W91238-17-R-00xx Attachment 1 8 Nov 2017

Statement of Work F-35A Munitions Maintenance Complex

Hill AFB, UT

1. Scope of Work

The work for this project is to design and construct a Munitions Maintenance Complex at Hill Air Force Base (HAFB), Utah. The F-35A Munitions Maintenance Complex will be located within the Munitions and Missile Storage (MAMS) area at HAFB. Facilities must be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements, and UFC 1-200-02, High Performance and Sustainable Building Requirements. The Contractor shall provide all labor, equipment, transportation, material and supervision to perform the design and construction of the complete operational facilities. Design and construction shall include all civil, paving, architectural, geotechnical, structural, utilities, landscaping, security, mechanical, electrical, demolition, and communications work to support the necessary construction.

Note: This intent of this Statement of Work is to provide general project information to interested Offerors of the subject procurement. Conceptual drawings are provided for reference. The complete project requirements, including but not limited to the Specific Technical Engineering and Design Criteria, Functional Design Criteria Room by Room Requirements, including all attachments, will be issued in the Phase 2 solicitation. A draft of the Specific Technical Engineering and Design Criteria is included in the Phase 1 solicitation for reference.

2. Description

2.1 The Contractor shall furnish and install all labor, materials, tools, equipment, and supervision necessary to provide a complete and usable project per the Specific Technical Engineering and Design Criteria, Functional Design Criteria Room by Room Requirements, including all attachments, Base Facility Design Standard, Architectural Compatibility Guide and requirements specified herein in Appendix 1.

Facilities must be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements, and UFC1-200-02, High Performance and Sustainable Building Requirements. Contractor shall include in the design the following features:

Provide a standalone Munitions Maintenance Facility(MMF) with two drive-through maintenance bays and an administrative support area;

Provide an addition to existing Building 988 that includes a storage bay and munitions maintenance bay;

Provide reinforced concrete footings, foundations, slabs, and maintenance bay walls; insulated steel frame walls with metal siding for the storage bay addition to Bldg 988; and an insulated standing seam metal roof over both the standalone facility and the additions to Bldg 988;

Equip maintenance bays with 115 VAC, 60 Hz, single phase and 115 VAC, 400 Hz, three phase power and explosion proof lighting, outlets, switches, and door openers;

Provide self-supporting 5-ton bridge crane in the maintenance bay addition to Bldg 988; and Provide fire detection/suppression system, including fire pumps;

Provide Intrusion Detection System(IDS);

Provide Lightning Protection System(LPS);

Project includes all supporting utilities, site improvements and pavements including access roads. Parking lot shall have an aggregate surface.

Options include: Steel mast pole LPS, asphalt concrete surfacing and striping of parking lot area, exterior lights/poles for parking lot area, Portland Cement Concrete(PCC) for pavement area behind the MMF.

This project will comply with DOD Antiterrorism Protection requirements per UFC 4-010-01.

Sustainable principles will be integrated into the design, development, and construction of this project in accordance with UFC 1-200-02.

This is a design-build contract therefore the Contractor is required to perform design work prior to construction. The design of architectural, interior design, structural, mechanical, electrical, civil, landscape and other engineering features of the work shall be accomplished, reviewed, approved and sealed by engineers, architects and interior designers who are licensed professionals with a minimum of six (6) years’ experience to practice in their respective professional field in a state or possession of the United States.

2.2 Special Design Requirements: The structural interior design (SID) shall be designed/supervised by a registered or certified (as appropriate for the state) interior designer who is National Council for Interior Design Qualification (NCIDQ) certified. The project must be designed to comply with UFC 1-200-02, High Performance and Sustainable Building Requirements. The RFP requires the Contractor to third-party validate the Federal/UFC requirements have been met using either the US Green Building Council (USGBC) or Green Building Initiative (GBI) Guiding Principle Compliance (GPC) systems. LEED certification is no longer required. The AF Sustainability Requirements Scoresheet will be used to track and report project compliance status at each submittal. Additional guidance can be found at http://www.wbdg.org/ccb/browse_cat.php?c=265. The hydraulic design, drawings and layout of the sprinkler system shall be prepared by a registered Fire Protection Engineer or National Institute for Certification in Engineering Technologies (NICET) Level 4 technician with 4 years current experience in design of fire protection systems. The geotechnical design shall be performed by a Geotechnical firm with at least five (5) years experience of geotechnical design work within the Ogden/Salt Lake City region.

Communications Systems Engineering and Design shall be performed by a Building Industry Consulting Service International (BICSI) Registered Communications Distribution Designer (RCDD). The shop drawings shall be Stamped and Signed by the RCDD certifying compliance with the applicable Electronic Industry Association/Telecommunication Industry Association (EIA/TIA) standards as required. Design of fire alarm system shall be done by a registered (NICET) Level 4 Designer, with at least three (3) years of current and applicable experience. The design drawings must bear the Designer's NICET Level 4 Certification and signature. Contractor shall have experience in Building Envelope with continuous Air Barrier Systems, and Lightning Protection Systems. The Contractor is responsible and liable for the complete design and shall not assume that the provided design criteria and drawings in this solicitation will alleviate him/her from performing any additional design as required to produce a complete set of construction documents.

The Government’s conceptual facility and site design provided in the RFP documents illustrates intent and functional relationships and does not indicate all necessary construction requirements or components. The written Phase 2 RFP describes associated technical, performance and systems requirements, and includes all specifications, attachments and drawings. The Contractor is responsible for the complete project design, shall retain all responsibilities, and be recognized as the Designer of Record.

3. General Project Requirements:

Contractor shall follow all security requirements for base access. All Contractor and subcontractor personnel will need to obtain badges for all access on base from the security office.

AT Level I Training: All Contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at http://jko.jten.mil.

The Contractor shall be responsible for the coordination of work performed by their employees and all subcontractors. The Contractor should inspect all work areas prior to submitting a proposal in accordance with FAR 52.236-3, Site Investigation and Conditions Affecting the Work. It shall be the Contractor’s responsibility to verify all current record drawings prior to the start of any and all design and /or construction work.

The Contractor shall be responsible for the coordination and proper relationship of this work to the building premises and thoroughly familiarize themselves with all details of the work and working conditions, to verify all dimensions in the field, and advise the Administrative Contracting Officer (ACO) of any discrepancies before performing any work.

The Contractor is responsible for maintaining the site and all other Contractor controlled areas in such a manner as to minimize the risk of injury or accident to site personnel or others who may be in the area.

The Contractor is also responsible for furnishing an identification badge/card to each individual working on the site.

END OF STATEMENT OF WORK