This solicitation requests proposals for the Replacement of the Fresno Jet Fuel Complex. The project involves constructing a new jet fuel complex at the Fresno Air National Guard base, including new above-ground storage tanks, a pump shelter, truck fillstands, offloads, and refueler truck parking. It also requires demolishing and removing existing underground storage tanks, truck loading and unloading systems, refueler truck parking facilities, and asbestos-containing materials. The contractor will construct new JP-8 jet fuel storage with steel tanks, foundations, containment, roofs and pans. The complex includes commercial truck unloading and loading stands, a pump house, storage building, cathodic protection, site work, utilities, pavement, communications, security fencing and gates, an emergency generator, lighting, fire protection and alarm systems. The solicitation is a competitive low-price technically acceptable procurement conducted by the Army Corps of Engineers, Sacramento District. Proposals are due by August 6, 2020. The period of performance is 730 days from notice to proceed.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to incorproate the follow ing changes: 1) Provide Summary of Changes; 2) Provide additional inquiries and responses; 3) Provide an updated price schedule; 4) Incorporate new specif ication section 27 10 00; 5) See changes in 00 22 00 in regards to Tab 7 of the Price Proposal and 6) Extend the proposal due date to 6 August 2020 at 11am.
Please note the conformed specif ications w ith the changes outlined in the summary of changes w ill be provided at the time of aw ard.
No other changes are made or implied.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 13
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123820R0054
X 9B. DATED (SEE ITEM 11)
30-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Jul-2020
CODE
US ARMY CORPS OF ENGINEERS, SACRAMENTO
CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123820R0054
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 30-Jul-2020 11:00 AM to 06-Aug-2020 11:00 AM.
CLIN 1001
The option status has changed from No Status to Option.
CLIN 1002
CLIN 1003
CLIN 1004
CLIN 1005
CLIN 1006
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been modified:
EVALUATIONS FACTORS
GENERAL SUBMISSION
REQUIREMENTS AND
INSTRUCTIONS, EVALUATIONS,
AND
CONTRACT
AWARD
1. OVERVIEW.
Proposals received in response to this solicitation for the Replacement of the Fresno Jet Fuel Complex that will be evaluated on Lowest Price Technically Acceptable method of obtaining a best value. The Contracting Officer will award to the responsible offeror that represents the best value considering all non-price factors described herein.
2. BASIS OF AWARD.
2.1. ELIGIBILITY FOR CONTRACT AWARD
In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the contracting officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.
2.2. SOURCE SELECTION USING THE LOW-PRICE, TECHNICALLY-
ACCEPABLE (LPTA) METHOD
The Government shall evaluate the lowest-priced offeror. Should that offeror’s proposal be found to be technically acceptable in all non-price factors, the Government shall stop evaluations and make direct award to said offeror, assuming their price is found to be fair and reasonable. Should the proposal not be technically acceptable in all non-price factors, or should the price offer not be found fair and reasonable, the Government shall evaluate the next lowest-price offeror. This process will repeat until a technically acceptable offeror whose price offer is fair and reasonable is selected.
3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
For purposes of this RFP, an “Offeror” may include a group of two or more entities that have formed a “contractor team arrangement,” as that term is defined in the Federal Acquisition Regulation, Section 9.601. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently-proposed contractor team arrangement, may be considered as a part of the evaluation of the Offeror’s proposal.
In the case of contractor team arrangements involving a prime contractor and subcontractor(s), where the prime contractor submits the proposal in response to this RFP, the prime contractor must have completed at least two of the total number of projects submitted for Factor 1 for consideration in response to the past performance requirements of this RFP. If information about a subcontractor is submitted and considered during the evaluation, the expectation is that this subcontractor will perform this work. Before utilizing another subcontractor for this work, the Government must consent.
An Offeror that relies upon the performance history of a member or members of a proposed contractor team arrangement will be expected to maintain that arrangement during performance of any contract awarded to that Offeror under this RFP. As a part of their proposal, the Offeror must provide a contractor team agreement signed by all parties, identifying the legal name(s) of all entities and describing the nature of each entity’s relationship (teaming/partnering, joint venture, etc.) and its role on this project. Past Performance information of other than the Offeror will not be considered without the teaming arrangements. In the case of joint ventures, at least one project will be submitted from each member to demonstrate past experience. This documentation shall be provided in applicable section of the Offeror's proposal.
