This is a Statement of Work (SOW) for the de-installation and installation of Air Traffic Control (ATC) equipment at Hatch Stagefield, Fort Rucker, Alabama. The contractor must provide all personnel and supervision to remove existing ATC equipment from the current Air Traffic Control Tower (ATCT) and install it into a newly constructed ATCT facility, including all required cabling and grounding in compliance with FAA-STD-019e and MIL-STD-188-124(B) standards.
The required equipment to be relocated includes one Interim Voice Switch Replacement (IVSR) with four positions, two radio racks, four TACO antennas, one FM antenna, one FM transceiver, two CM-300 VHF transceivers, three CM-300 UHF transmitters and receivers, one NAS Voice Recorder, an FMQ-13 wind measuring system with two indicators, and one rack-mounted uninterrupted power supply. Key contractor tasks include conducting an initial site survey to develop an Installation Bill of Materials; installing 12 runs of heliax cabling with antenna connectors; installing radio equipment racks; designing and procuring four communications consoles for the tower cab; performing operational testing witnessed by government representatives; and maintaining ISO 9001:2008 quality assurance compliance. The contractor must designate a single program management point of contact, participate in weekly progress meetings, and maintain complete financial accountability and program tracking records. Government-furnished items include the tower structure, all radios, power systems, antennas, the IVSR unit, and heliax cable. The solicitation is a 100% Total Small Business set-aside competed as a Firm Fixed Price contract under NAICS 238210 and PSC N059, awarded by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001_W9124G-26-R-A007.pdf | ||
| Attachment 6 RFP Questions Compiled.pdf | ||
| SITE VISIT Sign-In Sheet.docx | DOCX document | |
| W9124G-26-R-A007.pdf | ||
| Attachment 1_Hatch ATC Equipment Movement SOW.pdf | ||
| Attachment 3_Evaluation Criteria.pdf | ||
| Attachment 5_Past Performance Questionnaire.docx | DOCX document | |
| Attachment 4 Pricing Schedule.xlsx | XLSX spreadsheet | |
| Attachment 2_Instructions to Offerors.pdf | ||
| SITE VISIT Access to Fort Rucker.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Air Traffic Control Equipment De-Installation and Installation For Hatch Stagefield Fort Rucker, Alabama
1. Program Objectives
The contractor shall provide all personnel and supervision required to perform the de-installation of Air Traffic Control (ATC) equipment in the existing Air Traffic Control Tower (ATCT) at Hatch Stagefield, Fort Rucker, Alabama and the installation of the ATC equipment into newly constructed ATCT as per building design. Installation shall include all required cabling and grounding as specified in the appropriate regulations and standards FAA-STD-019e and MIL-STD-188-124(B).
2. Equipment
Equipment to be de-installed and relocated to the new tower will consist of the following:
· One Interim Voice Switch Replacement (IVSR) with three control positions and one maintenance position.
· Two radio racks.
· Four TACO Antennas
· One FM Antenna
· One FM Transceiver
· One CM-300 VHF receiver
· One CM-300 VHF transmitter
· Three CM-300 UHF transmitters
· Three CM-300 UHF receivers
· One NAS Voice Recorder (NVR)
· FMQ-13 (V) 2 Wind Instrument System with two indicators
· One rack mounted Uninterrupted Power Supply (UPS)
3. Survey
The contractor will require a Site Survey at the start-up of the project in order to identify the materials required and the most feasible course of action required to effectively relocate all equipment necessary to support the new ATCT and to establish an Installation Bill of Materials (IBOM).
4. Applicable Documents
The most current revision at the time of contract award of the following documents listed in the SOW or any superseding document from a part of this SOW to the extent specified herein. In the event of a conflict between the documents referenced herein and this SOW, the requirements of this SOW shall be the superseding requirement.
· FAA-STD-19E; Lightning Protection, Grounding, Bonding, and Shielding Requirements for Facilities
· FAA-STD-020B; Transient Protection, Grounding, Bonding, and Shielding for Equipment
· MIL-STD-188-124B; Grounding, Bonding and Shielding
5. Program Management
The contractor shall designate a single program management point of contact. The contractor shall develop management plans to ensure that all elements of this effort are successfully executed within the program budgets and schedules.
6. Meetings, Reviews and Inspections
An initial site survey will be required to identify the materials necessary to complete the equipment installation. The result of this survey shall be a combined Site Survey Report (SSR) / Project Concurrence Memorandum (PCM). Additional meetings may be required once a week to discuss progress, issues and proposed solutions. These weekly meetings may be telephonic.
