About this file

ATTACHMENT 2 PHASE II SUPPLEMENTAL CONTRACT REQUIREMENTS

View the file

Other files

File Type Posted
Phase_II_Amendment_0007_SF30.pdf PDF
W91238-15-R-0014__AM0007.pdf PDF
A_forthcoming_amendment_will_extend_the_due_date_of_proposals_from_11_Sep_2015_to_15_Sep_2015.docx DOCX document
Solication_Amendment_0006_SF_30_4_Sep_15.doc.pdf PDF
Solication_Amendment_Attach_04_Task_Order_Acknowlegement_4_Sep_15.pdf PDF
Amendment_0005_Phase_II.pdf PDF
PHASE_II_Amendment_Attach_04_TASK_ORDER_ACKNOWLEDGEMENT_STATEMENT.pdf PDF
PHASE_II__Amendment_MOTCO_FM_190-2_Camera_Pass.pdf PDF
PHASE_II_Amendment_Attach_03_Wage_Determination.pdf PDF
PHASE_II_Amendment_App_01_-_1965_SPECS.pdf PDF
PHASE_II_AMENDMENT_W91238-15-R-0014_SF_30.pdf PDF
PHASE_II_Amendment_App_03_-_NCIC_CONSENT_FORM_-_DEC_2014.pdf PDF
PHASE_II_Amendment_Attach_01_SOW__General_Purpose_Maintenance_Shop__2015-08-25_.pdf PDF
PHASE_II__Amendment_App_02_-_Access_Request_MOTCO_FORM_190-3_DEC_2014.pdf PDF
Amendment_W91238-15-R-0014-0003-_Central.pdf PDF
New_proposal_due_date_30_June_2015_at_2pm_PST.doc DOC document
Amendment_W91238-15-R-0014-0002-_Central.pdf PDF
Amendment_W91238-15-R-0014-0001-_Central.pdf PDF
A7_1-Specifications_6Mar15_FINAL.pdf PDF
A7.1_W91238-14-R-0014 _Central_SF1442.pdf PDF
W91238-15-R-0014.pdf PDF
Attachment_1_-_Specifications.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 02

SUPPLEMENTAL CONTRACT REQUIREMENTS

1. Performance Period. Refer to FAR 52.211-10. The performance period for the work stated above shall be 540 calendar days.

2. Liquidated Damages. Refer to FAR 52.211-12, Liquidated Damages-Construction.

Liquidated damages for this work is $2,512.00 for each day of delay.

3. Authorities. Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.

4. Wage Determination. General Decision No. CA150029 dated 08/14/2015 CA29, or its most current modification at the time of award is hereby applicable to work performed under this task order. The most current decision or its modification can be found at:

http://www.wdol.gov/wdol/scafiles/davisbacon/CA29.dvb?v=7

5. Time Extensions For Unusually Severe Weather. Refer to Default (Fixed-Priced Construction). All weather delay will need to be submitted and approved by the Contracting Officer Representative.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK- CONCORD, CA

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(06) (05) (05) (04) (01) (00) (00) (00) (01) (02) (05) (06) http://www.wdol.gov/wdol/scafiles/davisbacon/CA29.dvb?v=7

SUPPLEMENTAL CONTRACT REQUIREMENTS