Design-Build Potable Clean Water System, Dugway Proving Grounds, UT
Solicitation number
W91238-10-R-0008
Issued by

About this file

W91238-10-R-0008-0001 Specs Drawings

View the file

Other files

File Type Posted
W9128-10-R-0008-0004.pdf PDF
W91238-10-R-0008 Amd 0004 Specifications_7pgs.pdf PDF
SF30 Amd 0003.pdf PDF
SF30 Amd 0002.pdf PDF
Atch 4 Spec Dwg.pdf PDF
W91238-10-R-0008-0001.pdf PDF
Pre-Proposal Sign-In Sheet.pdf PDF
10-R-0008 Pre-Proposal Sign-In Sheet.txt TXT text file
PreProposal Conference Script 2009Dec16.pdf PDF
Wage Determination Tooele 20 Nov 09.pdf PDF
VOL-1_FRONT END.pdf PDF
VOL-2_SPECS-DWGS_W91238-10-R-0008.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DPG CLEAN POTABLE WATER SYSTEMS 1687

01010-1

SECTION 01010

STATEMENT OF WORK

1.0 PROJECT OBJECTIVES

2.0 SCOPE

2.1 SCOPE

2.2 SITE

2.3 GOVERNMENT-FURNISHED GOVERNMENT INSTALL EQUIPMENT (GFGI)

2.4 FURNITURE REQUIREMENTS

2.5 ACCIDENT PREVENTION PLAN

2.6 DPG WATER TREATMENT BACKGROUND

2.7 DPG WASTEWATER TREATMENT PONDS

2.8 OPTIONAL ITEMS

3.0 FUNCTIONAL AND AREA REQUIREMENTS

3.1 GENERAL REQUIREMENTS

3.2 FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3.3 TECHNICAL REQUIREMENTS

3.4 REFERENCES

4.0 APPLICABLE CRITERIA

4.1 APPLICABLE INDUSTRY CRITERIA

4.2 APPLICABLE MILITARY CRITERIA

4.3 PRECEDENCE

5.0 GENERAL TECHNICAL REQUIREMENTS

5.1 SITE PLANNING AND DESIGN

5.2 SITE ENGINEERING

5.3 ARCHITECTURE AND INTERIOR DESIGN

5.4 STRUCTURAL DESIGN

5.5 THERMAL PERFORMANCE

5.6 PLUMBING

AM-01

01010-2

5.7 ELECTRICAL SYSTEMS

5.8 HEATING, VENTILATING AND AIR CONDITIONING

5.9 ENERGY CONSERVATION

5.10 FIRE PROTECTION

5.11 SUSTAINABLE DESIGN

5.12 CONSTRUCTION AND DEMOLITION (C&D) WASTE MANAGEMENT

5.13 SECURITY (ANTI-TERRORISM STANDARDS)

6.0 PROJECT SPECIFIC REQUIREMENTS

6.1 GENERAL

6.2 APPROVED DEVIATIONS

6.3 FUNCTIONAL PREFERENCES

6.4 CIVIL DESIGN

6.5 SITE ENGINEERING

6.6 ARCHITECTURE

6.7 STRUCTURAL DESIGN

6.8 THERMAL PERFORMANCE

6.9 PLUMBING

6.10 SITE ELECTRICAL SYSTEMS

6.11 FACILITY ELECTRICAL SYSTEMS

6.12 HEATING, VENTILATING AND AIR CONDITIONING

6.13 ENERGY CONSERVATION

6.14 FIRE PROTECTION

6.15 SUSTAINABLE DESIGN

6.16 ENVIRONMENTAL

6.17 PERMITS

6.18 DEMOLITION

6.19 ADDITIONAL FACILITIES

6.20 MAINTENANCE AND OTHER GENERAL REQUIREMENTS

01010-3

APPENDICES

A. DPG WTP Photographs

B. DPG Water Chemistry Data and Well Data

C. DPG WTP Drawings

D. Program Basis for DPG WTP (for information only)

E. DPG Contact Information

F. Geotechnical Report (for information only)

G. DPG Chemical Warfare Material (CWM) Risk Assessment Information

H. Electric Meter Package Basic Cut Sheets

01010-4

1.0 PROJECT OBJECTIVES

The project objective is to design and construct functional drinking water treatment facilities for the Army at Dugway Proving Ground (DPG) that are consistent with the design and construction practices used for civilian sector projects that perform similar functions to the military projects.

It is the Army's objective that these buildings/facilities will have a 25-year useful life before a possible re-use/re-purpose or renovation requirement, to include normal sustainment, restoration, modernization activities. Therefore, the design and construction should provide an appropriate level of quality to ensure the continued use of the facility over that time period with the application of reasonable preventive maintenance and repairs that would be industry-acceptable to a major civilian sector project owner. The site infrastructure will have at least a 50-year life expectancy with industry-accepted maintenance and repair cycles.

The government is required by Public Law 102-486, Executive Order 12902, and Federal Regulations 10 CFR 435 to design and construct facilities in an energy-conserving manner while considering life cycle cost over the life of the facilities.

The project site should be developed for efficiency and to convey a sense of unity or connectivity with the adjacent buildings and with the Installation as a whole.

Requirements stated in this contract are minimums. Innovative, creative, and life cycle cost effective solutions, which meet or exceed these requirements are encouraged. Further, the Offeror is encouraged to seek solutions that will expedite construction (panelization, pre-engineered, etc.) and shorten the schedule. The intent of the Government is to emphasize the placement of funds into functional/operational requirements. Materials and methods should reflect this by choosing the lowest Type of Construction allowed by code for this occupancy/project allowing the funding to be reflected in the quality of systems selected.

2.0 SCOPE

2.1. WATER TREATMENT PLANT

Provide appropriate drinking water treatment facilities in accordance with this contract. This water treatment system is to treat and provide drinking water and is intended to be similar both functionally and technically to similar facilities in the private sector.