3.1.1 Media, Page Size, Margins, Fonts, and Page Limitations.
Submit only the hard-copy paper documents and electronic files specifically authorized elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal. Except where another size is specifically authorized for a specific submission, use only 8 1/2” x 11” paper. Use at least 1 inch margins, which may include headers and footers. Do not justify the right margin. Ensure that all text and graphics are clearly legible. Do not use a font size smaller than 10, unusual font styles such as script, or condensed fonts. For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, a foldout sheet will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.
3.1.2 Proposal Binding.
The preferred method for assembling proposals is a method that enables the rapid insertion or deletion of pages such as three ring binders. Ensure recommended capacity is not exceeded and that pages turn freely. Do not use spring clamps, spiral binding systems, or heat binding systems.
3.1.3 Conditioning of Offer.
Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal volumes. Inclusion of any standard company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the offer is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the offer; see “Inquiries”, located in Section 00 21 16, for points of contact. Notwithstanding the above, the offeror must clearly describe in the proposal cover sheet submitted with the price volume any exceptions, within the offer, to the contractual and/or technical terms and conditions of the solicitation.
3.1.4 Restrictions on Offeror-Provided Information.
“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must clearly mark the information in accordance with FAR 52.215-1, “Instructions to Offeror – Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data.” Files shall not contain classified data.
3.2 GENERAL PROPOSAL PREPARATION.
The proposal shall be submitted as summarized below and as required by the specifications.
(1) Volume I – Technical Volume
(a) Factor 1: Experience
(b) Factor 2: Network Analysis Schedule (NAS)
(c) Factor 3: Past Performance
(2) Volume II – Price Volume
(a) Proposal Cover Sheet
(b) Standard Form 1442, Acknowledgement of Amendments, Joint Venture Agreement
(c) Pricing Schedule
(d) Completed 52.204-8, printed out and applicable checkmark applied.
(e) Offer Guarantee
(f) Pre-Award Survey Information
(g) Sub-Contracting Plan
Each offeror must submit a proposal consisting of a “price” volume, and “technical” volume.
The price volume includes the signed offer and the offeror’s proposed prices. The technical volume includes all required information relating to the “non-price” evaluation factors. The two volumes must be submitted as separate, physically distinct volumes. All volumes must be received at the location shown in Block 8 of Standard Form 1442, not later than the date and time specified in Block 13 of Standard Form 1442. The information in the two volumes is evaluated separately and independently. Do not cross-reference similar material between the non-price and price volumes.
3.2.1 Marking of Proposal Volumes.
Mark each volume as either the “Price Volume” or “Technical Volume”. In addition, mark the outside front cover of each volume with the project title and location, solicitation number, name and address of the offeror, and volume copy number. (Markings which identify the offeror are not required on either the back cover or on the spine/binding.)
Offers are to be formatted and tabbed in accordance with the instructions that follow for each proposal volume.
Include a table of contents for each proposal volume.
4 TECHNICAL VOLUME
The Technical Proposal is to be submitted in one hard “original” and four (4) copies. In addition, submit one complete PDF copy. of the technical proposal on Compact Disk (CD).
4.1 FORMAT, CONTENTS, AND LIST OF TABS FOR THE TECHNICAL VOLUME.
Use 8-1/2” x 11” pages for the narrative portions of the proposal. There is not a page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location. Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal. Limit your submittals to the information specified;
excess information will not be evaluated. For purposes of the CD electronic version of the proposal, “tabs” means searchable PDF bookmarks.
4.2 Tab 1 of the Technical Volume: Factor 1 – Experience.
4.2.1.1 Submission Requirements
The offeror shall provide two (2) projects for each of the five (5) elements of jet fuel facilities-related work listed below. The offeror shall submit recent projects substantially completed within the last seven (7) years. A submitted project by either the offeror or its proposed subcontractor can demonstrate completion of one, some or all of the elements of jet fuel facilities related work listed below.
