This solicitation requests proposals for the construction of a new jet fuel complex at the Fresno Air National Guard base in Fresno, California. The project scope includes building new above-ground storage tanks, a pump shelter, truck fillstands, offloading facilities, and a refueler truck parking area. It also requires demolition of existing underground tanks, loading/unloading systems, and truck parking as well as removal of asbestos-containing materials. Offerors should provide pricing for base requirements and optional items using the schedule included. The solicitation was issued by the Department of the Army Corps of Engineers Sacramento District. Proposals are due by the scheduled closing date after which the contract will be awarded.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fresno Jet Fuel Pricing Schedule

Base CLIN Components Fuel Storage Tanks Job $ Pumphouse Job $ Truck Fillstands Job $ Truck Off-Load Job $ Site Work and Utilities Job $ Demolition Job $ Base CLIN Total $

Optional CLINS Option 1001 – Relocate LOX Tanks

Job $

Option 1002 – Automatic Tank Gauging System Equipment

Job $

Option 1003 – Disposal of Contaminated Soil

Cubic Yards

575 $ /per CY

Option 1004 – Removal & Disposal of Residual Oily Water and Sludge

Gallon 15,500 $

/per Gallon

Option 1005 – Furnish & Install Standby Generator

Job $

Option 1006 – Demolish Existing Barrier Wall & install new barrier wall

Job $

Option CLINS Total $

GRAND TOTAL $

Please list your G&A rate here Please list your Profit percentage here