RFI Responses_108th ADA BDE ACS_14SEP26.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
108th ADA BDE Access Control System
Solicitation number
W9124726QA035
Issued by

About this file

This file contains RFI (Request for Information) responses submitted by industry partners in response to the 108th ADA BDE Access Control System solicitation (W9124726QA035). The document is an Excel spreadsheet documenting questions and answers exchanged during the pre-award phase of this Army Materiel Command procurement. The RFI submission window closed after the site visit on 9 September 2026 at Fort Bragg, North Carolina, with responses consolidated and published on 14-15 September 2026 in a non-attribution format to all qualified offerors. These RFI responses informed a solicitation amendment (W9124726QA0350001) and revised Statement of Work issued prior to the final quote submission deadline.

The consolidated RFI responses addressed clarifications and guidance on requirements for an access control system to be implemented at two locations for the 108th Air Defense Artillery Brigade. Offerors were required to submit revised quotes by 22 September 2026 at 4:00 PM EDT via email to the Contracting Officer and Contract Specialist, with submissions organized in three volumes: Volume I (pricing in Excel format), Volume II (technical capability in searchable PDF not exceeding 25 pages addressing staffing, equipment, and project plans), and Volume III (past performance in searchable PDF not exceeding 10 pages covering up to three relevant projects from the last three years). The RFI responses document serves as the basis for understanding how industry input shaped the final solicitation requirements and conformed guidance issued to all bidders.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

W9124726QA035
RFI Tracker
QuestionAnswer
1. Will the access control systems need to be FICAM compliant?YES, FICAM COMPLIANT/STAND ALONE SYSTEM FOR BOTH facilities
a. Will the system be required to save card certificates (CAK, PIV-AUTH) and/or root certificates upon enrollment?save card certificates (CAK, PIV-AUTH) and/or root certificates upon enrollment for both facilities in addition to audit-log and reporting .
b. Will the card readers be required to verify card certificates at the reader (CAK for contactless, PIV-AUTH for keypads), or will the readers be expected to read only from the CAC’s FASC-N (FASC-N for contactless, FASC-N + PIN-to-PACS for keypads)?read only from the CAC’s FASC-N (FASC-N for contactless, FASC-N + PIN-to-PACS for keypads
2. Will the system be required to deny access upon CAC expiration dates?deny access upon CAC expiration dates for both facilities
3. X-4514 Access Control Panels: Can you please provide a photograph of the interior of the three existing Kantech enclosures?See Photos attached
4. X-4514 BOC Rear Exterior Door: Will this card reader be required to have a keypad for card and pin?KEYPAD NOT FOUND ON ORIGINAL SCOPE OF WORK. WILL BE ADDED TO THE SCOPE
x-4514 1. Please verify how many doors are present in the system. The existing Kantech control panels located in the Mechanical room have (6) composite cables going to them, but the PWS states that there are (8) doors to be upgraded.2 DOORS FOUND NOT ON ORIGINAL SCOPE OF WORK. WILL BE ADDED TO THE SCOPE, SOW WILL BE AMMENDED
x-4514 2. Verify that you intend to only utilize a CAC for entrance credentials and no intention for a prox card to be utilized.CAC for entrance credentials and no intention for a prox card to be utilized
x-4514 3. Does the Gov wish to use any additional badging for identification?No additional badging for identification
x-4514 4. Does the Gov wish to replace both existing entry hardware sets on the front entrance with electrified exit devices or (1) electrified and (1) mechanical?Yes, replace as needed
x-4514 5. Does the Gov wish to have (2) workstations attached to the new access control system (ACS)? Typically, there is an additional station in the S2 office.Just (1) workstation is required
x-4514 6. Given that the system is older and the Gov intends for cabling, peripheral security devices, and locking hardware to convey, what is the mechanism for defective items to be repaired or replaced once new system is integrated to the old system?Include a comprehensive one (1) year warranty on all newly installed hardware, software, controllers, power supplies, and cabling runs.
x-4514 (Electrical): High-resolution photos showing wire configurations for the three remaining panels in the Electrical Room.SEE ATTACHED PHOTOS
x-4514 (Front Entrance Cabling Infrastructure): High resolution photo of the cut wire. Is the conduit in the ceiling allowed to be spliced per NEC requirements?the conduit in the ceiling is allowed to be spliced per physical security requirements
(CAC requirements): Who will install the certificates in the access system? The 108th ADA BDE or DPTMS?108TH ADA BDE
(CAC Security Level): Are the CAC readers based off surface level authentication (CHUID) or certificate level authentication (PKI)?CERTIFICATE LEVEL AUTHENTICATION (PKI)
How old is the facility?BUILT IN 2011
How much square footage is in the facility?CONTACT REAL PROPERTY BRIAN VESLEY (DPW)
How stable is the power?UNSTABLE
Is there a dropped ceiling in all installation areas?YES
What type of walls are in the perimeter areas?BRICK EXTIERIOR AND DRYWALL INTERIOR
Will drilling between walls be required to run cable infrastructure?NO
Is conduit required? If so, what is the estimated total conduit footage?NOT EXPECTED FOR ANY CONDUIT TO BE REPLACED, ONLY EXCEPTION OF CONDUIT WOULD BE AT THE FRONT DOOR OF BUILDING X-4514
Are the door frames metal and concrete-filled?UNKNOWN
Please provide a comprehensive list of quantities for all required IDS items per location (e.g., motion sensors, glass-break sensors, etc.).OUT OF SCOPE 2 SYSTEMS ARE NOT TIED TOGETHER
Are there existing IDS sensors on doors? If so, please identify the doors.OUT OF SCOPE 2 SYSTEMS ARE NOT TIED TOGETHER
Who is the manufacturer of the existing IDS?OUT OF SCOPE 2 SYSTEMS ARE NOT TIED TOGETHER
Can the existing cable be reused? If so, what type of cable is currently installed?YES
Are the ceilings suspended or hard-lid construction?SUSPENDED
Are there existing cable trays for wiring above the ceilings?NO FOR BOTH BUILDINGS
Can existing wiring be utilized?YES
Is an uninterruptible power supply (UPS) required? If so, what power duration is required?YES FOR BOTH BUILDINGS, MINIMUM 12 HOUR DURATION
Are “or equal” equipment substitutions allowed?YES
Is plenum-rated wire acceptable?YES
Is after-hours access available to the contractor at no additional cost to the Government?NO FOR BOTH BUILDINGS
What is the installation height of exterior cameras, if any?10 FEET
Please provide or post responses to other questions and answers.N/A
Please provide a list of equipment and part numbers to be installed.UNKOWN
Are there pipe chases between floors?UNKOWN
What is the budget range for this project, and has funding been appropriated?YES, FUNDING HAS BEEN APPROPRIATED
Due to the high cost of parts, may the contractor invoice upon delivery of parts to the site, or are progress payments permitted?N/A
How many feet of new wire will need to be installed?UNKOWN
What type and quantity of cipher locks are required (e.g., X-10)?NONE