1) Demolition of existing jet fuel facilities and fuel systems
2) Removal of existing underground jet fuel tanks
3) Installation of above ground jet fuel tanks and fuel systems
4) Construction of jet fuel pump house and associated jet fuel systems
5) Construction of jet fuel transfer facilities
Each project example provided by the offeror shall include a narrative containing at least the following information:
• Project title and location
• Detailed description of the project and work performed
• Original contract award amount and final construction cost
• Original contract finish date and actual finish date
Formatting Limitations:
Each example project description shall not exceed three (3) pages (8.5 x 11 inches page size) including any images, graphics, charts and tables. If offeror submits more than three (3) pages for any example project description, the additional pages will not be evaluated. Start each example project on a new page.
Please number your project submissions and include a matrix similar to the one below for purposes of matching your submissions to their applicable experience areas.
Evaluation Areas Experience 1 - Put which project submission # meets this requirement
Experience 2 - Put which project submission # meets this requirement
Demolition of existing jet fuel facilities and fuel systems
Removal of existing underground jet fuel tanks
Installation of above ground jet fuel tanks and fuel systems
Construction of jet fuel pump house and associated jet fuel
Construction of jet fuel transfer facilities
4.2.1.2 Evaluation Criteria
Acceptable: a proposal will be rated Acceptable if it meets all of the following requirements:
(a) The proposal demonstrates that the offeror (including the Prime contractor and any subcontractor(s) the offeror may choose to employ or partner with) performed at least two relevant projects for each of the 5 work elements listed above
(b) All project were substantially completed within the last seven (7) years.
****For the purpose of this evaluation, substantially complete means that only punch list items remain for project acceptance, or that the majority of the elements of the project have been turned over to the customer for beneficial occupancy. A submitted project can demonstrate completion of one, some or all of the elements. ****
Unacceptable: a proposal will be rated Unacceptable if it does not meet the above stated requirement.
4.3 Tab 2 of the Technical Proposal: Factor 2 – Network Analysis Schedule
4.3.1 Submission Requirements:
The offeror shall submit a Network Analysis Schedule (NAS) showing the offeror’s proposed phasing of work and critical path of construction activities in a logical sequence based on the requirements contained in Specification Section 01 32 01, “Project Schedule.”
The schedule shall account for the following constraints:
• Use a Notice To Proceed (NTP) date of 30 November 20192020 for evaluation purposes only
• The period of performance for the entire contract is 730 days after the contractor receives Notice to Proceed (NTP) from the Government.
The presentation of the schedule shall include a network diagram that shows the order, duration, and interdependence of activities and clearly indicates the critical path. It shall also include a succinct narrative that explains the approach and logic of the proposed schedule. The narrative should identify important assumptions and explain any unusual or counter-intuitive aspects of the schedule, especially those related to task sequencing or critical path activity durations.
Formatting Limitations:
The schedule must consist of a Gantt chart of no more than two (2) pages in length (page size 11 x 17 inches) and the narrative statement. The narrative is limited to two (2) pages (page size 8.5 x 11 inches).
4.3.2 Evaluation Criteria
Acceptable: a proposal will be rated Acceptable if it meets all of the following requirements:
(a) A Gantt chart showing the order, duration and interdependence of major activities clearly indicating the critical path and not conflicting with any constraints identified in the technical specifications (e.g., pre-construction submittal review times)
(b) A narrative of two pages identifying important assumptions and explaining any unusual or counter-intuitive aspects of the offeror’s proposed network diagram.
Unacceptable: a proposal will be rated Unacceptable if it does not meet the above stated requirements.
4.5 Tab 3 of the Technical Proposal: Factor 3 Past Performance
4.5.1 Submission Requirements
a. The Offeror shall submit past performance information on the projects submitted in paragraph 4.2 under Factor 1 Experience. The Offeror shall provide completed performance evaluations for the submitted projects that demonstrate the Offeror’s performance on recent and relevant projects of similar scope, magnitude and complexity.
The Offeror shall provide formal performance evaluation if they are available. Formal performance evaluations are those that are similar to the Contractor Performance Assessment Reporting System (CPARS)
b. If a formal performance evaluation is not available, then the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project described above in 4.2.1.1. Ensure correct phone numbers and email addresses are provided for the client point of contact.
