7/13/2018
.59
Jordan Quantock, Contract Specialist
Robert Winters, Project Manager
Jeffrey Hicks, Technical Lead
Gavin Smith, Structural
Lindsey Roth, Mechanical
Shade Griffin, Electrical
Chauncey Hamilton, Project Engineer & COR
Portland District, USACE
12 July 2018
SOLICITATION: W9127N-18-R-0045
DETROIT TAINTER GATE REHABILITATION
SCOPE OVERVIEW FOR CONTRACTOR SITE VISIT
DISCLAIMER
• Everything presented here today is informal and does not constitute changes or deviations from the specifications.
• Any answers given here today are not official.
For official answers use the bidder inquiry procedures (Refer to Slide 9).
ADMINISTRATIVE
• Sign the Registry
• If you would like a copy of this presentation, include your email address
• Restrooms
• Designated Smoking Areas
• Emergency Exits
• Purpose/Ground Rules
• Project Overview and Challenges
• Jeff Hicks- Technical Lead
• Site Walk
AGENDA
PURPOSE
• Exchange information regarding the scope of the project, specification, and outcomes.
• Overview of the job site.
• Establish lines of communication with industry
• All questions and comments must be submitted through the bidder inquiry system.
GROUND RULES
• Information conveyed at this site visit does not qualify as the terms and conditions of this solicitation.
• All communications shall be conducted through the Contract Specialist or Contracting Officer.
Interested vendors should ask questions using the Bidder Inquiry System.
• Non-attendance at this event does not preclude an offeror from submitting a proposal in response to the RFP.
GROUND RULES CONT.
• Internal source selection plans and procedures will not be discussed.
• If an item is not mentioned or addressed during this presentation, do not assume it is not important.
• Utilize the Bidder Inquiry site that is included in the solicitation.
• Offerors shall not engage individual Government Personnel in private discussions at any time.
SOLICITATION OVERVIEW
• Terms and Conditions have been posted formally and publicly.
• Solicitation W9127N-18-R-0045
» Federal Business Opportunity (FBO) » Proposals due 23 July 2018
• Total SB Set-Aside Solicitation
• Open to small businesses only
• No subcontracting plan with their proposal
• Best Value/ Trade Off » Best value is a process used in competitive negotiated contracting to select the most advantageous offer by evaluating and comparing factors in addition to cost or price.
• Evaluation criteria is stated in Section 002100 of the solicitation.
SUBMISSION OF QUESTIONS
• Submit all questions in writing. All inquiries regarding this solicitation are to be submitted via ProjNet-Bid.
• Telephone and email inquires will not be accepted.
• ProjNet-Bid can be accessed through ProjNet at https://www.projnet.org/projnet/.
• The bidder inquiry key is: 3G67YS-TMEQMS
BIDDER INQUIRY
• Bidder inquiry closes COB 16 July 2018
• Proposals shall not be based on informal discussions during the site visit — submit questions via bidder inquiry.
PROPOSAL SUBMISSION
• Please read the entire solicitation package and follow instructions to ensure a complete proposal is prepared and submitted to NWP.
• Section 002100 - Submission of Proposals and Evaluation covers what to include in the proposal Volumes.
• Proposals are due 23 July 2018, 2:00 PM Pacific Time.
HISTORY AND OVERVIEW
• Structural analysis to current criteria indicates gate design strength is exceeded when operated at full pool.
• Resulting in implementation of gate operating restriction.
• Upgrade to ensure safety, functionality, and reliability of the tainter gate system.
SCHEDULE
• Proposals Due: 23 July 2018
• Contractor Award: 28 Sept 2018
• Notice to Proceed: 15 Oct 2018
• On-site Work Window:
• Gate Out-of-Service Period: 15 Oct – 31 Jan 2019
• If optional gates are awarded: 15 Oct – 31 Jan
• Road Closure: deck closed form 1 Nov – 31 Jan
STRUCTURAL MECHANICAL ELECTRICAL
PROJECT OVERVIEW:
• STRENGTHEN STRUT ARMS
• STIFFEN OUTBOARD RIBS
• REPLACE MACHINERY PLATFORMS
• REPLACE GATE SEALS
• TOUCH-UP PAINT
• REPLACE TRUNNION ASSEMBLIES
• WIRE ROPES AND CONNECTIONS
• HOIST EQUIPMENT
• LOAD LIMITING DEVICES
• BRAKE SYSTEMS
• POWER SYSTEM
• INTAKE SWITCHGEAR
• LOCAL INDICATION
• LIMIT SWITCHES
• ALARMS
ROAD CLOSURE:
• MACHINERY BELOW ROADWAY DECK
• REMOVABLE ACCESS HATCHES
• CRANE FOOTPRINT
• ACCOMMODATE EMERGENCY VEHICLES
QUESTIONS AND SITE WALK