This is a request for information (RFI) for vertical construction services multiple award indefinite delivery indefinite quantity (MA IDIQ) contracts at Fort Bragg, North Carolina. The Department of the Army Materiel Command Mission and Installation Contracting Command will award MA IDIQ contracts to execute a broad range of maintenance, repair, and minor construction projects on real property at Fort Bragg. Work will include new construction, maintenance and repair across various trades such as carpentry, roofing, electrical, HVAC, plumbing, and demolition. During the contract period, the government will identify specific construction tasks for projects. Final proposals are due by September 24, 2021. The RFI includes questions and answers to clarify requirements and contract terms.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs
| W91247-20-R-0009 |
| Fort Bragg DPW MATOC Vertical MAIDIQ |
| RFIs (Requests For Information) |
| ID | Request | Reference | Response | Respondent |
| 1 | Can the sign in sheet from the site visit be posted so Primes can utilize it to team up with qualified sub contractors? | Please see Amendment to FINAL Solicitation | MICC | |
| 2 | Can you please post pictures of the job site from the site visit? | Photos of the site will be posted with these answers. | DPW/BV | |
| 3 | Do we submit all volumes on June 21st or will there be another date when the solicitation updates from pre solicitation to solicitation? | Please see Amendment to FINAL Solicitation for revised due dates | MICC | |
| 4 | The Draft Solicitation states MAIDIQ will be based on a general SOW and will later be defined in the individual task orders. Is this the SOW that is in the draft solicitation or will we receive this at a later date? | Please see Amendment to FINAL Solicitation for FINAL SOW | MICC | |
| 5 | During the site visit earlier this week, the attendees were told the Government would send and RFI Excel spreadsheet for contractors to use when submitting technical questions. Will the Government post the spreadsheet prior to the final release of the solicitation or after? Also, per the Amendment 0002 draft, it stated questions are due three days from the site visit on 6/9. Is this still the case? And could you clarify if those are business days or calendar days? | Attachment 7 was posted with the FINAL Solicitation. Updates were posted based on the Final Site Visit held on 1 July 2021. | MICC | |
| 6 | Please indicate if front matter (cover, table of contents, glossary, list of tables/figures, tabs) is excluded from the page limitation. | L.3.2: Page Limit excludes Cover Page, Table of Contents, Glossary of Abbreviation and Acronyms, List of Tables and Drawings and/or figures) Font: Times New Roman; Minimum Font Style: Regular: Minimum Size: 10 point | MICC | |
| 7 | On page 62 (Amendment 0002), Volume II indicates 65 pages total with 33 resume pages and Paragraph 2.4 (page 6) indicates resumes are required; however, Section L does not mention resumes. Please indicate where resumes should be presented. | Resumes for Key Personnel are required in Volume II but don't count against the page limit, which remains 65 pages; and there is no page limit for resumes. | MICC | |
| 8 | Can a different font other than Times New Roman be used for graphics to enhance readability if it is also 10 point? | Conform to the solicitation | DPW/BV | |
| 9 | On page 62 Amendment 0002), Volume II indicates 65 pages total with 33 resume pages. Please confirm that the 33 pages are included in the 65 pages total. | Resumes for Key Personnel are required in Volume II but don't count against the page limit, which remains 65 pages; and there is no page limit for resumes. | MICC | |
| 10 | Please confirm that team subcontractors’ projects who have a signed teaming agreement can be used in Volume III—Past Performance. | Confirmed; Team subcontractors’ projects who have a signed teaming agreement can be used in Volume III—Past Performance. | MICC | |
| 11 | Is the Alternate PM considered a key personnel, i.e., is a resume required for this person? | Yes, Alternate PM would act as a PM and all information for PM position is required for that individual. The APM must meet all PM qualifications, including education and experience.Another Key Personnel member (besides the PM) can be dual-hatted as the APM, as long as that Key Personnel is identified as the APM, also meets all the requirements of the APM, and can validate they will be able to meet all requirements of both roles. On any task order, including the Notional Seed Project, if another Key Personnel is not identified as dual-hatted with the APM role, a separate APM FTE should be proposed. | DPW/TSB | |
| 12 | Will you consider moving the past performance timeframe from six to 10 years to allow additional projects to enhance the competitive nature of the acquisition | Conform to Page 66 - Volume III - Past Performance | MICC | |
| 13 | Will Notional seed project be awarded? | The Government reserves the right to award the Notional Seed project within a reasonable period of time, if it has funds, if it determines that doing so would be legally and contractually compliant, and if determines that doing so is in its best interests. | DPW/TSB | |
| 14 | If Notional seed project not be awarded has the work already been executed? | No, the work has not been executed | DPW/TSB | |
| 15 | In CLINs 2 and 4 the period of performance is stated as 270 CD after NTP. NTP occurs at the 65% of design. The total design period is 90 days. Please confirm the total period of performance for the notional seed project is 360 calendar days from award. | Total Period of performance is 360 calendar days from the NTP, the KTR can opt to start demolition after the 65% design is approved and could potentially finish the requirement in less than 360 days. | DPW/BV | |
| 16 | What should the contractor use as an award date for the notional seed project? | The award date for the notional seed project would be 30 Sep 2021 | DPW/BV | |
| 17 | Does the 90 CDs for design include all review periods? | The 90 calendar days for design includes review periods. | DPW/BV | |
| 18 | Should there be any long-lead material items can they be procured during the design period? | The contractor shall best decide how to accomplish the job. | DPW/BV | |
| 19 | The wage determination included with the draft is based on Highway Construction wages. The work is not related to this type of work. Will the wage determination be changed to building construction? | Attachment 1B - Wage Determination for Building has been uploaded with Final Solicitation | MICC | |
