Questions and Answers 1 to 8 _ Arc Flash Labeling for Multiple Facilities.pdf
PDF 85 KB Posted
- Attached to
- Arc Flash Study and Labeling Service Federal contract opportunity
- Solicitation number
- W9124824Q2007
About this file
This document is a set of Questions and Answers related to a solicitation for an Arc Flash Study and Labeling Service contract at Fort Campbell, Kentucky. The solicitation is for a non-personal services contract issued by the Department of the Army Materiel Command Mission and Installation Contracting Command.
The key details are:
- The contractor will be required to perform arc flash studies and provide arc flash labeling at multiple facilities at Fort Campbell.
- The government will provide as-built drawings, single-line diagrams, and equipment inventories for each task order after contract award, but not prior.
- Site visits may be permitted after award, time permitting, but are not required prior to submitting a quote.
- The government will accept the use of electrical analysis software for the arc flash studies, but requires increased PPE levels due to electrical manhole configurations.
- Quotes must be submitted through the PIEE system per the solicitation instructions, while questions can be submitted via email.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_3__Pricing_Schedule_Rev 1.xlsx | XLSX spreadsheet | |
| W9124824Q2007_P00001_Arc Flash Study and Lableling Service.pdf | ||
| Questions_and_Answers_9 to 25__Arc_Flash_Labeling_for_Multiple_Facilities_Rev 1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fort Campbell, Kentucky W9124824Q2007
Questions for Arc Flash Study & Labeling
Question 1: Will there be additional technical direction in association with this task. Arc flash studies require an understanding of the quantities and types of electrical equipment such as panelboards, transformers, large motors, transfer switches, etc.
Answer 1: The as-builts we have on record will be provided post-award, in accordance with the requirements for each consecutive Task Order. If the Contractor(s) need additional information beyond that, Contractors are welcome to obtain passes and tour the installation. Post-award and time permitting, site-visits may be conducted prior to the issuance of the first Task Order.
Question 2: Will an equipment inventory be provided?
Answer 2: Equipment inventory will be provided with each Task Order, but not prior to the award for this solicitation.
Question 3: Will electrical one or single-line diagrams be provided?
Answer 3: Yes, single-line diagrams will be provided with each Task Order, but not prior to the award for this solicitation.
Question 4: Is there a device list either from a customer-provided tabulation, drawings, or a model available, as well as the study specifications?
Answer 4: Yes, device lists will be provided with each Task Order, but not prior to the award for this solicitation.
Question 5: Does this facility accept SKM Power Tool to perform the Arc Flash Studies?
Answer 5: Electrical analysis software can be used for electrical studies, but electrical analysis software packages that perform arc flash calculations do not account for an electrical manhole configuration in which the electrical worker is inside an enclosed area rather than standing adjacent to an enclosure. Increase the arc flash PPE requirements by a minimum of one (1) arc flash hazard category above the arc flash calculation result. IAW UFC 3-560-01 Para. 7.3
Question 6: Will a site visit be scheduled/required?
Answer 6: No, a site visit will not be scheduled prior to award of the base contract, but Contractors are welcome to obtain passes and tour the installation.
Fort Campbell, Kentucky W9124824Q2007
Questions for Arc Flash Study & Labeling
Question 7: Will local presence be required, or will it be taken into account in the evaluation, or will the award be made purely based on experience and pricing?
Answer 7: Please refer to Section M of the solicitation for the relevant evaluation factors. Factors not included in Section M will not be used for offer evaluation.
Question 8: Are questions/RFIs for this solicitation are to be submitted over email and not through PIEE?
Answer 8: Questions and RFIs via email are acceptable, but ensure that all Quotes are submitted via PIEE and are submitted in accordance with (IAW) the solicitation instructions.