This document is a Pricing Schedule attachment related to a federal contract opportunity for Arc Flash Study and Labeling Service at Fort Campbell, Kentucky. The attachment provides base pricing for different service sizes ranging from 25 KVA to 5000 KVA, along with multipliers to adjust pricing based on factors such as voltage, number of distribution boards, facility size, and data availability. The 5-year estimated total for the contract is $240,900. The related federal contract opportunity is a solicitation for a non-personal services contract, with a solicitation number of W9124824Q2007, issued by the Department of the Army Materiel Command Mission and Installation Contracting Command.

View the file

Other files for this federal contract opportunity

Other files attached to Arc Flash Study and Labeling Service, newest first.
File Type Posted
W9124824Q2007_P00001_Arc Flash Study and Lableling Service.pdf PDF
Questions_and_Answers_9 to 25__Arc_Flash_Labeling_for_Multiple_Facilities_Rev 1.pdf PDF
Questions and Answers 1 to 8 _ Arc Flash Labeling for Multiple Facilities.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Pricing

NOTES:
Service SizeYear 1Year 2Year 3Year 4Year 5Base cost includes all labor, materials, equipment necessary to complete all data collection, calculations, building models/drawings, reports and reviews.
25-300 KVA$ - 0$ - 0$ - 0$ - 0$ - 0*Base cost includes labeling costs. Additional labeling costs will be wrapped into below multiplier.
500 kva$ - 0$ - 0$ - 0$ - 0$ - 0**Assume that each Service Size is associated with a low Voltage Facility, one (1) Distribution Board, less than 5k SF Facility Size, and available data is sufficient. This price will establish the base and the below percentage estimates will increase the price as the complexity increases.
750 kva$ - 0$ - 0$ - 0$ - 0$ - 0
1000 kva$ - 0$ - 0$ - 0$ - 0$ - 0
1500 kva$ - 0$ - 0$ - 0$ - 0$ - 0
2000 kva$ - 0$ - 0$ - 0$ - 0$ - 0
2500 kva$ - 0$ - 0$ - 0$ - 0$ - 0
3000 kva$ - 0$ - 0$ - 0$ - 0$ - 0
4000 kva$ - 0$ - 0$ - 0$ - 0$ - 0
5000 kva$ - 0$ - 0$ - 0$ - 0$ - 0
Multiplier
Voltage into Facility
120/2080%0%0%0%0%
120/2400%0%0%0%0%
277/4800%0%0%0%0%
347/6000%0%0%0%0%
# of Distribution Boards & Equipment
1-50%0%0%0%0%
6-100%0%0%0%0%
11-150%0%0%0%0%
16 - 200%0%0%0%0%
21 - 250%0%0%0%0%
26 - 300%0%0%0%0%
31 - 400%0%0%0%0%
41 - 500%0%0%0%0%
51-600%0%0%0%0%
61-700%0%0%0%0%
Facility Size
up to 5k SF0%0%0%0%0%
up to 10k SF0%0%0%0%0%
10k to 20k SF0%0%0%0%0%
20k to 50k SF0%0%0%0%0%
50k to 100k SF0%0%0%0%0%
100k to 200k SF0%0%0%0%0%
200k to 250k SF0%0%0%0%0%
250k to 300k SF0%0%0%0%0%
300k to 500k SF0%0%0%0%0%
Data Availability
Complete As-Builts with panel schedules and one-line0%0%0%0%0%
Complete As-Builts with panel schedules0%0%0%0%0%
Partial As-Builts with panel schedules0%0%0%0%0%
Partial As-Builts w/o panel schedules0%0%0%0%0%
Other Adders
Insufficient knowledge or data to show panel/equipment locations.0%0%0%0%0%Multiplier to include additional labor to survey facilities/locate equipment
Insufficient data/calculations from electrical utility company.0%0%0%0%0%Multiplier to include labor costs associated with additional calculations
Additional electrical feeds or emergency generators tied into the facility.0%0%0%0%0%Multiplier to include labor costs associated with additional calculations

