New Hogan Septic Service Question Answer 3.30.2026.pdf
PDF 50 KB Posted
- Attached to
- New Hogan Septic Service
- Solicitation number
- W9123826QA006
About this file
This is a Questions and Answers document for federal contract W9123826QA006, New Hogan Septic Service. The document provides clarifications on contract requirements for septic tank servicing at multiple facility locations.
The contract addresses maintenance of five septic tanks with the following capacities: Project Office Tank (2,000 gallons), NOB Tank residence (2,000 gallons), Maintenance Shop (2,000 gallons), Cameron Trailhead Restroom (2,000 gallons), and Dam Tank (250 gallons). All tank capacity figures are estimates based on historical data and have not been verified by actual tank drawings. Service is scheduled for one single occurrence in Option Year 4 (2030). This is designated as a brand-new contract requirement, though previous contracts for similar services existed under contract numbers W9123821P0003, W9123817P0043, and W9123813P0010. The government will not provide water for the contract operations. Contractors are responsible for waste disposal and must select their own disposal facility; no historical disposal facility has been identified or designated by the government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation.pdf | ||
| PWS.pdf | ||
| Wage Determinations 2015-5665.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9123826QA006, New Hogan Septic Service Question & Answer
Q1. When reading through Part B of the Performance Work Statement (PWS) it lists (5) septic tanks at various locations.
How many gallons each septic tank is and how often they need service
A1.
Are you referring to Option Year 4?
Project Office Tank – 2,000 gallons
NOB Tank (residence) – 2,000 gallons
Maintenance Shop – 2,000 gallons
Cameron Trailhead Restroom – 2,000 gallons
Dam Tank – 250 gallons
All numbers are estimates/approximates as they we provided by historical data and not confirmed by actual drawings of the septic tanks.
These tanks will be serviced one (1) time, only in Option Year 4 (2030).
Q2. We are performing independent research on the Combined Synopsis/Solicitation (W9123826QA006). We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number and what the total contract value was?
A2. Brand New Requirement
We have had previous contracts for this service. Below are the previous contracts:
W9123821P0003
W9123817P0043
W9123813P0010
Q3. Will water be provided by the government?
A3.
No, water will not be provided by the government.
Q4. Is there a historical disposal facility being used for this contract?
A4.
W9123826QA006, New Hogan Septic Service Question & Answer
Unknown. Disposal is the responsibly of the contractor and the septic company. They will dispose of all waste at their disposal facility of choice.
File details come from the government source that posted it. Updated .