This solicitation is for the construction of a new Type III Hydrant System at Fort Hood, Texas. The project includes constructing above ground fuel storage tanks, a pump shelter with control room, product recovery tank, truck loading and unloading points, spill containment facilities, and supporting infrastructure. The new fuel facility will supply a direct fuel system to an aircraft parking apron. Requirements also include installing new piping for a hydrant loop and demolition of existing hydrant pits.

The solicitation will be awarded as a competitive, firm-fixed price contract with an anticipated award date of September 30, 2021. Phase 1 proposals are due by September 10, 2021. The solicitation is issued by the Department of the Army Corps of Engineers Fort Worth District. The primary point of contact is Paige Stone and all questions must be submitted by email. The contract value is estimated between $25-100 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design-Bid-Build Request For Proposal

Fuel Facility Replacement RGAAF Fort Hood, TX

W9126G21R0037 Unrestricted

JULY 2021

US Army Corps of Engineers Fort Worth District

DESC2003 Fuels Facility Replacement RGAAF FH21FFR

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 00.01 SOLICITATION, OFFER AND AWARD, SF-1442

00 11 00.02 CONTRACT LINE ITEM SCHEDULE

00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

00 21 30 SITE VISITS

00 22 11 LOWEST PRICE TECHNICALLY ACCEPTABLE (LPTA) PROPOSAL

PREPARATION

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 CONTRACT CLAUSES

00 73 00 SPECIAL CONTRACT REQUIREMENTS

00 73 46 WAGE DETERMINATION SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 44 CONSTRUCTION SCHEDULE

01 01 10.00 44 SPECIAL PROJECT REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 23.33 AVIATION FUEL SYSTEM SPECIFIC SUBMITTAL REQUIREMENTS

01 35 10.00 44 SPECIAL PROJECT PROCEDURES FOR FORT HOOD

01 35 13 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 24.01 44 STORM WATER POLLUTION PREVENTION PLAN (TEXAS)

01 57 25.00 44 SWPP PLAN INSPECTION AND MAINTENANCE REPORT FORM

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 23.33 OPERATION AND MAINTENANCE MANUALS FOR AVIATION FUEL

SYSTEMS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

PROJECT TABLE OF CONTENTS Page 1

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD AND BLOCK INSULATION

07 22 00 ROOF AND DECK INSULATION

07 42 13 METAL WALL PANELS

07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 81 00 SPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 33 13 COILING COUNTER DOORS

08 51 23 STEEL WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL

PETROLEUM FUEL TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 13 - SPECIAL CONSTRUCTION

13 34 19 METAL BUILDING SYSTEMS

13 34 19.20 METAL CANOPY SYSTEMS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 08 00 HEAT TRACING FOR FREEZE PROTECTION

PROJECT TABLE OF CONTENTS Page 2

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 93.00 25 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00.00 25 COMMISSIONING OF HVAC SYSTEMS

23 09 23.01 LONWORKS INTERFACE FOR UTILITY METERING

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT

23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 26 - ELECTRICAL

26 05 26.00 40 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 19.00 40 MOTOR CONTROL CENTERS

26 27 14.00 20 ELECTRICITY METERING

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 32 15.00 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH

AUXILIARIES

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 17.00 10 CATHODIC PROTECTION SYSTEM (IMPRESSED CURRENT)

26 51 00 INTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 70 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 11.51 RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS

32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE BASE COURSES

32 11 23.23 BASE COURSE DRAINAGE LAYERS

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 13 15.20 CONCRETE PAVEMENT FOR CONTAINMENT DIKES

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13.53 HIGH-SECURITY FENCES (CHAIN LINK AND ORNAMENTAL) and GATES