7. Program Tracking and Reporting Requirements
The contractor shall maintain a record of the program schedules, action items, problem areas, and problem resolutions. The contractor shall also ensure that complete financial accountability is maintained and that all Contract Deliverable actions are delivered to the Government in accordance with the CDRC requirements. The contractor shall notify the Government of program issues that may impact the execution of this SOW. This will be accomplished through an email to the customer notifying of the project status.
8. Required Tasks
The contractor shall provide the procurement, installation, engineering, and modification services consisting of:
· Installation of the IVSR provided GFE to include all hardware, software and cabling including the installation and cabling for three operator positions within the tower cab and one maintenance position in the equipment room. Movement of the IVSR requires prior coordination with and supervision of Federal Aviation Administration (FAA) personnel.
· Install 12 runs of ½ Inch Heliax Cabling to include connectors and four TACO type antennas for the 12 radios provided GFE with all associated hardware terminating at supplied antenna patch panel. Label all antenna cables (i.e. UHF/VHF and to which antenna the cable is run. Install RG-213 from Antenna Patch Panel to radios.
· Install 1 FM Radio Antenna and run antenna cable to supplied patch panel.
· Install IDF Blocks in Radio Equipment Room. Label all circuits to include the labeling of lightning protection.
· Installation and cabling for two radio racks provided GFE for the mounting of radios within the equipment room.
· Install and cable Digital Audio Legal Recorder or NVR into the equipment room along with all associated hardware and cabling.
· Install and cable FMQ-13 with two indicators in tower cab and on the wind bird.
· Design, engineer, procure and install four (4) communications consoles into new ATCT cab. The contractor shall procure and provide all new hardware and grounding to complete the consoles installation.
9. Acceptance Testing
The contractor shall perform operational testing of the systems affected by the newly relocated and installed equipment. The operational testing will be verified and witnessed by a government (NAVAIDS) representative. Based on the successful completion of the operational testing, a Technical Acceptance Recommendation (TAR) report will be signed by the government and the Contractors.
10. Logistics and Acquisition
The contractor shall develop and implement material acquisition and subcontracting action plans to ensure that material acquisitions and subcontracts in support of this effort are successfully accomplished within the program budgets and schedule constraints. The contractor shall utilize the Government Supply system as the first option for accomplishing material acquisitions in support of the effort.
11. Subcontracts
The prime contractor will be required to pass on to any subcontractors and vendors the same or similar requirements as levied on them by this SOW. These requirements shall flow down to the lowest tier subcontractor or vendor associated with this project as necessary during the execution of this effort.
12. Quality Assurance
The contractor shall assure quality through implementation of a quality program that is compliant with ISO 9001.2008. The contractor will provide the government with a Quality Control Plan accepted by the government within 30 days of contract award. Government Quality Assurance personnel will conduct contract quality assurance and surveillance IAW the Quality Assurance Surveillance Plan (QASP).
13. Security and Safety
The Standards that apply to contractor operations on U. S. Military Bases are those specified for the operation in question by the Federal Occupational Safety and Health Administration (OSHA), the Environmental Protection Agency (EPA) and other Federal Regulatory bodies. The contractor does not have the legal or contractual authority to operate outside of the standards specified by regulatory agencies even if the Facility Operators have waivers approved for military and contract personnel approved by local commanders – even if the companies or other contract personnel recognize such waivers.
14. Travel
Contractor personnel or any representative of the contractor shall be required to travel to Fort Rucker, Alabama. The Joint Travel Regulations (JTR) will guide travel reimbursement.
15. Government Furnished Items (GFE)
In addition to those facilities, data, services, equipment, and materials provided under this SOW, the government shall provide the items listed in the subsections without cost to the contractor. GFE includes:
· Tower Structure
· 1 each VHF transmitter CM-300
· 1 each VHF receiver CM-300
· 3 each UHF transmitters CM-300
· 3 each UHF receivers CM-300
· 1 each FM Radio Transceiver
· Radio racks
· 1 each Rack Mounted Uninterrupted Power Supply (UPS)
· 1 each antenna patch panel
· 12 each antenna lightning protection
· 1 each AN-FMQ-13 Wind Measuring Set with bracket & two (2) indicators
· 1 each NAS Voice Recorder (NVR)
· 4 each Taco antennas to accommodate the above transmitters and receivers
· 1 each FM Antenna
· 1 each Interim Voice Switch Replacement (IVSR) with positions
· ½ Inch Heliax Cable with Connectors
· Power
· Communications capability
· Storage for IBOM and tools from receipt through the culmination of the project
16. Hazardous Materials Chemical products used in project performance must not contain certain Class I or Class II Ozone Depleting chemicals prohibited by contract and must not contain elements prohibited for use by the contractor (perchloroethylene and trichloroethylene).