5 Year Estimate

Service SizeEst. # BLDGsYear 1Est. # BLDGsYear 2Est. # BLDGsYear 3Est. # BLDGsYear 4Est. # BLDGsYear 5
25-300 KVA2$ - 02$ - 03$ - 05$ - 08$ - 0
500 kva1$ - 05$ - 05$ - 05$ - 05$ - 0
750 kva1$ - 02$ - 05$ - 03$ - 05$ - 0
1000 kva7$ - 08$ - 05$ - 03$ - 02$ - 0
1500 kva2$ - 05$ - 02$ - 02$ - 05$ - 0
2000 kva6$ - 02$ - 02$ - 05$ - 05$ - 0
2500 kva3$ - 02$ - 02$ - 05$ - 05$ - 0
3000 kva1$ - 02$ - 02$ - 05$ - 05$ - 0
4000 kva1$ - 02$ - 02$ - 05$ - 05$ - 0
5000 kva2$ - 02$ - 02$ - 02$ - 02$ - 0
Voltage into FacilityEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased Price
120/2085$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
120/2405$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
277/48011$ 3,300.0017$ 5,100.0015$ 4,500.0025$ 7,500.0032$ 9,600.00
347/6005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
# of Distribution Boards & EquipmentEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased Price
1-53$ 900.002$ 600.002$ 600.002$ 600.002$ 600.00
6-105$ 1,500.003$ 900.003$ 900.005$ 1,500.005$ 1,500.00
11-154$ 1,200.004$ 1,200.004$ 1,200.005$ 1,500.005$ 1,500.00
16 - 202$ 600.003$ 900.003$ 900.005$ 1,500.007$ 2,100.00
21 - 251$ 300.005$ 1,500.003$ 900.002$ 600.005$ 1,500.00
26 - 302$ 600.002$ 600.002$ 600.004$ 1,200.006$ 1,800.00
31 - 402$ 600.002$ 600.002$ 600.002$ 600.002$ 600.00
41 - 503$ 900.003$ 900.003$ 900.005$ 1,500.005$ 1,500.00
51-602$ 600.003$ 900.003$ 900.005$ 1,500.005$ 1,500.00
61-702$ 600.003$ 900.003$ 900.005$ 1,500.005$ 1,500.00
Facility SizeEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased Price
up to 5k SF1$ 300.002$ 600.002$ 600.002$ 600.005$ 1,500.00
up to 10k SF1$ 300.002$ 600.002$ 600.002$ 600.006$ 1,800.00
10k to 20k SF1$ 300.002$ 600.002$ 600.002$ 600.006$ 1,800.00
20k to 50k SF6$ 1,800.005$ 1,500.003$ 900.005$ 1,500.005$ 1,500.00
50k to 100k SF5$ 1,500.001$ 300.001$ 300.009$ 2,700.005$ 1,500.00
100k to 200k SF7$ 2,100.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
200k to 250k SF2$ 600.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
250k to 300k SF2$ 600.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
300k to 500k SF1$ 300.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00
Data AvailabilityEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased Price
Complete As-Builts with panel schedules and one-line7$ 2,100.005$ 1,500.004$ 1,200.007$ 2,100.0010$ 3,000.00
Complete As-Builts with panel schedules5$ 1,500.005$ 1,500.004$ 1,200.008$ 2,400.009$ 2,700.00
Partial As-Builts with panel schedules12$ 3,600.0020$ 6,000.0020$ 6,000.0020$ 6,000.0023$ 6,900.00
Partial As-Builts w/o panel schedules2$ 600.002$ 600.002$ 600.005$ 1,500.005$ 1,500.00
Other AddersEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased PriceEst. # BLDGsIncreased Price
Insufficient knowledge or data to show panel/equipment locations.5$ 1,500.007$ 2,100.006$ 1,800.008$ 2,400.0010$ 3,000.00
Insufficient data/calculations from electrical utility company.5$ 1,500.007$ 2,100.006$ 1,800.008$ 2,400.0010$ 3,000.00
Additional electrical feeds or emergency generators tied into the facility.15$ 4,500.005$ 1,500.005$ 1,500.005$ 1,500.005$ 1,500.00

Year Total $ 38,700.00 $ 43,500.00 $ 40,500.00 $ 54,300.00 $ 63,900.00