| 20 | Attachment 2 Pricing only has one CLIN. The notional seed project description contains 4 CLINs. Will Attachment 2 be updated to reflect the 4 CLINS? | Attachment 2 - Pricing Schedule has been uploaded with Final Solicitation | MICC | |
| 21 | Can Attachment 2 be presented in an Excel file? | Yes | MICC | |
| 22 | If a company has multiple team members can multiple IDIQ Capped Rates, including multiple G&A and Fee rates, be submitted with the proposal? | No, only one Attachment 4 - MA IDIQ CAP Rates can be submitted with the proposal. However, each Key Personnel labor category must be utilized for the notional seed project, and each Key Personnel labor category must be proposed using that labor category’s CAP rate. | MICC | |
| 23 | States we are to abate the lead based paint. Since the items containing lead based paint are being removed, doe the paint require abatement prior to demo? Please provide Lead Paint Survey. | SOW page 12 of 19 | Dispose of control materials in accordance with (IAW) all federal, state and local regulations. The KTR shall assume all painted or stained surfaces and residues at Fort Bragg are presumed to contain lead. | DPW/BV |
| 24 | Please define the scope of work for the Building Scientist. Does this size and type of | SOW page 10 of 19 & Section C, 2.2.3 of the Solicitation | The Building Scientist is to provide expertise on heat, air, and moisture considerations of a facility, especially with regards to building envelope. As with other key personnel, a single individual can fill more than one key personnel role. | DPW/TSB |
| 25 | Are air leak test required for the buildings? | SOW | A air leak test is required for the facility in accordance with UFC 1-200-02, ASHRAE 90.1 & 01 81 13. | DPW/BV |
| 26 | Are the interior stairs to be replaced? | A-100 & A-101 | The Interior stairs do not need to be replaced. | DPW/BV |
| 27 | What is the desired ceiling finish for the family latrines? | A-102 | Provide suspended acoustical ceiling IAW 09 51 00 ceiling height shall be 9'-0." | DPW/BV |
| 28 | Pease explain the scope of work required to encapsulate the crawl space | A-300 | The crawlspace shall be cleaned of debris, and a 15-Mil Vapor Barrier (VB) with all seams tapped shall be provide over 2-inches rigid polystyrene insulation on foundation walls and earth for the entire crawlspace. Provide a complete encapsulation system from a single manufacturer. Extend VB up interior foundation wall leaving a 3” gap from the top of the masonry wall. To form a complete seal, first apply Tape to the foundation wall prior to affixing VB to it. Once VB is sealed to the wall, install VB Term Bar over top of the VB inline with the VB Tape. Seal VB Wrap around all penetrations using VB Tape. Seal VB around all columns using VB Tape and VB Term Bar. Place VB Wrap directly over the crawl space floor. Overlap seams a minimum of twelve inches and seal with VB Tape | DPW/BV |
| 29 | To what extent are we to condition the crawl space? | A-300 | Crawlspace shall be conditioned and dehumidified similar to an occupied space. | DPW/BV |
| 30 | Confirm the wall finish in the mech and comm areas is to be painted gyp | A-100 | Wall finish in Mechanical Room (mech) and Communication Room (comm) areas, can be any material as required to provide adequate protection from combustible materials IAW UFC 1-200-01, minimal finishes is preferable. Provide Fire Resistant 3/4-inch plywood to mount the communications cabinet. | DPW/BV |
| 31 | Confirm the floor finish in the mech and comm areas is not to have self-leveling underlayment | A-102 | Floor Finish in Mechanical Room and Communication Room shall be any material as required to provide adequate protection from combustible materials IAW UFC 1-200-01, tile is not required in these spaces. Repair structure, subfloor as required for new finishes in Mechanical Room | DPW/BV |
| 32 | Are the trusses and underside of the decking to be painted in the mech and comm areas? | A-102 | Trusses and underside of the decking are not required to be painted in the Mechanical Room and Communication Room. All spaces shall be conditioned including areas above ceilings between the ceiling and the decking. | DPW/BV |
| 33 | Please confirm the existing walls in the mech and comm are already extend to the deck | A-101 | The contractor shall verify this condition in the field. | DPW/BV |
| 34 | Please confirm a lawn sprinkler system is not required | L-100 | Lawn irrigation systems are not part of the requirement. | DPW/BV |
| 35 | Please provide a drawing with the site contour lines for each site. | L-100 | The contractor shall conduct a site survey as part of their design. | DPW/BV |
| 36 | Note 3 states concrete to be warm color. Please confirm the concrete is to contain a color admizture other than grey | L-100 | The concrete shall include sand, and colorizers to provide a concrete that does not appear to be cement rich white, color shall be as selected after award. | DPW/BV |
| 37 | Spec section 32 93 00 is referenced. Please provide scope of work for the landscaping. Are trees required to be planted since some appear to be removed. Please provide the quantity, species, and sizes | SOW 7 of 19 | The Landscaping vegetation requirement is limited to planting grass to control erosion in disturbed areas. Remove all trees and other vegetation within a 20-foot offset from the perimeter of the facility. No trees will be planted to offset the removed trees. The Landscaping hardscaping requirement is limited to the removal of all existing impervious walks, stairs, ramps, paths, etc. used to access the building and providing new hardscaping that generally conforms to the intent of L-100. The Path extending westerly shall connect to former Bragg Boulevard, to provided accessible access to the facility and parking lot. | DPW/BV |
| 38 | States all work to conform to the most current version of UFC 1-200-02 High Performance and Sustainable Building Requirements. Please provide an edited copy of this report we are to follow and include in our design and pricing. As the DB contractor, we do not know what may be desired or required per these guidelines. Editing will eliminate protentional conflicts and misunderstandings during the design. This will likely add around 15% or more to the renovation cost of the building. | SOW 7 of 19 | UFC 1-200-02 High Performance And Sustainable Building Requirements is not a report. The document is located at: "https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-02". The Offeror is responsible for understanding and applying UFCs as applicable. | DPW/TSB |
