W9127817R0001-0001_Amendment_.pdf
PDF 202 KB Posted
- Solicitation number
- W9127817R0001
About this file
SOW revised 14 December 2017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127817R0001_Amendment_4.pdf | ||
| W9127817R0001_Amendment_3.pdf | ||
| 12.14.17_W91278-17-R-0002__Attachment_3.docx | DOCX document | |
| W9127817R0001-0002_Amendment.pdf | ||
| W91278-17-R-0001_Solicitation_Generator.pdf | ||
| Attachment_to__W91278-17-R-0001_Bid_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Follow ing Pages
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Dec-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91278-17-R-0001
X 9B. DATED (SEE ITEM 11)
29-Nov-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Dec-2017
CODE
ENDIST MOBILE CONTRACTING DIVISION
109 ST JOSEPH ST
MOBILE AL 36602
W91278 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91278-17-R-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
DESCRIPTION OF WORK 14 DEC 17
The following items are applicable to this modification.
AMENDMENT 0001
The purpose of this amendment is to:
1. Revised Statement of Work Dated 14 December 2017 below. Please note the track changes
2. The hour and date specified for receipt of Offers is not extended.
3. All other terms and conditions remain unchanged.
Description of Work 14 December 2017
1. General Description
1.1 Background. The hydroelectric facilities of the U.S. Army Corps of Engineers (USACE) South Atlantic Division (SAD) are experiencing more frequent failures with increasing equipment age. The number of failures, along with the reduced staff levels and increased contracting requirements have resulted in longer repair times for the units.
1.2 Objectives. It is the intent of this contract to expedite the process for the repair and replacement of hydroelectric generator components by having such repairs and replacements performed by the Original Equipment Manufacturer (OEM) by way of a Sole Source, Indefinite Delivery‐Requirements Contract (ID‐RC).
This contracting vehicle will reduce the amount of time needed to acquire such supplies and/or services due to the fact that the solicitation and evaluation period will be reduced, and the Equipment Manufacturer will be able to respond more rapidly due to their familiarity with the equipment and access to proprietary design documents.
The overall time saved will allow a more rapid response by USACE to the nation’s energy and environmental concerns in the case of failed or deteriorated generator components.
1.3 Description. This sole source ID‐RC contract is for supplies and services in support of USACE SAD for the repairs and replacement of generator components associated with USACE SAD hydroelectric facilities.
2. Work Statement of Services
2.1 General. The contractor specific tasks will be specified under each task order executed under this contract. Task orders will be issued on an as‐required basis to the OEM for the repairs and/or replacement of components. Repairs and/or component replacements will be accomplished under this contracting vehicle only up to the point that redesign of the machine is required or is considered more feasible by the Government. Also covered under this contract will be trouble shooting, analyzing, testing, and commissioning as it relates to the generator components repairs and replacement.
2.2 Equipment and Task. In general, equipment and tasks to be covered under this contract include hydroelectric generator components above the generator shaft to turbine shaft coupling and within the generator housing. Only those repairs and/or replacements that do not change the overall design of the machine are covered under this contract. Examples of equipment and tasks to be covered by this contract, include but are not limited to, the following:
Equipment and Task:
Performing inspections following a generator or generator component failure
Conducting performance test of the generator
Performing field test and commissioning
Re‐wedging
Re‐establishing corona suppression systems
Performing half coil splices
Installing coil jumper connections and insulation
Repair surge and/or circuit rings
Repairing clamping system components
Partial rewind of stator
Entire rewind stator (based on existing design)
Repairing stator laminations
Partial replacement of stator laminations
Complete replacement of laminations (based on existing design)
Manufacturing, installing and testing generator components
Manufacturing, installing and testing stator coils
Manufacturing, installing and testing stator bars
Performing electrical testing (i.e. interlaminar insulation (loop) test, El‐Cid test, DC ramp test, AC hipot test, DC hipot test, pole drop test, Megger test, blackout test, efficiency test, etc.)
Disassembly, aligning, and reassembly of generators
Repairing rotor poles
Manufacturing, installing and testing rotor poles
Removing, aligning and reinstalling rotor poles
Repairing / Replacing interpole rotor connections
Repairing / Replacing amortisseur windings
Repairing rotating exciters
Repairing generator shaft
Repairing spider frame
Repairing stator frame
Repairs to rotor & stator weldment
Repairs to major equipment foundations
Rotor Rim shrink analyses and re‐shrink
Repair / Replace key bars, key ways, shims, wedges
Rotor Balancing
Replacing CTs
Cleaning of generator components
2.3 Travel. Travel shall be required to accomplish the work specified per task order. The place of performance for the on‐site work shall be at the powerhouse or on Government property located near the powerhouse as identified in the individual task order. Travel costs must comply with Joint Travel Regulations (JTR) and are limited to what is allowed by the Federal Acquisition Regulations (FAR), note FAR 31.205‐46, Travel Costs.
