Perimeter Fence Repair/Reno - Irvington Site Office, Irvington Alabama
Solicitation number
W9127825QA013
Issued by

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for fence repair and renovation at the Irvington Site Office in Irvington, Alabama. The U.S. Army Engineer District Mobile is seeking a contractor to perform comprehensive fence services, including removal, repair, and replacement of existing fence features such as 48 line posts, 15 barbed wire arms, tension wire, and three-strand barbed wire around the perimeter fence. The project involves installing new components according to specific ASTM standards, ensuring proper drainage, and securing fence sections with rebar stakes.

The contract amendment extends the response due date to 13 October 2025, with a 90-day period of performance. Work will be conducted between 7:00 a.m. and 4:00 p.m. Monday through Friday at 7861 13th Street, Irvington, Alabama. The contractor must submit a safety plan, ensure all labor is certified, maintain insurance coverage, and restore perimeter security daily. Additional requirements include documenting existing site conditions, providing a company representative on-site, and complying with all applicable federal, state, and local regulations.

View the file

Other files

File Type Posted
Site Visit Summary.pdf PDF
W9127825QA013_Vendor_QandA_1Oct2025.pdf PDF
W9127825QA013_Vendor_QandA.pdf PDF
W9127825QA013_Vendor_QandA.pdf PDF
W9127825QA013_Fence_Repair_Solicitation.pdf PDF
Bid Schedule-Fence Repair.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form Continuation

The following changes have been made:

INFORMATION FROM TO

Response Due Date 08 Oct 2025 13 Oct 2025

List of Contract Documents, Exhibits, or Attachments

Miscellaneous text in this section has been modified to:

STATEMENT OF WORK

Fence Repair/Renovation

For the

Irvington Site Office, Irvington Alabama

1. Project Overview: The Contractor shall furnish all necessary management, labor, materials, supplies, tools, equipment, plant, and vehicles required to perform a variety of fencing services, including removal, repair, and replacement of existing fence features. This includes replacement of barbed wire, barbed wire support arms, tension wire, line posts, as well as installation of stakes and a small ditch barrier. This work will occur at the Irvington Site Office (Facility/Complex) in Irvington, Alabama. All work shall be performed in accordance with all terms and conditions, technical provisions, exhibits, etc., contained herein. Any equipment, materials, supplies, labor, etc., not expressly named in this specification, but otherwise necessary for orderly, safe and efficient work operation shall be provided by the Contractor at no additional cost to the Government. The Contractor shall provide properly licensed labor to perform work where Federal, State and Local laws require licensing or certification. The Contractor shall utilize a sufficient level of labor to accomplish all services required during the contract specified time periods. If the work performance is found to be poor, the Contractor shall take immediate corrective action to correct the work and to improve to the required standards at no additional cost to the Government.

2. References:

a. ASTM A121, Specification for Metallic-Coated Carbon Steel Barbed Wire

b. ASTM F567, Standard Practice for Installation of Chain Link Fence

c. ASTM F626, Specification for Fence Fittings

d. ASTM F1043, Specification for Strength and Protective Coatings of Metal Industrial Chain Link Fence Framework

e. ASTM F1083, Specification for Pipe, Steel, Hot-Dipped Zinc-Coated (Galvanized) Welded, for Fence Structures

W9127825QA0130001

f. ASTM F1665, Specification for Poly (Vinyl Chloride) (PVC) and Other Conforming Organic Polymer-Coated Steel Barbed Wire Used with Chain-Link Fence.

g. EM 385-1-1, Safety and Health Requirements Manual

3. Work Items:

3.1. LINE POSTS: Existing count of 48 each line posts that have been selected and shall be removed and replaced in the same location. Line posts shall be replaced with same size posts and set plumb (vertical within plus or minus 2 degrees ( 2) in each direction) in12-inch-wide x 24-inch deep concrete footings in accordance with ASTM F567. Concrete for post footings shall have a 28-day compressive strength of 2,500 psi. (17.2MPa). To ensure proper drainage and avoid water pooling around the posts, the top of concrete footings should be above existing ground elevation and sloped so

They shall be round steel pipe and rail: ASTM F1043 Group that water drains away from the posts.