| 39 | What is anticipated average daily/weekly use for these buildings including the number of occupants | SOW 7 of 19 | The facility will be used 7 days a week, expected maximum occupation is 100 pp / hr | |
| 40 | Pleae provide picutres of each building, interior and exterior. Was told at the Draft site visits taking picutes on Bragg is not allowed with out prior permission. | Site visit | See government response to question with ID2. | DPW/BV |
| 41 | Please confirm the steeples and brick chimenys are to be removed | Axbestos Reports | The steeples brick chimneys and small front protruding entry shall be demolished in entirety. Patch foundation where demolition occurs and to infill vents. Patches shall match the salient characteristics of adjacent wall. Coat the entire foundation with a mineral coating, color as selected after award. KTR shall salvage the copper cap for the steeple and provide it to the government. | DPW/BV |
| 42 | The solicitation says the questions are due 3 days after the site visit. Since the site visit is on July 1st and the Federal Holiday for the July 4th is immediately following, will the Government extend the question date to July 8th? | L1.Para C. | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 43 | Would the Government please consider extending this proposal from its current due date of 7/14 12AM to a minimum of 7/30 2PM? | SF1442 - 13A | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 44 | The SF1442 block 13A shows a due date and time of 7/14 12AM however, page 60 of 74 of the Solicitation notes a due date time of 12PM. Please confirm | SF1442 - 13A | Solicitation - page 60 of 74 L.1.c | Amendment Number P0005 - Block 13A of SF1442 still lists 24 September 2021. | MICC |
| 45 | Would the Government please consider extending the due date for technical questions from 7/4 9AM to at least 7/9 to account for the observed holiday. | Solicitation - page 60 of 74 L.1.c | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 46 | The Government has requested email submission for this proposal. Each Volume seems that it could well exceed 10MB or more. Would the Government please consider utilizing DoD SAFE for submission so that the Offeror can submit mutiple files as necessary instead of potentially having to break up each Volume into multiple files | Solicitation - page 60 of 74 L.1.b.i. | Proposal Submission via email only; Multiple submission are permitted. Please submit an email that summarizes, what and how many emails will be submitted. | MICC |
| 47 | If the Government decides not to utilize DoD SAFE for submission, would the Government please confirm the maximum file size they are able to receive per email and if the Offeror is permitted to send multiple submission emails. | Solicitation - page 60 of 74 L.1.b.i. | Multiple submission are permitted. Please submit an email that summarizes, what and how many emails will be submitted. | MICC |
| 48 | If the Government decides not to utilize DoD SAFE for submission, would the Government please confirm how the Offeror may recevieve notification that their submission email have been received. | Solicitation - page 60 of 74 L.1.b.i. | The Government will send a confirmation email after each submission | MICC |
| 49 | The SF1442 Block 13B notes that a Bid Guarantee is not required for this proposal however L.2.A Volume I notes that this Volume shall contain a Bid Guarantee. Would the Government please confirm if a Bid Guarantee is required for submission. | SF1442 - 13B | Solicitation - page 63 of 74 L.2.A | Bid Guarantee is not required for submission | MICC |
| 50 | Would the Government please confirm only Volume II of this submission may be submitted in .pdf as noted and that Volume I, Volume III, and Volume IV may only be submitted as Microsoft Word and Excel. | Solicitation - page 62-63 of 74 L.3.2.a | Page 62 - L.3.2.a. Volume II may be submitted in Microsoft Word and Adobe Acrobat version | DPW/TSB |
| 51 | Would the Government confirm that the Table of Contents and Glossory of Abberviations that are required for each of the 4 Volumes are excluded from the desiganted page limitations | Solicitation - page 63 of 74 L.3.2.c | Confirmed; Table of Contents and Glossary of Abberviations that are required for each of the 4 Volumes are excluded from the desiganted page limitations | MICC |
| 52 | In the Site Visit paragraph, the solicitation states technical questions shall be submitted in writing three calendar days after the specified site visit (scheduled for July 1). Given that three calendar days falls on July 4, a federal holiday weekend, would the Government consider extending the question submission period to five calendar days after the site visit? | L.1, c. Site Visit | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 53 | Standard Form 1442 lists July 14 as the proposal due date. Given the close proximity of the final site visit date, the technical questions submission date, and proposal due date, would the Government consider extending the proposal due date past July 14? Offerors will need two weeks from the time the Government posts answers to technical questions in order to review and adequately respond. | Standard Form 1442, Block 13 A | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 54 | Will the Government allow an Offeror to submit past performance projects that are greater than $5,000,000? | L.2, C. Volume III - Past Performance | No, the Government will NOT allow an Offeror to submit past performance projects that are greater than $5,000,000 | MICC |
| 55 | In the Site Visit paragraph, the solicitation states technical questions shall be submitted in writing three calendar days after the specified site visit (scheduled for July 1). Given that three calendar days falls on July 4, a federal holiday weekend, would the Government consider extending the question submission period to five calendar days after the site visit? | L.1, c. Site Visit | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 56 | Standard Form 1442 lists July 14 as the proposal due date. Given the close proximity of the final site visit date, the technical questions submission date, and proposal due date, would the Government consider extending the proposal due date past July 14? Offerors will need two weeks from the time the Government posts answers to technical questions in order to review and adequately respond. | Standard Form 1442, Block 13 A | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 57 | Will the Government allow an Offeror to submit past performance projects that are greater than $5,000,000? | L.2, C. Volume III - Past Performance | No, the Government will NOT allow an Offeror to submit past performance projects that are greater than $5,000,000 | MICC |