A design-build procurement method will be utilized for this work. DPG utilizes groundwater that contains contaminants above the Federal and State of Utah requirements. A water treatment system is required to reduce contaminant levels in water to satisfy primary and secondary drinking water requirements.

DPG prefers the water treatment plant to be typical and utilized successfully in other Utah locations. The preference is low operating costs; low use of standard water treatment chemicals; no plant operator certification upgrade required; minimum wasting of process/backwash water; and non-proprietary equipment. DPG desires an estimate of operating costs, operator certification requirements, and wastewater discharge flows to be submitted to John Craig (DPG). All work shall be performed in accordance with applicable regulations, requirements and codes.

01010-5

2.2. SITE

Provide all site improvements necessary to support the new building facilities. The Offeror shall design the exterior of the facility to be compatible with the surrounding context. The Offeror’s architectural design development should consider any existing building forms, materials, scale, proportions, and organizational layout, and be reflected in the proposal.

Pictures of surrounding architecture are permissible to establish the theme. The Contractor and A-E must certify that they have visited the site before preparing their proposal.

The construction cost limitation is $22,525,000. This amount includes the design effort as well as the construction effort. These costs are presented so that a level of quality can be established and avoid a misunderstanding by the Contractor in cases where they provide a higher cost proposal when a proposal of lesser scope, quality, and performance was funded and required. The Contractor is under no obligation to approach this ceiling.

2.3. GOVERNMENT-FURNISHED GOVERNMENT-INSTALLED EQUIPMENT (GFGI)

Coordinate with Government on GFGI item requirements. Provide all utility connections and space with required clearances for all GFGI items. D-B contractor shall provide a suitable Desk-top computer in English Village plant compatible with D-B contractor installed SCADA System.

2.4. FURNITURE REQUIREMENTS:

There is no furniture requirement or procurement for this contract. Furniture procurement is not included in this contract.

2.5. ACCIDENT PREVENTION PLAN

An accident prevention plan (APP) shall be submitted and reviewed by the USACE. This shall be submitted, reviewed and approved prior to any fieldwork. The SSHSP shall adhere to Federal OSHA 29 CFR 1910, 1926 and the US Army Corps of Engineers EM 385-1-1 (September 2008), and Utah requirements. Refer to Appendix G for Chemical Warfare Material (CWM) Risk Assessment information.

2.6. DPG WATER TREATMENT BACKGROUND

Dugway Proving Ground is located in Toole County, Utah approximately 85 miles southwest of Salt Lake City, Utah. Highway access to DPG is totally restricted from all directions except via State Highway 99 and 96, which converge at the DPG’s English Village main gate.

Water system identification numbers for English Village, Ditto Technical Facility, and the Carr Facility are 23054, 23021 and 23058, respectively. The system name and address is Dugway Proving Ground Water System, Dugway, Utah 84022. At English Village there are approximately 712 connections serving 1,230 people, at Ditto there are approximately 116 connections serving 500 people, and at Carr there are approximately 28 connections serving 93 people.

Note that this RFP is for work at DPG outside of English Village; therefore most English Village water system details will not be described in this RFP.

Ditto Technical Facility Water System. The source water for the Ditto water system is the Dugway Valley-Government Creek Aquifer, part of the Great Salt Lake regional flow system.

The two relevant zone of groundwater have been identified as a shallow and mid-level aquifer. Water production occurs in the mid-level aquifer which is composed of saturated

01010-6 older alluvium and is under confined conditions at Ditto. The Ditto water system (Number 23021) supplies domestic and industrial water to the Ditto Area, Avery Technical Center, Baker Area, and Michael Army Airfield. The system has a treatment capacity of approximately 1 million gallons per day and a storage capacity of 540,000 gallons.

Ditto Technical Facility Water Supply Wells. Two water supply wells provide raw water to the Ditto Technical Facility Water System. Wells 3 and 28 are located in Ditto. A third well located in Ditto, Well 31, is currently inactive and scheduled for abandonment. Groundwater is pumped into a 40,000 gallon ground-level raw water storage tank. Available existing pump information is as follows; Well #3 pump: 350gpm, 15hp, and approximately 20 psi working pressure. The two wells provide the drinking water at a rate of 580 to 770 gallons per minute.

Ditto Technical Facility Water Storage Tanks. The Ditto Technical Facility System has a current storage capacity of 540,000 gallons. Water storage is provided by 40,000 gallon ground-level raw water tank (Building 4101) located adjacent to and just north of the Ditto Water Treatment Facility (Building 4105). In addition, two 250,000-gallon elevated storage tanks provide water storage for the Ditto Technical Facility and Baker Area; one (Building 4106) located in the Ditto Technical Facility just south of the treatment facility, the other tank (Building 2050) is located approximately 6.25 miles west of the Ditto Technical Facility at the Baker Area. An inactive 100,000-gallon elevated tank (Building 4146) is also available for water storage at the Ditto Technical Facility. With the water plant, the raw water is chlorinated using chlorine-gas injection. Available existing pump information is as follows:

475 gpm, 175 ft head.

Ditto Technical Facility Water Distribution and Consumption. This system is considered a small (<10,000 connections) public, non-transient, non-community water system serving approximately 72 industrial facilities. The distribution length has 116 connections serving 500 people.

Carr Technical Center Water System. The Dugway Valley-Government Creek Aquifer is the source for this water system; the same aquifer supplies the Ditto system. This system is an existing, public, non-transient, non-community water system; System Number 23058. This system has a treatment capacity of approximately 900,000 gallons per day and a storage capacity of 350,000 gallons.

Carr Technical Center Water Supply Wells. Two water supply wells currently provide raw water. Well 33 is located 0.4 miles to the west of the Building 3143 near Bushnell Material Test Facility. Sodium hypochlorite treatment is administered to the raw water at Well 33.

The raw water at Well 5 is chlorinated with chlorine gas.

Groundwater from Well 5 is pumped to Building 3143, the Carr Technical Center Water Plant.