Completed PPQ’s should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project (s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Completed questionnaires may also be submitted by the preparer directly to the Government’s point of contact, DeAnna L. Mannel at DeAnna.L.Mannel@usace.army.mil prior to proposal closing date.
a. In addition to the above, the Government may review information obtained from any other sources in evaluating each offeror’s past performance. Sources may include, but are not limited to, past performance information retrieved through the using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
b. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
c. Start the information for each example project on a new page. There is not a page limitation for this submission.
4.4.2. Evaluation Criteria:
The past performance evaluation is an assessment of the offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements.
Past performance will be initially evaluated to determine whether the offeror’s present/past performance is recent, and relevant or not relevant to the effort to be acquired. Past performance will be considered recent if it has been completed within the last seven years or substantially complete at the time the proposal is submitted. It will be considered relevant if it is similar in size, scope, and complexity to this project.
Second, the past performance evaluation should determine how well the offeror performed on the prior contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past mailto:DeAnna.L.Mannel@usace.army.mil performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts.
NOTE: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined to have unknown (or “neutral”) past performance. In the context of acceptability/unacceptability, a neutral rating shall be considered “acceptable.”
In conducting the past performance evaluation, each Offeror shall be assigned one of the ratings in accordance with the table below.
Adjectival Rating Description Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown (See note above).
Unacceptable Based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.
5 PRICE VOLUME.
5.1 NUMBER OF SETS OF THE PRICE PROPOSAL.
Submit the price proposal volume in a both hard copy and electronic format. The electronic copy should be in a searchable, bookmarked “pdf” file format which will become part of the contract (this price volume may be on the same CD as the technical proposal, but both volumes must be in separate files).
5.1.1. FORMAT, CONTENTS, AND LIST OF TABS FOR THE PRICE PROPOSAL.
Use only 8-1/2” x 11” pages. There are no page limits for the price proposal; however, limit responses to required information. Excess information will not be evaluated. Organize your price proposal as indicated below. For the price volume only, “tab” means a bookmark on a searchable PDF document. If a tab is not applicable to your proposal, omit that tab but do not renumber the subsequent tabs.
Tab 1: Proposal Cover Sheet.
The proposal cover sheet is required by FAR 52.215-1(c)(2)(i)-(v). This provision, titled “Instructions to Offerors – Competitive Acquisition” is incorporated by reference in Section 00 21 00. The format and content for the proposal cover sheet follows:
PROPOSAL COVER SHEET
1. Solicitation Number.
2. The name, address, CAGE code, and telephone numbers of the offeror.
3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.
4. Names, titles, e-mail address, and telephone numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation:
5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(End of Proposal Cover Sheet) Tab 2: SF 1442; Acknowledgement of Amendments; Joint Venture Agreement The Standard Form (SF) 1442 must be completed by the offeror and duly executed with an original signature by the official(s) identified in the proposal cover sheet as authorized to bind the offeror in accordance with FAR 4.102, which includes specific instructions pertaining to individuals, partnerships, corporations, Joint Venture participants, and agents. Include the offeror’s CAGE code in block 14 of the SF 1442, along with the offeror’s address. All amendments must be acknowledged in accordance with the instructions on the Standard Form 30, Amendment. If the offeror is a Joint Venture (JV), include a copy of the JV agreement and indicate its status. *Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your proposal.
Tab 3: Contract Line Item Number (CLIN) and Pricing Schedule Submit the completed Contract Line Item Number (CLIN) Schedule on the SF 1442, and the Pricing Schedule with the offeror’s proposed contract prices inserted in the appropriate spaces.
Prices must be proposed for all contract line items (except for those CLINs deleted from the solicitation). Unit prices must be extended to the actual “dollar and cents” amounts (e.g., to two decimal places). Do not round off the extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission. Any qualification of pricing may render the proposal unacceptable and therefore not eligible for award. However, offerors are encouraged to use callouts, footnotes, etc. to explain their lines of thinking where it would aid in the Government finding the price(s) fair and reasonable.
Tab 4: Annual Representations and Certifications The offeror must have electronically completed the annual representations and certifications on the “System for Award Management” (SAM) website in accordance with FAR 52.204-8. The offeror is responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Please print out 52.204-8, and place the appropriate checkmark in section (b)(2).