| 58 | Per the solicitation, "This factor includes a design component within the Notional Seed Project as the design phase is not complete." Will the Government please specify what level of a design component needs to be included for this response? | L.2, B. (3)(b) Subfactor 2 - Concept for MA IDIQ Contract Notional Seed Project Response | The Offeror is not required or requested to submit a design in response to this solicitation. Development and submission of a full design package is required if Offeror awarded the seed project. | DPW/TSB |
| 59 | This being a design build, does the contractor have the option to leave the 2' bump out in the front of the buildings? If not, is there a foundation under the new section of wall that is to be built in to enclose where the bump out was? | A100 & A101 | The contractor shall assume a new foundation wall is required in this location. | DPW/BV |
| 60 | Is there an existing foundation under the new exterior wall at the area west side of the building being removed? | A100 & A101 | See government response to question with ID59. | DPW/BV |
| 61 | It appears the two new porches may require handrail since they are shown to be over a 2' drop, please confirm a metal handrail is sufficient or should the ground be brought up to eliminate this requirement | A100 & A101 | Provide Guards and Handrails as required IAW UFC 1-200-01. | DPW/BV |
| 62 | Please clarify if there is a total of 4" roof insulation or 6" roof insulation, even if code allows less. | A300 | Provide 6 inches of roof insulation. | DPW/BV |
| 63 | Please confirm since this is a design build the contractor has the option of not providing the roof sheathing bonded to the top layer of insulation. In order to build the new one foot overhangs, the roof sheathing is used to assist in supporting the overhang The overhang will needs to be brought back to the wood framed wall for support. | A300 | The contractor has the option of not providing the roof sheathing bonded to the top layer of insulation. | DPW/BV |
| 64 | Please confirm the existing roof overhang is to be removed and built to the profile shown or can the height of the fascia be increased to accommodate the new roof insulation? | A300 | Conform to the design intent of the solicitation. | DPW/BV |
| 65 | Page 14, F, 1 ,b,iii states to repair roof sheathing as required. A. For bidding purposes, up to what percentage of the roof sheathing are we to include? B. Is the existing roof sheathing the original sheathing? Would suspect if the existing roof sheathing is of 1x material it may not have any life remaining for insulation and roofing to adhere to. | SOW Seed Project | The contractor shall assume 100% of the sheathing requires replacement. | DPW/BV |
| 66 | A200 is showing the siding at the floor line, while A300 is showing siding 1' down on the foundation wall. Please confirm the siding is to be at the floor line for a smooth line at the porches, ramp, and step. | A200 & A300 | Conform to the wall section as drawn on A-300. | DPW/BV |
| 67 | Please provide the bases of design for the 3-dimensional nylon matrix, 0.5" thick. We suspect this is a vented underlayment hat is typically used for wood shingles | A300 & SOW | Basis of Design is Sharkskin Ventilated Roof Mat. Provide Leak barrier, ventilation layer and radiant barrier from a single manufacturer designed specifically for use under steel roofing. | DPW/BV |
| 68 | Please confirm the downspouts are to discharge onto splash blocks and not tied to a storm drain | A200 | Correct. Stormwater from downspouts should discharge to ground in a manner that is not erosive and does not interfere with pedestrian traffic. | DPW/TSB |
| 69 | Are the wood posts and beams to be left exposed or covered with cement trim boards of metal wrapped? | A200 | Wood posts and roof structure constituting the porches shall be designed using heavy timber to emulate the interior structure, and shall be receive a paint finish. Provide concealed standoff bases for all columns. | DPW/BV |
| 70 | What is the anticipate occupancy for the meeting room? I think if its over 30 people the doors will need to swing out and panic hardware and closures | A101 | Assume occupation will be 49 or less. | DPW/BV |
| 71 | Please confirm the fire water line will be provided by the government | SOW pg 14 | A fire lateral will be provided to within 5-feet of the facility, the KTR is responsible for coordinating with utility provider, and for the all work after the 5-foot demarcation. See government response to question with ID96. | DPW/BV |
| 72 | Do to material procurement delays and need to enclose the building once the demo is about complete, can the roof and exterior shell be included in the fast track process as well? | SOW | The government has no objections to a shell and core means and methods. | DPW/BV |
| 73 | Please confirm there is not requirements for new storm drainage inlets | L-100 | There is not a requirements for new storm drainage inlets, water shall drain away from the facility IAW UFC 1-200-01, UFC 3-201-01 & 3-201-02. | |
| 74 | Please confirm the General Contractor when lessened in their home state does not need to have a NC Contractor license as well since they are working on Federal property | SOW | Contractors need to be licensed in NC by specialty/work area | MICC |
| 75 | Can the Offeror submit past performance for a key subcontractor and submit this consent form. | SUBCONTRACTOR/TEAMING PARTNER CONSENT FORM | Yes, the Offeror submit past performance for a key subcontractor and submit this consent form | MICC |
| 76 | Will the government allow the use of subcontractors past performance for the projects the Offeror is to submit. | Specific Relevant Contracts Sheet, Section L | Yes, the government will allow the use of subcontractors past performance for the projects the Offeror is to submit | MICC |
| 77 | So as an example can the Offeror use 3 of their projects and 3 subcontractor projects to meet the requirement | Yes this example is acceptable | MICC | |