Available existing pump information is as follows; Well #5 pump: 280gpm, and approximately 90 psi working pressure. Within the water plant, the raw water is chlorinated using chlorine gas injection. The treated water is then pumped into a 100,000-gallon potable elevated storage tank located adjacent to the water plant.

Carr Technical Center Water Storage Tanks. The Carr system has a current storage capacity of 350,000 gallons provided by the two elevated tanks. A 100,000 gallon tank (Building 3145) is located adjacent to the Carr Water Treatment Facility (Building 3143). The newer second storage tank (Building 0802B) with a capacity of 250,000 gallons is located approximately 0.4 miles to the west near Well 33.

Carr Technical Center Water Distribution and Consumption. This system supplies domestic and industrial water to approximately 25 industrial facilities located at Carr Technical Center.

The Carr system is considered to be a small drinking water system because it serves less

01010-7 than 10,000 connections. The distribution length is two miles with 28 service connections serving a population of 93. Water is also supplied to 14 hydrants for fire protection.

The following table contains DPG well information for the water system.

Water System

Well Number

Casing Radius (in.)

Total Depth

(ft. bgs)

Pump Type Well Capacity (gpm)

Year Constructed

3 6,5 330 Turbine 400 1945 Ditto

28 8,6 336 Submersible 370 1959

5 5 335 Submersible 310 1944 Carr

33 - 405 Submersible 350 2003

Note that well 33 is treated with liquid chlorine, all other well treatment is by chlorine gas.

Bgs = below ground surface

The following table is for storage tank information at Ditto and Baker.

Tank Building Number

Location Capacity (gallons)

Dimensions

Ditto Raw Water Storage Tank

4101 Adjacent to Ditto Water Treatment Facility

40,000 18 ft tall, 20 feet in diameter

Ditto Elevated Storage Tank

4106 Ditto Cantonment 250,000 133 ft high, 40 feet in diameter

Baker Elevated Storage Tank

2050 Baker Cantonment 250,000 121 feet high, 40 feet in diameter

Carr Elevated Tank 3145 Carr Cantonment 100,000 92.5 feet high, 30.5 feet in diameter

Carr Elevated Tank 0802B South of Bushnell Material Test Facility

250,000 121 feet high, 40 feet in diameter

01010-8

2.8. OPTIONAL ITEMS

The following are additional optional items to be evaluated and priced separately. The government may choose to select any and/or all of the items for this RFP.

1. There are no optional items.

01010-9

3.0 FUNCTIONAL AND AREA REQUIREMENTS

3.1. GENERAL: THERE IS NO STANDARD ARMY MT PRODUCT LINE ITEM FOR A WATER

TREATMENT PLANT. NOTE IN THIS RFP THAT THE STANDARD MODEL RFP FORMAT

IS FOLLOWED AS PRACTICABLE. REFER TO PARAGRAPH 6 PROJECT SPECIFIC

REQUIREMENTS.

3.1.1. FACILITY RELATIONSHIPS: The facilities shall be oriented to support water treatment and daily operations, and should also be located near the respective wells and associated buildings.

3.1.2. GROSS BUILDING AREA: Gross building area shall be as calculated by IBC, which is the area included within surrounding exterior walls exclusive of vent shafts and courts. Areas of the building not provided with surrounding walls shall be included in the building area if such areas are included within the horizontal projection of the roof or floor above.

3.1.3. FUNCTIONAL SPACES: The space shall be sized to accommodate the required function, comply with code requirements, comply with overall gross area limitations and other requirements of the RFP.

3.1.4. HANDICAPPED ACCESS: These facilities are intended for use by able bodied personnel only, therefore, are not required to meet handicapped accessible requirements.

3.2. FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3.2.1. General: The DPG water treatment plant facilities are to be completely functional and operational and satisfy all applicable regulations, requirements, and codes.

3.2.2. DESIGN FREEDOM. Note there are no layouts provided in the applicable Army Standard Design for functional arrangements for water treatment facilities.

3.2.3. ARMY STANDARDS: Applicable Army standards for the DPG Water Treatment project shall be followed.

3.3. TECHNICAL REQUIREMENTS

Site Design: The following site design requirements are applicable to the design of the Water Treatment Facilities:

3.3.1. Architectural Design: Exterior architectural features of the building shall be designed in accordance with the established Installation architectural theme.

3.3.2. Fire Protection: Fire suppression systems will be designed in accordance with the latest edition of UFC 3-600-01; however, the water treatment system shall be classified as mission essential and shall be provided with sprinkler protection regardless of other criteria or code provisions. The facility shall be protected throughout by a complete automatic sprinkler system. The type, function and location of the fire alarm annunciator shall be coordinated with the DPG Fire Department.

3.3.3. Electrical and Communications:

(1) Receptacles. Power receptacles will be provided per NFPA 70 and in conjunction with the proposed equipment and facilities layouts.

01010-10

(2) Lighting. Interior lighting controls shall be provided in accordance with ASHRAE 90.1.

Local manual controls shall supplement automatic controls (occupancy sensors) in pump houses and associated water treatment buildings. Occupancy sensor controls shall be provided in restrooms, electrical rooms, telecommunications rooms and similar spaces.

Interior ambient illumination shall provide a generally glare free, high quality lighting environment and conform to IESNA RP-1-04.

(3) Telecommunications Systems. The project's facilities must connect to the Installation’s Outside Telecommunications (voice and data) System. Outside system improvement is D-B Contractor’s responsibility. All exterior communication system improvements shall be coordinated with Mr. Tom Morris “Superintendent of Utilities Maintenance”, phone: 435-831- 2326; and DOIM POC Mr. Donovan Pomikala, phone: 435-831-3399.

(4) Telecommunications outlets. Telecommunications outlets will be provided per I3A technical guide based on functional purpose of the various spaces (as modified by user special operational requirements and described herein) within the facility. The telecommunications system will consist of cabling, pathways, supporting structures, and outlets.

3.3.4. Furniture Systems: Not used.

3.4. REFERENCES

(1) Army Regulation 190-11 Physical Security of Arms, Ammunition and Explosives

(2) Army Regulation 190–13 The Army Physical Security Program

(3) Army Regulation 190-51, Security of Unclassified Army Property (Sensitive and Nonsensitive)

(4) Army Regulation 380–5 Information Security Program

(5) Army Regulation 380–19 Information Systems Security

01010-11

4.0 APPLICABLE CONSTRUCTION

4.1. APPLICABLE INDUSTRY CRITERIA

Applicable design and construction criteria references are listed in below. Criteria shall be taken from the most current references as of the date of issue of the RFP for Task Order 1 of this IDIQ. This list is not intended to include all criteria that may apply or to restrict design and construction to only those references listed. See also Paragraphs 3 and 6 for additional facility-specific applicable criteria.

International Code Council (ICC) International Building Code (IBC) International Mechanical Code (IMC) International Residential Code (IRC) International Plumbing Code (IPC) International Fuel Gas Code (IFGC) Energy Conservation Code (IEC)

Air Conditioning and Refrigeration Institute (ARI) ARI 310/380 Packaged Terminal Air-Conditioners and Heat Pumps ARI 440 Room Fan-Coil and Unit Ventilator ARI 445 Room Air-Induction Units ARI 880 Air Terminals

Air Movement and Control Association (AMCA) AMCA 210 Laboratory Methods of Testing Fans for Rating

American Architectural Manufacturers Association (AAMA) AAMA 605 Voluntary Specification Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and Panels AAMA 607.1 Voluntary Guide Specifications and Inspection Methods for Clear Anodic

Finishes for Architectural Aluminum AAMA 1503 Voluntary Test Method for Thermal Transmittance and Condensation

Resistance of Windows, Doors, and Glazed Wall Sections American Association of State Highway and Transportation Officials (AASHTO)

Roadside Design Guide [guardrails, roadside safety devices] Standard Specifications for Transportation Materials and Methods of Sampling and

Testing [Road Construction Materials] Standard Specifications for Structural Supports for Highway Signs, Luminaries and

Traffic Signals A Policy of Geometric Design of Highways and Streets Guide for Design of Pavement Structures, Volumes 1 and 2 [pavement design guide]

American Bearing Manufacturers Association (AFBMA) AFBMA Std. 9 Load Ratings and Fatigue Life for Ball Bearings AFBMA Std. 11 Load Ratings and Fatigue Life for Roller Bearings

American Boiler Manufacturers Association (ABMA) ABMA ISEI Industry Standards and Engineering Information

American Concrete Institute, ACI 318, Building Code Requirements for Structural Concrete ACI 315, Details and Detailing of Concrete Reinforcement ACI 530, Building Code Requirements for Masonry Structures

American National Standards Institute 11 (ANSI) ANSI Z21.10.1 Gas Water Heaters Vol. 1, Storage water Heaters with Input Ratings of

75,000 Btu per Hour or less ANSI Z124.3 American National Standard for Plastic Lavatories ANSI Z124.6 Plastic Sinks ANSI Z21.45 Flexible Connectors of Other Than All-Metal Construction for Gas

Appliances

01010-12

ANSI C2 National Electrical Safety Code ANSI/AF&PA NDS-2001 National Design Specification for Wood Construction

American Society of Civil Engineers (ASCE) Minimum Design Loads for Buildings and Other Structures – ASCE 7 Design and Construction of Sanitary and Storm Sewers, Manuals and Reports on

Engineering Practice – No. 37 [sanitary sewer and storm drain design criteria] American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE)

ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings ASHRAE Guideline 1-1996, The HVAC Commissioning Process ASHRAE Hdbk-IP Handbook, Fundamentals I-P Edition ASHRAE Standard 15 Safety Standard for Refrigeration Systems ASHRAE Standard 62.1 Ventilation for Acceptable Indoor Air Quality

American Society of Mechanical Engineers International (ASME) ASME BPVC SEC VII Boiler and Pressure Vessel Code: Section VII Recommended

Guidelines for the Care of Power Boilers ASME A17.1 Safety Code for Elevators and Escalators

American Institute of Steel Construction, Steel Construction Manual, 13th Edition American Iron and Steel Institute, North American Specification for the Design of Cold-

Formed Steel Structural Members AISI/COS NASPEC 2001 American Water Works Association (AWWA)

AWWA Standards [standards for water line materials and construction] American Welding Society, Welding Handbook Architectural Woodwork Institute (AWI)

AWI Quality Standards 7th Edition, Version 1.2 Associated Air Balance Council (AABC)

AABC MN-1 National Standards for Testing and Balancing Heating, Ventilating, and Air Conditioning Systems

AABC Associated Air Balance Council Testing and Balance Procedures Builders Hardware Manufacturers Association (BHMA)

ANSI/BHMA A156.4 American National Standards for Door Controls – Closers… Code of Federal Regulations (CFR)

49 CFR 192 Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards

10 CFR 430 Energy Conservation Program for Consumer Products Consumer Electronics Association

CEA 709.1B Control Network Protocol Specification CEA 709.3 Free-Topology Twisted-Pair Channel Specification CEA 852 Tunneling Component Network Protocols Over Internet Protocol Channels

Electronic Industries Association (EIA) EIA/TIA 568-B Commercial Building Telecommunications Cabling Standards EIA/TIA 569-A Commercial Building Standard for Telecommunications Pathways and

Spaces EIA/TIA 607 Commercial Building Grounding and Bonding Requirements for

Telecommunications Federal Highway Administration (FHWA)

Manual on Uniform Traffic Control Devices for Streets and Highways [signage and pavement markings for streets and highways]

U.S. Architectural and Transportation Barriers Compliance Board ADA Standards for Accessible Design 928 CFR Part 36) Illuminating Engineering Society of North America (IESNA)

IESNA RP-1 Office Lighting IESNA RP-8 Roadway Lighting IESNA Lighting Handbook, Reference and Application

Institute of Electrical and Electronics Engineers Inc. (IEEE) Standard for Use of the International System of Units (SI): the Modern Metric System

01010-13

LEED: Leadership in Energy and Environmental Design Green Building Rating System, Version 2.2, as developed by the U.S. Green Building Council (USGBC) LonMark International

LonMark Interoperability Guidelines (available at www.lonmark.org), including:

Application Layer Guidelines, Layer 1-6 Guidelines, and External Interface File (XIF) Reference Guide LonMark Resource Files (available at www.lonmark.org), including Standard Network Variable Type (SNVT) definitions

MBNA-01 Low Rise Building Systems Manual National Association of Corrosion Engineers International (NACE)

NACE RP0169 Control of External Corrosion on Underground or Submerged Metallic Piping Systems

NACE RP0185 Extruded, Polyolefin Resin Coating Systems with Adhesives for Underground or Submerged Pipe

NACE RP0285 Corrosion Control of Underground Storage Tank Systems by Cathodic Protection

NACE RP0286 Electrical Isolation of Cathodically Protected Pipelines National Electrical Manufacturers Association (NEMA) National Environmental Balancing Bureau (NEBB)

NEBB Procedural Standards Procedural Standards for Testing Adjusting Balancing of Environmental Systems

National Fire Protection Association (NFPA) NFPA 10 Standard for Portable Fire Extinguishers NFPA 13 Installation of Sprinkler Systems NFPA 13R Residential Occupancies up to and Including Four Stories in Height

Sprinkler Systems NFPA 20 Installation of Centrifugal Fire Pumps NFPA 24 Standard for the Installation of Private Fire Service Mains and Their

Appurtenances [underground fire protection system design] NFPA 30 Flammable and Combustible Liquids Code NFPA 30A Motor Fuel Dispensing Facilities and Repair Garages NFPA 31 Installation of Oil Burning Equipment NFPA 54 National Fuel Gas Code NFPA 58 Liquefied Petroleum Gas Code NFPA 70 National Electrical Code (2008) NFPA 72 National Fire Alarm Code (2007) NFPA 80 Standard for Fire Doors and Fire Windows NFPA 90a Installation of Air Conditioning and Ventilating Systems NFPA 96 Standard for Ventilation Control and Fire Protection of Commercial Cooking

Operations NFPA 101: Life Safety Code NFPA 780 Standard for the Installation of Lightning Protection Systems (2004)

National Food Code FDA Model Food Code

National Roofing Contractor’s Association NRCA Roofing and Waterproofing Manual

Occupational Safety and Health Administration (OSHA) OSHA Construction Industry Standards, Title 29, Code of Federal Regulations, Part

1926, Safety and Health Regulations for Construction Plumbing and Drainage Institute (PDI)

PDI G 101 Testing and Rating Procedure for Grease Interceptors with Appendix of Sizing and Installation Data

PDI WH201 Water Hammer Arrestors Precast Concrete Institute

PCI Design Handbook – Precast and Prestressed Concrete Sheet Metal and Air Conditioning Contractor’s National Association (SMACNA)

01010-14

SMACNA HVAC Duct Construction Standards HVAC Duct Construction Standards - Metal and Flexible

SMACNA Architectural Manual Architectural Sheet Metal Manual SMACNA HVAC TAB HVAC Systems - Testing, Adjusting and Balancing

State/Local Regulations State Department of Transportation Standard Specifications for Highway and Bridge

Construction State/Local Sedimentation and Erosion Control Design Requirements

State/Local Environmental Control Requirements State/Local Storm Water Management Requirements Steel Door Institute (SDI)

ANSI A250.8/SDI 100 Standard Steel Doors and Frames Steel Deck Institute, SDI Diaphragm Design Manual Steel Joist Institute, 41st Edition Catalog of Standard Specifications and Load Tables for Steel Joists and Joist Girders Underwriters Laboratories (UL)

UL 96A Installation Requirements for Lightning Protection Systems UL 300 Standard for Safety for Fire Testing of Fire Extinguishing Systems for

Protection of Restaurant Cooking Areas

Additional Criteria:

AFM 88-10, Volume 5, Water Supply, Water Distribution.

AFM 88-11, Volume1, Sanitary and Industrial Wastewater Collection-Gravity Sewers and

Appurtenances.

AFM 88-11, Volume 2, Sanitary and Industrial Wastewater Collection-Pumping Mains and

Force Mains.

4.2. APPLICABLE MILITARY CRITERIA

The project shall conform to the following criteria. Certain design impacts and features due to these criteria are noted for the benefit of the offeror. However, all requirements of the referenced criteria will be applicable, whether noted or not, unless otherwise specified herein.

Criteria shall be taken from the most current references as of the date of issue of this Task Order RFP.

Energy Policy Act of 2005 (Public Law 109-58)

UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings Unless otherwise specified in Project Specific Requirements, only the minimum protective measures as specified by the current Department of Defense Minimum Antiterrorism Standards for Buildings, UFC 4-010-01, are required for this project. The element of those standards that has the most significant impact on project planning is providing protection against explosives effects. That protection can either be achieved using conventional construction (including specific window requirements) in conjunction with establishing relatively large standoff distances to parking, roadways, and installation perimeters or through building hardening, which will allow lesser standoff distances. Even with the latter, the minimum standoff distances cannot be encroached upon. These setbacks will establish the maximum buildable area. All standards in Appendix B of UFC 4-010-01 must be followed and as many of the recommendations in Appendix C that can reasonably be accommodated should be included. The facility requirements listed in these specifications assume that the minimum standoff distances can be met, permitting conventional construction. Lesser standoff distances (with specific minimums) are not desired, however can be provided, but will require structural hardening for the building. See Project Specific Requirements for

01010-15 project specific siting constraints. The following list highlights the major points but the detailed requirements as presented in Appendix B of UFC 4-010-01 must be followed.

Standoff distance from roads, parking and installation perimeter; and/or structural blast mitigation

Blast resistant windows, frames, anchors, supports

Progressive collapse resistance for all facilities 3 stories or higher

Mailrooms have separate HVAC systems and are sealed from rest of building

UFC 4-023-03 Design of Buildings to Resist Progressive Collapse

Options to use tie force method or alternate path design

UFC 3-600-01 Design: Fire Protection Engineering for Facilities

UFC 4-021-01 Design and O&M: Mass Notification Systems Technical Guide for Installation Information Infrastructure Architecture (I3A) http://www.hnd.usace.army.mil/paxspt/isce/pubs.aspx

UFC 3-580-01 (Draft) Telecommunications Bldg Cabling Systems Planning/Design

UFC 1-200-01, Design: General Building Requirements

UFC 3-310-03A, Design: Seismic Design for Buildings

UFC 3-400-01, Design: Energy Conservation

UFC 3-400-02, Design: Engineering Weather Data

UFC 3-410-01FA, Design: Heating, Ventilating, and Air Conditioning

UFC 3-410-02A, Design: Heating, Ventilating, and Air Conditioning (HVAC) Control Systems

UFC 3-420-01, Design: Plumbing

UFC 3-450-01, Design: Noise and Vibration Control

4.3. PRECEDENCE

In the event of conflict between References and/or Applicable Military Criteria, the most stringent requirement will apply, unless otherwise specifically noted in the contract.

01010-16

5.0 GENERAL TECHNICAL REQUIREMENTS

This paragraph contains general technical requirements. See also Paragraph 3 for facility-specific technical requirements and Paragraph 6 for Project Specific Requirements.

5.1. SITE PLANNING AND DESIGN

5.1.1. STANDARDS AND CODES: The site planning and design shall conform to APPLICABLE

CRITERIA.

5.1.2. SITE PLANNING OBJECTIVES: Group buildings in configurations that create a sense of community and promote pedestrian use. See Chapters 2, 3, and 6 for additional site planning requirements relating to building functions.

5.1.3. Provide space at dumpster areas for recycling receptacles. Coordinate with DPG and contracting office on recycling receptacle types, sizes and access requirements and provide space at dumpster areas to accommodate them.

5.1.4. Exterior Signage: Provide exterior signage in accordance with DPG practice.

5.1.5. Existing Utilities: Limited base utilities maps and capacities for this site are included as part of this RFP. See chapter 6 for more detailed information. The Contractor is to verify utility and capacities information pertinent to this RFP.

5.2. SITE ENGINEERING

5.2.1. STANDARDS AND CODES: The site engineering shall conform to APPLICABLE CRITERIA.

5.2.2. SOILS: A report has not been prepared that provides raw data for the project site. The Contractor’s team shall include a licensed geotechnical engineer to develop earthwork and foundation recommendations and design parameters on which to base the Contractor’s proposal. If any additional subsurface investigation or laboratory analysis is required to better characterize the site or develop the final design, it shall be performed subsequent to the award under the direction of a licensed geotechnical engineer and shall be the full responsibility of the Contractor. There will be no separate payment for the cost of additional tests.

A final geotechnical evaluation report shall be prepared by the contractor’s licensed geotechnical engineer and submitted along with the first foundation design submittal. This report shall summarize the subsurface conditions; provide recommendations for the design of appropriate foundations, floor slabs, retaining walls, embankments, and pavements. The Contractor’s geotechnical report shall recommend the type foundation system to be used, lateral load resistance capacities for foundation systems, allowable bearing elevations for footings, grade beams, slabs, etc. An assessment of post-construction settlement potential including total and differential shall be provided. Recommendations regarding lateral earth pressures (active, at-rest, passive) to be used in the design of retaining walls shall be provided. The report shall include the recommended spectral accelerations and Site Class for seismic design along with an evaluation of any seismic hazards and recommendations for mitigation, if required. Calculations shall be included to support the recommendations for bearing capacity, settlement, and pavement sections. Supporting documentation shall be included for all recommended design parameters such as Site Class, shear strength, earth pressure coefficients, friction factors, subgrade modulus, California Bearing Ratio (CBR), etc.

In addition, the report shall provide earthwork recommendations, expected frost penetration, expected groundwater levels, recommendations for dewatering and groundwater control, and the possible presence of any surface or subsurface features that may affect the construction

01010-17 of the project such as sinkholes, boulders, shallow rock, old fill, old structures, soft areas, or unusual soil conditions.

The DB Contractor and the professional geotechnical engineer consultant shall certify in writing that the design of the project has been developed consistent with the Contractor’s final geotechnical report. The certification shall be stamped by the consulting professional geotechnical engineer and shall be submitted with the first design submission. If revisions are made to the initial design submission, a new certification shall be provided with the final design submission.

5.2.3. Design procedures and materials shall conform to one of the following 1) the USACE Pavement Transportation Computer Assisted Structural Engineering (PCASE) PROGRAM, 2) American Association of State Highway and Transportation Officials (AASHTO) or, 3) the applicable state Department of Transportation standards in which the project is located. See Section DESIGN AFTER AWARD for geotechnical report required information. Provide underdraining systems for pavement designs over cohesive soil subgrades. Regardless of the pavement design, a minimum flexible pavement section shall consist of 3 inches of asphalt and 8 inches of aggregate base. Roads shall be designed with a life expectance of 25 years with normal maintenance. Pavement markings and traffic signage shall comply with the Installation requirements and with the Manual on Uniform Traffic Control Devices. The only road work required in this solicitation will consist of gravel access driveways.

5.2.4. Parking Requirements

All handicap POV parking lots shall meet the ADA Accessibility Guidelines for accessible parking spaces. There are no parking lots required in this solicitation.

Parking spaces should be 9 ft by 18 ft.

5.2.5. UTILITIES: See chapter 6 for specific information on ownership of utilities and utility requirements. Meter all utilities (gas, water, electric) to each facility. For Government-owned utilities except electric, install meters that have wireless data transmission capability as well as have a continuous manual reading option. All meters will be capable of at least hourly data logging and transmission and provide consumption data for gas, water, and electricity. Gas and electric meters will also provide demand readings based on consumption over a maximum of any 15-minute period. Configure all meters to transmit at least daily even if no receiver for the data is currently available at the time of project acceptance. For privatized utilities, coordinate with the privatized utility(ies) for the proper meter base and meter installation.

5.2.6. PERMITS: The CONTRACTOR shall be responsible for obtaining all permits (local, state and federal) required for design and construction of all site features and utilities.

5.3. ARCHITECTURE AND INTERIOR DESIGN

5.3.1. STANDARDS AND CODES: The architecture and interior design shall conform to

APPLICABLE CRITERIA.

5.3.2. GENERAL: Overall architectural goal is to provide a functional, quality, visually appealing facility that is a source of pride for the installation and delivered within the available budget and schedule.

5.3.3. BUILDING EXTERIOR: Design buildings to enhance or compliment the visual environment of the Installation. Where appropriate, reflect a human scale to the facility. Building entrance should be architecturally defined and easily seen. When practical, exterior materials, roof

01010-18 forms, and detailing shall be compatible with the surrounding development and adjacent buildings on the Installation and follow locally established architectural themes. Use durable materials that are easy to maintain. Exterior colors shall conform to the DPG practice.

5.3.3.1. Building Numbers: Each building shall have exterior signage permanently attached on two faces of the building indicating the assigned building number or address.

Building number signage details and locations shall conform to the DPG practice.

5.3.4. BUILDING INTERIOR

5.3.4.1. Space Configuration: Arrange spaces in an efficient and functional manner.

5.3.4.2. Surfaces: Appearance retention is the top priority for building and furniture related finishes. Provide low maintenance, easily cleaned room finishes that are commercially standard for the facility occupancy specified, unless noted otherwise.

5.3.4.3. Color: The color, texture and pattern selections for the finishes of the building shall provide an aesthetically pleasing, comfortable, easily maintainable and functional environment for the occupants. Coordination of the building colors and finishes is necessary for a cohesive design. Color selections shall be appropriate for the building type. The use of color, texture and pattern shall be used to path or way find through the building. Trendy colors that will become dated shall be limited to non-permanent finishes such as carpet and paint. Finishes should be selected with regards to aesthetics, maintenance, durability, life safety and image. Limit the number of similar colors for each material. Color of Ceramic and porcelain tile grout shall be medium range color to help hide soiling. Plastic laminate and solid surface materials shall have patterns that are mottled, flecked or speckled. Finish colors of fire extinguisher cabinets, receptacle bodies and plates, fire alarms / warning lights, emergency lighting, and other miscellaneous items shall be coordinated with the building interior. Color of equipment items on ceilings (speakers, smoke detectors, grills, etc.) shall match the ceiling color.

5.3.4.4. Circulation: Circulation schemes must support easy way finding within the building.

5.3.4.5. Signage: Provide interior signage for overall way finding and life safety requirements.

A comprehensive interior plan shall be from one manufacturer and shall include the following sign types: Directional Signs; Room Identification Signs; Building Service Signs; Regulatory Signs; Official and Unofficial Signs, and Visual Communication Boards. Use of emblems or logos may also be incorporated into the signage plan.

5.3.4.6. Window Treatment: Treatment shall be provided in all exterior windows or locations where control of day light coming in windows or privacy at night is required. Uniformity of window covering color and material shall be maintained to the maximum extent possible within a building.

5.3.5. COMPREHENSIVE INTERIOR DESIGN

5.3.5.1. Comprehensive Interior Design (CID): CID includes the Structural Interior Design (SID) and the Furniture, Fixtures and Equipment (FF&E) Design. SID requires the accommodation of required FF&E within the building and the design, selection and coordination of interior finish materials that are integral to or attached to the building structure. The SID provides basic space planning for anticipated FF&E requirements in conjunction with the functional layout of the building and design issues such as life safety, privacy, acoustics, lighting, ventilation, and accessibility. Completion of a SID involves the selection and specification of applied finishes for the building’s interior

01010-19 features including, but not limited to, walls, floors, ceilings, trims, doors, windows, window treatments, built-in furnishings and installed equipment, lighting, and signage.

The SID package will include furniture floor plans, finish schedules, finish samples and any supporting interior elevations, details or plans necessary to communicate the building finish design and build out. The FF&E includes the design, selection, specification, color coordination and procurement documentation of the required items necessary to meet the functional, operational, sustainability, and aesthetic needs of the facility. The FF&E package will include placement plans, ordering and finish information on all freestanding furnishings and accessories, and cost estimates and will be coordinated with the Structural Interior Design (SID) interior finish materials. The selection of furniture style, function and configuration will be coordinated with the defined requirements. Examples of FF&E items are workstations, seating, files, tables, beds, wardrobes, draperies and accessories as well as markerboards, tackboards, and presentation screens. Criteria for furniture selection will include function and ergonomic considerations, maintenance, durability, sustainability, comfort and cost.

Structural Interior Design (SID) is required for all facility types. FF&E package is required as indicated in Paragraphs 2 and 3.

5.3.5.2. Color, Surface and Signage: Provide a signage package if not provided for in the buildings’ overall signage package.

5.4. STRUCTURAL DESIGN

5.4.1. STANDARDS AND CODES: The structural design shall conform to APPLICABLE CRITERIA.

5.4.1.1. GENERAL: The structural system needs to be compatible with the intended functions and components that allows for future flexibility and reconfigurations of the interior space. It is essential that the ability to remove equipment for maintenance and sufficient space for equipment access without removal be provided.