32 92 23 SODDING

32 93 00 EXTERIOR PLANTS

32 96 00 TRANSPLANTING EXTERIOR PLANTS

DIVISION 33 - UTILITIES

PROJECT TABLE OF CONTENTS Page 3

33 08 53 AVIATION FUEL DISTRIBUTION SYSTEM START-UP

33 09 53 AVIATION FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM

33 40 00 STORM DRAINAGE UTILITIES

33 52 23.15 POL SERVICE PIPING WELDING

33 52 43.11 AVIATION FUEL MECHANICAL EQUIPMENT

33 52 43.12 AVIATION FUEL PANTOGRAPHS

33 52 43.13 AVIATION FUEL PIPING

33 52 43.14 AVIATION FUEL CONTROL VALVES

33 52 43.23 AVIATION FUEL PUMPS

33 52 43.28 FILTER SEPARATOR, AVIATION FUELING SYSTEM

33 52 80 LIQUID FUELS PIPELINE COATING SYSTEMS

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

33 56 19 FUEL IMPERMEABLE LINER SYSTEM

33 56 21.17 SINGLE WALL ABOVEGROUND FIXED ROOF STEEL POL STORAGE TANK

33 56 21.18 SINGLE WALL POL TANK UNDERTANK INTERSTITIAL SPACE

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.15 BRIDGE CRANES, OVERHEAD MANUAL, UNDER RUNNING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

Project Title: Fuel Facility Replacement RGAAF at Fort Hood, Texas

This project w ill be Unrestricted

NAICS Code: 237120 FSC: Y1GC Size Standard: $39.5M

Magnitude of Construction betw een $25,000,000 and $100,000,000.

**If the contractor fails to provide adequate and acceptable bond documents and insurance certif icates w ithin ten days after contract aw ard, such failure shall constitute ground for termination for default w ithout the requirements for the Contracting Off icer to f irst issue a "show cause" letter. The Government w ill not allow the contractor to w ork on the project unless the bond documents and insurance certif icate have been accepted by the Contracting Officer and a signed Notice to Proceed has been issued to the contractor.**

PAIGE E STONE 817-886-1124

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

05-Aug-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______1 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________01 00 00.00 44

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________10 Sep 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

819 TAYLOR STREET, RM 3A37

FORT WORTH TX 76102

W9126G

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

11:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9126G21R0037 77

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section: 00 11 00 W9126G21R0037

Item Unit Line Item No. Description Quantity Unit Price Amount

0001 All work required for Hydrant Loop & 6 Hydrant Pits 1 JOB $ *** $

0002 All work required for Jet Fuel Storage Tanks (includes ATG infrastructure)* 1 JOB $ *** $

0003 All work required for Pump Shelter, Control Room, & POL Pumps 1 JOB $ *** $

0004 All work required for Fuel Truck Loading (1 Fillstand + 1 HHT/Fillstand)

1 JOB $ *** $

0005 All work required for Tank Truck Unloading (2 Truck Offloads) 1 JOB $ *** $

0006 All work required for Supporting facilities to include Site Improvement, Site Electrical, Civil Site Work, Demolition, Site Prep exclusive of the work for Generator, Trees, Communcations Package 1&2 1 JOB $ *** $

0007 All work required for installation of Diesel Generator 1 JOB $ *** $

0008 All work required for Tree Planting 1 JOB $ *** $

0009 All work required with

COMMUNICATIONS PACKAGE 1

from new pump shelter to fire station communications room. 1 JOB $ *** $

0010 All work required with

COMMUNICATIONS PACKAGE 2

from fire station communications room to manhole adjacent to Bldg 90078. 1 JOB $ *** $

OPTIONS

Fuel Facility Replacement RGAAF

FY 21

TOTAL BASE OFFER

BASE OFFER: All work required by the Contract exclusive of work required by the Option Items.

Fort Hood, TX

CONTRACT LINE ITEM SCHEDULE

Item Unit Line Item No. Description Quantity Unit Price Amount

Fuel Facility Replacement RGAAF

FY 21

Fort Hood, TX

CONTRACT LINE ITEM SCHEDULE

1 JOB $ *** $

1 JOB $ *** $

1 JOB $ *** $

1 JOB $ *** $

300 CY $ $

300 CY $ $

300 CY $ $

5 EA $ $

OPTION 1: All work required for procurement and install of KTR furnished ATG Equipment.

OPTION 2: All work required for Truck Offload Canopy

OPTION 3: All work required for Fill-stand Canopies (1 Fill-stand Flight Line+ 1 Fuel Farm).

OPTION 4: All work required for Natural Gas Emergency Generator (Swap out Diesel Generator for Natural Gas Generator).

OPTION 5: All work required for Contaminated Soil Testing and Stockpiling.

OPTION 6: Cost for removal of contaminated soil.

OPTION 7: Cost for backfill of removed contaminated soil with satisfactory material.

OPTION 8: All work required for Contaminated Ground Water Test.

