generating units with a total rated capacity of 612 MW. The successful offeror will replace the SU and CQ panels to improve reliability as the components are no longer manufactured. The solicitation number is W9127N-20-R-0016 and offers are due in accordance with SECTION 01 10 10.00 25 requirements. The opportunity aims to upgrade critical infrastructure supporting hydropower operations and navigation on the Columbia River.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace requirements of paragraph 3.6 GENERATING UNITS OUTAGE SCHEDULE with the following:
MCCs SU 11 through SU 18 will require an outage of the associated generating unit. SUA will require an outage of Fishwater Generating Units F1 and F2. Prepare and submit for approval a comprehensive and detailed proposed schedule in accordance with the requirements of SECTION 01 10 10.00 25.