IA Heavy Industrial Fence Framework, schedule 40 galvanized pipe per ASTM F1083. Existing fence shall be secured to the new posts with lacing wires being no more than 12-inch spacing and support arms reinstalled and secured by tamper-proof screws. Resultant post heights must match existing fence heights. One line post to be replaced on the east side of the entrance gate has a slightly larger diameter than the others. Multiple posts to be replaced have horizontal support arms that will require additional labor to remove and reinstall after replacement.

3.2. BARBED WIRE ARMS: Remove and replace a total of 15 damaged, bent, or rusted Type II, 45-degree Barbed Wire Arms. Support arms shall be 18-inches, facing outward, each holding three strands of barbed wire at regular intervals along the top of fence. These support arms must be permanently affixed to the fence posts with screws. Screws used to affix must be made tamper-proof Support arms must be constructed of material components shall be in accordance the most current versions of ASTM F626.

3.3. TENSION WIRE: The contractor shall remove and replace the existing tension wire around the entire perimeter. The contractor should be aware that some of the wire has become buried in the ground creating the need for some excavation to complete this task. Shall be installed 4-inches (101.6 mm) up from the bottom of the fence. Tension wire to be stretched taut, independently, between the terminal posts and secured to the terminal post using a brace band. Secure the tension wire to the chain link fabric with a 9-gauge (0.148-Inches) (3.76 mm) hog rings 12-inch on center and to each line post with a tie wire.

3.4. BARBED WIRE: Existing three strand barbed wire shall be removed and replaced around the entire perimeter fence including that atop the higher fence behind the Water Management shed totaling approximately 2,530-feet. Any fence other than perimeter fencing is not included in this contract. Barbed wire must consist double 12.5-gage (0.099-inch) (2.51 mm) twisted line wires with 14-gage (0.080-inch) (2.03 mm) round barbs. Barbed wire must be constructed of material components and shall be in accordance with the most current versions of ASTM A121 and ASTM F1665.

3.5. DITCH BARRIER: A ditch that passes under the perimeter fence on the north side of entry gate needs to be blocked to prevent entry but allow water to flow under the fence. Gap is approximately 10-feet x 1-foot. The contractor's solution for enclosure shall be submitted for approval. Existing gap closure method uses strands of barbed wire, secured on either end by a partially buried piece of line post set in concrete.

3.6. FENCE SECUREMENT: Fence sections with excessive movement at the bottom (after tension wire repair) shall have two 36-inch galvanized rebar stakes driven 24-inch into the ground and secured to the fence and tension wire. The stakes will be evenly spaced between the line posts. Sections with "excessive movement" shall be evaluated and selected by the Contracting Officer's Representative (COR) after tension wire repairs. Each fence section will be secured with (2) stakes. This contract line item consists of securing an estimated 25 fence sections with (2) stakes each, totaling 50 stakes.

3.7 NUTS AND BOLTS: Carriage bolts used for fittings shall be installed with the head on the secure side of the fence. All bolts shall be peened over to prevent removal of the nut.

3.8 CLEAN UP: The area of the fence line shall be left neat and free of any debris caused by the installation of the fence.

4. Additional Details:

4.1. SITE CONDITIONS: The Irvington site may include variable terrain and access limitations.

Repairs may be required at multiple, non-continuous segments of fence. Existing site conditions need to be reviewed and documented by the contractor. All existing damages or concerns shall be documented and communicated to the Government prior to start of work. Any damages made by the contractor to existing materials during the contract will be replaced at the contractor's expense. The contractor shall not proceed with repairs until site conditions and scope are jointly verified after awarded contract is issued.

Estimated quantities of services and/or work to be performed are described herein the BID SCHEDULE and these Specifications. See example bid schedule attached herein. These BID SCHEDULE quantities are approximate and are provided as information only to assist in preparation and evaluation of bids. The prospective bidders should visit the work site prior to bid opening to familiarize himself/herself with the working conditions, environment and quantity of work involved. The Contractor's responsibility, after award, shall include but shall not be limited to, all management necessary to assure all services are conducted in accordance with the contract requirement and all (State, County, City, and local) applicable laws, regulations, codes, or directives involving the work herein. The Contractor shall ensure all work meets or exceeds critical reliability rates or tolerances specified or included in reference documents. The Contractor shall perform all related Contractor administrative control, Contractor financial control, and maintenance of accurate and complete records and files.

4.2. CONTRACTOR'S REPRESENTATIVE: The Contractor will designate in writing and have on site, during any phase of work, a company representative, authorized by the Contractor to communicate with and conduct business with the COR. If this Contractor representative is not on site daily, the Contractor shall furnish a means of reliable communication between the two contract parties, all at no additional expense to the Government or this contract.

4.3. PERIOD OF CONTRACT: The period of performance for this contract is 90 days.

4.4. LOCATION OF WORK: The Scope of Work includes various work at the Irvington Site Office at Irvington, Alabama. The Irvington Site Office is in Irvington, Alabama, approximately one-half (1/2) mile southeast of the intersection of U.S. Hwy 90 and County Hwy 19 (Irvington-Bayou La Batre Hwy) adjacent to the former Alabama Power Company Field complex and Great Southern Wood Preserving.

Work Site Address: 7861 13th Street, Irvington, Alabama, 36544

4.5. WORKING HOURS: All work shall be performed between 7:00 a.m. and 4:00 p.m. (local time) on Monday through Friday each week, except Federal holidays when office buildings are closed (unless specified otherwise in this specification or agreed upon in writing by the COR).

4.6. PERMITS AND LICENSES: The Contractor shall, at his/her own expense, obtain any licenses or permits or certifications required to perform the contract work requirements. The Contractor shall comply with all current Federal, State, County, city and local laws, codes and regulations and shall comply with any subsequent changes.

4.7. PRE-BID SITE VISIT: A pre-bid site visit will be held prior to award, to discuss the project scope and to answer any questions or concerns of potential bidders.

4.8. PAYMENT: Contractor's invoice shall be submitted to the Irvington Site Office, U.S. Army Corps of Engineers, Mobile District, 7861 13th St., Irvington, Alabama 36544-2899.

4.9. RECORDS: The Contractor must give the Government written notice of date and time of work activity completion such that the Government Representative can perform the required acceptance inspection. This completion notification can be by written letter or email notification to the contract COR. The Contractor's work completion written notice must be forwarded to the Irvington Site Office not later than two (2) workdays (Monday-Friday) after the work is accomplished. A final punch list will be created during the acceptance inspection and final acceptance can then be made once any outstanding work items have been completed.

4.10. LABORERS/VEHICLES/QUALIFICATIONS CERTIFICATION AND INSURANCE: All labor utilized by the Contractor shall be certified as qualified for the assigned tasks. All vehicles, personal and commercial support vendors, shall have full insurance coverage and are subject to unannounced physical search, as directed by the COR.

4.11. SAFETY: The Contractor shall perform all activities of this contract under the safety requirements in accordance with the current version of EM 385-1-1, and applicable Federal and State regulations.

ATTN: Prior to start of any work under this contract the Contractor shall submit a written Safety Plan (Accident Prevention Plan), including an Activity Hazards Analysis evaluation, covering all anticipated work under this contract. Any Contractor equipment that fails to meet the requirement of that regulation will not be allowed to perform work under this contract. Any person found working in an unsafe manner will be stopped on the spot for corrective action by the Contractor and if not satisfactorily corrected that person will not be allowed to continue.

4.12. SECURITY: The contractor shall ensure that perimeter security is restored at the end of each workday. No fence sections shall be compromised and then left unattended. Temporary fence cover areas are required where applicable.

IDCode: J
Page: 1
Pages: 5
AmendNo: 0001
EffDate: 29 SEP 2025
ReqNo:
ProjNo:
IssCode: W91278
AdmCode:
IssuedBy: US ARMY ENGINEER DISTRICT MOBILE

KO CONTRACTING DIVISION, 109 ST JOSEPH ST

MOBILE, AL 36628-0001

UNITED STATES

GEOFFREY ROGERS, EMAIL: GEOFFREY.B.ROGERS@USACE.ARMY.MIL TELEPHONE: (251) 690-2079 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W9127825QA013
SolDate: 22 SEP 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE CONTINUATION
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: THE PURPOSE OF THIS AMENDMENT IS TO ADD ADDITIONAL INFORMATION TO THE STATEMENT OF WORK (SOW).

RESPONSE DATE HAS BEEN EXTENDED TO MONDAY, 13 OCTOBER 2025.

ALL OTHER ITEMS REMAIN THE SAME.

ContNameTitle:
CoNameTitle: ERICA M. COLLINS
ContDate:
CODate: 29 SEP 2025