Cost Schedule for Task Order 0001.pdf
PDF 525 KB Posted
- Solicitation number
- W9123822R0049
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers_.docx | DOCX document | |
| W91238-22-R-0049.pdf | ||
| Questions and Answers.docx | DOCX document | |
| Solicitation_Registration.pdf | ||
| Proposal_Manager.pdf | ||
| W91238-22-R-0049 (2).pdf | ||
| Proposal_Manager_Functions.pdf | ||
| USACE PAST PERFORMANE QUESTIONNAIRE (PPQ) TO BE COMPLETED BY CLIENT.pdf | ||
| W91238-22-R-0049.pdf | ||
| USACE PAST PERFORMANCE QUESTIONNAIRE (FORM PPQ-0).pdf | ||
| Labor Cost Schedule.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task Labor Categories Hours Cost Task 1.1 Post Award Meeting E.g. Project Manager
E.g. Contracts Manager
Task 1.2 Kickoff Meeting
Task 1.3 Review Meeting
Task 2 Accident Prevention Plan, Schedule, and Status Reports
Task 3.1 Year 1 Follow-Up Surveys
Task 3.2 Year 5 Follow-Up Surveys
Task 3.3Year 8 Follow-Up Surveys
Task 3.4 Wild Life Surveys
Task 3.5 Wetland Vegetation Surveys
Task 3.6 Biological Monitoring Report
Task 3.7 Wildlife and Wetland Vegetation Surveys Report
Task 4.1 Data Evaluation
Task 4.2 Data Management
Task 5 Weekly Progress Updates
Task 6 Annual Report Review Meeting
Task 7 Contractor Manpower Reporting* 0 $0.00
$0.00 Other Costs:
Notes to Offeror:
Include the appropriate Labor Category to complete each Task
Only include the Labor Categories Listed in the Base IDIQ contract (Do not include additional Labor categories)
Cost will be calculated by using the Labor Category Cost and multiplying it be the proposed hours of each Task in this Task Order
Task 7 is required by law and will not have any costs associated with the completion of the task