OPTION 9: All work required for Contaminated Ground Water Disposal. 50 GAL $ $

Contract Duration in Calendar Days After the Notice to Proceed is received.* DAYS

*Note: Contract duration for all work shall NOT exceed the duration specified in Section 01 00 00.00 44 CONSTRUCTION SCHEDULE. See Note No. 6.

TOTAL OFFER (BASE + OPTIONS)

Fuel Facility Replacement RGAAF

FY 20,

Fort Hood, TX

CONTRACT LINE ITEM SCHEDULE

NOTES:

NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

NOTE NO. 2. Offerors must insert a price on all numbered items of the CLIN Schedule. Failure to do so may result in the offer being unacceptable

NOTE NO. 3. CONDITIONS GOVERNING EVALUATION OF OFFERS AND AWARD OF CONTRACTS:

The Government may require the delivery of the numbered line items, identified in the schedule as option items, in the quantity and at the price stated in the schedule. Subject to the availability of funds, the Contracting Officer may exercise the option by written notice to the Contractor within the time indicated below from the Notice to Proceed:

NOTE NO. 4. All the extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

NOTE NO. 5. Include all costs for coordination and accommodation of Government-Furnished, Government- Installed Equipment as described in Section 01 11 00 STATEMENT OF WORK in the Contract Line Items for construction of the associated facilities.

NOTE NO. 6. The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to Proceed (NTP) is received by the Contractor, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for design and construction through completion, ready for turnover shall not exceed the number of calendar days specified in Section 01 00 00.00 44 Design and Construction Schedule. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP. See also Sections 00 73 00 Special Contract Requirements.

NOTE NO. 7. At the option of the Government, the Government may require the Contractor to perform the work identified as Optional line item(s) at the price(s) stated in the CLIN Schedule. There is no separate completion period for these option(s) and the work included therein shall be completed within the contract duration as proposed above. Exercise of the Option(s) shall be evidenced on Standard Form 30, citing FAR 52.217-7, as the authority for exercising the Option. The Option shall be deemed exercised at the time the Government deposits the SF30 in the mail or, if earlier, at the time it is delivered to the Contractor.

NOTE NO. 8. 52.217-5 EVALUATION OF OPTIONS (JUL 1990)

(a) Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(b) The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

Fuel Facility Replacement RGAAF

FY 20,

Fort Hood, TX

CONTRACT LINE ITEM SCHEDULE

NOTE NO. 9. Responders are advised that this requirement may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process based on decisions related to DOD changes in force structure and disposition of the Armed Forces.

NOTE NO. 10. The Army will procure this facility through a design and cost competition in accordance with the provisions set forth in this Request for Proposals (RFP). When awarded, it will be a "Firm Fixed Price Contract."

NOTE NO. 11. Any proposal that is materially unbalanced as to prices for the Base Schedule may be rejected.

An unbalanced proposal is one that is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work and can also exist where only overpricing or underpricing exists.

NOTE NO. 12. ABBREVIATIONS

For the purpose of this solicitation, the units of measure are represented as follows:

a. JOB

b. CY = Cubic Yards

c. GAL = Gallons

NOTE NO 13. Profit will not be paid on bonds or insurance.

END OF CLIN SCHEDULE

Section 00 21 00 - Instructions, Conditions and Notices to Offerors

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

1. GENERAL INFORMATION

1.1. GENERAL DESCRIPTION OF WORK

1.2. GOVERNMENT REQUIREMENTS FOR INCOMING MAIL AND PACKAGES

1.3. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

1.4. OFFEROR’S QUESTIONS AND COMMENTS

1.5. SMALL BUSINESS SIZE STANDARDS/NAICS CODE

1.6. PREPROPOSAL CONFERENCE/SITE VISIT

1.7. ESTIMATED CONSTRUCTION COST

2. PROPOSAL FORMAT AND GENERAL INSTRUCTIONS

2.1. PROPOSAL EXPENSE AND PRE-CONTRACT COSTS

2.2. ACCURACY IN PROPOSALS

2.3. PROPOSAL GENERAL INFORMATION

2.4. PROPOSAL FORMAT

2.5. JOINT VENTURE PROPOSAL REQUIREMENTS

2.6. BID GUARANTEE

2.7. CONTRACT PRICES BIDDING SCHEDULE

1.0 GENERAL INFORMATION

1.1 GENERAL DESCRIPTION OF WORK

The Government intends to establish Firm Fixed-Price (FFP) Contract for Fort Hood Fuel Facility Replacement project. The project will include all work in accordance with the plans and specification to make necessary repairs and upgrades to the Fuel Facility.