| 78 | of the 6 projects to satisfy Volume III - Past Performance | Yes this example is acceptable (Question 77 and 78 are one question) | MICC | |
| 79 | As their any Past Performance Surveys the govenrnment wants the Offeror to send to their clients | Volume III - Past Performance | Yes | MICC |
| 80 | If we need to submit Past Performance Surveys, can we used previoulsy filled out surveys from other submissions? | Yes, current surveys will be accepted, provided the Offerors contain all the information requested by the survey in this solicitation. The Government will evaluate Past Performance as stated in the solicitation | MICC | |
| 81 | Can we use CPARS instead of Past Performance Surveys? | Volume III - Past Performance | Conform to Page 66 - Volume III - Past Performance | MICC |
| 82 | What are the page counts per volume and what is the font size | All Volumes, General Questions | Please see Proposal Preparations Instructions Section L.3.2. and Section L.3.2.d | MICC |
| 83 | What specific posistions does the government want resuems for in the proposal? | Key Personnel | Offeror is to submit resumes for all Key Personnel. | DPW/TSB |
| 84 | Does the government want alternate resumes as well for each position? | That is at Offeror discretion. | DPW/TSB | |
| 85 | If we submit resumes does that go against the page count? | Resume pages are excluded from the page count | MICC | |
| 86 | Does this go againt any page count? | Schedule | Resume pages are excluded from the page count | MICC |
| 87 | Is there a geothermal well field nearby we can tie into? | No. | DPW/TSB | |
| 88 | Are we to provide a system that follows the design criteria or will DPW provide the desired mechanical system to level the playing field? | Offeror is responsible for designing, obtaining, constructing, and installing all components of the project. | DPW/TSB | |
| 89 | The Table in Section L.3.2 (page 62 of 74) indicates that Volume III, Tab B should be a Glossary while Section L.2.C.ii (page 66 of 74) indicates Tab B in Volume III should be a "Summary Page." What should be in Volume III, Tab B of the proposal? | Volume III of the Proposal | Page 66 correction: TAB B - Glossary of Abbreviations and Acronyms | MICC |
| 90 | SF 1442 states that proposals are due at 12:00 AM. Page 60 of 74 states that proposals are by 12:00 PM on the closing date. Which is correct? | Bid Date | Please see FINAL Solicitation Amendment Number 5 for revised dates and times | MICC |
| 91 | Page 72 of 74 of the Solicitation, Sub factor 3 identifies a $6 million for individual requirements and $25 million for an aggregate. Would MICC consider lowering these requirement values? These values seem high for a bonafide HubZone contractor to acquire on their own. | Bonding Requirements | No, the MICC will not lower these requirement values | MICC |
| 92 | What percentage of Task Orders does the Gov't feel will be Design / Build projects? | Design / Build Projects | The percentage of Design-Build Task Orders is not known. Current estimate is at least 35% and potentially more than 85% of Task Orders will be Design-Build. This is highly dependent upon Fort Bragg needs, which is dependent upon mission requirements. | DPW/TSB |
| 93 | Can / will the Gov't provide a lead paint survey? | Lead Paint | See government response to question with ID23. | DPW/BV |
| 94 | Is everything inside the (2) chapels the contractors responsibility to remove and dispose? Is anything being salvaged by the Gov't? | Salvage | See government response to question with ID41 & ID 110. | DPW/BV |
| 95 | Do either of the chapels fall under special provisions for historic renovation requirements? | Historic Buildings | The chapels have been determine to be ineligible and are not contributing assets to any historic district. | DPW/BV |
| 96 | There are several different styles of metal roof specified in the IDG. Can you indicate which roofing system should be utilized? | Roofing | The KTR shall provide an architectural metal roof utilizing a snap lock standing seam system over a rain screen substrate. See government response to question with ID67. | DPW/BV |
| 97 | Is a fire suppression system required in these two buildings? | Fire Suppression | Conform to the requirements of UFC 3-600-01. | DPW/BV |
| 98 | If we have 30 days for the initial design and the design is rejected, do we then have another 30 days for resubmission? | Design | The KTR is responsible for meeting contractual timelines, extensions will not be granted for nonperformance. | DPW/BV |
| 99 | "Regarding the mechanical system selection, if we’re replacing everything above the foundation, the building has to use 30% less energy than the baseline building in the energy code. But since we are keeping the exterior walls, meaning it’s technically not a full renovation, we’re required to comply with one of the following: All other renovations choose one of the following options: 1. Reduce measured building energy use by at least 30%, below FY 2003 or earlier, energy use baseline. 2. Reduce measured building energy use by at least 20% below FY 2015 energy use baseline. 3. Reduce model energy use (from all sources including renewable energy) by 30%compard to the ASHRAE 90.1 baseline building design for Commercial or Multi-Family High-Rise Residential Buildings, or the IECC baseline (using the Simulated Performance Alternative found in Section 405 of the IECC for Low-rise Residential buildings. (Refer to paragraph “Commercial and Multi-Family High-Rise Residential Buildings” for calculations of energy consumption reduction.) Numbers 1 and 2 would require us to install meters to determine the actual energy use, I suppose over the course of a year (We are not sure what happens if the energy use at the end of year one is too high…). So, we’d probably be going with number 3 since it’s purely modeling, no actually measuring. But if none of these are life cycle cost effective, we essentially provide the most energy efficient design that is life cycle cost effective. Based on my experience of energy modeling for LEED projects, it will be VERY difficult to demonstrate 30% energy savings. The reason is the size of the building. It is only 3,000 square feet or so. Energy savings compound as buildings get larger. WE have only been able to demonstrate 30% savings or more on a building that used a ground source heat pump system, and it was a sizeable school. The only systems I can see possibly working are: 1. Ground source heat pumps (would require geothermal wellfield 2. VRF system 3. Four-pipe VAV with very high efficiency