Tab 5: Bid Guarantee.
All offerors must submit a bid guarantee, (e.g., Standard Form 24, Bid Bond) which complies with the requirements of FAR 28.101 Bid Guarantees, and any Defense and Army supplements thereto.
Tab 6: Pre-Award Survey Information
a. The contracting officer is required to make an affirmative pre-award determination of the prospective contractor’s responsibility in accordance with the mandatory requirements of Part 9 of the Federal Acquisition Regulation (FAR) and its supplements. The contracting officer must have sufficient information available to determine that a prospective contractor meets these minimum standards. Therefore, the offeror is requested to provide the pre-award survey information described below with its price proposal:
(1) The completed Construction Contractor Data Form with Supplemental Schedules A-C (see attachment 6). If the offeror is a large multi-segmented business concerns, the data provided on the supplemental schedules may be limited to information that directly pertains to the specific segment of the business concern (i.e., the division, group, unit, etc.) proposed to perform work under the prospective contract with its own work force.
If the offer is being submitted by a Joint Venture, submit a separate form for each Joint Venture participant. The offeror may submit pre-award survey information in another format, provided that the information furnished is substantially the same as that which would be furnished on the Construction Contractor Data Form and its supplemental schedules.
(2) Current financial statements. If the financial statement is more than 60 days old, submit a certificate stating that the firm's financial condition is substantially the same, or, if not the same, state the changes that have taken place. If a Joint Venture, provide this information for each participant in the Joint Venture.
(3) Banking information. Provide letters from banks or other financial institutions with which the contractor conducts business. The letters should contain information about your firm's accounts, loans, lines of credit, etc. The Government is interested in financial stability, timely payments, the length and nature of the relationship between the firm and the financial institution, and the firm's financial ability to perform the contract.
The letters should also provide the name and telephone number of the bank representative the Government may contact. If a Joint Venture, provide this information for each Joint Venture participant.
The Government will treat the pre-award survey information submitted by the offeror as proprietary.
Tab 7: Sub-Contracting Plan –
(a) See FAR 52.219-9, Section 00 70 00, of this solicitation. Subcontracting Plans will be developed considering only the subcontracts actually to be awarded. Subcontracting Plans are required from other than small businesses if the contract price is over $1,500,000; they are not required from small business firms regardless of the contract price.
(b) For information on the evaluation of subcontracting plans, see Army Federal Acquisition Regulation Supplement, Appendix DD.
(c) Contact Ms. Michelle Morales (916)557-7641, Deputy for Small Business, with questions on the Subcontracting Plan requirements and further instructions on submission of Electronic Subcontracting Reporting System (eSRS) as required by FAR 52.219-9.
(d) The Corps of Engineers highly encourages all bidders to meet the recommended subcontracting goals as follows:
Small Businesses 30.0%
Small Disadvantaged Businesses 8.0%
Women-Owned Small Businesses 5.0%
HUBZone Small Business 5.0%
Veteran-Owned Small Business 1%
Service Disabled Veteran Owned 1.0% Small Business
The goals are calculated as a percentage of the TOTAL SUBCONTRACTING
DOLLARS, NOT THE TOTAL CONTRACT AMOUNT.
Per Amendment 0002, the Small Business Subcontracting Plan (Tab 7) may be submitted via email to DeAnna.L.Mannel@usace.army.mil no later than noon on 7 August 2020.
(End of Summary of Changes) mailto:DeAnna.L.Mannel@usace.army.mil
| 2. BASIS OF AWARD. |
| 2.2. SOURCE SELECTION USING THE LOW-PRICE, TECHNICALLY-ACCEPABLE (LPTA) METHOD |
| 3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS |
| The schedule shall account for the following constraints: |
| • Use a Notice To Proceed (NTP) date of 30 November 20192020 for evaluation purposes only |
| • The period of performance for the entire contract is 730 days after the contractor receives Notice to Proceed (NTP) from the Government. |
| The presentation of the schedule shall include a network diagram that shows the order, duration, and interdependence of activities and clearly indicates the critical path. It shall also include a succinct narrative that explains the approach and logic... |