1.2 GOVERNMENT REQUIREMENTS FOR INCOMING MAIL AND PACKAGES

The Offeror(s) must ensure that ALL mail inquiries are sent to the Fort Worth District, U.S. Army Corps of Engineers, relating to either pre-contract or post-contract award. A return mailing address is required on the outside of the envelope, package, box, etc. All mail must be addressed to the Contracting office as specified below (no exceptions):

U.S. Army Corps of Engineers, Fort Worth District ATTN: Paige Stone, Contract Specialist 819 Taylor Street (Room 2A17) Fort Worth, TX, 76102-0300

All Federal Express/UPS/etc. packages are required to have Offeror’s physical address and the above contracting office address including room number, contract specialist’s name for proper delivery.

1.3 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and all amendments are available by INTERNET ACCESS ONLY. All solicitation documents and amendments will be posted on the SAM website at http://www.SAM.gov/ and Offeror can access solicitation documents by the solicitation number, W9126G21R0037.

It is solely the Contractor’s responsibility to check the SAM.gov website for the solicitation and any amendments prior to the RFP closing date. The Offeror shall submit in its proposal all requested information as specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation. The Offeror must be registered with the System for Award Management Database (SAM) to receive a Government contract award.

Additional information regarding this solicitation and potential Offerors (i.e., interested vendors list) and/or subcontractors will be available on the SAM.gov website under the solicitation number.

1.4 OFFEROR'S QUESTIONS AND COMMENTS

Questions and/or comments relative to these documents should be submitted via e-mail to:

Contract Specialist – Primary POC U.S. Army Corps of Engineers, Fort Worth District ATTN: Paige Stone Phone: (817) 886-1124 Email: Paige.E.Stone@usace.army.mil Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via:

Bidder Inquiry

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

To submit and review bidder inquiries, bidders will need to be a current registered user or self-register into the ProjNet system. To self-register go to web page at http://www.projnet.org/projnet, click the BID tab, select Bidder Inquiry, select agency USACE, enter the Key for this RFP (listed above) and your e-mail address, and click login.

Fill in all required information and click create user. Verify that the information on the next screen is correct and click to continue.

From this page you may view all bidder inquiries or add an inquiry. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. Only one question will be allowed per inquiry. If multiple questions are included in a single inquiry, only the first question will be answered. All others will remain unanswered until entered in as a single inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

The Solicitation Number is: W9126G21R0037 The Bidder Inquiry Key is: Y57QR4-N5HEN9

The Bidder Inquiry System will be unavailable for new inquires 7 calendar days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the RFP, if necessary. If the System is not closed in a timely manner, an inquiry posted within the seven calendar days of the receipt of proposals would still be considered untimely and will not be answered.

Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

1.5 SMALL BUSINESS SIZE STANDARD/NAICS CODE

See Section 00 45 00, FAR 52.204-8 for the small business size standard/NAICS Code.

1.6 SITE VISIT

Pursuant to Contract Clause "FAR 52.236-3, Site Investigation and Conditions Affecting the Work," prospective offerors will be permitted to inspect the site where services are to be performed and to satisfy themselves as to all general and local conditions that may affect the cost of performance of the Contract to the extent such information is reasonably obtainable. Offerors are urged and expected to inspect the site where the work will be performed.

1.7 ESTIMATED CONSTRUCTION COSTS

The estimated cost of the proposed construction is between $25,000,000.00 and $100,000,000.00.

1.8 AVAILABILITY OF FUNDS

See Section 00 72 00, Clause 52.232-18, Availability of Funds.

2. PROPOSAL FORMAT AND GENERAL INSTRUCTIONS

2.1. PROPOSAL EXPENSE AND PRE-CONTRACT COSTS

This Request for Proposal (RFP) does not commit the Government to pay as a direct charge any costs incurred by the Offeror in the preparation and submission of its proposal or revisions. A stipend is not authorized for unsuccessful offerors.

2.2. ACCURACY IN PROPOSALS

Proposals must set forth with full, accurate, and complete information as required by this RFP, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

2.3. PROPOSAL GENERAL INSTRUCTIONS

In an effort to reduce paperwork and reduce cost, all proposals shall be submitted electronically. All submissions should be in Adobe PDF format. The Price Proposal and Technical Proposal shall be submitted as “separate” single files. Offerors may use compressions utility software such as WinZip or PKZip to reduce file size and facilitate transmission.

