Q&A Revision
(First & Second Round of Questions)
RFP W9124J‐20‐R‐EE15 (ECCS MAIDIQ)
4 January 2021
Q&A First Round:
Question 60. Attachment 2, PWS, Live Task Order, Stormwater Phase 1 Assessment, Section 5.5, Page
18. The PWS identifies 430 BMPs for the APG and Adelphi facilities. Please provide a breakdown of the numbers and types of BMPs (treatment units, drainage structures, management practices, etc).
Revised Answer: Current sites are listed in the associated SWPPPs ‐ “Attachment 5(i) ‐ APG Marinas
SWP3_Final”, “Attachment 5(j) ‐ APG SWP3_Final”, “Attachment 5(m) ‐ APG‐EA WWTP SWP3_Final”, and “Attachment 5(k) – Tanks Pipes P2 Plan”
Q&A Second Round:
Question 1: In reference to the Q&A posted for W9124J‐20‐R‐EE15 ECCS MAIDIQ, specifically Question
12 (below), the Government indicates that the individual permits (15DP2517 and 15DP2531) are provided as "...Attachment 5(q) and Attachment 5(r)..." Those attachments, however, pertain to the
Fort Irwin project. We are not finding the individual permits in the posted files and referenced in the
Government response. Can those be reposted?
Revised Answer: Yes, please see Attachment 5(s) ‐ APG permit 13DP2531 and Attachment 5(t) ‐ APG permit 15DP2517. RFP (conformed copy) Section J – Solicitation Attachment List/page 23 has been revised.
Question 25: The Army’s response to Question 10 provided two new references: “Attachment 5(p) ‐
APG SWM BMPs” and “Attachment 5(l) ‐ Adelphi Laboratory Center BMPs”. However, the post‐ construction BMP inventory contained within these new references do not total to 430 BMPs as noted in “Attachment+2+‐+PWS+Live+Task+Order_Seed+Project_+Final_20+DEC+2020”. Please clarify.
Revised Answer: The contractor is expected to inspect the 421 Historical BMPs listed in Attachment 5(p)
‐ APG SWM BMPs as well as the 66 listed in the planned/progress tab that are complete as of 1/1/2021 in the same spreadsheet. Additionally, the contractor is expected to inspect the 17 BMPs listed in
Attachment 5(l) ‐ Adelphi Laboratory Center BMPs. The total BMPs to be inspected is 504.
Question 26: The Army’s response to Question 60 referred to the following SWPPPs for details regarding post‐construction BMPs: “Attachment 5(i) ‐ APG Marinas SWP3_Final”, “Attachment 5(j) ‐ APG
SWP3_Final”, “Attachment 5(m) ‐ APG‐EA WWTP SWP3_Final”, and “Attachment 5(k) – Tanks Pipes P2
Plan”. However, these SWPPPs address industrial stormwater BMPs. Please clarify whether the BMPs contained within these referenced SWPPPs are to be included in the inventory of 430 post‐construction
BMPs to be inspected according to Section 5.5.1.5 of “Attachment+2+
+PWS+Live+Task+Order_Seed+Project_+Final_20+DEC+2020”.
Revised Answer: See “Attachment 5(p) ‐ APG SWM BMPs” and “Attachment 5(l) ‐ Adelphi Laboratory
Center BMPs”. Each of those attachments breaks down what type of BMP it is (wet pond, bioretention, etc.)