chillers and boilers. Residential heat pumps, which cost-wise would be ideal for a building this size, will not be adequate. We will have to use very low-e glazing, add insulation to the exterior walls, and have a very high R-value roof system. Solar panels are also an option but are obviously cost prohibitive and something we doubt Ft Bragg will want for a 3,000 square foot building. UFC 1-200-02 seems to be always listed as a requirement on many projects but feel like it’s rarely enforced in terms of demonstrating energy savings due to the type of mechanical system is typically provided. A. Is there a geothermal well field nearby we can tie into? B. Are we to provide a system that follows the design criteria or will DPW provide the desired mechanical system to level the playing field? We need this decision ASAP in order to continue our preliminary design and pricing to meet your submittal date." | SOW | There is no geothermal well field available. Offeror is responsible for designing, obtaining, constructing, and installing all components of the project. LCCA is the guiding determinant for building systems, with consideration for government staff operability and maintainability key components of that. | DPW/TSB |
| 100 | Form 1442 indicates a bid guarantee is not required, however the solicitation (Section L.2.A) indicates a Bid Guarantee shall be included in Volume I of the proposal. Please confirm what information is correct. | Form 1442 - Solicitation - Item 13b - Offer Guarantee | Bid guarantee is not required with proposal submission | MICC |
| 101 | Should the proposal for the Seed Project include Lead Based Paint investigation? | Seed Project - SOW | See government response to question with ID23. | DPW/BV |
| 102 | Is Fire Suppression, Protection and Mass Notification required per UFC for the Seed Project? | Seed Project - SOW | See government response to question with ID97. | DPW/BV |
| 103 | Is selective demolition allowable for Design Investigation? | Seed Project - SOW | Selective demolition is allowable for design investigation, after the kick off meeting. | DPW/BV |
| 104 | Who will be responsible for removing the trailer next to the North Building? | Seed Project - SOW | The KTR shall demolish the trailer, wood fencing and utilities serving the trailer, for the trailer adjacent to M2505. | DPW/BV |
| 105 | Please confirm the layout for each new building is identical, or provide layout for 2nd building if applicable. | Seed Project - SOW | The design intent is that the design for M2055 and M6205 are identical, however in reality the designs will be similar. The KTR shall be responsible to site adapting the design to the similar facilities. | DPW/BV |
| 106 | Should the proposal include pricing for the repair or replacement of the subfloor? | Seed Project - SOW | The proposal shall include pricing for the repair or replacement of the subfloor and structure where required. | DPW/BV |
| 107 | During the site visit it was mentioned the Altar(s) were to remain, however the drawings indicate they are to be removed. Please verify if the Altar shall remain or be removed. | Seed Project - SOW (A-100) | The KTR shall demolish as required to achieve the design intent of the new work, this includes the altar raised platform. | DPW/BV |
| 108 | Who will be responsible for removing the overgrowth vegetation within the jobsite(s)? | Seed Project - SOW | Offeror awarded the seed project is responsible for all site/building work, excluding construction/repair of utilities (any water supply, sanitary sewer, natural gas, or electrical power requirements). | DPW/TSB |
| 109 | Will conceptual drawings and/or specifications be provided for Mechanical and Electrical? | Seed Project - SOW | The government will not provide conceptual drawings and/or specifications be provided for Mechanical and Electrical, the intent of the RFP drawings is to provide a framework for other systems. Building systems shall conform to UFC 1-200-01 as well as UFC 3-401-01 Mechanical Engineering and UFC 3-501-01 Electrical Engineering. | DPW/BV |
| 110 | Who will be responsible for the removal and disposal of furniture (Pews, Desks, Chairs, Etc.)? Are there any requirements for turnover of real property to Government? | Seed Project - SOW | The KTR will be responsible for all demolition and disposal. The KTR shall salvage four pews to be reinstalled by the KTR in the vestibule of each facility, two per facility. | DPW/BV |
| 111 | There are no exterior doors specified for the mechanical rooms. Should exterior access be included for accessibility? | Seed Project - SOW | Exterior access to mechanical rooms is not a requirement of the project. | DPW/BV |
| 112 | Will there be any work included pertaining to the parking lot (Striping, Sealing, Etc.)? | Seed Project - SOW | Seal coat, stripe and provide signage for the parking lots adjacent to M2505 and M6205. Work shall be accomplished IAW UFC 1-200-01 and NCDOT standards. | DPW/BV |
| 113 | There isn't a ceiling type specified for the family latrines. Could the Government specify the ceiling type for these locations? | Seed Project - SOW (A-102) | See government response to question with ID27. | DPW/BV |
| 114 | Will the Government provide a design intent for Landscaping (Seeding/Vegetation)? | Seed Project - SOW (L-100) | See government response to question with ID37. | DPW/BV |
| 115 | Will the Government allow an Offeror to submit past performance projects that are greater than $5,000,000? | L.2, C. Volume III - Past Performance | No, the Government will NOT allow an Offeror to submit past performance projects that are greater than $5,000,000 | MICC |
| 116 | Per the solicitation, "This factor includes a design component within the Notional Seed Project as the design phase is not complete." Will the Government please specify what level of a design component needs to be included for this response? | L.2, B. (3)(b) Subfactor 2 - Concept for MA IDIQ Contract Notional Seed Project Response | The Offeror is not required or requested to submit a design in its proposal. However, design-build projects require proposals for both design and construction of the project. Thus, proposals for the notional seed project must include offeror’s proposed approach to, and pricing for, a full design package as well as the associated construction | DPW/TSB |
| 117 | Is a there a lead test report and/or hazardous material report for the two buildings of the Notional Seed Project? | Final Site Visit - 7/1/2021 | An asbestos report has been provided. See government response to question with ID23 | DPW/BV |