Title the file(s) in the following format:

W9126G21R0037_COMPANY NAME_ TECHNICAL

W9126G21R0037_COMPANY NAME_PRICE

Submit the Price and Technical proposals electronically via the DoD SAFE website at https://safe.apps.mil/.

In order for an outside user (the contractor) to submit a proposal for the solicitation, they must receive a drop-off request from an inside user (the government). When the inside user generates a drop-off request for you, you will receive an email with a link to submit your drop-off. Optionally, the Government may provide you with a request code. In that case, click the Drop-off button on the SAFE home page and enter the Request code.

To request and receive a drop-off request for this solicitation, email the Contract Specialist and Contracting Officer two (2) working days before the proposal due date. The Contracting Officer for this project is: Mr. John H.

Rodgers. Email address is john.h.rodgers@usace.army.mil. The Contract Specialist for this project is: Ms. Paige Stone. Email address is paige.e.stone@usace.army.mil. Include the solicitation number in your Email Subject Line: W9126G21R0037

2.4. PROPOSAL SUBMITTAL

1) Submit only the electronic documents. Submit only the electronic files that are specifically requested in Section 00 22 11. All files submitted shall be in PDF format. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages shall be numbered.

2) Searchable PDF pages shall be formatted to print on 8 ½ by 11 inch paper, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Spreadsheets and presentation drawings must fit to 11” x 17” paper size unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers of the solicitation, project title and company.

3) Hard copies shall not be submitted, with the exception of the bid guarantee. Refer to this section, 2.6 Bid Guarantee, for bid guarantee submission requirements.

4) “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR Clause (P) 52.215-1, Instructions to Offerors -- Competitive Acquisition, paragraph (e), Restriction on disclosure and use of data.

5) In the case of an Offeror that is part of a large, multi-segmented business concern, provide information directly pertaining to the specific segment of the business concern (i.e., the division, group, unit, etc.)

that will perform work under the prospective contract.

6) For submissions with page limitations, the corresponding PDF pages will be counted.

7) Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision or amendment, e.g., Error, Omission or Clarification shall be included and be annotated for each revision. Proposal replacement pages shall be numbered and clearly marked “REVISED”, with the date of revision.

2.5. JOINT VENTURE PROPOSAL REQUIREMENTS

Joint Venture:

When proposing as a joint venture, all members of the joint venture shall sign the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration.

If this is an 8(a) or HUBZone joint venture, the Offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively.

LLC:

When proposing as an LLC, the offeror must submit a copy of the operating agreement which clearly demonstrates the authority to bind the LLC.

2.6. BID GUARANTEE

Submit the Bid Guarantee in accordance Provision 52.228-1, Bid Guarantee, to the address in section, 1.4 Government Requirements for Incoming Mail and Packages, on or before the date indicated in Box 13 of the

SF1442.

2.7. CONTRACT PRICES BIDDING SCHEDULE

Payment for the items listed in the Bidding Schedule shall constitute full compensation for furnishing all plant, labor, equipment, appliances, materials and bonds (performance and payment), and for performing all operations required to complete the work in conformity with the drawings and specifications. All costs for work not specifically mentioned in the Bidding Schedule shall be included in the contract prices for the items listed.

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-22 Alternative Line Item Proposal JAN 2017 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.217-4 Evaluation Of Options Exercised At The Time Of Contract

Award

JUN 1988

52.217-5 Evaluation Of Options JUL 1990 52.232-2 Payments Under Fixed-Price Research And Development

Contracts

APR 1984

252.236-7008 Contract Prices-Bidding Schedules DEC 1991

CLAUSES INCORPORATED BY FULL TEXT

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)

(a) Definitions. As used in this provision--

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.

“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.

Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show--

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.

(3) Submission, modification, or revision, of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--

(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(f) Contract award.

(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

(2) The Government may reject any or all proposals if such action is in the Government's interest.

(3) The Government may waive informalities and minor irregularities in proposals received.

(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.

(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.

(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.

(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.

(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.

(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.

(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(iv) A summary of the rationale for award.

(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.

(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed Price (FFP) contract resulting from this solicitation.

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

16.4% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Bell County, TX

52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .