IDIQ JOB ORDER CONTRACT, FORT STEWART AND HUNTER ARMY AIRFIELD, GA
Solicitation number
W9124M21R0004
Issued by

About this file

This solicitation is for an indefinite-delivery, indefinite-quantity job order contract to provide minor construction services, sustainment, restoration, and modernization projects at Fort Stewart and Hunter Army Air Field in Georgia. The contractor shall furnish all labor, materials, equipment, transportation, and supervision to complete job orders that encompass tasks in construction trades such as carpentry, plumbing, HVAC, electrical work, concrete work, and more. Individual job orders will vary in size and scope up to $1 million. The total contract capacity is $49.9 million over one base year and four option years. The proposal due date is April 2, 2021. Pricing will be determined by multiplying task prices in the eGordian unit price book by the contractor's coefficients for overhead and profit.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011458261-0001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide site visit attendee list, provide answ er to questions submitted and clarif ication to the solicitation.

1. Update to Section C: C.1.23.2, C.5.3.2

2. Update to Section J: Exhibit C, Attachment 4, add attachment 7,8 and 9.

3. Update to Section L: 2. Proposal Preparation c.; Volume IV - Factor (3) - Past Performance 1) Past Performance Record.

4. See block 14 continuation sheet for details on the attendee list and Q&A.

5. The proposal due date has been extended to 2:00PM (Eastern Daylight Saving Time) 02 April 2021.

1. CONTRACT ID CODE PAGE OF PAGES

1 41

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Mar-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9124M21R0004

X 9B. DATED (SEE ITEM 11)

26-Feb-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Mar-2021

CODE

MICC - FORT STEWART

976 WILLIAM H. WILSON AVE SUITE 100

FORT STEWART GA 31314

W9124M 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9124M21R0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SITE VISIT AND Q&A

Site Visit Attendee List

Name Company Phone Number E-Mail Address Trey Dickson Global Go 770-490-0228 Trey.dickson@globalgo.com Marion Davis Charlton Enterprises 912-496-3173 marion@charltonenterprisesinc.com Rob Hawthorne Olgoonik 719-238-5999 rhawthorne@olgoonik.com Jim Wine DPW 912-320-5770 James.a.wine3.civ@mail.mil Carroll Suggs Siler 912-610-2323 carroll@siler.biz Tammy Siler Siler 865-617-9808 tammy@siler.biz Sharon Martin Civil Works Contracting 910-338-8737 Satkison@civilworkscontracting.com John Anderson ERS Corp 904-791-9992 J.anderson@ersfl.com James Daniel Tikigaq, Federal 504-941-1193 jdaniel@tikigaq.com ED Hartley NASCO 706-570-4320 Eddie.hartley@nascosa.com Neil Tuck Gordian 864-630-7702 n.tuck@gordian.com Bruce Presnell CMC Building, Inc. 910-228-9460 bpresnell@cmcbuildinginc.com Cory Donahoo Olgoonik Logistics, LLC 719-355-6240 cdonahoo@olgoonik.com Kirk Mathews REAMS 404-684-2500 kmathews@reamsenterprise.com Waldo Moody S&W 478-954-6280 waldo@sandwsales.com Jackson Rackley HE 228-403-0756 jrackley@harborenterprisesllc.com Lucas Stewart HE 229-221-4058 LStewart@harborenterprosesllc.com

MIG GOV, LLC

Sheung Li MICC (KS) Sheung.c.li.civ@mail.mil Mary Hightower MICC (KO) Mary.l.hightower2.civ@mail.mil

Question and Answer

1. Can the Government please provide the annual average dollar amount of work performed under a JOC at Ft Stewart over the past ten years?

Answer: This depends on the annual work plan funding allocations for each FY and/or each Quarter.

2. Does the Government anticipate utilizing the entire funding pool of $9,980,000.00 + contractor fees during the base and option years?

Answer: The $9.9M represents contract capacity should funding be available. The only guarantee is the “GUARANTEE MINIMUM” listed on the solicitation. The anticipated utilization of the entire amount of the proposed is set aside for projected projects that have been identified and/or anticipated for development, depending on funding allocations.

3. Will the government designate a space or location on base for a contractor office and storage facility?

Answer: The contractor is allotted a space as set by the perimeters identified in “PART 4 (C.4)” of the solicitation.

4. Is the size and scope of the mock project representative of the anticipated task orders that will be issued under this JOC?

Answer: The Mock Project was placed into the solicitation to represent a (hypothetical) project (on a variable / small scale) to retrieve responses from the solicitors for demonstrating their knowledge, experience, and applicable utilization of estimation tools and engineering techniques to accomplish a (potential) project of similarities of any magnitude within the boundaries / scope of the JOC as set forth in the solicitation.

5. Would the Government please confirm that the capacity for this proposed JOC is $9,980,000.00 per year for a total (base year + 4 option years) contract capacity of $49,900,000.00?

Answer: Capacity amount is as prescribed within the Solicitation. The $9.9M represents contract capacity should funding be available. The only guarantee is the “GUARANTEE MINIMUM” listed on the solicitation.

6. Would the Government please confirm the anticipated size of the task orders from this proposed JOC?

Answer: Task order size can be anything from $2,000 up to potentially $1,000,000.

7. Please advise if there is a Contractor yard available at Fort Stewart and/or Hunter Army Airfield in which a temporary construction office/trailer could be placed. If so, is power available?

Answer: The contractor is allotted a space as set by the perimeters identified in “PART 4 (C.4)” of the solicitation.

8. RFP, Section L, Mock Project, Page 118, Offerer(s) shall use attachment 6 – Mock Project Cost Estimate to complete the cost portion of the trial proposal. In lieu of using attachment 6 –Mock Project Cost estimate to complete the cost portion of the trial proposal, can the cost estimate be submitted in eGordian format? If not, is it acceptable to modify attachment 6 to follow the same format and logic of eGordian?

Answer: eGordian format is satisfactory / acceptable.

9. Do you have structural drawings for the project?

Answer: This is a Job Order Contract Solicitation which will consist of a multitude of projects/taskers requests at any given time within a given contract period and is not a sole contract being requested for an individual / independent project .

10. Can you please direct me to where I can view the exterior elevations, floor plans and the window schedule/details for the aluminum clad wood windows?

Answer: This information can and will be provided during the issuance of any and each task order, once awarded.

11. Please clarify that the contractor pricing for the base year and follow on option years is intended to utilize the estimated total not to exceed number of $9,980,000.00 + CTC adjustment Factor + Contractor Coefficients.

Answer: Please see Exhibit D – Bid Price Worksheet.

12. Are we allowed to use CPARS for past performance evaluation?

Answer: The Government uses CPARS to evaluate past performance. Offerors should not include their CPARS evaluations in their proposal packet.

13. Is there a minimum or maximum number of past performance records for similar size, scope, and complexity to this requirement?

Answer: The minimum number of past performance records for similar size, scope, and complexity to this requirement is five (5). The maximum number is ten (10).

14. The RFP required the Past Performance to be “Relevant” or similar in size and scope:

a) What determines a similar size for past performance, would it be $3.0 mil to mimic the bid bond requirement or between $2,000 and $1,000,000?

Answer: The similar size and scope would be between $2,000 and $1,000,000.

b) Does “relevant” or similar in Scope of Work Mimic the Mock Project or a variety of construction and trade areas such as general carpentry, general plumbing, heating, ventilating and air condition (HVAC) systems, fire suppression systems, general electrical systems, utility distribution systems, concrete construction, road paving systems, storm water systems, concrete masonry unit (CMU) construction, painting, roofing, demolition, and steel construction.

Answer: Please see C.1.1 Scope on section C – Descriptions and Specifications of the solicitation.

15. SF 1442, Item 13. A states Sealed offers in original and one (1) copy are due. Section L (c) states the technical and price proposal shall be organized into five (5) volumes as outlined in the chart below. The Chart that follows on page 114, under price, shows that only two (2) electronic copies (CD/DVD) are to be submitted with volume V. That would leave four (4) volumes to be bound and (2) electronic (CD/DVDs).

Please clarify.

Answer: Volume I: 1 CD/DVD, 1 hard copy binder; Volume II: 1 CD/DVD, 1 hard copy binder; Volume III: 1 CD/DVD, 1 hard copy binder, Volume IV: 1 CD/DVD, 1 hard copy binder; Volume V: 2 CD/DVD (1 protected format, 1 unprotected format), 0 hard copy binder. Total is 6 CD/DVDs, 4 binders.

16. Section L sentence 1, states that a bid guarantee in the amount of 20% of the bid price for the base year

($9,980,000), but 52.216-19 Order Limitations states that the contractor is not required to honor single Task orders over $500,000.00 or a combination of tasks over $9,980,000.00. Section 52.228-1 Bid Guarantee states 20% of the bid price or $3,000,000 whichever is less. (Question) Given a Bonding capacity letter from our surety is required to guarantee capacity to handle the base year value, will the bid bond required for proposal be lowered to the value of the Mock Task Order or $3,000,000 whichever is lower? The value of the base year could exceed contractors single bond capacity but lower than the contractors’ aggregate capacity.

Answer: In the solicitation, bid guarantee is required. As stated in FAR clause 52.216-19 (b) Maximum order. The contractor is not obligated to honor- (1) Any order for a single item in excess of $500,000; (2) Any order for a combination of items in excess of $9,980,000. The bid guarantee required for the proposal will not be lowered to the value of the Mock Task Order.

17. Given the circumstances and physical limitations of working in and around the COVID 19 pandemic, will the Contracting officials consider allowing an email or file transfer submission on this proposal rather than hard copies that have to be mailed which are subject to unknown delays and challenges out of the contractors control?

Answer: No.

18. The PPQ form provided in the above referenced solicitation is an unfillable PDF format and is difficult to complete. Could a fillable pdf or word document file please be provided to make it easier on the folks being asked to complete them.

Answer: A MS Word document version has been provided on beta.SAM.gov under the solicitation.

19. RFP, Section L, Proposal Submission, Page 112, Proposals shall be submitted via carrier or hand delivery to the following address: Considering the current pandemic, would the Government allow for an electronic submission instead of paper copies?

20. RFP, Section L, Proposal Preparation, ( c), Page 113, The table limits Volume II – Management Approach to 30 pages. Please confirm that the tables of contents, acronym lists, reference matrices and tables of figures are not included in the page count?

Answer: The total is 30 pages.

21. RFP, Section L, Proposal Preparation, ( c), Page 113, Section c of the Proposal Preparation stipulates that the Offeror will submit a total of 5 binders and 6 CD/DVDs. The table says that we need 2 electronic copies for Volume V, 1 protected format and 1 unprotected format. Would the Government please clarify if we are submitting a hard copy for Volume V – Price?

Answer: Volume V-Price shall be submitted in electronic format. NO HARD COPY Binder.

22. RFP, Section L, Proposal Preparation, Volume V – Price, Page 119, Financial Ability – The Government will review submitted bonding capacity to determine if Offeror(s) available bonding capacity will cover the estimated annual maximum contract value. Please clarify that the Government is referring to the bonding documents required in Volume I – RFP Documents, and we are not to submit additional bonding documents in Volume V – Price?

Answer: Yes.

23. RFP, Section L, PPR, Page 118, Offeror(s) shall submit a Past Performance Record (PPR) for all contracts awarded in the past five (5) years that are of similar scope, magnitude, and complexity to this requirement. Please confirm that contracts that have been awarded, performed or completed within the past five (5) years are acceptable.

Answer: Yes.

24. Please clarify the size of task orders on this contract. The SF 1449 lists 25,000,000 (25 Million) to 100,000,000 (100 Million) and this appears to be incorrect.

Answer: The $25,000,000 to $100,000,000 listed on the SF1442 is the magnitude of construction project. This amount is not the size of task orders.

25. In respect to submittals for Past Performance – the instructions state that offerors should provide contract references and PPQs for All contracts within the last 5 years. Is there a limit to how many, for example, we have well over 50 contracts/task orders in the last 5 years – does the Government really want us to submit over 50 references and 50 PPQ’s?

Answer: The minimum number of past performance records for similar size, scope, and complexity to this requirement is five (5). The maximum number is ten (10).

26. Can CPAR reports be submitted in lieu of PPQs?

27. May we use previously submitted PPQ's from other solicitations?

Answer: Please use your own discretion.

28. Would the government consider electronic submittal of all volumes in lieu of hard copies?

29. are we required to provide a bid bond on the "Mock Project"? Also, the company that is awarded the contract, will they be required to bond the estimated annual maximum contract value ($10,000,000.00) or only the minimum guarantee of ($50,000.00) upon award, and each task order once that dollar amount is reached?

Answer: Bid bond is not required on the “Mock Project”. The company that is awarded the contract, they are required to continuing bonding the estimated annual maximum contract value.

30. Please consider this email as a formal request for time extension to allow us to submit a proposal for the subject Solicitation.

Answer: The proposal due date has been extended.

31. In lieu of a Past Performance Questionnaire, if a project is currently available in CPARS, can the offeror include the CPARS in the past performance volume?

Answer: The Government uses CPARS to evaluate past performance. Offerors should not include their CPARS evaluations in their proposal packet.

32. Please identify the previous JOC Contract incumbent contractor and awarded contract task values.

Answer: The previous awarded JOC contract number is W9124M18D0002, please refer to website https://www.fpds.gov for more information.

33. Please advise if this is a New Contract (OR) if there is an Incumbent. If yes, please provide the information for the incumbent.

Answer: The previous awarded JOC contract number is W9124M18D0002, please refer to website https://www.fpds.gov for more information.

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 30-Mar-2021 02:00 PM to 02-Apr-2021 02:00 PM.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

GENERAL STATEMENT OF WORK STATEMENT (SOW) FOR

JOB ORDER CONTRACT (JOC)

INDEFINITE DELIVERY/INDEFINITE QUANTITY

US ARMY FORT STEWART (FS)/HUNTER ARMY AIRFIELD (HAAF)

Part I

INTRODUCTON AND SCOPE

C.1. Introduction. This Statement of Work applies to a Firm Fixed Price (FFP) Indefinite Delivery-Indefinite Quantity (IDIQ) JOB ORDER CONTRACT to provide construction services for a broad range of military sustainment, restoration, modernization, and construction projects, in support of U. S. Army Fort Stewart (FS) and Hunter Army Air Field (HAAF), Georgia (GA). The contract is intended to provide the Fort Stewart Garrison Commander and the Directorate of Public Works (DPW) the capability to provide timely and quality minor construction, sustainment, renovation and modernization projects for the facilities and components, which support the Soldiers, family members and civilians of the 3rd Infantry Division. Individual job orders will be issued under the IDIQ contract. The Government will not exercise any supervision or control over the Contractor employees.

The Contractor shall perform to the standards specified in this SOW. The Contractor shall be accountable to the Government for Contractor, Subcontractor personnel and for the quality and timeliness of work.

C.1.1 Scope. The Contractor shall provide all parts, labor, tools, equipment, materials transportation and supervision necessary to complete each Job Order placed against the IDIQ Contract at FS and HAAF, GA in accordance with the terms and conditions of the contract, each specific statement of work, specifications, and drawings. Individual Job Orders will vary in size and scope. Job Orders will encompass work in a variety of construction and trade areas;

such as general carpentry, general plumbing, heating, ventilating and air condition (HVAC) systems, fire suppression systems, general electrical systems, utility distribution systems, concrete construction, road paving systems, storm water systems, concrete masonry unit (CMU) construction, painting, roofing, demolition, and steel construction. All general construction related trade disciplines and managerial positions will be included along with some specialty technicians.

C.1.2 JOC System. The Contractor shall use the JOC system to prepare and submit Job Order Proposals, subcontractor lists, and other requirements specified by the JOC contract. The Contractor shall ensure all Contractor employees are trained and qualified on the use of the applications for use within the JOC program and submission of Job Order Proposals

C.1.3 Work by the Government. The Government reserves the right to undertake performance by Government personnel or other Contractors, for the same type or similar work as contracted for, as the Government deems necessary or desirable, and to do so will not breach or otherwise violate the contract, in accordance with Job Order Contracting Guide.

C.1.4 General Contract Requirements.

C.1.4.1 The Contractor shall complete the Sustainability Management System Awareness Training video available on the internet at https://home.army.mil/stewart/index.php/about/Garrison/DPW/environmental/prevention-and-compliance/sms and provide proof of completion to the COR within 10 calendar days of contract award. This requirement apply to all key personnel.

C.1.4.2 Contractor employees performing work under the contract shall be able to read, write, speak, and understand the English language in order to effectively carry out all contract requirements. They shall have a command of both the written and spoken English language to properly clearly, and effectively communicate in person or via electronic devices (telephone or Email) with co-workers, customers, and the general public.

C.1.4.3 General Protection/Security Policy and Procedures. All Contractor employees performing work under the contract shall comply with applicable installation, facility and area commander installation/facility access, local security policies and security procedures provided by the Security Manager Government representative. The Contractor shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor employees shall comply with all personal identity verification requirements as directed by Department of

Defense (DoD), HQ Department of Army (DA) or local policies. In addition to the changes otherwise authorized by the contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor and subcontractor security matters or processes.

C.1.4.4 Emergency Medical Treatment: Emergency medical treatment will be provided by the Winn Army Community Hospital in order to prevent undue suffering or loss of life. Emergencies will be treated only during the period of emergency and appropriate action will be taken to discharge or transfer such patients as soon as the emergency period ends. Charges for medical care will be at the prevailing rate and at the Contractor's expense.

C.1.4.5 Health and Safety: The Contractor and Contractor employees shall comply with all applicable existing post regulations on Government controlled property. The Contractor shall comply with all applicable Occupational Safety and Health Administration (OSHA) Regulations, to include Coronavirus (COVID-19) prevention measures and precaution measures in accordance with Centers for Disease Control and Prevention (CDC) guidelines and Fort Stewart/HAAF garrison command policies. Contractor shall comply with the safety provisions as outlined in "Safety and Health Requirements Manual,” EM 385-1-1 and installation policies. These regulations can be obtained from the FS Commander, Mission Installation Contracting Command (MICC), Building 621, FS, GA.

C.1.4.6 Contractor Employee Removal: The Government reserves the right to require removal of any Contractor employee from the job site who endanger persons or property, or whose continued employment is inconsistent with the interest of military security. The Government also reserves the right to require the Contractor to remove from the job site, any employee found to be under the influence of alcohol, drugs or any other incapacitating agent or any employee involved in the theft of Government property. The removal from the job site of such personnel shall not relieve the Contractor of the requirement to provide Contractor employees to perform services.

C.1.5 Installation Access Control Requirement

C.1.5.1. Contractor and their employees requiring access to the installation will be required to comply with the installation access control policy/procedures. The Government will not be responsible for damages due to delay/stoppages caused by failure to comply. At times, depending on the level of access control, it might take individuals longer than normal to get on or off the installation. Such time periods are not to be considered the basis of a claim against the Government.

C.1.5.2 Contractor shall coordinate with the Contracting Officer’s Representative (COR) to obtain installation access prior to start of work.

C.1.5.3. Government issued access cards are government property and must be relinquished to the Department of Emergency Services (DES) office upon request of the Government, termination of an employee or expiration of the contract.

C.1.5.4. All personnel employed by the Contractor or any representative of the Contractor entering the Government installation shall conform to all security regulations in effect during the contract period and shall be subject to such checks as may be deemed necessary to assure that no violations occur. No Contractor employee or representative will be permitted on the installation when such check reveals that his or her presence would be detrimental to the physical or operational security of the installation.

C.1.6. Contractor Employee Conduct.

C.1.6.1 General. Contractor and Contractor's employees, to include subcontractor personnel, shall be subject to the same general rules of conduct while on the installation that apply to Government civilian employees. The Government reserves the right to refuse installation access to any Contractor employee if the Contracting Officer (KO) determines it to be in the best interests of the Government. The Contractor will be required to respond within two (2) work days from the time contacted by the KO or his/her designated representative regarding conduct of Contractor employees.

C.1.6.2. The Contractor shall take appropriate personnel action, as required, in event employees become involved with civilian or military authorities as a result of misconduct.

C.1.6.3 The Contractor shall comply with the Homeland Security Presidential Directive 12 (HSPD-12) issued 31 Dec 13.

C.1.6.4. When passing troops in formation or jogging, FS and HAAF speed limit is 10 mph.

C.1.7 Environmental Compliance.

C.1.7.1 The Contractor shall comply with all Federal, State, and Local environmental laws and regulations. In case of a conflict among these laws and regulations, the most stringent law or regulation shall apply. If Contractor noncompliance with any applicable environmental law or requirement, the Government incurs any cost (e.g., the cost of cleaning up a hazardous waste spill); the Contractor shall indemnify the Government and provide reimbursement for these costs. If a Federal, State, or Regulatory Agency assesses any fine, penalty, or fee against the Government that is attributable to Contractor noncompliance with any environmental law or requirement, the Contractor shall indemnify the Government for the amount of the fine and other Government costs attributable to the violation. This provision is not intended in any way to waive the Government's rights under any other provision of the contract.

C.1.7.2. Contractor shall support all Executive Order (EO) 13514 goals to include the mandates to divert fifty percent (50%) of Municipal Solid Waste from the waste stream (via recycling) and to reduce our water consumption by two percent (2%) each year. The Installation Command Recycling Policy Memorandum is available at https://home.army.mil/stewart/index.php/about/Garrison/DPW/environmental/prevention-and-compliance/recycling.

C.1.8 Environmental Protection

C.1.8.1 General. Solid, liquid, and gaseous wastes. The Contractor shall be responsible for the proper disposal of all solid, liquid, and gaseous waste to include asbestos in accordance with all Federal, State, and Local codes and regulations, together with the following requirements:

C.1.8.2. Discharge of any waste into the environment, storm or sanitary sewers is prohibited.

C.1.8.3. The storage of any liquids except those for human consumption shall have secondary containment. The use of earthen berms as secondary containment is prohibited.

C.1.9. Disposal of debris, scrap and recyclables.

C.1.9.1 General. All debris, scrap, and trash caused by the operations under the contract shall be removed at the end of each work day. All of the debris/trash material shall be properly disposed of at the appropriate locations, i.e.

State regulated landfill located off the installation. All recyclables and/or salvage materials/equipment shall be transported to the appropriate Recycle Center, or Defense Reutilization and Marketing Office (DRMO), or as directed by the KO. When the recyclable material is appropriate for a recycle bin, the Government will provide the recycle bins to the Contractor. The contractor must coordinates with the COR to obtain the recycle bin.

C.1.9.2. Burning of materials and debris. No materials or debris shall be burned on FS and HAAF, GA.

C.1.9.3. Covered Chutes. All chutes for refuse, and the like, shall be covered or of such a design to fully confine the material to prevent the dissemination of dust.

C.1.9.4. The Contractor shall coordinate all activities, which may require environmental documentation, or State environmental permits with the DPW Contract Management Branch, as applicable.

C.1.9.5. Preserving Historical and Archeological Finds. The Contractor shall obtain clearance from the DPW Environmental Division prior to conducting any activities that have the potential to disturb significant cultural resources. Cultural resources are historic and prehistoric archeological sites, as well as buildings, structures, cemeteries, and in some cases, objects that are older than 50 years. Actions taken without coordination with the DPW Environmental Division that cause damage to significant resources may result in claims assessed against the Contractor for costs of mitigating the damage, AR 200-1, National Historical Preservation Act.

C.1.9.6. Removal of lighting and ballasts. All fluorescent light bulbs, high density discharge lamps (HD), or lighting ballasts are considered unsalvageable material and shall be recycled by a recycling center approved by the DPW Contract Management Branch.

C.1.9.7. Shipping documents (e.g. manifests, bills of lading, land ban forms, waste profiles) for transportation of hazardous material/wastes off-site shall be submitted for approval and signature to the Hazardous Waste Manager, Environmental Division, DPW at least three (3) calendar days prior to shipment of the material/wastes. These documents shall be completed in accordance with Local, State and Federal laws and regulations. In case of conflict among these laws and regulations, the most stringent law or regulation shall apply. Coordination for the documents shall be made through the DPW Contract Management Branch.

C.1.9.8. Borrow Material. The Contractor shall normally be required to procure all borrow material and top soil used on Job Orders issued under the contract from off Installation sources. The COR may approve the Contractor to use an on Installation borrow area. In these cases, the Contractor shall open, operate, and close the borrow area in strict compliance with all guidelines and regulations set forth by the FS Environmental and Natural Resources Division and by the Georgia State Soil and Water Conservation Commission. If local fill material is needed, a Borrow Pit Excavation Application must be completed and approved by the FS DPW Environmental Office prior to receiving a Borrow Pit Permit. Any borrow pit requests shall be coordinated through the DPW Contract Management Branch.

C.1.9.9. If a building upgrade/renovation project or new construction will require installation of a sanitary lift station, an alarm and fence surrounding the perimeter of the lift station is required, as is permitting for the lift station with the State of Georgia. Permitting shall be accomplished through the FS DPW Environmental Office;

coordination for all permits shall be through the FS DPW Contract Management Branch. For building upgrades/renovations or new construction, a Supervisory Control and Data Acquisition (SCADA) System must be installed that is compatible with the current system used on the Installation, along with an emergency electric generator.

C.1.9.10. All potable water lines on FS/HAAF must include a water meter and backflow preventer. These should be clearly identified as a requirement for all Contractors working on the Installation and must be clearly identified on all design submittals, such as specifications, design analysis, and drawings. In accordance with (IAW) the Georgia Water Stewardship Act, all construction must conserve water by installing the following:

1.) Toilets that do not exceed 1.28 gallons per flush.

2.) Showerheads that allow a flow of no more than an average of 2.5 gallons of water per minute at 60 pounds per square inch of pressure.

3.) Urinals that use no more than 0.5 gallons per flush.

4.) Lavatory faucets that use no more than 1.5 gallons per minute.

5.) Kitchen faucets that allow a flow of no more than 2.0 gallons per minute.

Construction is defined as the erection of a new building or the alteration of an existing building in connection with its repair or renovation or in connection with making an addition to an existing building and shall include the replacement of a malfunctioning, unserviceable, or obsolete faucet, showerhead, toilet, or urinal in an existing building.

C.1.9.11. All major renovation, repair or alteration of Federal buildings must comply with the U.S. Environmental Protection Agency Guiding Principles for Federal Leadership in High Performance and Sustainable Buildings. The Installation should make annual progress toward 100% conformance with the Guiding Principles for its existing building inventory by ensuring that all projects: 1. Employ integrated design principles; 2. Optimize Energy Performance; 3. Protect and Conserve Water; 4. Enhance Indoor Environmental Quality; and 5. Reduce Environmental Impact of Materials.

C.1.9.12. The Contractor shall obtain concurrence from FS DPW, Environmental Management Division, and U.S.

Army Garrison FS/HAAF for all standing operating procedures, plans, and operations involving disposal, handling, storage, and use of any materials, which could possibly impact the environment in any media (air, water, ground, noise). This concurrence shall be coordinated through the DPW Contract Management Branch.

C.1.9.13 The Contractor shall comply with applicable Federal Acquisition Regulation (FAR) Part 52 contract clauses that are listed in the contract, that are applicable and as prescribed in FAR Part 23 and EO 13423 and EO 13514.

C.1.9.14. Noise Control

C.1.9.14.1 The Contractor shall comply with all applicable federal, state and local laws, ordinances, and regulations relative to noise control.

C.1.9.15. Trucking

C.1.9.15.1 The Contractor shall load all trucks leaving the site with loose debris in a manner that will prevent dropping of materials on streets. All vehicles transporting hot-mix mixtures, sand, base course material, surfacing aggregates or dirt for work performance under the contract and traveling in excess of 35 mph over post area streets or main access roads of FS/HAAF shall have the materials covered with a tarpaulin, canvas, or shall be loaded a minimum of 6 inches below the top of the sideboards to avoid spillage of materials. The Contractor shall be responsible for cleaning up any materials that fall from the trucks.

C.1.9.16. Elevators

C.1.9.16.1. Any temporary use of an existing elevator shall be arranged with the COR and subject to Government controls. Such use will be of an intermittent nature. The Contractor shall provide and maintain suitable and adequate protection covering for the elevator machinery, the hatchway entrance, and the interior of elevator during the period of temporary use. Loads in excess of the rated capacity of the elevator will not be permitted.

C.1.9.16.2. The Government will bear the cost of electrical current for the operation of the elevator. On completion of the work, the Contractor shall remove the protective coverings together with any resultant dirt and debris, and leave the equipment in a condition equal to that which the Contractor found it. The Contractor shall be responsible for bearing the cost of repair for all damages that occurred because of the Contractor’s use and/or construction operation.

C.1.10 Safety and Health

(a) Applicable Publications. The publications listed below form a part of this SOW specification to the extent referenced. The publications are referred to in the text by basic designation only.

(b) Code of Federal Regulations (CFR). OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206; OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both parts 1910 and 1926, as they relate to construction safety and health. It is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402.

National Emission Standards for Hazardous Pollutants (40 CFR, Part 61) Federal Standard (Fed STD): 313A Safety Data Sheets, Preparation and the Submission of:

Safety and Health Requirements Manual, EM 385-1-1.

Use of Asbestos Containing Material, ETL 1110-1-118.

Policy and Guidelines for Asbestos Management, DA Circular 40-834.

C.1.10.1. Safety, Health, and Accident Prevention Plan. The Contractor will be responsible for developing a Safety, Health, and Accident Prevention Plan. This plan must be formatted IAW the 30 November 2014 of the EM 385-1-1, and all paragraphs must be in the order listed in the EM. This plan shall be fully developed and submitted to the Government for approval after contract awarded.

C.1.10.2. Definition of Hazardous Materials. Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910. Those most commonly encountered hazardous materials include asbestos, polychlorinated biphenyls (PCBs), explosives, and radioactive material, but may include others not listed. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, pipe covering, shingles, siding, roofing felt, mastic floor tiles and other common sources of asbestos.

C.1.10.3. Asbestos

(a) The Contractor is warned that exposure to airborne asbestos has been associated with four diseases: lung cancer, certain gastrointestinal cancers, pleural or peritoneal mesothelioma and asbestosis. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke, and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.

(b) The Contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in area(s) where contract work is to be performed. Asbestos-containing material (ACM) is any material that contains more than one percent asbestos by weight. Friable ACM is material that with hand pressure can crumble, pulverize or reduce to power when dry. Nonfriable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturant, impregnant or coating. Non-friable ACM does not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities.

(c) Care must be taken to avoid releasing, or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA) has set standards at 29 CFR 1910.1001 for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures, and other measures that must be taken when working with or around asbestos-containing materials. 29 CFR 1910.1001 has been identified as applicable to construction and 29 CFR 1926.55 for gases, vapors, fumes, dusts and mists). The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.140-156 for the control of asbestos emissions to the environment and handling and disposal of asbestos wastes.

(d) Friable ACM is not permitted by current criteria and shall not be used in new construction or modification projects (ETL 1110-1-118, 27 May 1983).

(e) The Contractor will identify the maintenance, modification, or demolition activities where exposure to asbestos dust may occur from previously installed friable or non-friable ACM. All precautions, to include proper work practices, medical surveillance, respiratory protection, industrial hygiene, and environmental protection requirements of OSHA (29 CFR 19210.1002), EPA (40 CFR 61.140-156) and U.S. Army Center for Public Works Technical Bulletin (PWRB) 200-1-144, Toxics Management, as applicable, shall be strictly adhered to.

(f) The Government will identify the known existence of asbestos in areas where work is to be performed under individual Job Orders prior to the issuance of the order. However, the Contractor shall identify and report any unforeseen findings of asbestos to the COR prior to initiating any actions under a Job Order.

(g) “Asbestos”, including chrysotile, ammosite, crocidolite, tremolite asbestos, anthophyllite asbestos, actinolite asbestos and any of these materials that have been chemically treated and/or altered is prohibited from incorporation into the work under the contract. This prohibition does not apply to nor prevent the removal and disposal of asbestos materials.

C.1.10.4. Safety Assurance C.1.10.4.1. Preconstruction Safety Meeting. Representatives of the Contractor shall meet with the COR prior to the start of repair, alteration or construction activities for the purposes of reviewing the Contractor's safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under the contract. The Contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract.

This meeting may be held in conjunction with the preconstruction conference, if so directed by the KO. The level of detail for the safety meeting is dependent upon the nature of the work and the potential inherent hazards. The Contractor's principal on-site representative(s), the general superintendent and his/her safety representative(s) shall attend this preconstruction safety meeting.

C.1.10.5. Compliance with Regulations. All work, including the handling of hazardous materials or the disturbance of dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1926/1910. Work involving the disturbance or dismantling of asbestos or asbestos-containing material; the demolition of structures containing asbestos; and/or the disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subparts A and B, ETL 1110-1-118 and U.S. Army Center for Public Works Technical Bulletin (PWRB) 200-1-144, Toxics Management. All work shall comply with applicable Federal, State, municipal safety requirements and regulations. Where there is a conflict between applicable regulations, the most stringent shall apply.

C.1.10.6. Contractor Responsibility. The Contractor shall assume full responsibility pertaining to the health and safety of its Contractor employees during the execution of work, and shall hold the Government harmless for any action taken on its part or that of its employees or subcontractors, which results in illness, injury, or death.

Contractors are required to report all accidents and injuries to the KO, the Installation Safety Office, Fort Stewart, and COR within four (4) hours. AR 385-40 requires that accidents and injuries be reported within seven (7) calendar days to the U.S. Army Safety Center. The Contractor shall prepare a Government-Furnished Department of the Army (DA) Form 285, Report of Army Accident, and submit it to the COR within seven (7) calendar days from an accident involving personnel injuries or property damages. A copy of the completed DA Form 285 shall be furnished to the KO as well. A copy of Workmen Compensation Reports or information provided telephonically to the Public Safety Business Center, Telephone 912-767-8132/7880 will suffice as notification. The COR and/or the Installation Safety Office may visit the work site to monitor for compliance with safety regulations.

C.1.10.7. Accident Prevention Plan (Indefinite Delivery Type) A Hazard Analysis/Safety Plan may be required for individual Job Orders after the Contractor’s Accident Prevention Plan is approved on the contract. The requirement for the Contractor to submit a Hazard Analysis/Safety Plan for individual Job Orders shall be contingent on the type and/or complexity of work to be performed on a particular Job Order. The COR shall make the determination for the requirement of a Hazard Analysis/Safety Plan for individual Job Orders. The Contractor shall furnish the Hazard Analysis/Safety Plan at no additional cost to the Government.

C.1.10.8. Fire Prevention and Protection

(a) The Contractor shall comply with fire prevention practices as set forth by the National Fire Protection Association in the National Fire Code and other recognized fire prevention agencies and Installation regulations. The Contractor shall obtain a written fire/hot permit from the Installation Fire Marshal for use of open flame devices, such as blow-torches, portable furnaces, tar kettles, or gas and electric welding and cutting equipment in, on, or within fifteen (15) feet of buildings. The Contractor shall be liable for any fire loss to Government property proximately caused by negligence or willful misconduct on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of the contract.

(b) Emergency Reporting Procedures. In the event of an emergency on FS/HAAF, the Contractor shall dial 911, or the Installation Emergency Hotline at 866-586-3116.

(c) The Contractor shall be responsible for securing a valid excavation permit prior to commencing any excavation on FS/HAAF. Excavation permits may be obtained by calling -811- 282-7411. The Contractor shall be responsible to maintain the location markings throughout the life of the Job Order.

C.1.10.9. Hazardous Materials. The Contractor shall bring to the attention of the COR any material suspected of being hazardous which he encounters during the execution of the work. A determination will be made by the KO as to whether the Contractor shall perform tests to determine if the material is hazardous. If the KO authorizes the

Contractor to perform tests and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required, subject to an equitable adjustment under the terms of the contract. Only the KO can approve a contract change to the contract or individual Job Orders.

C.1.10.10. Materials and Equipment. Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with the applicable regulations.

C.1.11. Asbestos Removal for Disposal C.1.11.1. Permits. The Contractor shall obtain any necessary permits from the State of Georgia and coordinate all asbestos removal projects with the FS DPW Environmental Branch twenty (20) calendar days prior to any asbestos removal operations.

C.1.11.2. Permits and Notifications. Obtain and submit necessary permits in conjunction with asbestos removal, hauling, and disposition, and provide notification of such actions at least ten (10) work days prior to starting work.

FS/HAAF asbestos projects must comply with requirements of the National Emissions Standards for Hazardous Air Pollutants (NESHAPS), EPA notification forms shall be provided to the FS DPW, Environmental Branch. The Contractor shall send written notification to:

Georgia Department of Natural Resource Environmental Protection Division

Lead Paint/Asbestos Program 4244 International Parkway

Suite 104 Atlanta, GA 30354

Phone Number: (404) 363-7026

C.1.12. Salvageable and Repairable Materials C.1.12.1. All existing materials shall remain the property of the U.S. Government unless otherwise indicated.

C.1.12.2. Materials classified as salvageable, serviceable, repairable, or recyclable in the contract technical provisions/plans or by the KO shall remain the property of the U.S. Government and shall be coordinated with the KO or the COR as to disposition within FS/HAAF. Components and materials classified as stated above shall be dismantled, thoroughly cleaned, and prepared for storage or recycle. All other materials demolished or otherwise removed as part of the work required in a Job Order shall become the property of the Contractor and the Contractor shall be responsible for proper disposal of said materials.

C.1.12.3. Prior to commencing work a joint inventory will be conducted by the Contractor, the COR, and the quality assurance/inspection agency. During the inventory, salvageable, serviceable, repairable, and recyclable materials will be identified. The Contractor will be given a copy of the joint inventory record and will be accountable for property as indicated above in paragraph C.1.12.2. This joint inventory will in no way limit or preclude the COR from designating additional materials to the stated classification above during the life of the contract or individual Job Order.

C.1.13. Excavation Permit. The Contractor shall be responsible for securing necessary…