| 118 | Is fire suppression a requirement for the Notional Seed Project? | Final Site Visit - 7/1/2021 | See government response to question with ID97. | DPW/BV |
| 119 | May Volume 1 be in pdf format since original signatures are required in Block 20B per section L.2.A.1? | Section L.2.A.1 | Page 61; L.3.2. Proposal Preparation Instructions - Volume I | MICC |
| 120 | The table within Section L.3.2.a, Volume I lists two TAB E sections. Please clarify if it should be “TAB E – Responsibility Statement” and “TAB F – OCI Mitigation Plan (if applicable)“ | The table within Section L.3.2.a, Volume I | Clarification - Volume I reads "TAB E – Responsibility Statement" and "TAB F – OCI Mitigation Plan (if applicable)" | MICC |
| 121 | The table within Section L.3.2.a, Volume I lists TAB A – TAB F. However in Section L.2.A, this section only lists TAB A-E. The difference between the sections is a missing Glossary of Abbreviations and Acronyms. Please clarify what is to be included in this section. | The table within Section L.3.2.a, Volume I | Page 63 - Section L.2.A. reads "TAB A-F" for Volume I | MICC |
| 122 | The table within Section L.3.2.a, Volume II lists TAB A – TAB F. However within section L.2.B.2 only TAB A-C are listed then it switches to Factor/Subfactor headings. Please clarify how the Government would like to see these organized. | The table within Section L.3.2.a, Volume I | Pages 64-66 - Section L.2.B.2 reads "TAB A-F" for Volume II | MICC |
| 123 | The table within Section L.3.2.a, Volume III lists TAB A – TAB E. However in Section L.2.C.2, this section only lists TAB A-D. The difference between the sections is a missing Glossary of Abbreviations and Acronyms. Please clarify what is to be included in this section. | The table within Section L.3.2.a, Volume III | Pages 66-67 - Section L.2.C.2 reads "TAB A-E" for Volume III | MICC |
| 124 | Please confirm the following TAB sections are NOT included in the page limitations: (1) Cover page, (2) Table of Contents, (3) Glossary of Abbreviations and Acronyms; (4) List of Tables and Drawings and/or figures (if applicable). | Section L.3.2 | Page 62 - L.3.2.c | MICC |
| 125 | The table within Section L.3.2.a, Volume III, under the column “MAXIMUM PAGE LIMIT” it says “15 Page count see paragraph L.2.c.2.iv below”. Please confirm this volume page limit is only referencing L.2.c.2.iv, Volume III, TAB D – Specific Relevant Contracts Forms at stated in the table and does not include TAB B-Summary Page and TAB C-Consent Letters. | The table within Section L.3.2.a, Volume III | Page 67 reference page count for TAB E and page limit does not include TAB A, TAB B, or TAB C. | MICC |
| 126 | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" list the Building Scientist (PE, Forensic Engineering, Building Science Certification). What does this mean? What is the minimum requirement? Can the person have any of the three certifications listed (PE, Forensic Engineering, Building Science Certification)? Or can the person have two of the three listed certifications? Or must the person have all three certifications? Since this is the only "Key Personnel", other than the PM with additional qualifying requirements, will the Government clarify the minimum certification requirements for the Building Scientist? | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" | The Building Scientist is to provide all three certifications (PE, Forensic Engineering, and Building Science Certification) | MICC |
| 127 | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" list the Building Scientist (PE, Forensic Engineering, Building Science Certification). We have never seen a requirement for a Forensic Engineering certification or professional registration. Although some colleges offer coursework in forensics, in an on-line search, we cannot find any professional organization that offers a "Forensic Engineering" certification or registration. Will the Government clarify, or provide the name of the Certification/Registration Authority for the "Forensic Engineering certification? | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" | See National Academy of Forensic Engineers (NAFE). | DPW/BV |
| 128 | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" list the Building Scientist (PE, Forensic Engineering, Building Science Certification). There is a professional organization that is the Certification Authority for a Building Scientist. However, your list limits a person as being a PE. Can an Architect fulfill this role? | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" | No, the Government already has a RA Key Personnel Category. | DPW/TSB |
| 129 | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" list the Building Scientist (PE, Forensic Engineering, Building Science Certification). There is a professional organization that is the Certification Authority for a Building Scientist. However, this Building Scientist Certificate is open to non-professionally registered persons. Is the PE really a requirement? | RFP page 6 of 74, para 2.3.3 - The "Other Key Personnel" | The Government will NOT allow an RA Key Personnel category. The Key Personnel identified on the Contractor solicitation proposal shall be utilized on each TO as applicable to the required work unless individuals of equal or higher qualifications are provided. The Contractor shall provide a Key Positions list with supporting qualifications information for approval in response to each RTOP for review and approval by the KO. The Building Scientist is to provide all three certifications (PE, Forensic Engineering, and Building Science Certification) | DPW/TSB |
| 130 | RFP page 65 0f 74, L.2.C.3 states "Please note that the Notional Seed Project will not result in an awarded task order. The Notional Seed Project is for Offeror evaluation purposes. (The Government intends to award a contract for the Seed Project, but it will not be at the time of this MA IDIQ contract award." See the two underlined sections. In the first sentence it states the Notional Seed Project will NOT RESULT IN AN AWARD; and later states that the Government INTENDS TO AWARD. Which is it? Will the Government make an award, at any time, of the Notional Seed Project for the Notional Seed Project price in Volume IV? | RFP page 65 0f 74, L.2.C.3 | The Government reserves the right to award the Notional Seed project within a reasonable period of time, if it has funds, if it determines that doing so would be legally and contractually compliant, and if determines that doing so is in its best interests. Price evaluation of the Notional Seed project for purposes of the IDIQ total evaluated price, will be based on evaluation of all 4 CLINs in the Notional Seed project. | |
