W9127821R0050 23 STS Meeting Minutes and Sign-in_07212021.pdf
PDF 16 MB Posted
- Solicitation number
- W9127821R0050
About this file
This document provides details for a federal contract solicitation to construct facilities for the Special Operations Forces Special Tactics Operations at Hurlburt Field, Florida. The solicitation seeks the construction of 103,700 square feet of facilities including administrative areas, team rooms, equipment, vehicle and watercraft maintenance and storage areas, a covered storage area, rappelling tower, and antenna platform. The facilities will comply with requirements for high performance and sustainable building, low impact development features, anti-terrorism force protection, physical security mitigation, and cybersecurity of control systems. The contract duration is estimated at 900 calendar days. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Mobile.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127821R0050 - Approved_SAM_Brand Name JA for Trane HVAC_AF_Hurlburt Field FL.pdf | ||
| AM07.pdf | ||
| W9127821R0050 AM06.pdf | ||
| W9127821R0050 AM05.pdf | ||
| W9127821R0050 AM05 DRAWINGS.pdf | ||
| W9127821R0050 AM04 DRAWINGS.pdf | ||
| W9127821R0050 AM04.pdf | ||
| W9127821R0050 AM03 DRAWINGS.pdf | ||
| W9127821R0050 AM03.pdf | ||
| W9127821R0050 AM02.pdf | ||
| W9127821R0050 AM02 DRAWINGS.pdf | ||
| W9127821R0050 AM01.pdf | ||
| APPB.pdf | ||
| RTA DRAWINGS VOL1 of 4.zip | ZIP file | |
| VOL3.PDF | ||
| RTA DRAWINGS VOL3 of 4.pdf | ||
| VOL4.PDF | ||
| VOL2.PDF | ||
| RTA DRAWINGS VOL2 of 4.pdf | ||
| RTA DRAWINGS VOL4 of 4.pdf | ||
| EM 385-1-1.pdf | ||
| VOL1.PDF |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Minutes – Pre-bid site visit
Minutes-Pre-Bid site visit Agenda 23 STS Page 1 of 1
USACE
Mobile District
Project: FTEV 103005 SOF Special Tactics Operations Facility
(23 STS)
FY 21
Date: 21 JULY 2021
Location: On Site Hurlburt Field, Florida
Opening Remarks and Introductions @ 0930 at Hurlburt Resident Engineer Office
Lauren Arington, Mobile District COE Engineering Technical Lead o Discussed bid schedule and instructed all to fill out the bid schedule completely or proposal would not be accepted. Proposals due 9 of August.
o Access to the site during construction will need to be coordinated through the project engineer.
o Instructed all questions be input into Dr. Checks as the official process for answering questions concerning the project.
o Reminded contractors that existing repel tower is not to be demolished.
Proceeded to project location @ 0945 hours
Contractor’s allowed to walk the project site, and view existing buildings to be demolished.
End of meeting @ 1045 hours
Sign-in sheet attached