2.4 Work Not Within Scope. Work not covered by this ID‐RC includes repairs and/or replacement components that appreciably changes the overall design of the machine. Examples of such work includes a complete rewind or restacking of the machine with newly redesigned components. Replacement with identical components, based on the current design is acceptable; however, under normal circumstances, complete rewinds that are planned replacements and not the result of failed components are not within the scope of work for this ID‐RC. The Contracting Officer shall have the final authority to determine whether the repair constitutes a replacement that is considered outside the scope of this contract.
3. Performance of Services
3.1 Rendering Service. The Contractor shall render the required services as entailed by the individual task order or as ordered by the Contracting Officer during the contract period. The Contractor shall be capable of supporting work seven days a week for twenty‐four (24) hours each day, when necessary.
3.2 Designation of Program Project Manager. Within five (5) calendar days from the date of award of the base contract, the Contractor shall notify the Government as to whom it has designated as the Program Project Manager (PM) for the work to be performed under this contract. The PM shall serve as the point of contact between the Government and the Contractor and shall have full authority to act on behalf of the Contactor.
4. Personnel
4.1 General. The Contractor shall furnish the services of professionally qualified personnel under the terms and conditions set forth in the contract and the individual Task Order. The types of disciplines required shall include, but are not limited to, Contract Project Manager, Task Manager, Scheduler, Work Site Supervisor, Technician, Quality Control Personnel, Safety personnel, Equipment Operator, Electrician, Mechanic, Laborers Millwright, and Clerical. Engineering technical support may require the following disciplines: Electrical, Mechanical and Structural Engineers.
4.2 Contract Project Manager. The Contract Project Manager (CMPM) shall be the single point of contact for this Contract. The CMPM shall be knowledgeable in management of hydroelectric generator rehabilitation and the specific activities identified in this contract. The CM PM is responsible for identifying to the Government in writing those individuals who have contractual authority for the company. If replaced, notification shall be submitted in writing to the Contracting Officer within five (5) business days.
4.3 Task Manager. For each task order issued, the Contractor shall designate in writing to the Contracting Officer a Task Manager (TM). The TM can be the ContractProject Manager. The TM shall be the single point of contact for the task order, and shall be responsible for the management and execution of all activities in exact accordance with the requirements of the task order. If replaced, notification shall be submitted in writing to the Contracting Officer within five (5) business days.
4.4 Work Site Supervisor. For each task order issued including site work, the Contractor shall designate in writing to the Contracting Officer a Work Site Supervisor. This person shall be the single point of contact for site work. The Supervisor shall be able to or provide a person who can present operational instructions fluently in the English language.
4.5 Other Personnel Qualifications. The qualifications for all other personnel shall be specified under each task order.
5. Equipment, Supplies, Documents, and Data
5.1 Contractor‐Furnished Items. Specific equipment, materials, documents and data to be furnished by the Contractor shall be detailed in the individual task orders, as applicable. Contractor‐furnished items shall depend on the individual task order.
5.2 Government‐Furnished Supplies. Specific equipment, materials, supplies and pertinent documents and data shall be furnished by the Government as indicated per task order.
6. Contractor Compensation
Work under this ID‐RC will be performed using Firm Fixed Price task orders.
7. Subcontractor
7.1 Subcontracts. The Contractor shall cause appropriate contract clauses and other terms and conditions to be inserted in all subcontracts relating to this contract, and ensure fulfillment by subcontractors.
7.2 Relationship between Subcontractor and Government. Nothing contained in this contract shall be construed as a contractual relationship between the Government and the subcontractor of the primary Contractor.
7.3 Approval of Subcontractors. Prior to award of any task order in which subcontractors will be utilized, the Contractor may be asked to provide, in writing, a list of all the subcontractors, a statement to the extent and character of the work to be done under the subcontract, and the following information:
1. Name of the subcontractor;
2. Subcontractor’s experience with respect to performing work for which it is being proposed to perform, as referenced in the Statement of Work for each individual task order.
7.3.1 Once a subcontractor is submitted with a proposal, and if the award has been made based on the subcontractor’s experience or capabilities, the Contractor cannot change subcontractors unless justification has been made it writing and approved by the Contracting Officer specified on the task order.
(End of Summary of Changes)
File details come from the government source that posted it.