| DPW/TSB | ||||
| 131 | Please provide the As-Built Record Drawings of the original construction and any renovations of Buildings M-6205 and M-2505. | KTR shall verify all existing conditions, the government will provide available information with this response. - See Attachment 12 | DPW/BV | |
| 132 | Please provide the CAD for Attachment 1C. | See government response to question with ID131. | DPW/BV | |
| 133 | On the provided “Specific Relevant Contracts Sheet” beginning on page 68 of 74 of the Solicitation, the first more narratively written section and the more form-fill type section have different sections in addition to, the form-fill section having a section repeated (item 2 and item 5). Please clarify what section the Government would like the offeror to respond to. If the more form-fill (second) section please clarify if the Government would like the offeror to include the duplicated sections as written in the solicitation. | On the provided “Specific Relevant Contracts Sheet” beginning on page 68 of 74 | Offeror shall complete the “Specific Relevant Contracts Sheet” beginning on page 68 of 74 of the Solicitation. To clarify - please use the first more narratively written section. Insure all information is captured in offeror submission. | MICC |
| 134 | In the “Specific Relevant Contracts Sheet” beginning on page 68 of 74 of the Solicitation, in the second more form-fill section, Item 6 is “Change Dates”. Please advise as to what this means. The offeror believes it is intended to request Modification dates to the relevant project included. | On the provided “Specific Relevant Contracts Sheet” beginning on page 68 of 74 | Offeror shall leave Item 6 blank. | MICC |
| 135 | Can the Government please provide the "Fort Bragg" Standard Specifications referenced during the site visit that have been tailored to the installation standard requirements? The sections listed in in Paragraph 9 Applicable Specifications as the installation's standard specifications were not part of the previous Attachments included on the BetaSAM.gov website. | Atch 1A Notional Seed Project Scope of Work | The specifications will be provided with this response. See attachment section of the solicitation. | DPW/BV |
| 136 | Can the Government provide a comprehensive Lead Based Paint Survey for each building? | Atch 1A Notional Seed Project Scope of Work | See government response to question with ID23. | DPW/BV |
| 137 | Lead Based paint (LBP) Demolition indicates that lead based paint is to be removed with the use of "Sponge blasting" as an acceptable method. Please clarify if ALL lead based paint has to be completely removed OR if loose and flaking paint can be removed with any remaining and solidly adhered LBP encapsulated with an approved coating system to prevent LBP from bleeding through the new coating surface? | Atch 1A Notional Seed Project Scope of Work Paragraph 10.C.1.c.b | All hazardous materials shall be demolished and disposed of IAW question with ID23. | DPW/BV |
| 138 | During the site visit, it appeared that the existing, original lap siding was covered with aluminum siding an a rigid insulation blue board. Can the Government confirm that the exisitng, original lap siding contains lead based paint? | Atch 1A Notional Seed Project Scope of Work | See government response to question with ID23. | DPW/BV |
| 139 | The referenced paragraph mentions abatement of "Visible Mold". Can the Government provide a Mold Survey in order to determine the requirements for Mold Abatement of "Visible Mold"? | Atch 1A Notional Seed Project Scope of Work Paragraph 10.C.1.c | The government does not have a mold survey, the KTR shall verify in the field. At the end of the undertaking indoor relative humidity shall be able to maintained at between 30% and 50%. | DPW/BV |
| 140 | Does the Government (AHJ) require a sprinkler system for this building given its occupancy and construction type? Paragraph K mentions a Fire Alarm System but does not address Fire Suppression (sprinkler) being required. | Atch 1A Notional Seed Project Scope of Work Paragraph K | See government response to question with ID97. | DPW/BV |
| 141 | What will the Government consider to be the 'construction limits' beyond the building line in all directions in terms of site clearing, grading, and landscaping (i.e. 50' from the building line, 100' from the building line, etc.)? | Atch 1A Notional Seed Project Scope of Work Paragraph D | The government considers the construction limits 75-feet from the facility perimeter, except parking lot limits are the extent of the parking lot. See government response to question with ID37. | DPW/BV |
| 142 | There is an existing single wide modular trailer behind Building M2505 on the Watson Street side of the building. Please clarify if the Contractor is responsible for removal / disposal of this existing trailer? | Atch 1A Notional Seed Project Scope of Work | See government response to question with ID104. | DPW/BV |
| 143 | Please clarify the utility demarcation/connection points from the building line (i.e. 5' for water, 10' for sewer, or to the nearest existing service line)? | Atch 1A Notional Seed Project Scope of Work | Domestic Water, Fire Water, Gas: 5-feet from the facility. Sanitary: first sanitary clean out stub up outside the facility located 5-feet from the facility. Electrical: the KTR shall provide a conduit to the secondary side of the transformer. The utility provider will provide the cabling from the transformer into the Main Distribution Panel for the KTR to connect. Communications: communication vault servicing the facility. | DPW/BV |
| 144 | Please clarify if the Contractor or Privatized Utility Provider is responsible for final connections to the new service lines to be installed to the buildings? | Atch 1A Notional Seed Project Scope of Work | See government response to question with ID143. | DPW/BV |
| 145 | Please confirm if the existing steeples and Mechanical Room Additions at each building are to be demolished and not replaced as part of this project? | Atch 1A Notional Seed Project Scope of Work | The steeples and mechanical room additions at each building are to be demolished and not replaced as part of this project. | DPW/BV |