5.5. THERMAL PERFORMANCE

5.5.1. STANDARDS AND CODES: Building construction shall conform to APPLICABLE CRITERIA.

5.5.2. BUILDING ENVELOPE SEALING PERFORMANCE REQUIREMENT. Not required for unoccupied buildings.

5.5.2.1. Performance Criteria and Substantiation: Demonstrate performance of the continuous air barrier for the opaque building envelope by the following tests:

(a) Test the completed building and demonstrate that the air leakage rate of the building envelope does not exceed 0.25 cfm/ft2 at a pressure differential of 0.3” w.g.

(75 Pa) in accordance with ASTM’s E779 (2003) and E-1827-96 (2002). Accomplish test using either pressurization or depressurization or both. Do not test the building until verifying that the continuous air barrier is in place and installed without failures in accordance with installation instructions so that repairs to the continuous air barrier, if needed to comply with the required air leakage rate, can be done in a timely manner.

(b) Test the completed building using Infrared Thermography testing. Use infrared cameras with a resolution of 0.1 deg C or better. Perform testing on the building envelope in accordance with ISO 6781:1983 and ASTM C1060-90 (1997).

(c) Notify the Government at least three working days prior to the tests to provide the Government the opportunity to witness the tests. Provide the Government written test results confirming the results of all tests.

01010-20

5.6. PLUMBING

5.6.1. STANDARDS AND CODES: The plumbing system shall conform to APPLICABLE CRITERIA.

5.7. ELECTRICAL SYSTEMS

5.7.1. STANDARDS AND CODES: The electrical systems for all facilities shall conform to

APPLICABLE CRITERIA.

5.7.2. MATERIALS AND EQUIPMENT: Materials, equipment and devices shall, as a minimum, meet the requirements of Underwriters Laboratories (UL) where UL standards are established for those items. Wiring for branch circuits shall be copper. Motors larger than one-half horsepower shall be three phase. All electrical systems shall be pre-wired and fully operational unless otherwise indicated. Wall mounted electrical devices (power receptacles and communication outlets) shall have matching colors, mounting heights and faceplates.

5.7.3. POWER SERVICE: Primary service from the base electrical distribution system to the pad-mounted transformer and secondary service from the transformer to the building service electrical equipment room shall be underground. See paragraph 6 for additional site electrical requirements.

5.7.3.1. Spare Capacity: Provide 10% space for future circuit breaker in all panelboards serving residential areas of buildings and 15% spaces in all other panelboards.

5.7.4. LIGHTING: Lighting shall comply with the recommendations of the Illumination Engineering Society of North America (IESNA). Interior lighting shall utilize electronic ballast and energy efficient fluorescent lamps with a Color Rendering Index (CRI) of 85 or higher and a Correlated Color Temperature of 4100K. Fluorescent lamps shall be the low mercury type qualifying as non-hazardous waste upon disposal. Surface mounted fixtures shall not be used on acoustical tile ceilings.

5.7.5. TELECOMMUNICATION SYSTEM: All building telecommunications cabling systems (BCS) shall conform to APPLICABLE CRITERIA to include I3A Technical Guide and the UFC 3-580- 01 (Draft) Telecommunications Bldg Cabling Systems Planning/Design. An acceptable BCS encompasses, but is not limited to, copper and fiber optic (FO) entrance cable, termination equipment, copper and fiber backbone cable, copper horizontal distribution cable, workstation outlets, racks, cable management, patch panels, cable tray, cable ladder, conduits, grounding, and labeling. The project’s facilities (new Ditto and Carr treatment plants and other auxiliary buildings must connect to the Installation telecommunications (voice and data) system through the new outside plant (OSP) telecommunications (underground infrastructure and cabling system) per I3A guidance. Connections to the OSP cabling system shall be from each building’s main cross connect located in the telecommunications room and\or closet etc.

5.7.6. LIGHTNING PROTECTION SYSTEM: A lightning protection system carrying a U.L. Letter of Findings shall be provided for these critical facilities as per NFPA 780.

5.8. HEATING, VENTILATING, AND AIR CONDITIONING

5.8.1. STANDARDS AND CODES: The HVAC system shall conform to APPLICABLE CRITERIA.

5.8.2. DESIGN CONDITIONS. Design shall be based on weather data from ASHRAE Handbook – Fundamentals (current edition), Design conditions for DPG, UT: cooling: 1.0 percentile, heating: 99 percentile. Indoor design conditions shall conform to Table 5-1. Indoor air quality shall conform with the current ASHRAE Standard 62.1 and OSHA requirements.

TABLE 5-1 – INDOOR DESIGN DATA

01010-21

Heating

Indoor Design Temperature 68°F

Unoccupied Space Design Temperature 40°F

Cooling

Indoor Design Temperature 78°F

5.8.2.1. To prevent mold formation in buildings, air conditioning systems must be designed to maintain space humidity at reasonable levels. Include the following considerations in the design of the air conditioning systems. Avoid over sizing of cooling equipment.

Design single zone systems and multi-zone systems to maintain an indoor design condition of 50% relative humidity. Size cooling coils for the greater of the cooling load calculated at the design dry bulb temperature condition or the design humidity condition. Where fan coil units are used, provide a non-permeable wall covering behind the unit. Provide ventilation air from a separate dedicated air handling unit. Do not condition outside air through fan coil units. Avoid the use of direct expansion cooling coils in air handling units with constant running fans that handle outside air.

5.8.3. BUILDING AUTOMATION SYSTEM. The Building Automation System (BAS) and UMCS/EMCS shall not be required.

5.8.4. TESTING, ADJUSTING AND BALANCING. Not required for unoccupied buildings. Testing and balancing of air and hydronic systems shall be accomplished by a firm certified for testing and balancing by the Associated Air Balance Council (AABC), National Environmental Balancing Bureau (NEBB), Testing and Balancing Bureau (TABB). TAB shall be performed in accordance with the requirements of the standard under which the TAB Firm’s qualifications are approved, i.e., AABC MN-I, NEBB TABES, or SMACNA HVACTAB unless otherwise specified herein.